Bilateral scaffold shoulder pole steel platform applied to steel structure courtyard part
By erecting a double-sided scaffolding steel platform on the patio of the steel structure, and using the fixed joint design of the shoulder beam and the connecting beam, the problems of few attachment points and welding damage of the high-rise structure are solved, and a safe and economical cantilever scaffolding is achieved.
Patent Information
- Application Number
- CN202420547504.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-20
- Publication Date
- 2024-11-12
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
When setting up double-sided scaffolding in the steel structure patio, there are problems such as few structural attachment points and irreversible damage to the original structure through welding construction. Especially in high-rise buildings, it is difficult to safely and economically mount the inner and outer cantilever scaffolding.
Design a double-sided scaffolding steel platform to fix the shoulder pole and the connecting beam on the original structure H-shaped steel beam, and set up position parts on the connecting beam, and fix them using clamps and connecting steel plates to avoid pulling up and down support and Welding minimizes damage to the original structure.
It effectively solves the problem of fewer attachment points in high-rise structures, avoids the impact of welds on the original structure, and realizes the safe and economical installation of internal and external cantilever scaffolding, reducing the damage to the original structure.
Smart Images

Figure CN221989854U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, and more specifically, particularly relates to a double-sided scaffolding shoulder pole steel platform applied to a steel structure patio. Background Art
[0002] Steel structures have been widely used in civil buildings. Due to the requirements of building functions and shapes, full-height patios are set up. Due to masonry and curtain wall projects, it is necessary to set up cantilever scaffolding on both sides of the patio. Steel structure projects generally have high floor heights. The patent with announcement number CN219118710U discloses a double-sided scaffolding shoulder pole steel platform used in the patio of the steel structure. Multiple sleeves are embedded on the wall facade, and horizontal horizontal bars are set between the sleeves. The longitudinal horizontal bars and vertical bars are combined to form a support frame. A construction platform is set on the support frame, and the two ends of the horizontal horizontal bar are inserted into the sleeve to form a horizontal support. There are certain technical difficulties compared with the traditional upper pull and lower support settings. There are only beams and column components in the patio, and there is no floor slab. Therefore, there are few attachment points for cantilever scaffolding on both sides of the inside and outside. In addition, welding construction causes irreversible damage to the original steel structure, so the weld needs to be set with caution. Utility Model Content
[0003] In order to overcome the above-mentioned shortcomings, the utility model aims to provide a double-sided scaffolding shoulder pole steel platform applied to the steel structure patio area. According to the situation of the steel structure floor height, the setting of upper pull and lower support is avoided. In view of the situation that the welds are prone to damage to the original structure, by adding components, the original structure H-shaped steel beams are reasonably utilized, and the weld positions are shifted to minimize the damage to the original structure.
[0004] A double-sided scaffolding shoulder pole steel platform used in a steel structure patio, comprising:
[0005] A shoulder beam fixedly connected to the H-shaped steel beam of the original structure, and a connecting beam fixedly connected to the shoulder beam; the connecting beam is located above the shoulder beam; a positioning piece is arranged on the upper end surface of the connecting beam, and the positioning piece is used to connect the scaffolding upright pole;
[0006] The shoulder beam is fixedly connected to the original structure H-shaped steel beam through a connecting piece, and is fixedly connected to the original structure H-shaped steel beam through a clamp.
[0007] Furthermore, the lower end surface of the connecting member is fixedly connected to both sides of the upper flange of the original structure H-shaped steel beam; the upper end surface of the connecting member is fixedly connected to the lower end surface of the shoulder beam.
[0008] Furthermore, the clamp is in the shape of an "X"; the clamp clamps the shoulder beam and the two ends of the clamp are welded to the upper end surface of the original structural H-shaped steel beam.
[0009] Furthermore, a limiting piece is arranged in the gap between the clamp and the web of the shoulder beam.
[0010] Furthermore, the limiting member is made of wedge-shaped square wood.
[0011] Furthermore, the link beam is arranged perpendicularly to the shoulder beam.
