Lead screw connection type curtain wall
Through the curtain wall connected in the form of screw, combined with the combined structure of the main keel, secondary keel and screw, the problems of low flatness and construction efficiency of clay brick walls are solved, and the smoothness and construction convenience are achieved, and the construction convenience is enhanced. Wind and earthquake resistance.
Patent Information
- Application Number
- CN202420546211.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-20
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-03-20
AI Technical Summary
In the prior art, the wall flatness of metal circular pipes or round steel bars makes it difficult to control, the brick positioning and limiting capacity are poor, and the construction efficiency is low.
The curtain wall adopts the form of screw connection, through the combination of the main keel, the secondary keel and the screw, the screw nut is used to connect it to the secondary keel, and a washer and a wedge are set to control the spacing and displacement of the bricks, improving flatness and construction convenience.
Effectively control the positioning and limit of bricks, improve wall flatness, simplify construction processes, improve construction efficiency, and enhance the structure's wind load resistance and earthquake resistance.
Smart Images

Figure CN221989666U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction, in particular to a curtain wall in the form of a screw rod connection. Background Art
[0002] Building curtain wall refers to the non-load-bearing outer wall enclosure of a building, usually composed of panels (glass, metal plates, stone plates, ceramic plates, etc.) and the supporting structure behind (aluminum beams and columns, steel structures, glass ribs, etc.). The building curtain wall is composed of a supporting structure system and panels, and can have a certain displacement capacity relative to the main structure. It is an external protective structure or decorative structure of the building that does not share the effects on the main structure. The curtain wall is the outer wall enclosure of the building, which is non-load-bearing and is hung up like a curtain, so it is also called a hanging wall. It is a lightweight wall with decorative effects commonly used in modern large and high-rise buildings. It is composed of a structural frame and inlaid panels, and is a building enclosure structure that does not bear the load and effects of the main structure.
[0003] In recent years, resource-saving and environmentally friendly industries have flourished. The selection of reasonable new building materials is particularly important for the manufacture, transportation and construction process of building materials. Dry-hanging clay bricks have the characteristics of factory manufacturing and on-site installation, which meets the needs of environmental protection and social development. For example, a high-stability dry-hanging clay brick wall structure with a publication number of CN218176254U uses metal round tubes or round steel bars to pass through the holes on the clay bricks. However, the commonly used metal round tubes or round steel bars to string clay bricks easily make the flatness of the wall difficult to control, the positioning and limiting capabilities of each brick are poor, and the clay bricks are difficult to connect, and the on-site construction efficiency is low. Utility Model Content
[0004] The utility model aims to solve the problems in the prior art of using metal round tubes or round steel bars to string clay bricks, which easily leads to poor control of the flatness of the wall surface, poor positioning and limiting capabilities of each brick, poor docking between clay bricks, and low on-site construction efficiency, and provides a curtain wall in the form of a screw rod connection.
[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0006] A curtain wall in the form of a screw rod connection, comprising a plurality of bricks, a plurality of main purlins extending vertically and a plurality of secondary purlins perpendicular to and fixedly connected to the main purlins, a predetermined number of the bricks being arranged between two adjacent secondary purlins in the vertical direction, the curtain wall in the form of a screw rod connection also comprising a plurality of screw rods, the secondary purlins being provided with mounting holes, the screw rods being passed through the mounting holes and being connected to the secondary purlins through screw rod nuts, the adjacent screw rods being arranged at intervals in the horizontal direction and being connected in the vertical direction; the bricks being provided with through holes, the bricks being passed through the through holes and being connected to the screw rods.
