Spraying device and coal gas dechlorination tower

By designing a spray device in the gas dechlorination tower, including spray pipes, support members and gas collecting rings, the tower wall corrosion problem caused by excessive spraying volume is solved, and efficient dechlorination is achieved under a small spray area. Extend the life of the equipment.

CN222000341UActive Publication Date: 2024-11-15HUNAN LIYU NEW ENERGY TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420062197.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-10
Publication Date
2024-11-15
Estimated Expiration
2034-01-10

AI Technical Summary

Technical Problem

While increasing the spray volume, the existing spraying device causes corrosion of the gas dechlorination tower and the tower wall of the spraying device, reducing the service life of the equipment, and the splashed slurry causes corrosion of the spraying device, reducing the spraying device. Effect.

Method used

A spraying device is designed, including a slurry supply pipe, a spraying pipe, a support piece and an air-collecting ring. The spraying pipe is equipped with multiple nozzles. The spraying unit is arranged at intervals along the tower height direction, and the branch pipe is arranged perpendicularly with the nozzle. The gas collecting ring is arranged at an angle to the tower wall, and the support is fixedly connected to the tower wall and the spray pipe. The flow regulating valve and pressure gauge are used to regulate the slurry flow and pressure.

Benefits of technology

In the case of reducing the spray area, the spraying effect is improved, the gas escape is prevented, the service life of the equipment is extended, and the efficient dechlorination rate is ensured with a smaller spraying amount.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222000341U_ABST
    Figure CN222000341U_ABST
Patent Text Reader

Abstract

The utility model provides a spraying device and a coal gas dechlorination tower, and relates to the field of coal gas purification. Wherein the spraying device comprises a slurry supply pipeline, a spraying pipeline, a supporting piece and a gas gathering ring, the gas gathering ring and the tower wall of the coal gas dechlorination tower are arranged at an angle, the supporting piece is fixedly connected with the tower wall and the spraying pipeline respectively, the spraying pipeline is provided with a plurality of nozzles, and the slurry supply pipeline is communicated with the spraying pipeline to supply slurry to the spraying pipeline; the slurry supply pipeline is output from the spraying pipeline, coal gas can be sprayed and purified, the gas gathering ring is arranged, the gas gathering ring and the tower wall are arranged at an angle, the gas gathering ring can prevent the coal gas from escaping along the tower wall, all the coal gas can be sprayed and washed through the spraying pipeline, and the coal gas purification effect is improved. And high dechlorination efficiency can be ensured under the condition of small spraying amount, and the spraying effect is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of coal gas purification, and in particular to a spray device and a coal gas dechlorination tower. Background Art

[0002] In a coal gas dechlorination tower, a spray device is generally used to purify the coal gas. In order to increase the spraying volume, the existing spray device is designed with a larger spray coverage area, which will cause a large slurry impact on the tower wall of the coal gas dechlorination tower, resulting in tower wall corrosion, reducing the service life of the coal gas dechlorination tower. In addition, the back-splashed slurry will also cause corrosion to the spray device, also reducing the service life of the spray device.

[0003] Therefore, how to improve the spraying effect while reducing the spraying area becomes an urgent problem to be solved. Utility Model Content

[0004] The purpose of the present application is to provide a spraying device and a coal gas dechlorination tower, which can improve the spraying effect while reducing the spraying area.

[0005] In a first aspect, the utility model provides a spray device for a coal gas dechlorination tower, the spray device comprising a slurry supply pipe, a spray pipe, a support and a gas gathering ring, the gas gathering ring being arranged at an angle to the tower wall of the coal gas dechlorination tower, the support being fixedly connected to the tower wall and the spray pipe respectively, the spray pipe being provided with a plurality of nozzles, the slurry supply pipe being connected to the spray pipe to provide slurry to the spray pipe.

[0006] In an optional embodiment, the spray pipeline includes a plurality of spray units, and the plurality of spray units are arranged at intervals along the height direction of the coal gas dechlorination tower, each of the spray units is respectively connected to the slurry supply pipeline, and each of the spray units is provided with the nozzle.

[0007] In an optional embodiment, each of the spray units comprises a main pipe, multiple secondary pipes and multiple branch pipes, the main pipe is connected to the slurry supply pipe, each of the secondary pipes is connected to the main pipe, and each of the branch pipes is connected to the secondary pipes and is provided with the nozzle.

[0008] In an optional embodiment, each of the secondary pipes is vertically arranged with respect to the main pipe, each of the branch pipes is vertically arranged with respect to the secondary pipe, and each of the branch pipes is provided with at least one of the nozzles.

[0009] In an optional embodiment, each of the branch pipes is provided with a nozzle, and the nozzle is located at an end of the branch pipe away from the tower wall.