[0012] Furthermore, at least two shoulder-pole beams are arranged; and at least two link beams are arranged.
[0013] Furthermore, the connecting piece is a connecting steel plate.
[0014] Furthermore, the length of the connecting steel plate is greater than the width of the H-shaped steel beam of the original structure, and the width of the connecting steel plate is greater than the width of the shoulder pole beam.
[0015] Furthermore, the shoulder beam and the connecting beam are respectively made of I-beams.
[0016] Furthermore, the positioning member is a positioning steel bar head made of a steel bar segment.
[0017] Compared with the prior art, the beneficial effects of the utility model are:
[0018] This is used for the double-sided scaffolding shoulder pole steel platform in the steel structure patio area. It is suitable for the parts where cantilever scaffolding needs to be set up on both the inside and outside of the steel structure. It is combined with the original H-shaped steel beam of the structure. A shoulder pole beam is fixed above the original H-shaped steel beam. Multiple connecting beams are vertically welded above the shoulder pole beam. The upper end surface of the connecting beam is provided with positioning pieces. The positioning pieces are used to connect the scaffolding uprights. This can effectively avoid the problem of fewer attachment points when the steel structure is high, and avoid the influence of welds on the original H-shaped steel beams as much as possible. It can safely and economically set up the inner and outer cantilever scaffolding steel platform. In view of the high steel structure floor, avoid setting up upper pulls and lower supports. In view of the situation where welds are prone to damage to the original structure, by adding components and rationally utilizing the original H-shaped steel beams, the weld positions are transferred to minimize damage to the original structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0020] Figure 1 It is a schematic diagram of the overall structure of the double-sided scaffolding shoulder pole steel platform used in the steel structure patio area in the embodiment.
[0021] Figure 2 It is a schematic diagram of the exploded view of the double-sided scaffolding shoulder pole steel platform used in the steel structure patio area in the embodiment.
[0022] Figure 3 Schematic diagram of the connecting member in the embodiment.
[0023] Figure 4 Schematic diagram of the shoulder pole beam in the embodiment.
[0024] Figure 5 It is a schematic diagram of the "X"-shaped clamp in the embodiment.
[0025] Figure 6 It is a front view of the double-sided scaffolding shoulder pole steel platform used in the steel structure patio area in the embodiment.
[0026] In the figure: 1. H-shaped steel beam of the original structure; 2. Shoulder pole beam; 3. Connecting beam; 4. Positioning piece; 5. Connecting piece; 6. Clamp; 7. Limiting piece. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0028] like Figure 1-Figure 6 As shown, this embodiment provides a double-sided scaffolding pole steel platform applied to the steel structure patio, including a pole beam 2 fixedly connected to the original structure H-shaped steel beam 1, and a connecting beam 3 fixedly connected to the pole beam 2. The connecting beam 3 is located above the pole beam 2, and the upper end surface of the connecting beam 3 is provided with a positioning member 4, which is used to connect the scaffolding upright pole. The pole beam 2 is fixedly connected to the original structure H-shaped steel beam 1 through a connecting member 5, and is fixedly connected to the original structure H-shaped steel beam 1 through a clamp 6.
[0029] In this embodiment, the shoulder beam 2 and the connecting beam 3 are respectively made of I-beams. Figure 1 , Figure 2 , Figure 4 As shown, the connecting beam 3 is arranged vertically on the shoulder beam 2. At least two shoulder beams 2 are arranged, and at least two connecting beams 3 are arranged. In this embodiment, two shoulder beams 2 are arranged, and they are arranged symmetrically with the central axis of the original H-shaped steel beam as the symmetry axis, and four connecting beams 3 are arranged. The connecting beam 3 is vertically welded to the shoulder beam 2, and the positioning piece 4 is welded on the connecting beam 3. A plurality of positioning pieces 4 are arranged on the upper end surface of each connecting beam, and the positioning piece 4 is a positioning steel bar head made of a steel bar segment.
