Oil unloading equipment for oil drum
By using heating structure and steam nozzle in the oil drum oil discharge equipment to heat and melt the solidified grease in the flange oil drum, the problems of time-consuming and labor-intensive oil discharge and waste in the prior art are solved, and efficient grease automatic Shedding and barrel cleaning.
Patent Information
- Application Number
- CN202420793993.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-17
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-04-17
AI Technical Summary
In the prior art, waste grease unloading method for solidifying in flange oil barrels is time-consuming and labor-intensive, low efficiency and wastes a lot of hot water.
Design an oil barrel oil discharge equipment, including heating structure and valve switch, heat and melt the solid oil and grease in the oil barrel through steam pipes and steam nozzles, and use the design of oil inlet pipes and oil discharge ports to achieve automatic peeling of grease and discharge, reduce manual removal operations, improve oil unloading efficiency, and simplify barrel cleaning.
It greatly improves the efficiency of oil unloading, reduces the action of manually removing grease, reduces the use of hot water, and ensures that the barrel body is clean.
Smart Images

Figure CN222024086U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field related to the treatment of kitchen waste grease, and in particular to an oil drum unloading device. Background Art
[0002] When dealing with waste kitchen grease, flange oil barrels are generally used as storage devices, and the amount of grease in the flange oil barrels needs to be collected and transported when it reaches a certain level. However, due to the low frequency of collection and transportation, after a certain period of time, the grease in some flange oil barrels solidifies due to cooling, and the solidified waste grease needs to be unloaded to get out of the flange oil barrel. In the related art, the method of unloading solidified waste grease from flange oil barrels is as follows: the grease is soaked and melted by adding hot water into the barrel, and the upper layer of grease is poured out after melting. In order to speed up the unloading efficiency, a shovel is usually used to manually shovel out the soaked and melted grease in the barrel, and the actions of adding water, soaking, and shoveling out are repeated until all the grease is poured out. However, when shoveling out manually, it is inevitable that some grease adheres to the barrel body, and it needs to be manually rinsed and wiped with hot water. Therefore, the above-mentioned unloading method is not only time-consuming and labor-intensive, but also inefficient and wastes a lot of hot water. Utility Model Content
[0003] The utility model provides an oil drum unloading device, which is used to solve the problem that the oil unloading method in the related technology is not only time-consuming and labor-intensive, but also low in efficiency and wastes a large amount of hot water.
[0004] The utility model provides an oil drum unloading device, comprising:
[0005] The equipment body is provided with an oil unloading chamber for accommodating an oil barrel and an oil inlet pipeline for discharging grease, a side wall of the oil unloading chamber is provided with an oil unloading port, the oil unloading port is used to be fixedly matched with the outlet end of the oil barrel, and the oil unloading port is communicated with the oil inlet pipeline;
[0006] A heating structure, used for heating and melting the solid grease in the oil barrel, wherein the heating structure is arranged on the equipment body and is located between the oil unloading port and the oil inlet end of the oil inlet pipeline;
[0007] A valve switch is arranged on one side of the device body, and is used to control the start and stop of the heating structure.
[0008] According to an oil drum unloading device provided by the utility model, the heating structure comprises:
[0009] A heating cavity, one end of which is connected to the oil unloading port, and the other end of which is connected to the oil inlet end of the oil inlet pipeline;
[0010] A steam pipe, used for conveying steam, the steam pipe is arranged in the heating cavity, and the valve switch is used for controlling the on and off of the steam pipe;
[0011] A steam nozzle is used for spraying steam toward the oil unloading port, and the steam nozzle is connected with the steam pipe.
[0012] According to the oil drum unloading equipment provided by the utility model, the steam nozzle is a direct spray nozzle, and the center line of the steam nozzle coincides with the center line of the oil unloading port.
[0013] According to an oil drum unloading device provided by the utility model, the heating structure comprises a diffuser spray nozzle, the diffuser spray nozzle is connected to the steam pipe, and the spraying area of the diffuser spray nozzle at least covers the oil inlet end of the oil inlet pipeline.
