Highway subgrade anti-settlement device

By adopting multiple pile columns and ejecting columns in the highway roadbed settlement device, and using structures such as reinforcement rods and anti-blocking to improve the contact area and stability between pile columns and roadbeds, the poor stability of pile foundations in the prior art is solved. The problem has significantly reduced the local settlement of highways.

CN222024812UActive Publication Date: 2024-11-19CNNC HUACHEN ENG MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323544899.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-25
Publication Date
2024-11-19
Estimated Expiration
2033-12-25

AI Technical Summary

Technical Problem

The existing highway subgrade settlement device improves the tightness of the soil in the subgrade by pile driving, but the stability of the pile foundation column is poor and local settlement is prone to occur.

Method used

Multiple pile columns and ejection columns are used. The outer wall of the pile column is equipped with reinforcement holes and installation grooves, and built-in reinforcement rods and anti-exit blocks. The contact area and stability of the pile columns and roadbed are increased through the plug-in of the ejection columns, and the contact area and stability of the pile columns and roadbeds are increased. Connecting rope and elastic cushion improve fixation.

Benefits of technology

The smoothness and stability of pile column insertion into the roadbed is improved, the local settlement of highways is reduced, and the overall stability of the roadbed is enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222024812U_ABST
    Figure CN222024812U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of subgrade settlement prevention, and provides a highway subgrade settlement prevention device which comprises a plurality of piles and a plurality of ejection columns, the piles are all inserted into a subgrade, and mounting grooves allowing the ejection columns to be inserted are formed in the piles; a plurality of reinforcing holes are formed in the outer wall of the pile column, and all the reinforcing holes are formed in the circumferential direction of the outer circumferential wall of the pile column at intervals; reinforcing rods are movably mounted in the reinforcing holes, and are positioned in the mounting grooves in a normal state; and when the ejection columns are inserted into the mounting grooves, the ejection columns force the reinforcing rods to be inserted into the roadbed. According to the highway subgrade anti-settlement device, the ejection columns can force all the reinforcing rods to be inserted into the subgrade, the contact area of the pile columns and the subgrade is increased, the stability of the pile columns in the subgrade is improved, and the situation of local settlement of a highway is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of roadbed anti-settlement, and in particular to a highway roadbed anti-settlement device. Background Art

[0002] When a highway is used for a long time and bears high loads, it will often cause the entire roadbed to sink, which will make the highway uneven. When vehicles travel on the uneven road surface, safety accidents are prone to occur due to the bumps of the vehicles. Therefore, highway roadbed anti-settling devices have appeared.

[0003] Existing highway roadbed settlement devices generally use piling to improve the compactness of the soil in the roadbed, but the pile foundation columns are generally round. After being driven into the roadbed, they remain stable through the friction between the pile wall and the soil. The stability is poor and local settlement is prone to occur. Utility Model Content

[0004] In order to improve the stability of piles in the roadbed, the present application provides a highway roadbed anti-settling device.

[0005] The present application provides a highway subsidence prevention device that adopts the following technical solution:

[0006] A highway roadbed anti-settling device comprises a plurality of piles and a plurality of ejector columns, wherein the piles are all inserted into the roadbed, and the piles are provided with mounting grooves for the ejector columns to be inserted into; the outer wall of the piles is provided with a plurality of reinforcement holes, and all the reinforcement holes are arranged at intervals along the circumferential direction of the outer wall of the piles; reinforcement rods are movably installed in the reinforcement holes, and all the reinforcement rods are normally located in the mounting grooves; when the ejector columns are inserted into the mounting grooves, the ejector columns force the reinforcement rods to be inserted into the roadbed.

[0007] By adopting the above technical solution, when the pile is inserted into the roadbed, the reinforcement rods are all located inside the shell to improve the smoothness of the pile insertion into the roadbed and improve the efficiency of pile installation. After the pile is installed in the roadbed, the ejector column is inserted into the installation groove, and the ejector column can force all the reinforcement rods to be inserted into the roadbed, increase the contact area between the pile and the roadbed, increase the stability of the pile in the roadbed, and reduce the occurrence of local settlement of the highway.

