Special panel for post-cast strip construction formwork

By designing a special panel for post-pouring belt construction, the problem of degradable pipe installation in post-pouring belt construction is solved, the simple installation of the formwork and efficient waterproof sealing are achieved, and the sealing and monitoring capabilities of the construction joints are improved.

CN222009590UActive Publication Date: 2024-11-15JIANGSU GUANGYUE ENERGY SAVING TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420666180.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-02
Publication Date
2024-11-15
Estimated Expiration
2034-04-02

AI Technical Summary

Technical Problem

In the prior art, it is difficult to synchronize and accurately install the degradable pipe at a predetermined position during the construction of the rear casting tape, and the installation and disassembly are time-consuming and labor-intensive, and the water-stop effect is not ideal.

Method used

A special panel for the post-pouring belt construction formwork was designed, including the plate body, the first groove and the extension groove, for inserting and limiting the degradable pipe, ensuring that the pipeline is embedded in the post-pouring belt construction joint after concrete pouring. and the second groove is fixed with the steel mesh strip to achieve simple installation and removal of the formwork.

Benefits of technology

The synchronous installation of degradable pipes in the construction joints of the rear casting belt is achieved, which simplifies the construction steps, shortens the construction period, provides convenient installation of waterproof seal structures, and enhances the waterproof seal of the construction joints by combining multi-layer seals and flexible seals. and monitoring capabilities.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222009590U_ABST
    Figure CN222009590U_ABST
Patent Text Reader

Abstract

The utility model provides a special panel for a post-cast strip construction template, relates to the technical field of building construction, and mainly aims to provide a construction template panel which is convenient for synchronously mounting a degradable pipe in a construction joint in a concrete pouring process. The construction formwork panel comprises a plate body, the plate body is used for blocking pouring grout of a concrete structure body to be poured, and the face, facing the pouring grout in the Z direction, of the plate body is a plate face; the first groove is formed in the plate face in an inward concave mode, and a degradable pipe embedded in the first groove is installed on the plate body. According to the construction formwork panel, the effect of synchronously pre-burying the degradable pipe in the construction joint during concrete pouring construction can be achieved, and convenience is provided for installing a concrete structural joint reverse construction method waterproof sealing structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, in particular to a special panel used for a post-casting strip construction template. Background Art

[0002] In the pouring construction of reinforced concrete structures with a large area, in order to prevent harmful cracks that may be caused by uneven shrinkage or uneven settlement of the cast-in-place reinforced concrete structure, it is necessary to reserve a post-casting belt at the corresponding position according to the design or construction specifications, and use the construction template to separate the pouring area into a pouring belt and a post-casting belt. During construction, the pouring belt is first poured with concrete. After a few days, the separating construction template is removed, and concrete is poured in the post-casting belt. The segmented pouring method effectively solves the problem of harmful cracks caused by concrete deformation. However, it also raises the problem of waterproof sealing of the construction joint between the pouring belt and the post-casting belt.

[0003] CN217399743U discloses a reverse waterproof sealing structure for concrete structural joints, which discloses a technical solution of arranging a degradable tube in a construction joint, and is used to solve the waterproof sealing problem of concrete structural joints including post-casting joints. Specifically, the degradable tube built into the construction joint forms a reserved channel and a grouting conduit in the construction joint after degradation, and the reserved channel can cooperate with the grouting conduit to pour a sealing waterproof material into the construction joint to achieve a sealing and waterproof treatment of the construction joint. In addition, by installing a sensor in the reserved channel, the airtightness of the cavity is monitored, thereby realizing long-term monitoring of the waterproof performance of the waterproof structure.

[0004] In the prior art, the post-casting strip construction mostly uses a fish scale plate welded on a water-stop steel plate as the panel of the construction formwork for concrete pouring, which is expensive and time-consuming and labor-intensive to install and disassemble. In addition, the water-stopping effect of the water-stop steel plate is not ideal. In order to quickly implement the above technical solution, it is necessary to develop a matching special construction formwork panel that can accurately install a degradable pipe at a predetermined position during the formation of the post-casting strip construction joint, and is easy to install and disassemble. Summary of the invention

[0005] The purpose of the present invention is to provide a special panel for post-casting strip construction formwork to solve the technical problem in the prior art that it is difficult to synchronously pre-embed a degradable pipe at a predetermined position in a construction joint during post-casting strip concrete pouring construction. The preferred technical solution among the many technical solutions provided by the present invention can produce a number of technical effects as described below.