[0014] According to an oil drum unloading device provided by the utility model, there are multiple oil unloading ports, multiple oil inlet pipes, and multiple groups of heating structures, wherein each of the oil inlet pipes is connected to two of the oil unloading ports, and the oil inlet pipes correspond to the heating structures one by one.
[0015] According to the oil drum unloading equipment provided by the utility model, each group of the heating structure has two steam nozzles, and each steam nozzle is arranged in a one-to-one correspondence with each oil unloading port.
[0016] According to the oil drum unloading equipment provided by the utility model, in each group of the heating structures, the two steam nozzles are respectively located at the two ends of the steam pipe, and the diffuser nozzle is located in the middle of the steam pipe.
[0017] According to the oil drum unloading equipment provided by the utility model, the width of the heating cavity is gradually reduced from the oil unloading port to the oil inlet end of the oil inlet pipeline.
[0018] According to an oil barrel unloading device provided by the utility model, the width of one end of the heating cavity close to the oil unloading port is greater than the width of the oil unloading port, and the width of one end of the heating cavity close to the oil inlet pipe is adapted to the oil inlet end of the oil inlet pipe.
[0019] According to an oil drum unloading device provided by the utility model, a grid structure is provided on the device body at the oil inlet end corresponding to the oil inlet pipeline.
[0020] The utility model provides an oil barrel unloading device. When in use, the operator turns the flange oil barrel filled with waste grease upside down into the oil unloading port, operates the valve switch, heats and melts the grease blocks in the oil barrel through the heating structure, and falls off to the oil inlet pipeline for discharge to the next processing process. Compared with the oil unloading method in the related art, the waste grease blocks solidified in the barrel are unloaded by heating and melting, which greatly improves the oil unloading efficiency and eliminates the action of manually shoveling out the grease. When the barrel body is heated, the grease stains adhered to the barrel body are easy to scrub, which is conducive to ensuring the cleanliness of the barrel body and reduces the use of hot water. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the technical solutions in the present invention or the prior art, a brief introduction will be given below to the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0022] Figure 1 This is a schematic diagram of the overall structure of the oil drum unloading equipment provided by the utility model;
[0023] Figure 2 The utility model is a schematic diagram showing part of the structure of the oil drum unloading equipment.
[0024] Reference numerals:
[0025] 100, equipment body; 110, oil unloading chamber; 111, oil unloading port; 120, oil inlet pipeline; 130, grid structure;
[0026] 200, heating structure; 210, steam chamber; 220, steam pipe; 230, steam nozzle; 240, diffuser nozzle; 300, valve switch. DETAILED DESCRIPTION
[0027] In order to make the purpose, technical solution and advantages of the utility model clearer, the technical solution of the utility model will be described clearly and completely in conjunction with the drawings in the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0028] Combine the following Figure 1-Figure 2 The utility model is described in detail.
[0029] Reference Figure 1 and Figure 2According to the utility model, an oil barrel unloading device is provided, including an equipment body 100, a heating structure 200 and a valve switch 300. The equipment body 100 is provided with an oil unloading chamber 110 for accommodating the oil barrel and an oil inlet pipe 120 for discharging the grease. The oil unloading chamber 110 is used to accommodate the oil barrel, and the oil unloading port 111 is used to be fixedly matched with the outlet end of the oil barrel, and the oil unloading port 111 is connected to the oil inlet pipe 120; the heating structure 200 is used to heat and melt the solid grease in the oil barrel, and the heating structure 200 is arranged on the equipment body 100, and the heating structure 200 is located between the oil unloading port 111 and the oil inlet end of the oil inlet pipe 120; the valve switch 300 is arranged on one side of the equipment body 100, and the valve switch 300 is used to control the start and stop of the heating structure 200.