[0007] The curtain wall of the screw rod connection type provided by the utility model is fixed on the mounting hole on the secondary keel by the screw rod, and the bricks are passed through the screw rod; the screw rods are arranged at intervals in the horizontal direction and connected to each other in the vertical direction. The bricks of the curtain wall are divided into multiple units by the main keel and the secondary keel in cooperation with the screw rod, and the positioning and limiting of the bricks can be well controlled, thereby improving the flatness of the entire wall surface. Compared with metal pipes or steel bars, the screw rod is connected to the secondary keel through the screw rod nut, and the position of the screw rod is easier to adjust. During construction, since the screw rods in the vertical direction can be connected or disconnected to each other, the screw rods can be disconnected first to pass through the bricks, such as clay bricks, and then the screw rods can be connected in the vertical direction, and the clay bricks are strung on the screw rods to form a group. According to the size of the clay bricks, the arrangement method, the number of bricks in the string group and the size of the actual construction curtain wall, the number and position relationship of the main keel and the secondary keel are determined. The clay bricks are hung on the keel after being strung together. After the screw nut is fixed, the screw is tightened, which can more conveniently apply the upper and lower preload force, and the bricks are arranged in an orderly manner while being strung together. The main keel is connected to the embedded parts through the adapter, so that the clay bricks are fixed on the main structure in a flat and orderly manner. The curtain wall of this structural form can greatly improve the convenience of on-site construction. The reserved through holes and mounting holes make the installation of bricks and screws very simple, without the need for complicated welding and other processes, which improves the construction efficiency.
[0008] Optionally, a washer is provided between two adjacent through holes in the vertical direction, the screw rod passes through the washer, and at least a portion of the washer is located in the through hole.
[0009] With this structural setting, by setting a washer between two bricks, the gap width between the upper and lower adjacent bricks can be well controlled, the positioning accuracy of each brick can be improved, and the flatness of the wall surface can be improved. At the same time, at least part of the washer is located in the through hole, which can increase the effective contact area between the screw rod and the brick, enhance the tightness of the connection between them, and thus improve the connection reliability of the entire structure; the washer can also prevent the screw rod from directly rubbing against the hole wall of the brick, protect the hole wall to a certain extent, and extend the service life.
[0010] Optionally, the gasket includes a protrusion and wedge-shaped portions arranged on both sides of the protrusion, at least part of the wedge-shaped portion is wedged into the through hole, the protrusion extends between two adjacent bricks in the vertical direction, and the protrusion is used to control the distance between two adjacent bricks.
[0011] The raised portion extends into the gap between adjacent bricks, which can accurately control the spacing between bricks and improve the accuracy of brick positioning, thereby further improving the flatness of the entire wall; the wedge-shaped portion is wedged into the through-hole of the brick, and through the limiting effect of the wedge-shaped structure, the displacement of the brick in the vertical and horizontal directions can be effectively limited to ensure the accurate position of the brick; the design of the raised portion and the wedge-shaped portion not only controls the spacing between bricks, but also limits the displacement of bricks, thereby preventing the bricks from being misplaced and ensuring the overall flatness of the wall; the interference fit between the wedge-shaped portion and the through-hole and the supporting effect of the raised portion enhance the rigidity and stability of the entire structure and improve the wind load resistance and earthquake resistance.
[0012] Optionally, the gasket is a ceramic structural component.
[0013] The gasket is preferably a ceramic structural part. The ceramic material itself has high hardness and excellent corrosion resistance, acid and alkali resistance, high temperature resistance and other properties. In outdoor applications, it can well resist erosion in various harsh environments and ensure the long-term stability of the structure.
[0014] Optionally, the raised portion is a circular ring structure.
[0015] With this structural setting, the raised portion is set as a circular ring structure, so that the raised portion can better control the distance between two adjacent bricks above and below, thereby improving the overall stability.
[0016] Optionally, the wedge-shaped portion is symmetrically arranged with the raised portion as the center.
[0017] With this structural setting, the wedge-shaped parts are symmetrically distributed on both sides of the raised part, so that the bricks can obtain symmetrical limiting constraints in both horizontal and vertical directions, avoiding the offset problem that may be caused by unidirectional wedge limiting, and improving the symmetry and accuracy of positioning.
[0018] Optionally, at least two screw rods are passed through each of the bricks.
[0019] With this structural setting, there is a certain risk in connecting with a single screw rod. If the screw rod is damaged or fails, the entire brick will lose support. Using at least two screw rods for connection provides a redundant design, which greatly enhances the reliability of the connection and the safety of the structure. Two or more screw rods can provide good constraints for the bricks, increase the bricks' shear resistance in the horizontal and vertical directions, and make the entire structure more solid. Multiple screw rods can disperse the stress on different screw rods, avoid excessive stress concentration at a single point, delay the occurrence of problems such as fatigue cracking, and increase the service life of the structure.
