Lifting structure for switchboard cabinet of hydropower station

By designing the lifting structure of the distribution board cabinet of the hydropower station, the power distribution board cabinet is lifted by lifting seats, booms, lifting hoists and floor hooks, the problem of flooding of the distribution board cabinet of the hydropower station is solved, and the flood risk is reduced and rapid recovery of operation is achieved. effect.

CN221987982UActive Publication Date: 2024-11-12GUANGSHUI TAOJIANG HYDROPOWER DEV CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323578489.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-27
Publication Date
2024-11-12
Estimated Expiration
2033-12-27

AI Technical Summary

Technical Problem

Hydropower station distribution panel cabinets are easily flooded in harsh climates, resulting in equipment damage and economic losses.

Method used

A hydropower station distribution board cabinet lifting structure is designed, including lifting seats, booms, lifting hoists, steel beams and floor hooks. The distribution board cabinets are lifted through these components to reduce the risk of flooding.

Benefits of technology

The structure is simple, low cost and convenient to operate. It can effectively reduce the chance of power distribution panel cabinets being flooded, and there is no need to make major changes to the factory to ensure the normal operation of the hydropower station.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221987982U_ABST
    Figure CN221987982U_ABST
Patent Text Reader

Abstract

A hoisting structure of a distribution board cabinet of a hydropower station comprises the distribution board cabinet installed indoors, a roof floor is arranged above the distribution board cabinet, the hoisting structure further comprises a hoisting base, hoisting rods, hoisting hoists, a steel beam and floor hoisting hooks, the distribution board cabinet is installed on the hoisting base, the hoisting rods are arranged on the left side and the right side of the hoisting base, and hoisting rings are arranged at the top ends of the hoisting rods. The steel beam is arranged on the top side of the roofing floor, the floor lifting hook penetrates into the top side of the roofing floor from the bottom side of the roofing floor and is connected to the steel beam, and an upper lifting hook and a lower lifting hook of the lifting hoist are connected to the floor lifting hook and the lifting ring respectively. The distribution board cabinet hoisting device is simple in structure and low in cost, a workshop does not need to be greatly changed, the distribution board cabinet can be hoisted to the air by arranging the floor lifting hook on the roof floor and utilizing the hoisting hoist and the hoisting base, operation is easy and convenient, and the probability that the distribution board cabinet is submerged by flood can be effectively reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of hydropower station facilities, in particular to a lifting structure of a power distribution panel cabinet of a hydropower station. Background Art

[0002] Hydroelectric power stations can use water energy to generate electricity and have the function of flood prevention and drought resistance. However, affected by bad weather, hydroelectric power stations also have the risk of waterlogging. Flooding of plant buildings will cause damage to the equipment in the plant, especially the distribution cabinet. If the distribution cabinet is damaged by flooding, it will take a long time for the normal operation of the hydroelectric power station to be restored, causing huge economic losses. Therefore, how to prevent the distribution cabinet from being flooded is the technical problem to be solved by this utility model. Utility Model Content

[0003] In order to solve the above technical problems, the utility model provides a lifting structure for a power distribution panel cabinet of a hydropower station, through which the power distribution panel cabinet can be lifted, thereby greatly reducing the probability of the power distribution panel cabinet being submerged by floods.

[0004] In order to achieve the above-mentioned purpose, the utility model provides a lifting structure of a distribution panel cabinet in a hydropower station, comprising a distribution panel cabinet installed indoors, with a ceiling floor above the distribution panel cabinet, and also comprising a lifting seat, a hanging rod, a lifting hoist, a steel beam and a floor hook. The distribution panel cabinet is installed on the lifting seat, the hanging rod is arranged on the left and right sides of the lifting seat, a lifting ring is arranged on the top of the hanging rod, the steel beam is arranged on the top side of the ceiling floor, the floor hook penetrates from the bottom side of the ceiling floor to the top side of the ceiling floor and is connected to the steel beam, and the upper and lower hooks of the lifting hoist are respectively connected to the floor hook and the lifting ring.

[0005] As a further improvement of the utility model, the lifting seat is formed by connecting channel steels in a rectangular shape, the hanging rod is vertically connected to the lifting seat, the height of the hanging rod is higher than the height of the distribution board cabinet, and a reinforcing diagonal brace is connected between the hanging rod and the lifting seat.

[0006] As a further improvement of the present invention, at least two beams are arranged on the bottom side of the roof floor, and the two ends of the steel beam are respectively located above the two beams.

[0007] As a further improvement of the present invention, a through hole is provided on the ceiling floor, and the floor hook is passed through the hole on the ceiling floor, and the gap between the hole and the floor hook is filled with sealant.

[0008] As a further improvement of the utility model, a waterproof coating layer is provided on the top side of the ceiling slab around the opening, a waterproof concrete layer is provided on the waterproof coating layer, and the steel beam is provided on the waterproof concrete layer.

[0009] As a further improvement of the utility model, the floor hook is threadedly connected to the steel beam, and a waterproof concrete block is arranged on the steel beam at the threaded connection.

[0010] As a further improvement of the utility model, the lifting hoist is a hand chain hoist.

[0011] The beneficial effects of the utility model are as follows: the utility model has a simple structure, low cost, and does not require major changes to the factory building. By setting a floor hook on the roof floor and using a lifting hoist and a lifting seat, the distribution panel cabinet can be lifted into the air. The operation is simple and convenient, and can effectively reduce the probability of the distribution panel cabinet being submerged by floods. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic diagram of the three-dimensional structure of the utility model;

[0013] Figure 2 This is a schematic diagram of the planar structure of the utility model;

[0014] Marking description: distribution panel cabinet 1, ceiling floor 2, opening 21, beam body 22, waterproof coating layer 23, waterproof concrete layer 24, waterproof concrete block 25, lifting seat 3, hanging rod 4, reinforcing diagonal brace 41, lifting ring 42, lifting hoist 5, upper hook 51, lower hook 52, steel beam 6, floor hook 7. DETAILED DESCRIPTION

[0015] The utility model is further described below in conjunction with the accompanying drawings and specific embodiments.

