Steel pipe hoisting clamp for building steel structure

By introducing motor drive gear system and automated clamping mechanism into steel pipe lifting fixtures for building steel structures, safety hazards and ply replacement problems are solved in manual operation, automatic clamping and diversity adaptation are achieved, and work efficiency and safety are improved. .

CN221987973UActive Publication Date: 2024-11-12LIAONING BAILONG RISHENG CONSTRUCTION ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420621647.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-28
Publication Date
2024-11-12
Estimated Expiration
2034-03-28

AI Technical Summary

Technical Problem

The existing steel pipe hoisting fixtures for building steel structures require manual operation, which poses safety risks, is complicated to operate, and is not convenient for ply plate replacement, resulting in limited types of clamped steel pipes, which reduces the practicality of the device.

Method used

Design a steel pipe lifting fixture including motor, gear, support plate, rectangular block, horizontal plate, moving block and arc-shaped clamp. The gear drives the rack and horizontal plates to move through the motor, automatically clamp the steel pipe, and through positioning bolts and The positioning plate enables easy replacement of arc-shaped clamps.

Benefits of technology

It realizes automatic clamping of steel pipes, improves operating safety and work efficiency, facilitates ply plate replacement, is suitable for steel pipes of different sizes, and enhances the diversity and practicality of the device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221987973U_ABST
    Figure CN221987973U_ABST
Patent Text Reader

Abstract

The utility model discloses a steel pipe hoisting clamp for a building steel structure, which belongs to the technical field of building steel structures and comprises a cross beam, a motor is fixedly mounted on the rear side of an inner cavity of the cross beam, a gear is fixedly mounted at the output end of the motor, and supporting plates are fixedly mounted on the left and right sides of the top and the bottom of the inner cavity of the cross beam. A first rectangular block is arranged at the top of the right side of the right supporting plate, a first transverse plate is fixedly installed on the left side of the first rectangular block, the left side of the first transverse plate movably penetrates through the supporting plates, and a second rectangular block is arranged at the bottom of the left side of the left supporting plate. According to the steel pipe clamping device, the steel pipe can be automatically clamped, manual operation of workers is avoided, the working safety of the workers is improved, the arc-shaped clamps can be conveniently replaced, the device can be suitable for steel pipes of different sizes, the structure is simple, operation is convenient, and the use diversity of the device is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building steel structures, in particular to a steel pipe hoisting clamp for building steel structures. Background Art

[0002] Steel structure is mainly composed of beams, steel columns, steel trusses and other components made of steel sections and steel plates. It is one of the main types of building structures. Because of its light weight and simple construction, it is widely used in large factories, venues, super high-rise buildings and other fields. Steel pipes are also a type of steel structure. Lifting clamps are required during the transportation of steel pipes.

[0003] The patent document with publication number CN212334351U discloses a steel pipe lifting clamp for building steel structure, including a support frame, characterized in that the inner side surface of the support frame is rotatably connected to one end of a screw rod, and the other end of the screw rod passes through the side wall of the support frame and is fixedly connected to a knob, the screw rod is rotatably connected to the side wall of the support frame through a bearing, the screw rod has positive and negative threads symmetrically distributed in the center, and both ends of the screw rod are fixedly connected to mutually symmetrical threaded blocks, a through groove is provided on the lower wall of the support frame, the threaded block passes through the through groove and is fixedly connected to a circular arc clamp, and the threaded block is slidably connected to the through groove, a hollow column is fixedly connected to the upper surface of the support frame, a sliding column is interactively connected in the hollow column, a limiting mechanism is arranged between the hollow column and the sliding column, and two opposite sides of the sliding column are fixedly connected to a steel pipe balancing mechanism, the utility model presses the steel pipe with a downward middle pressure plate to provide support for both ends of the steel pipe, so that the steel pipe remains balanced and prevents the steel pipe from tilting in the air.

[0004] The device in the above technical solution requires the staff to manually operate the lifting clamp, which is dangerous and very troublesome to operate, reducing the working efficiency of the device, and it is inconvenient to replace the clamp, resulting in a small number of steel pipe types that can be clamped by the clamp, requiring the use of multiple lifting clamps, reducing the practicality of the device; therefore, we propose a steel pipe lifting clamp for building steel structures to solve this problem. Utility Model Content

[0005] The utility model aims to provide a steel pipe hoisting clamp for building steel structure to solve the problems raised in the above background technology.

[0006] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0007] A steel pipe lifting fixture for a building steel structure comprises a cross beam, a motor is fixedly installed on the rear side of the inner cavity of the cross beam, a gear is fixedly installed on the output end of the motor, and support plates are fixedly installed on the left and right sides of the top and bottom of the inner cavity of the cross beam, a first rectangular block is arranged on the top of the right side of the support plate on the right side, a first cross plate is fixedly installed on the left side of the first rectangular block, the left side of the first cross plate movably passes through the support plate, a second rectangular block is arranged on the bottom of the left side of the support plate on the left side, a second cross plate is fixedly installed on the right side of the second rectangular block, and the right side of the second cross plate movably passes through the support plate, a moving block is fixedly installed on the left side of the bottom of the first cross plate and the right side of the bottom of the second cross plate, the bottom of the moving block movably passes through the cross beam, an arc clamp is arranged on the bottom of the moving block, the top of the arc clamp extends to the inside of the moving block, a fixing plate is fixedly installed on the side away from the moving block, and a positioning plate is arranged on the corresponding side of the moving block.