[0020] Optionally, the screw rods adjacent to each other in the vertical direction are connected via screw rod sleeves.
[0021] A screw sleeve is used to connect two adjacent screws in the vertical direction. A single screw segment can be inserted and fixed first, and then they are butted in the vertical direction and connected with a sleeve, which greatly improves the operational convenience of the construction.
[0022] Optionally, the bricks are staggered in the vertical direction.
[0023] With this structural setting, after the staggered arrangement, the bricks are interlocked and limited with each other, so that the entire system forms a relatively continuous overall structure in the vertical direction. The structural integrity and synergy are enhanced. The staggered arrangement avoids the continuous distribution of vertical joints, helps to eliminate the resulting stress concentration, and makes the stress more evenly distributed in the wall, thereby improving the structure's resistance to cracking.
[0024] Optionally, the main keel uses a rectangular tube structure, and the secondary keel uses an angle steel structure.
[0025] It is preferred that the main keel use a rectangular tube structural member. The rectangular tube is a hollow closed steel structure with a large cross-sectional moment of inertia and high bending stiffness. It can provide good bending bearing capacity for the main keel and ensure that the main keel has sufficient structural strength when subjected to stress. The rectangular tube cross-section is rectangular or square and has high torsional stiffness. It can effectively resist torsional deformation and improve the overall stability of the main keel when subjected to stress. It is preferred that the secondary keel be an angle steel structural member. The angle steel structure has a relatively simple shape, which makes it easy to drill holes in the angle steel and pass the screw rod through it, which is beneficial to the connection and installation of the screw rod and the secondary keel.
[0026] In summary, due to the adoption of the above technical solution, the beneficial effects of the utility model are:
[0027] 1. The curtain wall of the screw rod connection type provided by the utility model is fixed on the installation hole on the secondary keel, and the bricks are inserted thereon by the screw rod; the screw rods are arranged at intervals in the horizontal direction and connected to each other in the vertical direction. The bricks of the curtain wall are divided into multiple units by the main keel and the secondary keel in cooperation with the screw rod, which can well control the positioning and limiting of the bricks, thereby improving the flatness of the entire wall surface. Compared with metal pipes or steel bars, the screw rod is connected to the secondary keel through the screw rod nut, which makes it easier to adjust the position of the screw rod. During construction, since the screw rods in the vertical direction can be connected or disconnected to each other, the screw rods can be disconnected first to insert bricks, such as clay bricks, and then the screw rods can be connected in the vertical direction, and the clay bricks can be strung on the screw rods into small groups. According to the size, arrangement, number of bricks in the string and the size of the actual construction curtain wall, the number and position relationship of the main keel and the secondary keel can be determined. The clay bricks are hung on the keel after being strung together. After the screw nut is fixed, the screw is tightened, which can more conveniently apply the upper and lower preload force, and the bricks are arranged in an orderly manner while being strung together. The main keel is connected to the embedded parts through the adapter, so that the clay bricks are fixed on the main structure in a flat and orderly manner. The curtain wall of this structural form can greatly improve the convenience of on-site construction. The reserved through holes and mounting holes make the installation of bricks and screws very simple, without the need for complicated welding and other processes, which improves the construction efficiency.
[0028] 2. The curtain wall in the screw rod connection form provided by the utility model can well control the gap width between two adjacent bricks by setting a washer between two bricks, improve the positioning accuracy of each brick, and improve the flatness of the wall surface. At the same time, at least part of the washer is located in the through hole, which can increase the effective contact area between the screw rod and the brick, enhance the tightness of the connection between them, and thus improve the connection reliability of the entire structure; the washer can also prevent the screw rod from directly rubbing against the hole wall of the brick, protect the hole wall to a certain extent, and extend the service life.