[0016] like Figure 1 , 2 As shown, a lifting structure of a power distribution cabinet of a hydropower station includes a power distribution cabinet 1 installed indoors, and a ceiling floor 2 is located above the power distribution cabinet 1. It also includes a lifting seat 3, a suspension rod 4, a lifting hoist 5, a steel beam 6 and a floor hook 7.

[0017] The lifting seat 3 is welded in a rectangular shape by channel steel. The switchboard cabinet 1 is welded on the lifting seat 3. The suspension rod 4 is vertically welded on the center of gravity connection position on the left and right sides of the lifting seat 3. The center of gravity connection position of the switchboard cabinet 1 can be determined by the two-point off-ground trial lifting method. Reinforced diagonal braces 41 are respectively connected between the front and rear sides of the suspension rod 4 and the lifting seat 3, and the connection strength between the suspension rod 4 and the lifting seat 3 is strengthened by the reinforced diagonal braces 41. The height of the suspension rod 4 is higher than the height of the switchboard cabinet 1, and a lifting ring 42 is welded on the top of the suspension rod 4.

[0018] A hole is drilled on the roof slab 2 at a position corresponding to the suspension rod 4 by a concrete coring machine to form a through hole 21 with a diameter of 50 mm. Two beams 22 are arranged adjacent to each other at intervals on the bottom side of the roof slab 2. The steel beam 6 is erected on the top side of the roof slab 2, and the two ends of the steel beam 6 are respectively located above the two beams 22. The beams 22 are used to unload the concentrated load of the hook onto the beams 22. The floor hook 7 penetrates from the bottom side of the roof slab 2 through the hole 21 to the top side of the roof slab 2 and is threadedly connected to the steel beam 6.

[0019] The hoisting hoist 5 is a hand chain hoist or an electric hoist. In this embodiment, the hoisting hoist 5 is a hand chain hoist. The upper hook 51 and the lower hook 52 of the hoisting hoist 5 are hooked on the floor hook 7 and the ring 42 respectively. During the flood season, the distribution cabinet 1 can be lifted into the air by operating the hoisting hoist 5, thereby effectively reducing the probability of the distribution cabinet 1 being submerged by floods. After the flood season, the distribution cabinet 1 is lowered to the ground to quickly restore the normal operation of the hydropower station.

[0020] Furthermore, in order to improve the waterproofness of the structure and prevent water from seeping in from the hole 21, the following structure is also provided: the gap between the hole 21 and the floor hook 7 is filled with sealant, a waterproof coating layer 23 is provided on the top side of the ceiling slab 2 around the hole 21, a waterproof concrete layer 24 is provided on the waterproof coating layer 23, the steel beam 6 is provided on the waterproof concrete layer 24, and at the same time, a waterproof concrete block 25 is provided on the steel beam 6 at the threaded connection of the floor hook 7.

[0021] The above embodiments are only used to illustrate the present invention and are not intended to limit the present invention in any form. Any person with ordinary knowledge in the technical field may make partial changes or modifications to the technical contents disclosed in the present invention without departing from the scope of the technical features of the present invention, and the equivalent embodiments without departing from the technical features of the present invention are still within the scope of the technical features of the present invention.

Claims

1. A lifting structure for a power distribution cabinet of a hydropower station, comprising a power distribution cabinet installed indoors, with a ceiling floor above the power distribution cabinet, characterized in that: It also includes a lifting seat, a lifting rod, a lifting hoist, a steel beam and a floor hook. The distribution panel cabinet is installed on the lifting seat, the lifting rod is arranged on the left and right sides of the lifting seat, a lifting ring is arranged on the top of the lifting rod, the steel beam is arranged on the top side of the ceiling floor, the floor hook penetrates from the bottom side of the ceiling floor to the top side of the ceiling floor and is connected to the steel beam, and the upper and lower hooks of the lifting hoist are respectively connected to the floor hook and the lifting ring.

2. A lifting structure for a power distribution cabinet of a hydropower station according to claim 1, characterized in that: The lifting seat is formed by connecting channel steels in a rectangular shape, the suspension rod is vertically connected to the lifting seat, the height of the suspension rod is higher than the height of the switchboard cabinet, and a reinforcing diagonal brace is connected between the suspension rod and the lifting seat.

3. A lifting structure for a power distribution cabinet of a hydropower station according to claim 1, characterized in that: At least two beams are arranged on the bottom side of the ceiling floor, and two ends of the steel beam are respectively located above the two beams.

4. A lifting structure for a power distribution cabinet of a hydropower station according to claim 1, characterized in that: The ceiling floor is provided with a through hole, and the floor hook is passed through the hole on the ceiling floor, and the gap between the hole and the floor hook is filled with sealant.

5. A lifting structure for a power distribution cabinet of a hydropower station according to claim 4, characterized in that: A waterproof coating layer is arranged around the opening on the top side of the ceiling floor, a waterproof concrete layer is arranged on the waterproof coating layer, and the steel beam is arranged on the waterproof concrete layer.

6. A lifting structure for a power distribution cabinet of a hydropower station according to claim 4, characterized in that: The floor hook is threadedly connected to the steel beam, and a waterproof concrete block is arranged on the steel beam at the threaded connection position.

7. The lifting structure of a power distribution cabinet of a hydropower station according to claim 1 is characterized by: The lifting hoist is a hand chain hoist.