[0008] Optionally, an anti-dropping block is fixed to one end of the reinforcement rod close to the pile foundation, and all the anti-dropping blocks are tied together by a connecting rope.

[0009] By adopting the above technical solution and setting an anti-detachment block, the situation where the reinforcement rod is detached from the pile column can be reduced, thereby maintaining the stability of the pile column in the roadbed; by setting a connecting rope, the situation where the reinforcement rod is detached from the pile column when the pile column is inserted into the roadbed can be reduced, and when the ejector column is inserted into the installation groove, the ejector column can expand the connecting rope and break it, thereby improving the smoothness of the ejector column being inserted into the installation groove.

[0010] Optionally, the anti-slip block is provided with a cut surface, and the cut surfaces of all the anti-slip rods are enclosed to form a guide groove for the ejection column to be inserted.

[0011] By adopting the above technical solution and providing the guide groove, the ejection column is further facilitated to be smoothly inserted into the adjacent anti-slip block.

[0012] Optionally, a plurality of grooves are provided on the surface of the reinforcement rod.

[0013] By adopting the above technical solution and providing the groove, the contact area of ​​the reinforcement rod inserted into the roadbed can be increased, and the stability of the pile foundation inserted into the roadbed can be improved.

[0014] Optionally, an elastic block is disposed on the outer wall of the reinforcement rod, and an elastic groove for the elastic block to be engaged is opened on the inner wall of the reinforcement hole.

[0015] By adopting the above technical solution, the clamping cooperation between the elastic clamping block and the elastic clamping groove can improve the stability of the reinforcement rod fixed to the pile foundation and reduce the free movement of the reinforcement rod in the reinforcement hole when the pile foundation is inserted into the roadbed.

[0016] Optionally, the reinforcement hole is arranged to be inclined upward at one end close to the mounting groove.

[0017] By adopting the above technical solution, the reinforcement hole is set at an angle, that is, when the reinforcement rod is inserted into the reinforcement hole, the extension direction of the reinforcement rod is staggered with the extension direction of the pile column; the smoothness of the reinforcement rod insertion is improved, and the stability of the pile column inserted into the roadbed is improved.

[0018] Optionally, two adjacent piles are connected by a connecting plate, and the connecting plate can be detachably mounted on the piles.

[0019] By adopting the above technical solution, two piles are connected by a connecting plate, so that all the piles can be integrated, further improving the stability of the piles inserted into the roadbed, and further reducing the occurrence of local settlement of the road surface.

[0020] Optionally, the connection plate is provided with a threaded hole, and the pile column is provided with a threaded groove. When the connection plate is connected to the pile column, bolts are passed through both the threaded hole and the threaded groove.

[0021] By adopting the above technical solution, after the pile is installed on the roadbed, the connecting plate is abutted against the surface of the pile, the threaded hole of the connecting plate and the threaded groove of the pile are arranged opposite to each other, and the connecting plate and the pile are fixed with bolts; and the bolt structure is simple, which is convenient for the staff to install it.

[0022] In summary, the present application includes at least one of the following beneficial technical effects:

[0023] 1. After the pile is installed in the roadbed, the ejector column is inserted into the installation groove. The ejector column can force all the reinforcement rods to be inserted into the roadbed, increase the contact area between the pile and the roadbed, increase the stability of the pile in the roadbed, and reduce the local settlement of the highway;

[0024] 2. By setting up anti-detachment blocks and connecting ropes, the situation of the reinforcement rod detaching from the pile column can be reduced, the stability of the pile column in the roadbed can be maintained, and the situation of the reinforcement rod detaching from the pile column when the pile column is inserted into the roadbed can be reduced; when the ejector column is inserted into the installation groove, the ejector column can expand the connecting rope and break it, thereby improving the smoothness of the ejector column being inserted into the installation groove. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a structural schematic diagram of this embodiment;

[0026] Figure 2 Schematic diagram of the installation of piles and ejector columns in this embodiment;

[0027] Figure 3 is a partial cross-sectional view of the pile column of this embodiment;

[0028] Figure 4 yes Figure 3 A local enlarged view of point A;

[0029] Figure 5 yes Figure 3 A partial enlarged view of point B.