[0008] Preferably, the sides of the positioning plates that are away from each other are movable through the arc clamp and the moving block, and the height of the moving block on the left side is greater than the height of the moving block on the right side.

[0009] Preferably, racks are fixedly installed on the bottom of the first cross plate and the top of the second cross plate, the gears and racks are meshed with each other, limiting blocks are fixedly installed on the front and rear sides of the first cross plate and the second cross plate, and limiting grooves matching the limiting blocks are provided on the front and rear sides of the inner cavity of the support plate.

[0010] Preferably, a positioning bolt is provided at the bottom of the positioning plate, the top thread of the positioning bolt passes through the positioning plate and the thread extends to the inside of the fixing plate, and an anti-slip pad is fixedly installed on the corresponding side of the arc clamp.

[0011] Preferably, a connecting block is fixedly installed on the top of the crossbeam, and a connecting buckle is fixedly installed on the top of the connecting block.

[0012] Preferably, a sliding hole adapted to the moving block is provided at the bottom of the crossbeam.

[0013] Compared with the prior art, the beneficial effects of the utility model are:

[0014] 1. In the utility model, by starting the motor to rotate forward, the motor rotates forward to drive the gear to rotate, the gear drives the first horizontal plate to move to the right through the meshing rack at the top, and the gear drives the second horizontal plate to move to the left through the rack at the bottom. The first horizontal plate and the second horizontal plate drive the arc clamp to move closer to each other through the moving blocks, so that the steel pipe can be clamped automatically, avoiding the need for manual operation by the staff, and improving the work safety of the staff.

[0015] 2. In the utility model, the positioning bolt is moved downward by rotating forward, so that the positioning bolt is away from the positioning plate and is removed, and then the two positioning plates are moved closer to each other and removed, and finally the arc clamp is moved downward and removed, which can facilitate the replacement of the arc clamp and make the device suitable for steel pipes of different sizes. The structure is simple, the operation is convenient, and the use diversity of the device is improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a three-dimensional structural schematic diagram of a steel pipe lifting fixture for building steel structure proposed by the utility model;

[0017] Figure 2 This is a schematic cross-sectional view of a steel pipe lifting fixture for a building steel structure proposed by the utility model;

[0018] Figure 3 for Figure 2 A partial enlarged view of part A.

[0019] In the figure: 1. beam; 2. motor; 3. gear; 4. support plate; 5. first rectangular block; 6. first horizontal plate; 7. second horizontal plate; 8. rack; 9. limit block; 10. second rectangular block; 11. moving block; 12. arc clamp; 13. connecting buckle; 14. fixing plate; 15. positioning plate; 16. positioning bolt; 17. anti-slip pad; 18. connecting block; 19. sliding hole. DETAILED DESCRIPTION

[0020] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.

[0021] Reference Figure 1-3 A steel pipe lifting fixture for building steel structure comprises a crossbeam 1, a motor 2 is fixedly installed on the rear side of the inner cavity of the crossbeam 1, a gear 3 is fixedly installed on the output end of the motor 2, support plates 4 are fixedly installed on the left and right sides of the top and bottom of the inner cavity of the crossbeam 1, a first rectangular block 5 is arranged on the top of the right side of the support plate 4 on the right side, a first cross plate 6 is fixedly installed on the left side of the first rectangular block 5, the left side of the first cross plate 6 movably penetrates the support plate 4, a second rectangular block 10 is arranged on the bottom of the left side of the support plate 4 on the left side, a second cross plate 7 is fixedly installed on the right side of the second rectangular block 10, the right side of the second cross plate 7 movably penetrates the support plate 4, a moving block 11 is fixedly installed on the left side of the bottom of the first cross plate 6 and the right side of the bottom of the second cross plate 7, the bottom of the moving block 11 movably penetrates the crossbeam 1, an arc clamp 12 is arranged on the bottom of the moving block 11, the top of the arc clamp 12 extends to the inside of the moving block 11, a fixing plate 14 is fixedly installed on the side away from the moving block 11, and a positioning plate 15 is arranged on the corresponding side of the moving block 11.

[0022] In this embodiment, the side away from the positioning plate 15 is movable through the arc clamp 12 and the moving block 11, the height of the moving block 11 on the left is greater than the height of the moving block 11 on the right, the bottom of the first cross plate 6 and the top of the second cross plate 7 are fixedly installed with a rack 8, the gear 3 and the rack 8 are meshed with each other, the front and rear sides of the first cross plate 6 and the second cross plate 7 are fixedly installed with limiting blocks 9, and the front and rear sides of the inner cavity of the support plate 4 are provided with limiting grooves adapted to the limiting blocks 9. Through the limiting blocks 9, the first cross plate 6 and the second cross plate 7 can be limited, thereby improving the stability of the left and right movement of the first cross plate 6 and the second cross plate 7.

