Tied bar arch splicing support

By using support columns, limit grooves and curved plates in the tie arch splicing bracket, the problems of installation stability and rapid splicing efficiency of tie arches are solved, and the rapid and stable installation and overall erection of the arch ribs are achieved. promote.

CN221989110UActive Publication Date: 2024-11-12CHINA RAILWAY FIRST GRP SECOND ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420202660.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-29
Publication Date
2024-11-12
Estimated Expiration
2034-01-29

AI Technical Summary

Technical Problem

The stability of the existing tie-in arch is difficult to ensure, and the rapid splicing efficiency is not high. Especially when the span and the arch rib weight are large in the construction of continuous bridges, insufficient support of the support horns affects the integrity.

Method used

Design a rod-tied arch splicing bracket, including installing support columns between adjacent bridge piers, the top of the arch rib is equipped with a load-bearing beam and a vertical rod, the bottom is equipped with a support hole, the column penetrates through the through hole, and the height is adjusted through the drive member, The ribs can be installed quickly and stably; the limit grooves and the connecting positions are matched to facilitate the installation of the connecting rods, and the arc plates and arc grooves are matched to the limit load-bearing beams to improve the overall erection efficiency.

Benefits of technology

The fast splicing and structural stability of the tie rod arch is achieved, and the height adjustment of the support columns and drive parts is adjusted to reduce the lifting height. The through holes improve the stability of the arch ribs, and the limit grooves and arc-shaped plates ensure the installation stability of the connecting rod, which improves the overall Erection efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221989110U_ABST
    Figure CN221989110U_ABST
Patent Text Reader

Abstract

The utility model discloses a tie bar arch splicing support, which belongs to the technical field of bridge construction and comprises a tie bar arch mounted between two adjacent piers, and a plurality of supporting upright posts used for supporting the tie bar arch are mounted between the two adjacent piers. The tie bar arch comprises two symmetrically-arranged arch ribs and tie bars connected between two arch feet of the arch ribs, a plurality of connecting rods distributed along the arch ribs are installed between the two arch ribs, a bearing beam is installed at the tops of the arch ribs, vertical rods are connected between the bearing beam and the arch ribs, a plurality of supporting holes are formed in the bottom faces of the arch ribs, and the connecting rods are connected with the supporting holes. The top ends of the supporting stand columns are supported in the supporting holes. By means of the tied arch splicing support, quick splicing of tied arches can be achieved, the structure is stable, and the supporting stand columns are arranged, so that the arch ribs are stably supported in the arch rib mounting process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of bridge construction, and in particular relates to a tie arch splicing bracket. Background Art

[0002] For the construction of prestressed concrete continuous beam bridge bodies, according to different support types, commonly used construction methods include: hanging basket cantilever pouring construction method, full-span support pouring construction method, pier-type support pouring construction method, comprehensive use of full-span supports and pier-type supports to cast-in-place concrete continuous beams, and cantilever assembly method; if the continuous beam construction is simultaneously subject to tight schedule and poor site geological conditions, the above-mentioned support method is used for cast-in-place, which will result in problems such as high steel consumption, the need for special reinforcement of the site foundation, and the possible non-recovery of the steel invested in the early stage.

[0003] In view of the above problems, the existing patent CN 215164738 U discloses a tie-arch quick-assembly bracket, and develops a tie-arch load-bearing bracket with a lighter structure, better economy and easier construction. However, in this technology, the arch ribs are supported during the installation process by supporting brackets. Since the span between adjacent piers of existing continuous bridges is large and the weight of the arch ribs is heavy, it is difficult to ensure stability during the installation process if the support is only provided by supporting brackets. At the same time, it is necessary to pre-install supporting brackets on the piers before casting the piers, which affects the integrity of the piers. In addition, the quick splicing efficiency of the quick-assembly bracket is not high. Utility Model Content

[0004] In view of this, an object of the utility model is to provide a tie arch splicing bracket, which is used to solve the problem in the prior art that the stability of the tie arch installation process is difficult to ensure.

[0005] In order to achieve the above object, the utility model provides the following technical solutions:

[0006] The utility model provides a tie arch splicing bracket, comprising: a tie arch installed between two adjacent bridge piers, a plurality of support columns for supporting the tie arch installed between the two adjacent bridge piers, the tie arch comprising two symmetrically arranged arch ribs and a tie rod connected between two arch feet of the arch ribs, a plurality of connecting rods distributed along the arch ribs installed between the two arch ribs, a load-bearing beam installed on the top of the arch rib, a column connected between the load-bearing beam and the arch rib, a plurality of support holes provided on the bottom surface of the arch rib, and the top ends of the support columns supported in the support holes.

[0007] Furthermore, a plurality of limit grooves distributed along the arch ribs are provided on opposite sides of the two arch ribs, and a connecting position cooperating with the limit grooves is provided on the connecting rod, and the connecting position is connected to the connecting rod as a whole, and the connecting rod cooperates with the limit grooves through the connecting position to connect two adjacent arch ribs.