[0006] To achieve the above object, the present invention provides the following technical solutions:

[0007] The special panel for post-casting strip construction template provided by the present invention comprises:

[0008] A plate body, the plate body is used to block the pouring slurry of the concrete structure to be poured, and the side of the plate body facing the pouring slurry in the Z direction is the plate surface;

[0009] The first groove is concavely arranged on the board surface, and the degradable tube embedded in the first groove is installed on the board body.

[0010] Based on the above technical solution, the present invention can also be improved as follows.

[0011] As a further improvement of the present invention, the first groove is a U-shaped groove, the notch diameter of the first groove is larger than the diameter of the degradable tube, and the groove depth of the first groove is equal to the radius of the degradable tube.

[0012] As a further improvement of the present invention, an extension groove extending along the Y direction of the plate body is further provided on the plate surface, and the extension groove is connected to the first groove and is used to extend the two ends of the degradable tube outside the concrete structure.

[0013] The degradable tube is installed or limited on the panel by the first groove and its extension groove provided on the panel surface. After the concrete is poured and hardened, the panel is removed and the post-casting strip is poured, the degradable tube is just embedded in the post-casting strip construction joint. After the degradable tube is degraded, a reserved channel is formed in the post-casting strip construction joint, providing necessary conditions for subsequent waterproof sealing construction.

[0014] As a further improvement of the present invention, at least one end surface of the plate body in the Y direction is recessed inward to form a second groove, the second groove is arranged corresponding to the concrete steel mesh bars constituting the concrete structure to be cast, and the plate body is connected to the concrete steel mesh bars via the second groove.

[0015] As a further improvement of the present invention, the second groove is a U-shaped straight groove that passes through the plate body along the Z direction, the groove diameter of the second groove is not less than the diameter of the steel mesh bar, and the groove depth of the second groove is equal to the radius of the steel mesh bar.

[0016] As a further improvement of the present invention, at least a portion of the first groove is a linear groove extending along the X direction of the plate body.

[0017] The first groove of the linear groove can provide a relatively gentle and relaxed installation environment, which is helpful for the installation of the degradable pipe and can also reduce the resistance to the flow of slurry during the later grouting.

[0018] As a further improvement of the present invention, at least a portion of the first groove may also be a curved groove extending along the X direction of the plate body.

[0019] As a further improvement of the present invention, at least one end surface of the plate body in the Y direction is recessed inwards to form a second groove;

[0020] The second grooves are arranged corresponding to the concrete steel mesh bars constituting the concrete structure to be cast, and the plate body is connected to the concrete steel mesh bars via the second grooves.

[0021] As a further improvement of the present invention, the two end surfaces of the plate body are both provided with the second grooves, and each end surface is provided with at least two second grooves.

[0022] As a further improvement of the present invention, the second groove is a U-shaped straight groove that passes through the plate body along the Z direction, the groove diameter of the second groove is not less than the diameter of the steel mesh bar, and the groove depth of the second groove is equal to the radius of the steel mesh bar.

[0023] As a further improvement of the present invention, the overall panel after the three special panels are assembled from top to bottom is provided with four first grooves, wherein three of the first grooves are formed on the middle plate body, and one is provided at the bottom edge of the special panel at the lower position, and after the pre-buried degradable tube is degraded, a plurality of cavities at different positions are formed at the position of the first groove, and different materials are selectively sealed according to the positions of these cavities to form a composite waterproof structure of different materials;

[0024] In addition, among the three special panels assembled from top to bottom, the top end surface of the special panel at the top position and the bottom end surface of the special panel at the bottom position are not provided with the second groove.

[0025] As a further improvement of the present invention, the plate surface is also provided with outwardly protruding convex points, and the convex points can form an interlocking structure with the casting surface formed after the casting slurry solidifies.

[0026] Compared with the prior art, the special panel for post-cast strip construction formwork and the use method provided by the preferred embodiment of the present invention have the following outstanding advantages.

[0027] (1) Compared with the post-casting construction formwork panel in the prior art, this construction formwork panel has low cost and is easier to install. It does not require welding of water-stop steel plates. After the construction is completed, the concrete structure layer can be cast in one go without the need for layered casting. Compared with the existing construction formwork panel, this construction formwork panel is also easier to dismantle.

[0028] (2) The construction template panel can simultaneously complete the placement of degradable tubes in the construction joints during the formation of the construction joints of the post-cast zone, without the need for additional construction of the placement of degradable tubes. This simplifies the construction steps, shortens the construction period, and provides convenience for the rapid installation of the reverse construction waterproof sealing structure of the post-cast zone construction joints.

[0029] (3) The special panel used for the post-casting strip construction template can simultaneously complete the accurate retention of the degradable tube at the predetermined position in the construction joint during the formation process of the post-casting strip construction joint, and complete the accurate installation of the degradable tube at the predetermined position in the construction joint, which provides convenience for the accurate installation of the reverse construction waterproof sealing structure of the post-casting strip construction joint.