[0010] In an optional embodiment, the secondary pipeline extends to the tower wall, and the secondary pipeline is fixedly connected to the tower wall via a support.

[0011] In an optional embodiment, a flow regulating valve is provided between each of the spray units and the slurry supply pipeline, and the flow regulating valve is used to adjust the slurry flow of each of the spray units.

[0012] In an optional embodiment, a pressure gauge is provided between each of the spray units and the slurry supply pipeline.

[0013] In an optional embodiment, the support member is located below the spray pipe and is fixed to the spray pipe, and the support member is provided with a plurality of connection parts, and the plurality of connection parts are respectively fixedly connected to the tower wall.

[0014] In a second aspect, the utility model provides a coal gas dechlorination tower, comprising the spray device described in the aforementioned embodiment.

[0015] Compared with the prior art, the beneficial effects of this application are:

[0016] The slurry of the present application is output from the spray pipe through the slurry supply pipe, which can spray and purify the coal gas. The present application is provided with a gas gathering ring, which is arranged at an angle to the tower wall so that the gas gathering ring can prevent the coal gas from escaping along the tower wall. All the coal gas can be sprayed and washed through the spray pipe, and a higher dechlorination efficiency can be guaranteed even at a smaller spray volume, thereby improving the spraying effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.

[0018] Figure 1 An angled schematic diagram of a spray device in some embodiments is shown;

[0019] Figure 2 Another angle schematic diagram of the spray device in some embodiments is shown;

[0020] Figure 3 Schematic diagrams of assembling the spray pipe and the support member in some embodiments are shown;

[0021] Figure 4 The installation principle flow chart of the coal gas dechlorination tower in Example 2 is shown.

[0022] Description of main component symbols:

[0023] 100-slurry supply pipeline; 200-spray pipeline; 210-spray unit; 211-main pipeline; 212-secondary pipeline; 213-branch pipeline; 214-nozzle; 215-flange; 300-support; 400-gas gathering ring; 410-first bending part; 420-second bending part; 500-support; 510-main body; 520-fixing ring; 600-flow regulating valve; 700-pressure gauge. DETAILED DESCRIPTION

[0024] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.

[0025] In the description of the present application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0026] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0027] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0028] In the present application, unless otherwise clearly specified and limited, a first feature being “above” or “below” a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being “above”, “above”, and “above” a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being “below”, “below”, and “below” a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0029] Embodiment 1

[0030] This embodiment is applicable to a coal gas dechlorination tower, which is in a tower shape and has a cylindrical chamber inside.

[0031] See also Figure 1 and Figure 2 This embodiment provides a spray device. Specifically, the spray device includes a slurry supply pipeline 100, a spray pipeline 200, a support member 300 and a gas gathering ring 400.

[0032] The slurry supply pipeline 100 can provide slurry, and the slurry is configured as alkaline solution, and the alkaline solution reacts with chlorine elements in the coal gas to achieve dechlorination treatment.

[0033] Specifically, the slurry supply pipeline 100 is arranged in a vertical state, and the slurry supply pipeline 100 uses a pump as a power to transport the slurry. In this embodiment, only one slurry supply pipeline 100 is arranged. At this time, only one pump is needed, and the pump is arranged on the side around the bottom of the tower. After starting the pump, the slurry is transported upward from the slurry supply pipeline 100 below.

[0034] In this embodiment, dechlorination treatment can be achieved by using only one pump, thereby saving preparation cost and spraying cost while ensuring the spraying effect, and reducing the floor space occupied by the pump.

[0035] The spray pipe 200 is connected to the slurry supply pipe 100, and the slurry is provided to the spray pipe 200 by the slurry supply pipe 100. The spray pipe 200 is provided with a plurality of nozzles 214, and the nozzles 214 are used to spray the slurry. To prevent the slurry from impacting the tower wall, the spraying direction of the nozzles 214 is set to be vertically downward in this embodiment.

[0036] Specifically, the spray pipeline 200 includes a plurality of spray units 210 , which are arranged at intervals along the height direction of the gas dechlorination tower, each spray unit 210 is connected to the slurry supply pipeline 100 , and each spray unit 210 is provided with a nozzle 214 .

[0037] Since the plurality of spray units 210 are arranged at intervals along the height direction of the coal gas dechlorination tower, the spraying requirements of the coal gas dechlorination tower at different heights can be met, thereby improving the dechlorination rate.

[0038] See also Figure 2 and Figure 3 Each spray unit 210 includes a main pipeline 211, multiple secondary pipelines 212 and multiple branch pipelines 213, and each spray unit 210 is made of 2205 duplex steel with strong corrosion resistance.

