Middle straining beam template for preventing slab staggering of cylindrical pier

By designing the cylindrical pier anti-fault beam formwork, the combination structure of the semicircular side formwork and the quarter arc-connected flat plate side formwork, combined with the use of rubber strips, the malfunction and leakage in the construction of the cylindrical pier is solved. The slurry problem has improved the construction quality and appearance standards and reduced the cost of later repair.

CN221989119UActive Publication Date: 2024-11-12SHANGHAI CIVIL ENG GRP CO LTD OF CREC +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420426694.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-06
Publication Date
2024-11-12
Estimated Expiration
2034-03-06

AI Technical Summary

Technical Problem

In the construction of cylindrical piers, the difficulty in installing existing forms leads to gaps in contact between the formwork and the concrete, resulting in problems such as slurry leakage, honeycomb lint surfaces and misplaced tables, which increases the cost of later defect treatment.

Method used

A cylindrical pier anti-fault Taichung beam formwork was designed, including semicircular side formwork, quarter arc-connected flat plate side formwork, middle standard section flat plate side formwork, quarter arc-connected flat plate bottom formwork and middle standard section Flat plate bottom mold, by optimizing the formwork structure and the use of rubber strips, ensures close contact and vertical installation between the formwork and the concrete surface.

Benefits of technology

It effectively reduces the problem of wrong stages, avoids the occurrence of slurry leakage and honeycomb squid surfaces, improves construction quality and appearance standards, reduces the cost of later repair, and promotes civilized construction and standardized construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221989119U_ABST
    Figure CN221989119U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of engineering technology science, in particular to a column pier slab staggering prevention middle straining beam formwork which comprises a middle standard section flat plate bottom formwork, quarter arc connecting flat plate bottom formworks are laid at the two ends, after the bottom formworks are formed, quarter arc connecting flat plate side formworks are laid on the quarter arc connecting flat plate bottom formworks, and the quarter arc connecting flat plate side formworks are laid on the middle standard section flat plate bottom formworks. A semicircular side formwork is laid on the outer side of the quarter arc connecting flat plate side formwork, a middle standard section flat plate side formwork is laid on the middle standard section flat plate bottom formwork, and the upper ends and the lower ends of the semicircular side formwork and the quarter arc connecting flat plate side formwork all protrude out of the middle standard section flat plate side formwork. The utility model has the advantages that the problem of direct slab staggering between the straining beam and the upper and lower pier columns in the cylindrical pier is reduced, and the perpendicularity of template installation can be ensured through the lap joint mode of the template and the completed structure. The conditions of slab staggering, slurry leakage and voids and pitted surfaces are effectively controlled, secondary repairing is avoided, the appearance quality is guaranteed, civilized construction is facilitated, and standardized construction is promoted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of engineering technology and science, in particular to a tie beam template for a cylindrical pier to prevent misalignment. Background Art

[0002] At present, the construction template of the tie beam in the circular pier column is composed of a semi-circular template connected to a 1 / 4 arc and a flat plate. The template size and height are the same. During installation, special attention should be paid to the connection between the bottom template of the column and the completed concrete surface. The installation is difficult and the roughening of the top surface will cause gaps in the contact between the template and the concrete, resulting in frequent leakage, honeycombed surface, misalignment and other problems. Utility Model Content

[0003] The utility model aims to overcome the deficiencies of the prior art and provide a cylindrical pier anti-misalignment center tie beam template to improve the construction quality of the center tie beam of the circular pier column, solve the misalignment problem when the cylinder is connected to the center tie beam, reduce the defect processing in the later stage, and avoid unnecessary cost expenditure.

[0004] In order to achieve the above purpose, a tie beam template for the anti-misalignment platform of a cylindrical pier is designed, which includes a semicircular side template, a quarter arc connecting flat plate side template, a middle standard section flat plate side template, a quarter arc connecting flat plate bottom template and a middle standard section flat plate bottom template.

[0005] A quarter arc connecting flat plate bottom mold is laid at both ends of the middle standard section flat plate bottom mold to form a bottom mold. After the bottom mold is completed, a quarter arc connecting flat plate side mold is laid on the quarter arc connecting flat plate bottom mold, and a semicircular side mold is laid on the outer side of the quarter arc connecting flat plate side mold. The middle standard section flat plate side mold is laid on the middle standard section flat plate bottom mold.