[0030] Explanation of the reference numerals: 1. Pile; 11. Positioning plate; 12. Mounting groove; 13. Reinforcement hole; 14. Elastic card slot; 15. Anti-slip groove; 16. Connecting groove; 17. Threaded groove; 2. Ejector column; 3. Reinforcement rod; 31. Elastic card block; 32. Groove; 33. Anti-slip block; 34. Connecting hole; 35. Connecting rope; 36. Section; 4. Connecting plate; 41. Threaded hole; 42. Bolt. DETAILED DESCRIPTION

[0031] The following is combined with Figure 1-5 This application is described in further detail.

[0032] The embodiment of the present application discloses a highway roadbed anti-settling device.

[0033] Reference Figure 1 and Figure 2 A highway roadbed anti-settling device includes a plurality of piles 1 and a plurality of ejector columns 2. All the piles 1 are plugged into the roadbed, and two adjacent piles 1 are arranged at intervals. A positioning plate 11 is fixed on the upper surface of the pile 1, and the positioning plate 11 can abut against the upper surface of the roadbed to improve the stability of the pile 1 plugged into the roadbed. An installation groove 12 for the ejector column 2 to be inserted is opened on the upper surface of the pile 1, and the inner wall of the installation groove 12 matches the outer wall of the ejector column 2.

[0034] Reference Figure 3 and Figure 4 A plurality of reinforcement holes 13 are provided on the inner wall of the installation groove 12. All the reinforcement holes 13 are arranged at intervals along the circumferential direction of the outer wall of the pile column 1. The reinforcement holes 13 are arranged at an angle at one end close to the outer shell, that is, the extension direction of the reinforcement holes 13 is staggered with the extension direction of the pile column 1. A reinforcement rod 3 is movably installed in the reinforcement hole 13. An elastic block 31 is fixed on the outer wall of the reinforcement rod 3. An elastic slot 14 for the elastic block 31 to be inserted is provided on the inner wall of the reinforcement hole 13. When the elastic block 31 and the elastic slot 14 are inserted and matched, the reinforcement rod 3 is located in the pile column 1. When the ejector column 2 is inserted into the installation groove 12, the ejector column 2 forces the reinforcement rod 3 to be inserted into the roadbed.

[0035] Reference Figure 3 The end of the reinforcing rod 3 away from the housing is set as a tip, and by staggering the extension direction of the reinforcing rod 3 and the extension direction of the pile 1, the smoothness of the reinforcing rod 3 inserted into the roadbed can be increased, and the installation efficiency can be improved. A plurality of grooves 32 are provided on the surface of the reinforcing rod 3. When the reinforcing rod 3 is inserted into the roadbed, the contact area of ​​the reinforcing rod 3 in the roadbed can be increased, and the stability of the pile 1 installed in the roadbed can be improved.

[0036] Reference Figure 5 , an anti-dropout block 33 is provided at one end of the reinforcement rod 3 close to the pile column 1, and an anti-dropout groove 15 for the anti-dropout block 33 to be inserted is provided on the inner wall of the installation groove 12; the anti-dropout block 33 is provided with a connecting hole 34, and both ends of the connecting hole 34 are connected with both ends of the anti-dropout block 33; a connecting rope 35 is passed through the connecting holes 34 of all the anti-dropout blocks 33, and the connecting rope 35 ties all the anti-dropout blocks 33 together to keep the anti-dropout blocks 33 normally located in the pile column 1; in this embodiment, the connecting rope 35 is made of polypropylene material, which is not easy to break and can maintain the stability of the reinforcement rod 3 in the pile column 1; and when the ejector column 2 is inserted into the installation groove 12, the ejector column 2 can expand the connecting rope 35 and break it, thereby improving the smoothness of the ejector column 2 being inserted into the installation groove 12.