[0039] The main pipeline 211 is connected to the slurry supply pipeline 100 through a shock-absorbing flexible connection, and the main pipeline 211 runs through the tower wall. The main pipeline 211 passes through the center of the cylindrical chamber and extends to the opposite tower wall, and the main pipeline 211 is fixedly connected to the tower wall through a support.

[0040] Each time the pipeline 212 is connected to the main pipeline 211 through the flange 215, compared with gluing and PP welding, the installation method of the flange 215 connection is simpler, which reduces the time that the installers stay in the gas dechlorination tower and protects the health of the installers.

[0041] It is understandable that each sub-pipe 212 and the main pipe 211 may also be connected by means of a slipknot thread or a ferrule, which is not limited here.

[0042] Each branch pipe 213 is connected to the secondary pipe 212 and is provided with a nozzle 214. The branch pipe 213 and the secondary pipe 212 are pre-connected outside the gas dechlorination tower, which can further reduce the time that the installers stay in the gas dechlorination tower.

[0043] This embodiment may be configured as follows: each sub-pipeline 212 is vertically disposed with respect to the main pipe 211 , each branch pipe 213 is vertically disposed with respect to the sub-pipeline 212 , and each branch pipe 213 is provided with at least one nozzle 214 .

[0044] There is one main pipeline 211, four secondary pipelines 212, and twelve branch pipelines 213. Every three branch pipelines 213 are located on the same secondary pipeline 212. Two of the three branch pipelines 213 are butt-joined, and the other branch pipeline 213 is arranged away from the tower wall, that is, each branch pipeline 213 close to the tower wall is provided with a nozzle 214, and the nozzle 214 is located at the end of the branch pipeline 213 away from the tower wall.

[0045] In this way, the spraying efficiency can be maximized, and the slurry will not impact the tower wall, thus extending the service life of the gas dechlorination tower and the spraying device.

[0046] The secondary pipeline 212 extends to the tower wall, and the secondary pipeline 212 is fixedly connected to the tower wall through a support 500. Specifically, one end of the secondary pipeline 212 is connected to the main pipeline 211 through a flange 215, and the other end is connected to the tower wall through a support 500. The support 500 includes a body 510 and a fixing ring 520 fixedly connected to the body 510. The secondary pipeline 212 is inserted into the fixing ring 520, and the body 510 is fixedly connected to the tower wall. Here, the body 510 and the tower wall can be fixedly connected by welding or the like.

[0047] The nozzle 214 is configured as a spiral nozzle. The nozzle 214 close to the tower wall adopts a 90° nozzle, and the nozzle 214 away from the tower wall adopts a 120° nozzle. This embodiment can appropriately increase the spraying area and enhance the spraying effect without impacting the tower wall.

[0048] The support member 300 is fixedly connected to the tower wall and the spray pipe 200 respectively. The support member 300 is located below the spray pipe 200 and is fixed to the spray pipe 200. The support member 300 is provided with a plurality of connection parts, and the plurality of connection parts are fixedly connected to the tower wall respectively. Therefore, the support member 300 and the tower wall form a plurality of supporting action points, which greatly improves the supporting capacity of the support member 300.

[0049] In this embodiment, the support member 300 is welded from multiple square tubes, and the cross-section of the support member 300 is I-shaped. The main pipeline 211 and the secondary pipeline 212 are both mounted on the square tubes. The branch pipeline 213 is located in the gap between adjacent square tubes, and the nozzle 214 sprays slurry downward from the gap.

[0050] The gas gathering ring 400 is set at an angle with the tower wall of the coal gas dechlorination tower. In this embodiment, the gas gathering ring 400 is made by bending a 5mm thin plate, and the gas gathering ring 400 includes a first bending portion 410 and a second bending portion 420. The angle between the first bending portion 410 and the second bending portion 420 is configured to be a preset value between 30° and 60°. When the angle is configured to be 30°, the angle between the first bending portion 410 and the tower wall is 75°, and the angle between the second bending portion 420 and the tower wall is 75°.

[0051] In actual use, the gas gathering ring 400 is disposed at a position 300 mm to 800 mm below the main pipeline 211, and the gas gathering effect is optimal.

[0052] In this embodiment, the gas collecting ring 400 is provided to prevent the gas from escaping along the tower wall. All the gas can be sprayed and washed by the spray device, and a high dechlorination efficiency can be ensured at a small spray volume.

[0053] Furthermore, a flow regulating valve 600 is provided between each spray unit 210 and the slurry supply pipeline 100, and the flow regulating valve 600 is used to adjust the slurry flow of each spray unit 210. Specifically, the flow regulating valve 600 can control each spray unit 210 to be at the same flow rate, thereby ensuring the spraying effect.