[0008] Furthermore, the top wall of the arch rib is provided with an arc-shaped groove extending along the arch rib, the arc-shaped groove is connected with the limiting groove, and the load-bearing beam is provided with an arc-shaped plate cooperating with the arc-shaped groove, and the arc-shaped plate can cover the connecting rod setting.

[0009] Furthermore, the vertical pole is connected between the load-bearing beam and the curved plate.

[0010] Furthermore, the tie rod is provided with a plurality of through holes arranged coaxially with the support holes, and the support columns are arranged to pass through the through holes.

[0011] Furthermore, a driving member capable of driving the supporting column to move in a vertical direction is installed at the bottom end of the supporting column.

[0012] The beneficial effects of the utility model are:

[0013] The utility model can realize the rapid splicing of the tie arch through the tie arch splicing bracket, and the structure is stable. By arranging the support column, the arch rib is stably supported during the installation of the arch rib. By arranging the driving member, the height of the support column can be adjusted, thereby driving the arch rib to move to a corresponding height, so that when the arch rib is installed, the height of the arch rib can be reduced; by arranging the through hole, the support column is allowed to pass through the through hole, thereby further improving the stability of the arch rib; by arranging the connection position and the limiting groove, the rapid installation of the connecting rod is convenient; by arranging the arc plate and the arc groove, the installation of the load-bearing beam is convenient, and the arc plate can be pressed against the connecting rod to limit the axial direction of the connecting rod, thereby ensuring the installation stability of the connecting rod; by arranging the vertical rod between the load-bearing beam and the arc plate, the vertical rod is connected with the load-bearing beam and the arc plate to form a whole, thereby improving the overall erection efficiency of the tie arch.

[0014] Other advantages, objectives and features of the utility model will be described in the following description and will be apparent to those skilled in the art to some extent, or those skilled in the art can be taught from the practice of the utility model. The objectives and other advantages of the utility model can be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] In order to make the purpose, technical solution and beneficial effects of the utility model clearer, the utility model is described with the following drawings:

[0016] Figure 1 This is an exploded view of the installation of the first embodiment of the utility model;

[0017] Figure 2 This is a schematic diagram of the structure of the first embodiment of the utility model after installation is completed;

[0018] Figure 3 It is a structural schematic diagram of the arch rib of the utility model.

[0019] The markings in the attached drawings are as follows: pier 1, arch rib 2, limit groove 201, support hole 202, arc groove 203, tie rod 3, through hole 301, connecting rod 4, connection position 401, load-bearing beam 5, arc plate 501, and vertical pole 6. DETAILED DESCRIPTION

[0020] like Figures 1 to 3 As shown, the utility model provides a tie arch splicing bracket, comprising: a tie arch installed between two adjacent piers 1, and a plurality of support columns 5 installed between the two adjacent piers 1 for supporting the tie arch, the tie arch comprising two symmetrically arranged arch ribs 2 and a tie rod 3 connected between two arch feet of the arch rib 2, a plurality of limit grooves 201 distributed along the arch rib 2 are arranged on opposite sides of the two arch ribs 2, the cross section of the limit groove 201 is convex, a connecting rod 4 is installed in the relative limit groove 201 between the two arch ribs 2, and the two ends of the connecting rod 4 are provided with connecting positions 401 matched with the limit groove 201, a load-bearing beam 5 is installed on the top of the arch rib 2, the load-bearing beam 5 is connected to the arch rib 2 through a column 6, a plurality of support holes 202 are arranged on the bottom surface of the arch rib 2, a plurality of through holes 301 arranged coaxially with the support holes 202 are arranged side by side on the tie rod 3, and the support column 5 passes through the through hole 301 and extends into the support hole 202 to support the arch rib 2;

[0021] The top wall of the arch rib 2 is provided with an arc groove 203 extending along the arch rib 2, the arc groove 203 is connected with the limit groove 201, the load-bearing beam 5 is provided with an arc plate 501 matched with the arc groove 203, the arc plate 501 can cover the connection rod 4, and the vertical rod 6 is connected between the load-bearing beam 5 and the arc plate 501;

[0022] The support column 5 is equipped with a driving member capable of moving the support column 5 in the vertical direction. The driving member includes either a pneumatic cylinder or a hydraulic cylinder. By installing the bottom end of the support column 5 on the output end of the driving member, the height of the support column 5 can be adjusted.