[0030] The utility model provides an oil barrel unloading device. When in use, the operator turns the flange oil barrel filled with waste grease upside down into the oil unloading port 111, operates the valve switch 300, heats and melts the grease blocks in the oil barrel through the heating structure 200, and falls off to the oil inlet pipeline 120 for discharge to the next processing process. Compared with the oil unloading method in the related art, the waste grease blocks solidified in the barrel are unloaded by heating and melting, which greatly improves the oil unloading efficiency and eliminates the action of manually shoveling out the grease. When the barrel body is heated, the grease adhered to the barrel body is easy to scrub, which is conducive to ensuring the cleanliness of the barrel body and reduces the use of hot water.
[0031] It is understandable that, referring to Figure 1 and Figure 2 In the embodiment of the utility model, the heating structure 200 includes a heating cavity 210, a steam pipe 220 and a steam nozzle 230. One end of the heating cavity 210 is connected to the oil unloading port 111, and the other end of the heating cavity 210 is connected to the oil inlet end of the oil inlet pipeline 120. The steam pipe 220 is used to transport steam. The steam pipe 220 is arranged in the heating cavity 210. The valve switch 300 is used to control the on and off of the steam pipe 220. The steam nozzle 230 is used to spray steam to the oil unloading port 111. The steam nozzle 230 is connected to the steam pipe 220. With the above structure, the valve switch 300 is turned, and the steam pipe 220 transports steam to the steam nozzle 230. The grease block is heated and melted by the steam nozzle 230. During the heating process, the barrel body can be manually shaken to accelerate the shedding of the grease block and improve the heating efficiency. The heating time and temperature can be conveniently controlled by the valve switch 300.
[0032] It should be noted that in the embodiment of the utility model, by turning the valve switch 300, steam is allowed to enter the steam pipe 220 or the steam is stopped from entering the steam pipe 220; the diameter of the oil unloading port 111 is consistent with the diameter of the flange oil barrel, the steam pipe 220 and the steam nozzle 230 are both located below the oil unloading port 111, and the oil inlet pipeline 120 is located below the oil unloading port 111 and the steam pipe 220, and the grease in the barrel automatically falls off due to gravity.
[0033] Specifically, refer to Figure 2 In the embodiment of the utility model, the steam nozzle 230 is a direct spray nozzle, and the center line of the steam nozzle 230 coincides with the center line of the oil unloading port 111. When in use, the steam is directly sprayed to heat the center of the barrel to melt and fall off the grease block. At the same time, the grease around the barrel automatically falls off due to gravity, and the heat is concentrated. Under the same pressure, the heating distance is farther. It can be understood that the steam nozzle 230 is set 5 cm below the center of the oil unloading port 111.
[0034] It should be noted that, in the embodiment of the utility model, the steam nozzle 230, that is, the direct spray nozzle, has a spray distance that can spray to the bottom of the flange oil drum, so that the bottom of the flange oil drum is heated and melted.
[0035] Specifically, refer to Figure 2 In the embodiment of the utility model, the heating structure 200 includes a diffuser nozzle 240, which is connected to the steam pipe 220, and the spray area of the diffuser nozzle 240 at least covers the oil inlet end of the oil inlet pipe 120. With the above structure, the diffuser nozzle 240 is provided at the same time, and the oil blocks falling off the barrel are heated and melted for a second time, and flow into the oil inlet pipe 120, so as to avoid the oil residue in the heating cavity 210, and the spray range is wide, and the distance between the heated oil and the diffuser nozzle 240 is close, which is conducive to improving the processing efficiency.
[0036] Of course, in some embodiments, the heating structure 200 may also be an electric heating, radiation heating, or other structure, which is not limited here.