[0030] Specifically, the lower end surface of the connecting member 5 is fixedly connected to both sides of the upper flange of the original structure H-shaped steel beam 1, and the upper end surface of the connecting member 5 is fixedly connected to the lower end surface of the shoulder beam 2. Figure 1-Figure 3 , Figure 6 As shown, the connecting member 5 adopts a rectangular connecting steel plate, and the length of the connecting steel plate is greater than the width of the original H-shaped steel beam 1, and the width of the connecting steel plate is greater than the width of the shoulder beam 2, so that the shoulder beam 2 can be stably connected to the original H-shaped steel beam 1 through the connecting steel plate. The connecting steel plate is fully welded to the lower wing of the I-beam as the shoulder beam 2, and the connecting steel plate is welded to the upper flange of the original H-shaped steel beam 1 through fillet welds. More specifically, in this embodiment, the length of the connecting steel plate is slightly longer than the width of the original H-shaped steel beam 1, the width of the connecting steel plate is longer than the width of the shoulder beam 2, the connecting steel plate is welded to the upper flange fillet welds on both sides of the original H-shaped steel beam 1, the connecting steel plate is perpendicular to the direction of the original H-shaped steel beam and is not welded, and the connecting steel plate is retained without cutting when the scaffold is dismantled. The lower wing of the shoulder beam 2 and the contact surface of the connecting steel plate are fully welded around, and the scaffolding loads borne by the two sides of the shoulder beam 2 are not much different.
[0031] In this embodiment, the clamp 6 is in a "X" shape, the clamp 6 clamps the shoulder beam 2 and the two ends of the clamp 6 are welded to the upper end surface of the original H-shaped steel beam 1. Figure 1-Figure 2 , Figure 5-Figure 6 As shown, the "X"-shaped clamp 6 clamps the shoulder beam 2 and the two ends are welded to the upper wing of the original H-shaped steel beam 1. At least two clamps 6 are arranged on the same shoulder beam 2 to ensure a firm fixation. The inner dimension of the "X"-shaped clamp 6 is larger than the outer dimension of the shoulder beam 2, and the two sides of the "X"-shaped clamp 6 extend outward to meet the welding length of 10 times the diameter. The welded part of the "X"-shaped clamp 6 is not cut when the scaffold is dismantled.
[0032] In order to make the clamp 6 clamp the shoulder pole beam more firmly, a limiting member 7 is arranged in the gap between the clamp 6 and the web of the shoulder pole beam 2. The limiting member 7 is a wedge-shaped square wood, one side of which is flat and abuts against the web of the shoulder pole beam 2, and the other side of which is inclined and abuts against the clamp 6, so that the shoulder pole beam 2 can be stably inserted into the clamp 6. In order to further improve the limiting effect, a long square wood is added on the basis of the wedge-shaped square wood, and the long square wood abuts against the web of the shoulder pole beam 2, and the abutment with the clamp 6 still uses a wedge-shaped square wood, that is, the limiting member can also use a structure combining a long square wood and a wedge-shaped square wood, such as Figure 5 shown.
[0033] The double-sided scaffolding shoulder pole steel platform provided in this embodiment is used for the steel structure patio. During production, the connecting steel plate is welded to both sides of the upper flange of the original H-shaped steel beam, and no welding is performed perpendicular to the beam direction to avoid the generation of a full-length cutting weld on the upper flange of the original H-shaped steel beam. A shoulder pole beam is fixed to the upper part of the connecting steel plate to bear the scaffolding loads on both sides, and can offset the bending moment generated by the loads on both sides at the support. During disassembly, only the shoulder pole I-beam is cut, and the connecting steel plate is retained.
[0034] When the steel structure patio is not used for the erection of a double-sided scaffolding steel platform, the double-sided scaffolding shoulder pole steel platform provided by this embodiment is used for the steel structure patio, which is safe and easy to construct and operate. Among them, the connecting piece 5 is connected to the original structure H-shaped steel beam 1 through two edge fillet welds, and the width of the connecting piece 5 and the corresponding weld length are obtained through mechanical calculation. The shoulder pole beam 2 is placed on the connecting piece 5, and the contact surface is filled with fillet welds all around. The "J"-shaped clamp 6 is clamped on the top of the shoulder pole beam 2, and the two side feet are welded to the upper flange of the original structure H-shaped steel beam 1. The welding length is not less than the specification requirements, and the spare part between the "J"-shaped clamp 6 and the shoulder pole beam 2 can be filled with wooden squares. A plurality of connecting beams 3 are laid on the shoulder pole beam 2, and the positioning steel bar heads are welded on the top for erecting scaffolding uprights.