[0023] The present invention can realize the rapid splicing of the tie arch by the tie arch splicing bracket, and the structure is stable. By setting the support column 5, the arch rib 2 can be stably supported during the installation process. By setting the driving member, the height of the support column 5 can be adjusted, thereby driving the arch rib 2 to move to the corresponding height, so that when the arch rib 2 is installed, the height of the arch rib 2 can be reduced. By setting the through hole 301, the support column 5 is allowed to pass through the through hole 301, thereby further improving the stability of the arch rib 2. ; By setting the connection position 401 to cooperate with the limiting groove 201, the connecting rod 4 can be quickly installed; by setting the arc plate 501 to cooperate with the arc groove 203, the installation of the load-bearing beam 5 is facilitated, and the arc plate 501 can press the connecting rod 4 to limit the axial direction of the connecting rod 4, thereby ensuring the installation stability of the connecting rod 4; by setting the vertical rod 6 between the load-bearing beam 5 and the arc plate 501, the vertical rod 6 is connected to the load-bearing beam 5 and the arc plate 501 to form a whole, thereby improving the overall erection efficiency of the tie arch.

[0024] Embodiment 1:

[0025] The method for erecting the tied arch splicing support in this scheme includes the following steps:

[0026] S1. Installing support columns 5: According to the distance between two adjacent bridge piers 1 and the spacing between the support holes 202 on the arch rib 2, a support column 5 is set up between two adjacent bridge piers 1, so that when the tie arch is hoisted, the support holes 202 on the arch rib 2 can correspond to the support columns 5;

[0027] S2, installing the arch rib 2: hoist one of the arch ribs 2 in the tie arch, so that the support column 5 can pass through the through hole 301 and extend into the support hole 202 to support the arch rib 2, and the support column 5 is raised and lowered by the driving member, so that the arch rib 2 is installed at a preset height position;

[0028] S3, installing the connecting rod 4: after hoisting the two arch ribs 2 on the corresponding supporting columns 5, hoisting a plurality of connecting rods 4 respectively so that the connecting position 401 on the connecting rod 4 is installed in the relative limiting groove 201 between the two arch ribs 2;

[0029] S4, installing the load-bearing beam 5: installing the arc-shaped plate 501 on the load-bearing beam 5 in the arc-shaped groove 203 that matches it, so that the arc-shaped plate 501 presses the connection position 401 on the connecting rod 4;

[0030] S5. Install multiple distribution beams along the top of the load-bearing beam 5.

[0031] Embodiment 2:

[0032] The method for erecting the tied arch splicing support in this scheme includes the following steps:

[0033] S1. Installing support columns 5: According to the distance between two adjacent bridge piers 1 and the spacing between the support holes 202 on the arch rib 2, a support column 5 is set up between two adjacent bridge piers 1, so that when the tie arch is hoisted, the support holes 202 on the arch rib 2 can correspond to the support columns 5;

[0034] S2, splicing tie arch: firstly, connect the connecting rod 4 between two adjacent arch ribs 2, then install the load-bearing beam 5 on the arch rib 2 so that the arc plate 501 is installed in the arc groove 203 and presses the connecting rod 4, and finally install multiple distribution beams on the top of the load-bearing beam 5;

[0035] S3, erecting the tie arch: hoisting the assembled tie arch to the position where the support column 5 and the support hole 202 correspond one to one, and adjusting the height of the tie arch to a preset position through the driving member.

[0036] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the utility model.

Claims

1. A tie arch splicing bracket, comprising: A tie arch installed between two adjacent bridge piers is characterized in that: a plurality of support columns for supporting the tie arch are installed between the two adjacent bridge piers, the tie arch includes two symmetrically arranged arch ribs and a tie rod connected between two arch feet of the arch ribs, a plurality of connecting rods distributed along the arch ribs are installed between the two arch ribs, a load-bearing beam is installed on the top of the arch rib, a column is connected between the load-bearing beam and the arch rib, a plurality of support holes are provided on the bottom surface of the arch rib, and the top ends of the support columns are supported in the support holes.

2. The tie arch splicing bracket according to claim 1, characterized in that: A plurality of limit grooves distributed along the arch ribs are provided on opposite sides of the two arch ribs, and a connecting position cooperating with the limit grooves is provided on the connecting rod, and the connecting position is connected to the connecting rod as a whole, and the connecting rod cooperates with the limit grooves through the connecting position to connect two adjacent arch ribs.

3. The tie arch splicing bracket according to claim 1, characterized in that: The top wall of the arch rib is provided with an arc groove extending along the arch rib, the arc groove is connected with the limiting groove, and the load-bearing beam is provided with an arc plate matching the arc groove, and the arc plate can cover the connecting rod setting.

4. The tie arch splicing bracket according to claim 3, characterized in that: The vertical rod is connected between the load-bearing beam and the arc-shaped plate.

5. The tie arch splicing bracket according to claim 1, characterized in that: The tie rod is provided with a plurality of through holes arranged coaxially with the support holes, and the support columns are arranged to pass through the through holes.

6. The tie arch splicing bracket according to claim 1, characterized in that: A driving member capable of driving the supporting column to move in a vertical direction is installed at the bottom end of the supporting column.