[0037] It is understandable that, referring to Figure 1 and Figure 2In the embodiment of the utility model, there are multiple oil unloading ports 111, multiple oil inlet pipes 120, and multiple groups of heating structures 200, wherein each oil inlet pipe 120 is connected to two corresponding oil unloading ports 111, and the oil inlet pipes 120 correspond to the heating structures 200 one by one. Through the above structure, multiple oil unloading ports 111 are heated and melted at the same time, which greatly improves the oil unloading efficiency and helps to reduce the oil unloading time. Of course, in some embodiments, there are multiple oil unloading ports 111, multiple oil inlet pipes 120, and multiple groups of heating structures 200, and the oil unloading ports 111, the oil inlet pipes 120 and the heating structures 200 correspond to each other one by one; or, three or more oil unloading ports 111 correspond to one oil inlet pipe 120, and one oil inlet pipe 120 corresponds to one or more refueling structures, which is not limited here.
[0038] It should be noted that, refer to Figure 1 and Figure 2 In the embodiment of the utility model, the number of the above-mentioned oil unloading ports 111 is six, the number of the oil inlet pipes 120 is three, and the number of the heating structures 200 is three. Of course, the above-mentioned number can also be other, which is not limited here.
[0039] Specifically, in the embodiment of the utility model, each group of heating structures 200 has two steam nozzles 230, and each steam nozzle 230 is arranged in a one-to-one correspondence with each oil discharge port 111. With the above structure, each oil discharge port 111 has a dedicated steam nozzle 230 to heat it, so the accuracy and controllability of heating can be improved, thereby making the heating process more effective and controllable. The one-to-one arrangement can ensure that each oil discharge port 111 receives the same heating treatment, avoiding the situation of uneven heat distribution, and improving heating efficiency and product quality.
[0040] Specifically, in the embodiment of the utility model, the oil drum unloading equipment is also provided with a stainless steel cover, which is provided on the multiple oil unloading ports 111 to keep the heating cavity 210 closed when not in use to prevent steam from flowing out.
[0041] Specifically, refer to Figure 2 In the embodiment of the utility model, in each group of heating structures 200, two steam nozzles 230 are respectively located at the two ends of the steam pipe 220, and the diffuser nozzle 240 is located in the middle of the steam pipe 220. The above structure is simple and easy to assemble and maintain.
[0042] Specifically, refer to Figure 2In the embodiment of the utility model, the width of the heating cavity 210 is gradually reduced from the oil unloading port 111 to the oil inlet end of the oil inlet pipe 120. Through the above arrangement, the reduced chamber width of the heating cavity 210 makes the grease tend to flow toward the direction of the oil inlet pipe 120, thereby more effectively guiding the fluid flow and improving the oil unloading efficiency. It should be noted that the cross-sectional shape of the above heating cavity 210 is an inverted trapezoidal structure.
[0043] Specifically, refer to Figure 2 In the embodiment of the utility model, the width of one end of the heating cavity 210 near the oil unloading port 111 is greater than the width of the oil unloading port 111, and the width of one end of the heating cavity 210 near the oil inlet pipe is adapted to the oil inlet end of the oil inlet pipe 120. With the above structure, the width of one end of the heating cavity 210 near the oil unloading port 111 is greater than the width of the oil unloading port 111, which is conducive to slowing down the fluid velocity of the grease, thereby reducing the pressure of the fluid impacting the oil unloading port 111, helping to reduce the possibility of overflow or splashing, improving the stability of the fluid, facilitating the receiving of the fallen grease, and guiding it to the oil inlet end of the oil inlet pipe 120. The structure is simple, which is conducive to steam heating and melting the grease.
[0044] It is also understandable that, with reference to Figure 2 In the embodiment of the utility model, a grille structure 130 is provided at the oil inlet end of the oil inlet pipe 120 on the equipment body 100, which is helpful to prevent debris from flowing into the oil inlet pipe 120. It can be understood that when the grille structure 130 blocks a certain amount of debris, the operator cleans it; or when the steam nozzle 230 and the diffuser nozzle 240 work for a certain period of time, the operator performs maintenance and adjustment.