[0054] Furthermore, a pressure gauge 700 is provided between each spray unit 210 and the slurry supply pipeline 100. The pressure gauge 700 is used to monitor the slurry pressure of each spray unit 210 to ensure that each spray unit 210 is at the same pressure, thereby improving the spraying effect.

[0055] Embodiment 2

[0056] See also Figure 1 This embodiment provides a coal gas dechlorination tower, which includes the spray device of embodiment one.

[0057] Since the support member 300 of the spray device adopts an I-shaped structure, the support member 300 and the tower wall of the coal gas dechlorination tower have four supporting points in total, and the four supporting points are evenly distributed on the tower wall, which has good supporting performance.

[0058] In this embodiment, the spray device can be configured in multiple numbers, and the multiple spray devices are arranged at intervals along the height direction of the coal gas dechlorination tower.

[0059] Please base on Figure 4 Also see Figures 1 to 3 Based on the above content, the installation principle of the gas dechlorination tower is further explained as follows:

[0060] S100. Connect three nozzles 214 to the corresponding three branch pipes 213 outside the coal gas dechlorination tower respectively, repeat four times, and form four groups of branch pipe 213 assemblies.

[0061] S200. Connect four groups of branch pipes 213 components to four secondary pipes 212 respectively to form four groups of secondary pipes 212 components.

[0062] S300. Weld the gas gathering ring 400 and the support member 300 in sequence in the coal gas dechlorination tower, so that the gas gathering ring 400 and the support member 300 are fixedly connected to the tower wall respectively.

[0063] S400 . Install the main pipeline 211 above the support 300 .

[0064] S500 . Connect the main pipeline 211 and four sets of secondary pipeline 212 components via flange 215 .

[0065] S600. Connect the main pipeline 211 and the slurry supply pipeline 100 via a shock-absorbing flexible connection.

[0066] This embodiment adopts the spray device of the first embodiment, so this embodiment has all the advantages of the first embodiment. On the one hand, this embodiment is easy to install and replace. On the other hand, this embodiment has a small spray volume, high processing efficiency and a long service life.

[0067] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0068] Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations on the present application. Ordinary technicians in this field can change, modify, replace and modify the above embodiments within the scope of the present application.

Claims

1. A spray device for a coal gas dechlorination tower, characterized in that: It includes a slurry supply pipeline, a spray pipeline, a support and a gas gathering ring. The gas gathering ring is set at an angle with the tower wall of the coal gas dechlorination tower. The support is fixedly connected to the tower wall and the spray pipeline respectively. The spray pipeline is provided with a plurality of nozzles. The slurry supply pipeline is connected with the spray pipeline to provide slurry to the spray pipeline.

2. The spray device according to claim 1, characterized in that: The spray pipeline includes a plurality of spray units, and the plurality of spray units are arranged at intervals along the height direction of the coal gas dechlorination tower. Each of the spray units is respectively connected to the slurry supply pipeline, and each of the spray units is provided with the nozzle.

3. The spray device according to claim 2, characterized in that: Each of the spray units comprises a main pipeline, a plurality of secondary pipelines and a plurality of branch pipelines. The main pipeline is connected to the slurry supply pipeline, each of the secondary pipelines is connected to the main pipeline, and each of the branch pipelines is connected to the secondary pipelines and is provided with the nozzles.

4. The spray device according to claim 3, characterized in that: Each of the secondary pipes is vertically arranged with respect to the main pipe, each of the branch pipes is vertically arranged with respect to the secondary pipe, and each of the branch pipes is provided with at least one of the nozzles.

5. The spray device according to claim 4, characterized in that: Each branch pipe is provided with a nozzle, and the nozzle is located at an end of the branch pipe away from the tower wall.

6. The spray device according to claim 3, characterized in that: The secondary pipeline extends to the tower wall, and the secondary pipeline is fixedly connected to the tower wall via a support.

7. The spray device according to any one of claims 2 to 6, characterized in that: A flow regulating valve is provided between each of the spraying units and the slurry supply pipeline, and the flow regulating valve is used to adjust the slurry flow of each of the spraying units.

8. The spray device according to claim 7, characterized in that: A pressure gauge is also provided between each of the spray units and the slurry supply pipeline.

9. The spray device according to any one of claims 1 to 6, characterized in that: The support member is located below the spray pipe and is fixed to the spray pipe. The support member is provided with a plurality of connection parts, and the plurality of connection parts are respectively fixedly connected to the tower wall.

10. A coal gas dechlorination tower, characterized in that: A spray device comprising any one of claims 1 to 9.