[0035] The double-sided scaffolding pole steel platform applied to the steel structure patio provided in this embodiment is suitable for the parts where cantilever scaffolding needs to be set up on both the inside and outside of the steel structure. In view of the high floor height of the steel structure, it is avoided to set up upper pull-up and lower support. In view of the situation where the weld seam is easy to damage the original structure, by adding components, reasonably utilizing the original structure H-shaped steel beam, and shifting the weld seam position, the damage to the original structure is minimized.
[0036] The double-sided scaffolding shoulder pole steel platform applied to the steel structure patio in this embodiment, combined with the original structure H-shaped steel beam, can effectively avoid the problems of high structural layers and few structural attachment points, and avoid the influence of welds on the original structure H-shaped steel beam as much as possible, so as to safely and economically build inner and outer cantilever scaffolding steel platforms.
[0037] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A double-sided scaffolding pole steel platform used in the steel structure patio, characterized in that: include: A shoulder beam (2) fixedly connected to the original structural H-shaped steel beam (1), and a connecting beam (3) fixedly connected to the shoulder beam (2); the connecting beam (3) is located above the shoulder beam (2); a positioning member (4) is arranged on the upper end surface of the connecting beam (3), and the positioning member (4) is used to connect to the scaffolding upright pole; The shoulder beam (2) is fixedly connected to the original structure H-shaped steel beam (1) via a connecting piece (5), and is also fixedly connected to the original structure H-shaped steel beam (1) via a clamp (6).
2. The double-sided scaffolding shoulder pole steel platform used in the steel structure patio according to claim 1 is characterized in that: The lower end surface of the connecting member (5) is fixedly connected to both sides of the upper flange of the original structure H-shaped steel beam (1); the upper end surface of the connecting member (5) is fixedly connected to the lower end surface of the shoulder beam (2).
3. The double-sided scaffolding shoulder pole steel platform used in the steel structure patio according to claim 2 is characterized in that: The clamp (6) is in the shape of a "X"; the clamp (6) clamps the shoulder beam (2) and the two ends of the clamp (6) are welded to the upper end surface of the original structural H-shaped steel beam (1).
4. The double-sided scaffolding shoulder pole steel platform used in the steel structure patio according to claim 3 is characterized in that: A limiting member (7) is arranged in the gap between the clamp (6) and the web of the shoulder beam (2).
5. The double-sided scaffolding shoulder pole steel platform used in the steel structure patio according to claim 4 is characterized in that: The limiting member (7) is made of wedge-shaped square wood.
6. The double-sided scaffolding shoulder pole steel platform used in the steel structure patio according to claim 5 is characterized in that: The link beam (3) is arranged vertically on the shoulder beam (2).
7. The double-sided scaffolding shoulder pole steel platform used in the steel structure patio according to claim 6 is characterized in that: At least two of the shoulder-pole beams (2) are arranged; and at least two of the link beams (3) are arranged.
8. The double-sided scaffolding shoulder pole steel platform used in the steel structure patio according to claim 7 is characterized in that: The connecting member (5) is a connecting steel plate; the length of the connecting steel plate is greater than the width of the original structural H-shaped steel beam (1), and the width of the connecting steel plate is greater than the width of the shoulder beam (2).
9. The double-sided scaffolding shoulder pole steel platform used in the steel structure patio according to claim 8 is characterized in that: The shoulder beam (2) and the connecting beam (3) are respectively made of I-beams.
10. The double-sided scaffolding shoulder pole steel platform used in the steel structure patio according to claim 9 is characterized in that: The positioning member (4) is a positioning steel bar head made of a steel bar segment.