[0045] It should be noted that in the embodiment of the utility model, when in use, the operator turns the flange oil barrel filled with waste grease upside down into the oil unloading port 111, turns the steam valve switch 300, so that the steam nozzle 230 heats and melts the grease block, and manually shakes the barrel body during the heating process to accelerate the grease shedding; after the grease falls off, it falls above the grid structure 130, and the diffuser nozzle 240 above the grid structure 130 heats the grease block at the same time, and flows into the oil inlet pipe 120. After the oil unloading is completed, the melted grease attached to the flange oil barrel body is wiped with a rag to keep the barrel body clean and tidy.
[0046] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the various embodiments of the utility model.
Claims
1. An oil drum unloading equipment, It is characterized in that include: The equipment body (100) is provided with an oil unloading chamber (110) for accommodating an oil barrel and an oil inlet pipeline (120) for discharging grease, a side wall of the oil unloading chamber (110) is provided with an oil unloading port (111), the oil unloading port (111) is used to be fixedly matched with the outlet end of the oil barrel, and the oil unloading port (111) is communicated with the oil inlet pipeline (120); A heating structure (200) is used to heat and melt the solid grease in the oil barrel, the heating structure (200) is arranged on the equipment body (100), and the heating structure (200) is located between the oil unloading port (111) and the oil inlet end of the oil inlet pipeline (120); A valve switch (300), wherein the valve switch (300) is arranged on one side of the device body (100), and the valve switch (300) is used to control the start and stop of the heating structure (200).
2. The oil drum unloading equipment according to claim 1, It is characterized in that The heating structure (200) comprises: A heating cavity (210), one end of the heating cavity (210) being in communication with the oil unloading port (111), and the other end of the heating cavity (210) being in communication with the oil inlet end of the oil inlet pipeline (120); A steam pipe (220) for conveying steam, the steam pipe (220) being arranged in the heating cavity (210), and the valve switch (300) being used for controlling the on and off of the steam pipe (220); A steam spray head (230) is used for spraying steam toward the oil unloading port (111), and the steam spray head (230) is connected to the steam pipe (220).
3. The oil drum unloading equipment according to claim 2, It is characterized in that The steam spray head (230) is a direct spray head, and the center line of the steam spray head (230) coincides with the center line of the oil unloading port (111).
4. The oil drum unloading equipment according to claim 2, It is characterized in that The heating structure (200) comprises a diffuser nozzle (240), the diffuser nozzle (240) being in communication with the steam pipe (220), and the spraying area of the diffuser nozzle (240) at least covering the oil inlet end of the oil inlet pipeline (120).
5. The oil drum unloading equipment according to claim 4, It is characterized in that There are a plurality of oil unloading ports (111), a plurality of oil inlet pipes (120), and a plurality of heating structures (200), wherein each of the oil inlet pipes (120) is correspondingly connected to two of the oil unloading ports (111), and the oil inlet pipes (120) correspond one to one to the heating structures (200).
6. The oil drum unloading equipment according to claim 5, It is characterized in that Each group of the heating structures (200) has two steam spray heads (230), and each steam spray head (230) and each oil discharge port (111) are arranged in a one-to-one correspondence.
7. The oil drum unloading equipment according to claim 6, It is characterized in that In each group of the heating structures (200), the two steam nozzles (230) are respectively located at two ends of the steam pipe (220), and the diffuser nozzle (240) is located in the middle of the steam pipe (220).
8. The oil drum unloading equipment according to claim 2, It is characterized in that The width of the heating cavity (210) is gradually reduced from the position of the oil unloading port (111) to the oil inlet end of the oil inlet pipeline (120).
9. The oil drum unloading equipment according to claim 8, It is characterized in that The width of one end of the heating cavity (210) close to the oil unloading port (111) is greater than the width of the oil unloading port (111), and the width of one end of the heating cavity (210) close to the oil inlet pipeline is compatible with the oil inlet end of the oil inlet pipeline (120).
10. The oil drum unloading equipment according to claim 1, It is characterized in that A grid structure (130) is provided on the equipment body (100) at the oil inlet end corresponding to the oil inlet pipeline (120).