[0029] 3. The curtain wall of the screw rod connection type provided by the utility model has a raised portion extending into the gap between adjacent bricks, which can accurately control the spacing between bricks and improve the accuracy of brick positioning, thereby further improving the flatness of the entire wall surface; the wedge-shaped portion is wedged into the through-hole of the brick, and the displacement of the brick in the vertical and horizontal directions can be effectively limited by the limiting effect of the wedge-shaped structure, thereby ensuring the accurate position of the brick; the design of the raised portion and the wedge-shaped portion not only controls the spacing between bricks, but also limits the displacement of bricks, thereby preventing the bricks from being misplaced and ensuring the overall flatness of the wall; the interference fit between the wedge-shaped portion and the through-hole and the supporting effect of the raised portion enhance the rigidity and stability of the entire structure and improve the wind load resistance and earthquake resistance. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 This is a schematic diagram of the curtain wall structure in the form of screw rod connection;
[0031] Figure 2This is a schematic diagram of the structure of the curtain wall with screw rod connection after bricks are removed;
[0032] Figure 3 yes Figure 2 A magnified view of part A;
[0033] Figure 4 It is a schematic diagram of the brick structure;
[0034] Figure 5 This is a schematic diagram of the keel structure;
[0035] Figure 6 This is a vertical section diagram of the curtain wall in the form of screw rod connection;
[0036] Figure 7 yes Figure 6 A magnified view of part B;
[0037] Figure 8 This is a cross-sectional diagram of a curtain wall in the form of a screw rod connection;
[0038] Fig. 9 It is a vertical cross-sectional diagram of the gasket.
[0039] Numbers in the figure: 1-main keel, 2-secondary keel, 21-mounting hole, 3-screw, 4-screw nut, 5-brick, 51-through hole, 6-washer, 61-protrusion, 62-wedge-shaped part, 7-screw sleeve. DETAILED DESCRIPTION
[0040] The present invention is further described in detail below in conjunction with test examples and specific implementation methods. However, this should not be understood as the scope of the above subject matter of the present invention being limited to the following embodiments, and all technologies realized based on the content of the present invention belong to the scope of the present invention.
[0041] Unless otherwise specified, in the description of the specific embodiments of the present invention, the terms indicating the orientation or position relationship such as "up", "down", "left", "right", "center", "inside", "outside", etc. are all expressions based on the orientation or position relationship shown in the drawings, or the orientation or position relationship when the invented product / equipment / device is usually used. These terms of orientation or position relationship are only for the convenience of describing the scheme of the present invention or simplifying the description in the specific embodiments, so as to facilitate the technicians to quickly understand the scheme, rather than indicating or implying that a specific device / component / element must have a specific orientation, or be constructed and operated in a specific position relationship, and therefore cannot be understood as a limitation on the present invention.
[0042] In addition, if the terms "horizontal", "vertical", "overhanging", "parallel" and the like appear, it does not mean that the corresponding devices / components / elements are required to be absolutely horizontal or vertical or overhanging or parallel, but may be slightly tilted or have deviations. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but may be slightly tilted. Alternatively, it can be simplified to mean that the corresponding devices / components / elements are set in directions such as "horizontal", "vertical", "overhanging", "parallel", etc., and can have an error / deviation of ±10% relative to the corresponding direction setting, more preferably an error / deviation within ±8%, more preferably an error / deviation within ±6%, more preferably an error / deviation within ±5%, and more preferably an error / deviation within ±4%. As long as the corresponding device / component / element is within the error / deviation range, it can still achieve its role in the scheme of the present invention.
[0043] In addition, the expressions “first”, “second”, “third”, etc. that appear in the terms are merely descriptions used to distinguish the same or similar components and should not be understood as emphasizing or implying the relative importance of specific components.
[0044] In addition, in the description of the embodiments of the present invention, "several", "plurality" and "a number" represent at least 2. It can be any number such as 2, 3, 4, 5, 6, 7, 8, 9, and even more than 9.
[0045] In addition, in the description of the technical solution of the present invention, unless otherwise clearly specified / defined / restricted, the terms "set", "install", "connect", "connected", "provided with", "laid", and "arranged" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection, and can be welding, riveting, bolting, threading, and other commonly used connection means in the field. This connection can be a mechanical connection, an electrical connection, or a communication connection; it can be a direct connection, or an indirect connection through an intermediate medium, and it can be the internal connection of two elements.