[0030] (4) The construction template panel is a special panel designed to match the overall construction of the reverse construction waterproof sealing structure of the post-casting joint. In addition to considering the characteristics of the template panel, its construction also fully considers the design and construction requirements of the waterproof sealing structure, and has outstanding customized special features, which is essentially different from the existing construction template panels. The template panel is set with a second groove and a first groove in accordance with the construction design requirements of the waterproof sealing structure. The second groove is combined with the steel mesh ribs for panel assembly and fixation, and its size, number and spacing are designed in accordance with the size and spacing of the ribs; the first groove is used to carry and install the degradable tube, and its size, number, shape and position are designed in accordance with the size, number, shape and position of the reserved channel formed after the degradable tube is degraded in the construction joint.

[0031] (5) Compared with the prior art that uses water-stop steel plates to rigidly seal construction joints, the reverse waterproof sealing structure after installation adopts a multi-layer sealing method that combines flexible sealing and rigid sealing, and uses a reserved closed cavity to detect and monitor the waterproof sealing of construction joints. This not only solves the problem that the water-stop steel plate is not sealed properly, is prone to leakage, and cannot be repaired without loss after the problem occurs, but also solves the problem that the waterproof sealing of construction joints cannot be detected and monitored. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0033] Figure 1 It is a structural schematic diagram of a special panel for a post-casting strip construction template of the present invention;

[0034] Figure 2 yes Figure 1 The main view of

[0035] Figure 3 yes Figure 1 Side view of

[0036] Figure 4 It is a structural schematic diagram of another embodiment of the special panel for post-casting strip construction formwork of the present invention;

[0037] Figure 5 It is a structural schematic diagram of another embodiment of the special panel for post-casting strip construction template of the present invention;

[0038] In the figure: 1, panel; 2, second groove; 3, first groove. DETAILED DESCRIPTION

[0039] To make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described in detail below. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other implementation methods obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention.

[0040] In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", "third", etc., are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.

[0041] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0042] The post-cast strip involves the bottom plate, wall and top plate. For the convenience of explanation, the technical solution of the present invention is specifically described below with reference to the drawings, taking the construction of the post-cast strip of the bottom plate as an example. The situation of the top plate and the wall can be implemented for reference.

[0043] like Figure 1-5 As shown, the present invention provides a special panel for post-casting strip construction formwork provided by the present invention, and the construction formwork panel includes a plate body 1 which is in the shape of a plate as a whole, and the plate body 1 has a certain thickness and extends a certain length in both the Y direction and the X direction.

[0044] Specifically, Figure 1-Figure 3 As shown, at least one end of the plate body 1 in the Y direction is recessed inward and forms a second groove 2 for fixing the panel, and the number of the second grooves 2 located at any end of the plate body 1 in the Y direction is at least two; one side portion of the plate body 1 in the Z direction is recessed inward and forms a plurality of first grooves 3, and the two ends of the first groove 3 extend to the two sides of the plate body 1 in the X direction respectively.

[0045] It should be noted that the Y direction and the X direction are both perpendicular to the Z direction of the plate 1 .

[0046] The plate body 1 is used to separate two different construction areas. The plate body 1 is installed and fixed by the second groove 2 provided on the plate body 1, and the first groove 3 is used for semi-embedded installation of the degradable pipe.

[0047] In this embodiment, the first groove 3 is concavely arranged on the side of the plate body 1 facing the concrete in the Z direction. Figure 1 and Figure 3 shown.

[0048] The X direction, Y direction, and Z direction are perpendicular to each other. Figure 1 shown.

[0049] This structure is used to ensure that the first grooves 3 are arranged in sequence along the Y direction of the plate body 1 .

[0050] As an optional implementation, the first groove 3 is a linear groove structure.

[0051] The first groove 3 of the linear groove can provide a relatively gentle and relaxed installation environment, which is helpful for pipeline installation and reduces the resistance of liquid flow as much as possible.

[0052] As an optional implementation, the first groove 3 is parallel to the X direction.

[0053] In order to facilitate the installation and fixation of the construction template panel, as an optional implementation, both ends of the panel in the Y direction are formed with a second groove 2, such as Figure 1 and Figure 2 At this time, the construction template panel can be half-embedded into the corresponding steel grid ribs through the second grooves 2 at both ends of the panel in the Y direction to achieve fixed connection of the plate body 1. To prevent the plate body from sliding, reinforcing ribs can be set diagonally on the plate body 1, and it can also be used in conjunction with the template support structure.