[0023] In this embodiment, a positioning bolt 16 is provided at the bottom of the positioning plate 15, and the top thread of the positioning bolt 16 passes through the positioning plate 15 and extends to the inside of the fixing plate 14 through the thread. An anti-skid pad 17 is fixedly installed on the corresponding side of the arc clamp 12, and a connecting block 18 is fixedly installed on the top of the beam 1. A connecting buckle 13 is fixedly installed on the top of the connecting block 18. A sliding hole 19 adapted to the moving block 11 is provided at the bottom of the beam 1. The anti-skid pad 17 can increase the friction between the arc clamp 12 and the steel pipe, thereby improving the clamping effect of the steel pipe.

[0024] In this embodiment, when in use, the motor 2 is started to rotate forwardly through the external controller, and the forward rotation of the motor 2 drives the gear 3 to rotate. The gear 3 drives the first cross plate 6 to move to the right through the meshing rack 8 at the top, and the gear 3 drives the second cross plate 7 to move to the left through the rack 8 at the bottom. The first cross plate 6 and the second cross plate 7 respectively drive the arc clamp 12 to move closer to each other through the moving block 11, so that the steel pipe can be clamped automatically, avoiding the need for manual operation by the staff. The positioning bolt 16 is moved downward by the forward rotation, and the positioning bolt 16 is moved away from the positioning plate 15 and removed, and then the two positioning plates 15 are moved closer to each other and removed, and finally the arc clamp 12 is moved downward and removed, so that the arc clamp 12 can be easily replaced.

[0025] The above is a detailed introduction to a steel pipe lifting clamp for building steel structure provided by the utility model. This article uses specific embodiments to explain the principle and implementation method of the utility model. The description of the above embodiments is only used to help understand the method and core idea of ​​the utility model. It should be pointed out that for ordinary technicians in this technical field, without departing from the principle of the utility model, the utility model can also be improved and modified, and these improvements and modifications also fall within the scope of protection of the claims of the utility model.

Claims

1. A steel pipe lifting fixture for building steel structure, comprising a crossbeam (1), characterized in that: A motor (2) is fixedly mounted on the rear side of the inner cavity of the cross beam (1), a gear (3) is fixedly mounted on the output end of the motor (2), support plates (4) are fixedly mounted on the left and right sides of the top and bottom of the inner cavity of the cross beam (1), a first rectangular block (5) is arranged on the top of the right side of the support plate (4) on the right side, a first cross plate (6) is fixedly mounted on the left side of the first rectangular block (5), the left side of the first cross plate (6) movably passes through the support plate (4), a second rectangular block (10) is arranged on the bottom of the left side of the support plate (4) on the left side, the right side of the second rectangular block (10) is fixedly mounted A second transverse plate (7) is installed, the right side of the second transverse plate (7) movably penetrates the support plate (4), a moving block (11) is fixedly installed on the left side of the bottom of the first transverse plate (6) and the right side of the bottom of the second transverse plate (7), the bottom of the moving block (11) movably penetrates the cross beam (1), an arc clamp (12) is arranged at the bottom of the moving block (11), the top of the arc clamp (12) extends to the inside of the moving block (11), a fixing plate (14) is fixedly installed on the side away from the moving block (11), and a positioning plate (15) is arranged on the side corresponding to the moving block (11).

2. The steel pipe hoisting fixture for building steel structure according to claim 1, characterized in that: The side of the positioning plate (15) that is away from each other movably penetrates the arc-shaped clamp (12) and the moving block (11), and the height of the moving block (11) on the left side is greater than the height of the moving block (11) on the right side.

3. The steel pipe hoisting fixture for building steel structure according to claim 1, characterized in that: A rack (8) is fixedly mounted on the bottom of the first transverse plate (6) and the top of the second transverse plate (7); the gear (3) and the rack (8) are meshed with each other; limit blocks (9) are fixedly mounted on the front and rear sides of the first transverse plate (6) and the second transverse plate (7); and limit grooves matching the limit blocks (9) are provided on the front and rear sides of the inner cavity of the support plate (4).

4. The steel pipe hoisting fixture for building steel structure according to claim 2, characterized in that: A positioning bolt (16) is provided at the bottom of the positioning plate (15), and the top thread of the positioning bolt (16) passes through the positioning plate (15) and extends into the interior of the fixing plate (14). An anti-slip pad (17) is fixedly installed on the corresponding side of the arc clamp (12).

5. The steel pipe hoisting fixture for building steel structure according to claim 1, characterized in that: A connecting block (18) is fixedly mounted on the top of the crossbeam (1), and a connecting buckle (13) is fixedly mounted on the top of the connecting block (18).

6. The steel pipe hoisting fixture for building steel structure according to claim 1, characterized in that: The bottom of the crossbeam (1) is provided with a sliding hole (19) adapted to the moving block (11).