Device for collecting working time of air drill machinery
By setting up a pressure transmitter and paperless recorder on the high-pressure air duct of the air drill, the working status and operating time of the air drill is monitored in real time, and the problems of difficulty and safety hazards of traditional on-site tracking methods are solved, and the working time of the air drill machinery is realized. Fast, accurate collection and safe monitoring.
Patent Information
- Application Number
- CN202420278632.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-05
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-02-05
AI Technical Summary
In hydropower and pumped storage projects, traditional on-site tracking method used to determine the working time of air drilling machinery has problems such as difficulty and safety hazards.
Design a device, including air drill, air compressor, pressure transmitter and paperless recorder, by setting pressure transmitter and paperless recorder on high-pressure air ducts, the working status of the air drill is monitored and recorded in real time using pressure changes. and run time to avoid the impact of dust and falling rocks.
It realizes the rapid and accurate collection of working hours of air drilling machinery, reduces safety risks, is convenient to operate, and has reliable monitoring data.
Smart Images

Figure CN221990355U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of work efficiency measurement, in particular to a device for collecting the working time of a pneumatic drill machine. Background Art
[0002] The ergonomics measurement of mechanical equipment refers to the process of collecting, recording and analyzing data on the working time of machinery during the construction process. At present, the "four new technologies" are widely used in the construction of hydropower and pumped storage projects. Project pricing often faces projects that lack quotas or exceed the scope of application of quotas. At the same time, industry quotas and enterprise quotas are important pricing bases for effectively guiding project investment preparation and cost estimation. Due to factors such as rising prices and inflation over the years, the quotas also need to be revised regularly. And ergonomics measurement is one of the most effective and widely used means to supplement and revise quotas.
[0003] There are a lot of underground caverns in hydropower and pumped storage projects, which need to rely on mechanical equipment such as pneumatic drills and down-the-hole drills for construction. These machines all need to use air compressors to supply air to achieve mechanical operation, and pneumatic drills are the most widely used. Due to the narrow working surface in the underground caverns, poor light, large dust, and many falling rocks, it is difficult to use the traditional on-site tracking method to measure the working time of the pneumatic drills, and there are safety hazards. Utility Model Content
[0004] In order to overcome the above-mentioned shortcomings of the existing on-site tracking method for determining work efficiency, the technical problem to be solved by the utility model is to provide a device that can indirectly and quickly collect the working time of a pneumatic drill machine.
[0005] The technical solution adopted by the utility model to solve its technical problems is:
[0006] A device for collecting the working time of a pneumatic drill includes a pneumatic drill and an air compressor for providing high-pressure gas to the pneumatic drill, and also includes an electrically connected pressure transmitter and a paperless recorder. The pressure transmitter is arranged on a high-pressure air duct between the air compressor and the pneumatic drill, and the paperless recorder is used to record the pressure changes of the pressure transmitter, and judge and record the working condition and working time of the pneumatic drill based on the pressure changes.
[0007] Furthermore, the air compressor, pressure transmitter and paperless recorder are all arranged in an open area not affected by dust from the construction site.
[0008] Furthermore, a three-way joint is provided on the pipeline of one end of the high-pressure air duct close to the air compressor, and the pressure transmitter is connected to the high-pressure air duct through the three-way joint.
[0009] Furthermore, the pressure transmitter is connected to the paperless recorder via a data line.
[0010] The beneficial effect of the utility model is that by adding a device for collecting the mechanical working time of the pneumatic drill to the high-pressure air duct of the traditional pneumatic drill, the wind pressure value in the air duct can be monitored and recorded in real time, so as to judge the working status of the pneumatic drill and record the running time of the pneumatic drill. The operation is convenient, the monitoring data is accurate and reliable, and at the same time the safety risks brought by the traditional in-hole tracking method can be reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a schematic diagram of the overall structure of the utility model.
[0012] Figure 2 The utility model is a schematic diagram of the connection structure of the pressure transmitter and the paperless recorder.
[0013] Marked in the figure are, 1-air compressor, 2-paperless recorder, 3-high-pressure air duct, 4-air drill, 5-pressure transmitter, 6-three-way connector, 7-data cable. DETAILED DESCRIPTION
[0014] The utility model is further described below in conjunction with the accompanying drawings.
[0015] It should be noted that if there are directional indication terms in the present invention, such as up, down, left, right, front, and back directions and orientation terms, they are for the purpose of facilitating the description of the relative position relationship between components, and are not for the absolute position of the related components or the position relationship between components. They are only used to explain the relative position relationship and movement of the components in a certain posture. If the specific posture changes, the directional indication will also change accordingly. If there are terms related to quantity in the present invention, such as "multiple", "multiple", "several", etc., they specifically refer to two or more.