[0006] The upper and lower ends of the semicircular side formwork and the quarter-circular plate side formwork both protrude from the middle standard section plate side formwork. The protruding parts of the upper ends of the semicircular side formwork and the quarter-circular plate side formwork are provided with connecting flanges for directly connecting to the circular pier formwork for casting the column. The protruding parts of the lower ends of the semicircular side formwork and the quarter-circular plate side formwork are used for overlapping the structure that has completed the pouring of concrete.

[0007] A rubber strip is provided in the gap between the quarter-arc formwork formed by the quarter-arc plate side formwork and the quarter-arc plate bottom formwork and the cylindrical concrete surface.

[0008] The upper and lower ends of the semicircular side formwork and the quarter-circular arc connecting flat plate side formwork protrude at least 20 cm from the middle standard section flat plate side formwork.

[0009] Compared with the prior art, the utility model has the following advantages:

[0010] The utility model greatly reduces the misalignment problem between the tie beam and the upper and lower pier columns in the cylindrical pier by optimizing the template design, and can ensure the verticality of the template installation by overlapping the template with the completed structure. It effectively controls the occurrence of misalignment, slurry leakage, and honeycomb surface, avoids secondary repairs, ensures the appearance quality, and is conducive to civilized construction and standardized construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 , front view of tie beam formwork in the center of cylindrical pier anti-misalignment platform;

[0012] Figure 2 , top view of the tie beam formwork in the cylindrical pier anti-misalignment platform;

[0013] Figure 3 , two views of the semicircular side formwork of the tie beam formwork in the center of the cylindrical pier to prevent misalignment;

[0014] Figure 4 , three views of the 1 / 4 arc template of the cylindrical pier anti-misalignment platform tie beam template;

[0015] Figure 5 , three views of the side formwork of the standard section of the tie beam formwork in the center of the cylindrical pier to prevent misalignment;

[0016] Figure 6 , three views of the bottom formwork of the standard section of the tie beam formwork for the cylindrical pier anti-misalignment platform;

[0017] Figure 7 , three views of the 1 / 4 arc bottom formwork of the cylindrical pier anti-misalignment platform tie beam formwork;

[0018] Figure 8 , Assembly drawing of tie beam template for anti-misalignment platform of cylindrical pier;

[0019] Fig. 9 , Schematic diagram of the effect after pouring the tie beam formwork in the cylindrical pier anti-misalignment platform;

[0020] In the figure: 1. Semicircular side mold; 2. Quarter-circular arc connected to flat plate side mold; 3. Middle standard section flat plate side mold; 4. Quarter-circular arc connected to additional flat plate bottom mold; 5. Middle standard section flat plate bottom mold. DETAILED DESCRIPTION

[0021] In order to make the purpose, principle and structure of the utility model clearer, it is further described below in conjunction with the drawings and specific embodiments.

[0022] The utility model provides a tie beam template for preventing misalignment of a cylindrical pier, comprising:

[0023] It is composed of a semicircular side mold 1, a quarter arc connected flat plate side mold 2, a middle standard section flat plate side mold 3, a quarter arc connected flat plate bottom mold 4, and a middle standard section flat plate bottom mold 5. Figure 1 shown.

[0024] The semicircular side formwork 1 plate panel is made of δ=5mm steel plate; the connecting flange is δ=12mm, the rib plate is 12mm, the connecting holes are φ18X28, and the hole spacing is ±0.5; the back rib is made of 100# channel steel bent into the required semicircular shape to ensure the shape and force of the template panel. Figure 2 As shown;

[0025] The quarter arc connecting plate side formwork 2 plate panel is made of δ=5mm steel plate; the connecting flange is δ=12mm, the rib plate is 12mm, the connecting holes are φ18X28, and the hole spacing is ±0.5; the back rib is made of 100# channel steel bent into the required semicircular shape to ensure the shape and force of the template panel. Figure 3 shown.

[0026] The 3-plate face plate of the middle standard section flat plate side formwork is made of δ=5mm steel plate; the connecting flange is δ=12mm, the rib plate is 12mm, the connecting holes are all φ18X28, and the hole spacing is ±0.5; the back rib is made of 100# double-jointed channel steel for tension reinforcement. Figure 5 shown.

[0027] The middle standard section flat bottom formwork 5 panel is made of δ=5mm steel plate; the connecting flange δ=12mm, the rib plate=12mm, the connecting holes are φ18X28, the hole spacing is ±0.5; the back rib is reinforced with 100# channel steel. Figure 6 shown.