[0054] Or, if Figure 4As shown, the upper end face of the plate body 1 in the Y direction is provided with a second groove 2, and the lower end face is not provided with a second groove 2. The number of the above-mentioned first grooves 3 is three, and one of the first grooves 3 is provided at the edge of the lower end face of the plate body 1 in the Y direction. The second groove 2 provided on the upper end face is used to semi-embed the steel mesh bars to fix the plate body 1. The lower end face is directly in contact with the bottom plate cushion layer without steel mesh bars, so the second groove 2 is not provided. The first groove 3 is provided at the edge of the lower end face in order to set a degradable pipe at this position, so as to facilitate the later sealing operation of the contact gap between the construction joint of the post-casting belt and the cushion layer.

[0055] The number and arrangement positions of the second grooves 2 and the first grooves 3 can be flexibly adjusted according to actual needs, and this embodiment does not limit them.

[0056] In addition to the above structure, the first grooves 3 may also be configured as curved groove structures arranged in sequence along the Y direction.

[0057] In addition to the above structure, the surface of the plate body 1 may be fixed with related fixings, which are used to further fix the conduit to prevent the conduit from falling off the surface of the plate body 1. The above fixings may be related structures disclosed in the prior art, such as clamps, etc., and their specific structures and installation positions are not limited here.

[0058] In addition, in order to enhance the firmness of the contact surface between the successively poured concrete surfaces, a protruding point protruding outward can be provided on the surface of the plate body 1 on the side where the first groove 3 is provided, so as to construct an interlocking structure between the casting surfaces formed after the concrete is poured successively and solidified.

[0059] Specifically, in this embodiment, the convex points are dot-shaped structures with a diameter of 2 mm and a height of 1 mm, which are distributed on the surface of the side of the plate body 1 that contacts the concrete except the first groove 3. Generally speaking, the convex points can be arranged randomly or in an array, and the interval between two adjacent convex points is about 10 mm.

[0060] Considering that the construction area to be poured may have different depths, if the above depth is greater than the maximum height of the construction formwork panel, multiple construction formwork panels need to be spliced ​​together.

[0061] In some embodiments, the number of the construction template panels for splicing is three, and the number and distribution positions of the first grooves 3 can be adjusted according to actual needs.

[0062] like Figure 5As shown, at this time, the three construction template panels are spliced ​​in sequence along the vertical direction, and the second grooves 2 on the two adjacent construction template panels are arranged oppositely and form perforations for accommodating the steel mesh of the construction site. At the same time, the steel mesh can also help fix the construction template panels. Figure 5 In the embodiment, a first groove 3 extending in the horizontal direction is provided at the bottom of the construction template panel located at the bottom, three mutually parallel first grooves 3 are provided on the construction template panel located in the middle, and no first groove 3 is provided on the construction template panel located at the top. The degradable tube is half-embedded in the first groove 3 for pre-embedding, and the pre-embedded degradable tube can form multiple cavities at different positions at the position of the first groove 3 after degradation, and different materials are selectively sealed according to the positions of these cavities to form a composite waterproof structure of different materials.

[0063] In addition, a plurality of second grooves 2 may be provided on the top of the upper construction template panel, such as Figure 5 As shown, the second groove 2 may not be provided.

[0064] In addition, the plate body 1 is provided with an extension groove extending along the Y direction of the plate body 1 on one side of the plate body 1 provided with the first groove 3, and the extension groove is connected with the first groove 3, and is used to extend the two ends of the degradable tube outside the concrete structure. The cross section of the extension groove is the same as that of the first groove 3.

[0065] It should be noted that the above Figure 1-Figure 5 The relevant dimensions and proportions in the figure are for illustration only. The thickness, width, length of the plate 1 and the specific dimensions of the second groove 2, the first groove 3 and the related protrusions thereon can be adjusted according to the specific construction design. The above drawings are not intended to limit the protection scope of the relevant embodiments.

[0066] It can be understood that the special panel for the post-casting strip construction template provided in this embodiment can be conveniently installed at the relevant position, and can also quickly realize the installation and positioning of the degradable pipes that need to be embedded, so as to facilitate the sealing and waterproofing construction at the construction joint. Compared with the traditional construction template panel, the construction template panel is a special panel designed to match the waterproof sealing structure construction of the post-casting strip construction joint inverse method. In addition to considering the characteristics of the template panel, its construction also fully considers the design and construction requirements of the waterproof sealing structure, and has outstanding customized special features.