[0046] Example 1
[0047] A curtain wall with a screw rod connection. Figure 1In the embodiment shown, the main frame is composed of two main keels 1 extending in the vertical direction and three secondary keels 2 fixedly connected to the main keels 1. The extension direction of the secondary keels 2 is perpendicular to the main keels 1. Specifically, the main keels 1 can use rectangular tubes, and the secondary keels 2 can use angle steels. Preferably, the main keel 1 uses a rectangular tube structural member. The rectangular tube is a hollow closed steel structure with a large cross-sectional moment of inertia and high bending stiffness. It can provide the main keel 1 with good bending bearing capacity and ensure that the main keel 1 has sufficient structural strength when subjected to stress. The rectangular tube has a rectangular or square cross-section and has a high torsional stiffness. It can effectively resist torsional deformation and improve the overall stability of the main keel 1 when subjected to stress.
[0048] like Figure 5 As shown, each secondary keel 2 is provided with a plurality of mounting holes 21, and screw rods 3 are passed through the mounting holes 21. The extension direction of screw rods 3 is approximately parallel to the main keel 1, that is, screw rods 3 also extend in the vertical direction. It can be understood here that screw rods 3 can use screw rods commonly used in industrial production. Preferably, the secondary keel 2 is an angle steel structural member, and the angle steel structure is relatively simple in shape, which is convenient for opening holes in the angle steel and passing the screw rods 3 therein, and is conducive to the connection and installation of the screw rods 3 and the secondary keel 2.
[0049] like Figure 1 , 2 An implementation method is shown in which eighteen screw rods 3 are passed through each secondary keel 2. Of course, the number of screw rods 3 and mounting holes 21 is determined by specific construction requirements. The number of screw rods 3 can be the same as the number of mounting holes 21, or the number of mounting holes 21 can be greater than the number of screw rods 3.
[0050] like Figure 6 , 7 As shown, the screw rod 3 passes through the mounting hole 21, and the screw rod 3 is connected to the secondary keel 2 through the screw rod nut 4 installed on the upper and lower surfaces of the secondary keel 2. A gasket can also be placed between the screw rod nut 4 and the secondary keel 2 to ensure a stable connection.
[0051] A predetermined number of bricks 5 are installed in the main frame according to actual construction requirements, such as Figure 4 As shown, the brick 5 can be a clay brick with a through hole 51. Figure 4 Each clay brick has four through holes 51. It can be understood that the number of through holes 51 is not necessarily four, but can also be two, three, five, etc.
[0052] like Figure 1 , 2As shown, adjacent screw rods 3 are arranged at intervals in the horizontal direction, and adjacent screw rods 3 are connected in the vertical direction, for example, two adjacent screw rods 3 in the vertical direction are connected by a screw rod sleeve 7. Here, the screw rod sleeve 7 can use a sleeve commonly used in industrial production, that is, the interior of the screw rod sleeve 7 is reserved with an internal thread matching the external thread of the screw rod 3, and the ends of the adjacent upper and lower screw rods 3 are respectively screwed into the internal threads at both ends of the screw rod sleeve 7, and the splicing of the screw rod 3 is achieved through threaded connection. The screw rod sleeve 7 is used to connect two adjacent screw rods 3 in the vertical direction, and a single screw rod segment can be inserted and fixed first, and then docked in the vertical direction and connected with the screw rod sleeve 7, which greatly improves the operational convenience of the construction.
[0053] The brick 5 is passed through the screw rod 3 through the through hole 51. At least two screw rods 3 are passed through each brick 5. There are certain risks in the connection of a single screw rod 3. If the screw rod 3 is damaged or fails, the entire brick 5 will lose support. The use of at least two screw rods 3 for connection provides a redundant design, greatly enhancing the reliability of the connection and the structural safety; two or more screw rods 3 can provide good constraints for the brick 5, increase the shear resistance of the brick 5 in the horizontal and vertical directions, and make the entire structure more solid; multiple screw rods 3 can disperse the stress on different screw rods 3, avoid excessive stress concentration at a single point, delay the occurrence of problems such as fatigue cracking, and increase the service life of the structure.
[0054] The bricks 5 can be arranged in a staggered distribution in the vertical direction, that is, an I-shaped joint is formed between adjacent bricks 5. After the bricks 5 are staggered, the bricks 5 are interlocked and limited with each other, so that the entire system forms a relatively continuous overall structure in the vertical direction, and the structural integrity and synergy are enhanced. The staggered arrangement avoids the continuous distribution of vertical joints, which helps to eliminate the stress concentration caused by it, so that the stress is more evenly distributed in the wall, and the anti-cracking ability of the structure is improved.