[0028] The 4-plate face plate of the quarter arc connecting plate bottom formwork is made of δ=5mm steel plate; the connecting flange δ=12mm, the rib plate=12mm, the connecting holes are all φ18X28, and the hole spacing is ±0.5; the back rib is reinforced with 100# channel steel. Figure 7 shown.

[0029] Usage: After the pier column is constructed to the designed tie beam elevation, the hoop method or bracket method is used to support the system to lay the bottom formwork. First, lay the quarter arc connected flat plate bottom formwork 4 and then lay the middle standard section flat plate bottom formwork 5. After the laying is completed, check whether the template joints are smooth. After confirmation, tighten all the bolts of the connecting flange. Place rubber strips between the quarter arc formwork and the cylindrical concrete surface according to the size of the gap. After the bottom formwork construction is completed and the steel bars are tied, install the semicircular side formwork 1, the quarter arc connected flat plate side formwork 2, and finally install the middle standard section flat plate side formwork 3. Figure 8 , 9 .

[0030] Formwork processing and production: The figure only shows the size of the middle tie beam formwork corresponding to the cylindrical formwork with a diameter of 1.8m. The size of the force that the formwork needs to bear can be calculated according to the size of different models, the amount of reinforced concrete used, the size of the safety factor, etc., and the selected material model can be flexibly adjusted. However, when making, please note that the height of the formwork 1 (semicircular side formwork) and 2 (quarter arc connecting to the flat plate side formwork) must be higher than the required tie beam size height by at least 20cm above and below to ensure the smoothness of the tie beam when connecting to the pier column below and the smoothness of the tie beam when connecting to the pier column above, and to ensure the transition.

[0031] Formwork operation: After the pier column is constructed to the designed tie beam elevation, the hoop method or bracket method is used to support the system to lay the bottom formwork. First, lay the quarter arc connected flat plate bottom formwork 4 and then lay the middle standard section flat plate bottom formwork 5. After laying, check whether the template joints are smooth. After confirmation, tighten all bolts of the connecting flange. Place rubber strips between the quarter arc formwork and the cylindrical concrete surface according to the size of the gap. After the bottom formwork construction is completed and the steel bars are tied, install the semicircular side formwork 1, the quarter arc connected flat plate side formwork 2, and finally install the middle standard section flat plate side formwork 3. Figure 8 , 9 : Assembly diagram of the tie beam formwork in the center of the cylindrical pier to prevent misalignment, and schematic diagram of the effect after pouring the tie beam formwork in the center of the cylindrical pier to prevent misalignment.

[0032] The above is only a specific implementation method of this utility model, but the protection scope of the utility model is not limited thereto. Any technician familiar with the technical field within the technical scope disclosed by the utility model, according to the technical solution and new concept of the utility model, shall be covered by the protection scope of the utility model.

Claims

1. A tie beam template for a cylindrical pier anti-misalignment platform, comprising a semicircular side template, a quarter arc connected flat plate side template, a middle standard section flat plate side template, a quarter arc connected flat plate bottom template and a middle standard section flat plate bottom template, Features A quarter arc connecting flat plate bottom mold is laid at both ends of the middle standard section flat plate bottom mold to form a bottom mold. After the bottom mold is completed, a quarter arc connecting flat plate side mold is laid on the quarter arc connecting flat plate bottom mold, and a semicircular side mold is laid on the outer side of the quarter arc connecting flat plate side mold. The middle standard section flat plate side mold is laid on the middle standard section flat plate bottom mold. The upper and lower ends of the semicircular side formwork and the quarter-circular plate side formwork both protrude from the middle standard section plate side formwork. The protruding parts of the upper ends of the semicircular side formwork and the quarter-circular plate side formwork are provided with connecting flanges for directly connecting to the circular pier formwork for casting the column. The protruding parts of the lower ends of the semicircular side formwork and the quarter-circular plate side formwork are used for overlapping the structure that has completed the pouring of concrete.

2. A cylindrical pier anti-misalignment tie beam template as claimed in claim 1, Features A rubber strip is provided in the gap between the quarter-arc formwork formed by the quarter-arc plate side formwork and the quarter-arc plate bottom formwork and the cylindrical concrete surface.

3. A tie beam template for preventing misalignment of cylindrical piers as claimed in claim 1, Features The upper and lower ends of the semicircular side formwork and the quarter-circular arc connecting flat plate side formwork protrude at least 20 cm from the middle standard section flat plate side formwork.