[0067] The specific method for using the special panel of the present invention comprises the following steps:

[0068] Step S1: Based on the design requirements, the special panel of the construction template and the degradable pipe are installed at the corresponding positions of the concrete steel mesh bars. At this time, the special panel of the construction template is separated into several casting areas;

[0069] Step S2: performing concrete pouring construction on all separated pouring areas respectively;

[0070] Step S3: For the hardened casting area, the special panel of the construction template is removed and the degradable pipe is left, and the post-casting zone concrete pouring construction is carried out, and the operation of pre-embedding the degradable pipe during the post-casting zone pouring construction is completed.

[0071] Through the above-mentioned installation method, the installation and fixation of the construction template panel and the degradable pipe can be conveniently and quickly realized, which is conducive to the rapid progress of subsequent construction.

[0072] In addition, in step S1, the installation order of the special panel and the degradable tube of the construction template is as follows:

[0073] Step S11: Based on the design requirements, the special panel of the construction template is fixedly installed on the corresponding position of the concrete steel mesh bar through the second groove to complete the assembly and fixing operation of the special panel of the construction template. At this time, the special panel of the construction template is separated into several casting areas;

[0074] Step S12: Based on the pre-set sealing and waterproof design requirements, the degradable tube is half-embedded and fixed in the first groove. At this time, both ends of all the degradable tubes are extended outside the casting area through the extension groove, completing the pre-embedded installation of the degradable tube.

[0075] Alternatively, step S1 may also be performed in the following order:

[0076] Step S11: based on the pre-set sealing and waterproof design requirements, the degradable tube is half-embedded and fixed in the first groove;

[0077] Step S12: Based on the design requirements, the special panel of the construction template is fixedly installed on the corresponding position of the concrete steel mesh bar through the second groove to complete the assembly and fixation of the special panel of the construction template. At this time, the special panel of the construction template is separated into several casting areas. At this time, both ends of all the degradable tubes are extended outside the casting area through the extension groove.

[0078] During actual installation, the construction formwork panel can be installed at the corresponding position first, and then the degradable tube can be installed on the construction formwork panel; or, the degradable tube can be installed on the construction formwork panel, and then the construction formwork panel can be installed at the corresponding position of the concrete steel mesh bar.

[0079] In addition, the above-mentioned panel can be used as a construction formwork alone without adding additional formwork support and fixing devices, and can also be fixed and assembled in combination with formwork support devices and other devices according to construction requirements.

[0080] In addition, according to the specific construction design requirements, special panels can be used as a whole or only locally at predetermined locations.

[0081] According to the method of using the special panel for the post-cast strip construction formwork, during the process of forming the construction joint of the post-cast strip, the degradable tube can be retained in the construction joint simultaneously, without the need to carry out additional construction of inserting the degradable tube, which simplifies the construction steps, shortens the construction period, and provides convenience for the rapid installation of the reverse waterproof sealing structure of the post-cast strip construction joint.

[0082] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A special panel for post-casting strip construction formwork, characterized in that: include: A plate body, the plate body is used to block the pouring slurry of the concrete structure to be poured, and the side of the plate body facing the pouring slurry in the Z direction is the plate surface; The first groove is concavely arranged on the board surface, and the degradable tube embedded in the first groove is installed on the board body.

2. The special panel for post-casting strip construction formwork according to claim 1 is characterized in that: The first groove is a U-shaped groove, the groove diameter of the first groove is larger than the diameter of the degradable tube, the groove depth of the first groove is equal to the radius of the degradable tube, the first groove extends along the X direction of the plate body and at least part of the first groove is a linear groove and / or a curved groove.

3. The special panel for post-casting strip construction formwork according to claim 1 is characterized in that: The plate surface is also provided with an extension groove extending along the Y direction of the plate body, and the extension groove is communicated with the first groove and is used to extend the two ends of the degradable tube to the outside of the concrete structure.

4. The special panel for post-casting strip construction formwork according to claim 1 is characterized in that: At least one end surface of the plate body in the Y direction is recessed inwards to form a second groove; The second grooves are arranged corresponding to the concrete steel mesh bars constituting the concrete structure to be cast, and the plate body is connected to the concrete steel mesh bars via the second grooves.

5. The special panel for post-casting strip construction formwork according to claim 4 is characterized in that: The second groove is a U-shaped straight groove that passes through the plate body along the Z direction. The groove diameter of the second groove is not less than the diameter of the steel mesh bar, and the groove depth of the second groove is equal to the radius of the steel mesh bar.

6. The special panel for post-casting strip construction formwork according to claim 1, characterized in that: The plate surface is also provided with outwardly protruding convex points, and the convex points can form an interlocking structure with the casting surface formed after the casting slurry solidifies.

Citation Information

Cited By

  • Special panel for post-cast strip construction formwork and using method

    CN118148350A