[0016] like Figure 1 As shown, the utility model is a device for collecting the working time of a pneumatic drill, including a pneumatic drill 4 and an air compressor 1 for providing high-pressure gas to the pneumatic drill 4, and also includes an electrically connected pressure transmitter 5 and a paperless recorder 2, wherein the pressure transmitter 5 is arranged on a high-pressure air duct 3 between the air compressor 1 and the pneumatic drill 4, and the paperless recorder 2 is used to record the pressure change of the pressure transmitter 5, and judge and record the working condition and working time of the pneumatic drill 4 according to the pressure change. Among them, the air compressor 1 provides high-pressure wind power to the pneumatic drill 4 through the high-pressure air duct 3 to drive the pneumatic drill 4 to work. The electrical connection between the pressure transmitter 5 and the paperless recorder 2 is preferably connected via a data line 7, and the pressure transmitter 5 and the paperless recorder 2 need to be powered by an external power supply.
[0017] The working principle of the utility model is: under normal circumstances, after the air compressor 1 is turned on, when the air drill 4 is not working, the high-pressure gas does not flow and gathers in the high-pressure air duct 3. At this time, the air pressure value in the high-pressure air duct 3 is maintained at about 0.8Mpa; when the air drill 4 is running, the high-pressure gas is discharged through the air drill 4, and the gas in the high-pressure air duct is in a flowing state. At this time, the air pressure value in the pipe will be maintained between 0.5-0.6Mpa. Therefore, the air pressure value in the high-pressure air duct 3 is recorded in real time by the paperless recorder 2, and then the time when the air pressure value is 0.5-0.6Mpa can be counted to calculate the mechanical working time of the air drill 4.
[0018] In order to prevent dust near the working surface from affecting the operation of the equipment, the air compressor 1, pressure transmitter 5 and paperless recorder 2 are preferably all arranged in an open area that is not affected by dust on the construction site.
[0019] For the installation method of the pressure transmitter 5, such as Figure 2 As shown, a three-way joint 6 can be provided on the pipeline of the high-pressure air pipe 3 at one end close to the air compressor 1, and the pressure transmitter 5 is connected to the high-pressure air pipe 3 through the three-way joint 6. Specifically, during installation, a three-way joint 6 of a size matching the diameter of the high-pressure air supply pipe 3 and the end diameter of the pressure transmitter 5 is selected first, and then the three-way joint 6 is installed at a suitable position of the high-pressure air pipe 3, so that the two straight ports of the three-way joint 6 are connected to the high-pressure air pipe 3, and the T-shaped port is connected to the pressure transmitter 5.
[0020] The utility model adds a device for collecting the mechanical working time of the pneumatic drill to the high-pressure air duct of the traditional pneumatic drill, which can monitor and record the wind pressure value in the air duct in real time, so as to judge the working status of the pneumatic drill and record the running time of the pneumatic drill. The operation is convenient, and the monitoring data is accurate and reliable. At the same time, the safety risks brought by the traditional in-hole tracking method can be reduced, and the utility model has good practicality and application value.
Claims
1. A device for collecting the working time of a pneumatic drill, comprising a pneumatic drill (4) and an air compressor (1) for providing high-pressure gas to the pneumatic drill (4), characterized in that: It also includes an electrically connected pressure transmitter (5) and a paperless recorder (2), wherein the pressure transmitter (5) is arranged on a high-pressure air pipe (3) between the air compressor (1) and the air drill (4), and the paperless recorder (2) is used to record the pressure change of the pressure transmitter (5), and judge and record the working condition and working time of the air drill (4) according to the pressure change.
2. The device for collecting the working time of a pneumatic drill according to claim 1, characterized in that: The air compressor (1), the pressure transmitter (5) and the paperless recorder (2) are all arranged in an open area that is not affected by dust from the construction site.
3. The device for collecting the working time of a pneumatic drill according to claim 1, characterized in that: A three-way joint (6) is provided on the pipeline of one end of the high-pressure air pipe (3) close to the air compressor (1), and the pressure transmitter (5) is connected to the high-pressure air pipe (3) via the three-way joint (6).
4. The device for collecting the working time of a pneumatic drill according to claim 1, characterized in that: The pressure transmitter (5) is connected to the paperless recorder (2) via a data line (7).