[0037] The anti-slip block 33 is provided with a cut surface 36, and the cut surfaces 36 of all the anti-slip blocks 33 form a guide groove for the ejector column 2 to be inserted; by providing the guide groove, the ejector column 2 is facilitated to abut against the cut surface 36, and the reinforcement rod 3 is moved toward the side away from the pile column 1, thereby further improving the convenience of installing the ejector column 2 in the installation groove 12.

[0038] Reference Figure 1 , two adjacent piles 1 are connected by a connecting plate 4, and the positioning plate 11 is provided with a connecting groove 16 for the connecting plate 4 to be inserted; the inner wall of the connecting groove 16 is provided with a threaded groove 17, and the connecting plate 4 is provided with a threaded hole 41. When the connecting plate 4 is inserted into the connecting groove 16, the threaded groove 17 and the threaded hole 41 are arranged opposite to each other, and a bolt 42 is penetrated through the threaded groove 17 and the threaded hole 41. The connecting plate 4 can be connected to the pile 1 by the bolt 42, and all the piles 1 can be connected to form a whole, which further improves the stability of the pile 1 installed in the roadbed and further reduces the situation of local settlement of the road surface.

[0039] The implementation principle of a highway roadbed anti-settling device in the embodiment of the present application is:

[0040] When the pile 1 is inserted into the roadbed, the reinforcement rods 3 are all located inside the shell to improve the smoothness of the insertion of the pile 1 into the roadbed and improve the installation efficiency of the pile 1. After the pile 1 is inserted into the roadbed, the ejector column 2 is inserted into the installation groove 12. The ejector column 2 can force all the reinforcement rods 3 to be inserted into the roadbed, increase the contact area between the pile 1 and the roadbed, increase the stability of the pile 1 in the roadbed, and reduce the occurrence of local settlement of the highway.

[0041] The above are preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A highway subsidence prevention device, characterized in that: The invention comprises a plurality of piles (1) and a plurality of ejector columns (2), wherein the piles (1) are all inserted into a roadbed, and the piles (1) are provided with mounting grooves (12) for the ejector columns (2) to be inserted into; the outer wall of the piles (1) is provided with a plurality of reinforcement holes (13), and all the reinforcement holes (13) are arranged at intervals along the circumferential direction of the outer wall of the piles (1); reinforcement rods (3) are movably installed in the reinforcement holes (13), and all the reinforcement rods (3) are normally located in the mounting grooves (12); when the ejector columns (2) are inserted into the mounting grooves (12), the ejector columns (2) force the reinforcement rods (3) to be inserted into the roadbed.

2. A highway subsidence prevention device according to claim 1, characterized in that: An anti-dropout block (33) is fixed to one end of the reinforcement rod (3) close to the pile foundation, and all the anti-dropout blocks (33) are tied together by a connecting rope (35).

3. A highway roadbed anti-settling device according to claim 2, characterized in that: The anti-slip block (33) is provided with a cut surface (36), and the cut surfaces (36) of all the anti-slip rods are enclosed to form a guide groove for the ejection column (2) to be inserted.

4. The highway subsidence prevention device according to claim 1, characterized in that: The surface of the reinforcement rod (3) is provided with a plurality of grooves (32).

5. The highway subsidence prevention device according to claim 1, characterized in that: An elastic clamping block (31) is provided on the outer wall of the reinforcement rod (3), and an elastic clamping groove (14) for clamping the elastic clamping block (31) is provided on the inner wall of the reinforcement hole (13).

6. The highway subsidence prevention device according to claim 1, characterized in that: One end of the reinforcement hole (13) close to the mounting groove (12) is arranged to be inclined upward.

7. The highway subsidence prevention device according to claim 1, characterized in that: Two adjacent piles (1) are connected by a connecting plate (4), and the connecting plate (4) can be detachably mounted on the piles (1).

8. The highway subsidence prevention device according to claim 7, characterized in that: The connection plate (4) is provided with a threaded hole (41), and the pile column (1) is provided with a threaded groove (17). When the connection plate (4) is connected to the pile column (1), a bolt (42) is passed through both the threaded hole (41) and the threaded groove (17).