[0055] The curtain wall of the screw rod connection form provided by the utility model is fixed on the mounting hole 21 on the secondary keel 2 by the screw rod 3, and the brick 5 is passed through it by the screw rod 3; the screw rod 3 is arranged at intervals in the horizontal direction and connected to each other in the vertical direction. The bricks 5 of the curtain wall are divided into multiple units by the main keel 1 and the secondary keel 2 in cooperation with the screw rod 3, and the positioning and limiting of the bricks 5 can be well controlled, thereby improving the flatness of the entire wall surface. Compared with metal pipes or steel bars, the screw rod 3 is connected to the secondary keel 2 through the screw nut 4, and the position of the screw rod 3 is easier to adjust. During construction, since the screw rods 3 in the vertical direction can be connected or disconnected to each other, the screw rod 3 can be disconnected first to pass the brick 5, such as clay bricks, and then the screw rod 3 is connected in the vertical direction, and the clay bricks are hung on the screw rod 3 in a string to form a group. According to the size, arrangement mode, number of bricks in the string group and the size of the actual construction curtain wall, the number and position relationship of the main keel 1 and the secondary keel 2 are determined. The clay bricks are mounted on the keel after being strung together. After the screw nut 4 is fixed, the screw 3 is tightened, which can more conveniently apply the upper and lower preload forces, and the bricks are arranged in an orderly manner while being strung together. The main keel 1 is connected to the embedded parts through the adapter, so that the clay bricks are fixed on the main structure in a flat and orderly manner. The curtain wall of this structural form can greatly improve the convenience of on-site construction. The reserved through holes 51 and the mounting holes 21 make the installation of the bricks 5 and the screw 3 very simple, without the need for complicated welding and other processes, thereby improving the construction efficiency.
[0056] Example 2
[0057] On the basis of Example 1, this embodiment installs a gasket 6 between two adjacent bricks 5 in the vertical direction, and the gasket 6 may be a ceramic gasket. Preferably, the gasket 6 is a ceramic structural member, and the ceramic material itself has high hardness and excellent corrosion resistance, acid and alkali resistance, high temperature resistance and other properties, and can well resist erosion in various harsh environments in outdoor applications, ensuring the long-term stability of the structure.
[0058] The specific position of the gasket 6 is between two adjacent through holes 51 in the vertical direction, for example Figure 7 As shown, from top to bottom, the screw rod 3 can first penetrate into the through hole 51 of the upper brick 5, then penetrate into the washer 6, and then penetrate into the through hole 51 of the lower brick 5. It can be understood that Figure 7 As shown, between two adjacent bricks 5 above and below the secondary keel 2, the gasket 6 may not be provided due to the separation of the secondary keel 2.
[0059] By arranging the washer 6 between the two bricks 5, the gap width between the two adjacent bricks 5 can be well controlled, the positioning accuracy of each brick 5 can be improved, and the flatness of the wall surface can be improved. At the same time, at least part of the washer 6 is located in the through hole 51, which can increase the effective contact area between the screw rod 3 and the brick 5, enhance the tightness of the connection between them, and thus improve the connection reliability of the entire structure; the washer 6 can also prevent the screw rod 3 from directly rubbing against the hole wall of the brick 5, protect the hole wall to a certain extent, and extend the service life.
[0060] Specifically, Figure 6-9 As shown, the gasket 6 specifically includes a circular raised portion 61 and wedge-shaped portions 62 symmetrically arranged on both sides of the raised portion 61 with the raised portion 61 as the center. The raised portion 61 is preferably a circular ring structure, so that the raised portion 61 can better control the distance between two adjacent bricks 5, thereby improving the overall stability; the wedge-shaped portions 62 are symmetrically distributed on both sides of the raised portion 61, so that the bricks 5 can obtain symmetrical limit constraints in both the horizontal and vertical directions, avoiding the offset problem that may be caused by the unidirectional wedge limit, and improving the symmetry and accuracy of positioning. Fig. 9 As shown, the portion of the wedge-shaped portion 62 close to the raised portion 61 is relatively wide, and gradually narrows toward the end away from the raised portion 61. At least part of the wedge-shaped portion 62 is wedged into the through hole 51, and the raised portion 61 extends between two adjacent bricks 5 in the vertical direction. The raised portion 61 is used to control the distance between two adjacent bricks 5. For details, please refer to Figure 7 As shown, the annular protrusion 61 is clamped between two bricks 5, the wedge-shaped portion 62 above the protrusion 61 is wedged into the through hole 51 of the upper brick 5, and the wedge-shaped portion 62 below the protrusion 61 is wedged into the through hole 51 of the lower brick 5, that is, at least part of the gasket 6 is located in the through hole 51.
[0061] The raised portion 61 extends into the gap between adjacent bricks 5, which can accurately control the spacing between bricks 5 and improve the accuracy of positioning bricks 5, thereby further improving the flatness of the entire wall surface; the wedge-shaped portion 62 is wedged into the through hole 51 of the brick 5, and through the limiting effect of the wedge-shaped structure, the displacement of the brick 5 in the vertical and horizontal directions can be effectively limited to ensure the accurate position of the brick 5; the design of the raised portion 61 and the wedge-shaped portion 62 not only controls the spacing between bricks 5, but also limits the displacement of bricks 5, thereby preventing the bricks 5 from being misplaced and ensuring the overall flatness of the wall; the interference fit between the wedge-shaped portion 62 and the through hole 51 and the supporting effect of the raised portion 61 enhance the rigidity and stability of the entire structure and improve the wind load resistance and earthquake resistance.
[0062] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A curtain wall in a screw rod connection form, comprising a plurality of bricks (5), a plurality of main keels (1) extending vertically, and a plurality of secondary keels (2) vertically and fixedly connected to the main keels (1), wherein a predetermined number of the bricks (5) are arranged between two adjacent secondary keels (2) in the vertical direction, and characterized in that: It also comprises a plurality of screw rods (3), the secondary keel (2) is provided with a mounting hole (21), the screw rod (3) is passed through the mounting hole (21) and is arranged in the secondary keel (2), the screw rod (3) is connected to the secondary keel (2) through a screw rod nut (4), adjacent screw rods (3) are arranged at intervals in the horizontal direction, and adjacent screw rods (3) are connected in the vertical direction; the brick (5) is provided with a through hole (51), the brick (5) is passed through the through hole (51) and is arranged in the screw rod (3).
2. The curtain wall with screw rod connection according to claim 1, characterized in that: A washer (6) is arranged between two adjacent through holes (51) in the vertical direction, the screw rod (3) passes through the washer (6), and at least a portion of the washer (6) is located in the through hole (51).
3. The curtain wall with screw rod connection according to claim 2, characterized in that: The gasket (6) comprises a protruding portion (61) and wedge-shaped portions (62) arranged on both sides of the protruding portion (61), at least part of the wedge-shaped portion (62) is wedged into the through hole (51), and the protruding portion (61) extends between two adjacent bricks (5) in the vertical direction, and the protruding portion (61) is used to control the distance between two adjacent bricks (5).
4. The curtain wall with screw rod connection according to claim 2, characterized in that: The gasket (6) is a ceramic structural component.
5. The curtain wall with screw rod connection according to claim 3, characterized in that: The raised portion (61) is a circular ring structure.
6. The curtain wall with screw rod connection according to claim 3, characterized in that: The wedge-shaped portion (62) is symmetrically arranged with the raised portion (61) as the center.
7. A curtain wall with screw rod connection according to any one of claims 1 to 6, characterized in that: At least two screw rods (3) are passed through each brick (5).
8. A curtain wall with screw rod connection according to any one of claims 1 to 6, characterized in that: The adjacent screw rods (3) in the vertical direction are connected via screw rod sleeves (7).
9. A curtain wall with screw rod connection according to any one of claims 1 to 6, characterized in that: The bricks (5) are staggered in the vertical direction.
10. A curtain wall with screw rod connection according to any one of claims 1 to 6, characterized in that: The main keel (1) uses a rectangular tube structural member, and the secondary keel (2) uses an angle steel structural member.