Concrete sheet pile construction structure

By using technical means such as anchor rods, T-troughs, I-shaped plates and connecting rods in concrete slab pile structural structures, the problem of poor stability in the existing technology is solved, efficient installation is achieved and practicality and safety is enhanced.

CN222025016UActive Publication Date: 2024-11-19吴坚
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420396691.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-01
Publication Date
2024-11-19
Estimated Expiration
2034-03-01

AI Technical Summary

Technical Problem

The existing concrete slab pile structural structure has poor stability during installation, resulting in low working efficiency and poor practicality.

Method used

Multiple sheet pile bodies are quickly connected and installed through anchor rods, T-troughs, I-plates and connecting rods, and the stability and safety are enhanced through baffles and protective mechanisms to prevent sheet piles from tilting and falling by passers-by.

Benefits of technology

It improves the working efficiency and practicality of the concrete slab pile structure, enhances stability and safety, and ensures effective transmission and safety of road loads.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222025016U_ABST
    Figure CN222025016U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of municipal roads, in particular to a concrete sheet pile construction structure which is convenient to fix, improves working efficiency and enhances practicability. Comprising a plurality of sheet pile bodies, a connecting mechanism comprises a plurality of connecting rods, anchor rods are fixedly installed at the bottom ends of the sheet pile bodies, first T-shaped grooves and second T-shaped grooves are formed in the sheet pile bodies, the attaching positions of every two sheet pile bodies located on the same vertical face are connected through an I-shaped plate, and baffles are fixedly installed at the inner ends of the sheet pile bodies; u-shaped plates are fixedly installed on the multiple sheet pile bodies, the two ends of the connecting rod are slidably clamped with the two U-shaped plates located on the same vertical face correspondingly, the protection mechanisms are installed on the sheet pile bodies and used for protecting the sheet pile bodies, the anchor rods on the multiple sheet pile bodies are sequentially inserted into the bottom of a foundation pit, and the multiple sheet pile bodies are attached. The second T-shaped groove of one pile plate body is attached to the second first T-shaped groove of the adjacent pile plate body to form an I-shaped groove.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of municipal roads, in particular to a concrete sheet pile construction structure. Background Art

[0002] Municipal roads refer to urban roads. Municipal roads are divided into five levels according to their position in the road network, traffic functions and service functions along the route: expressways, trunk roads, secondary trunk roads, branch roads and district roads (residential and industrial areas). During the construction of municipal roads, concrete sheet piles are needed to provide support and reinforcement. Reinforced concrete sheet piles are not just individual sheet pile components, but refer to the combined pile bodies formed by sinking reinforced concrete sheet pile components. They are a foundation pit retaining structure that is easy to factory-produce and assemble. They can withstand the load of the road and transfer the load to the lower layer of the foundation, thereby ensuring the safety and stability of the road. As the main component material of sheet piles, concrete can play a supporting and reinforcing role through its solid organizational structure and excellent bearing performance.

[0003] For example, the utility model patent with Chinese patent publication number CN217678387U discloses a municipal road concrete sheet pile construction structure, including ground and sheet piles, the front and rear end surfaces of the outer wall of the ground are both bonded with a plurality of sheet piles, the plurality of sheet piles are bonded to each other in pairs, and both ends of the outer wall of the sheet pile are provided with a docking mechanism, the docking mechanism includes a T-slot and a T-block, the T-slot and the T-block are respectively processed at both ends of the outer wall of the sheet pile, and the inner wall of the T-slot at one end is slidably connected to the outer wall of the T-block at the other end;

[0004] It is found in the use of the above-mentioned prior art that the device cooperates with the T-slot and the T-block so that when multiple pile plates are fitted together, the T-slot of one pile plate and the T-block of another pile plate can be slidably connected to quickly dock the multiple pile plates, which is convenient for building roads. However, the concrete sheet piles are installed only by relying on the clamping of the T-slot and the T-block, which has poor stability and is prone to tilting, reducing work efficiency, resulting in poor practicality. Utility Model Content

[0005] Technical issues solved

[0006] In order to solve the above technical problems, the utility model provides a concrete sheet pile construction structure which is easy to fix, improves work efficiency and enhances practicality.

[0007] Technical Solution

[0008] To achieve the above-mentioned purpose, the present application provides the following technical solutions: a concrete sheet pile construction structure, comprising a plurality of sheet pile bodies, the connecting mechanism comprising a plurality of connecting rods, the bottom ends of the plurality of sheet pile bodies are fixedly installed with anchor rods, the plurality of sheet pile bodies are provided with a first T-slot and a second T-slot, the two sheet pile bodies located on the same vertical plane are connected at their joints by an I-shaped plate, the inner ends of the plurality of sheet pile bodies are fixedly installed with baffles, the plurality of sheet pile bodies are fixedly installed with U-shaped plates, the two ends of the connecting rods are respectively slidably clamped with the two U-shaped plates located on the same vertical plane, and the protective mechanism is installed on the sheet pile body to protect the sheet pile body.

[0009] By adopting the above technical scheme, the anchor rods on multiple sheet pile bodies are inserted into the bottom of the foundation pit in turn, the multiple sheet pile bodies are fitted together, the second T-slot of one pile sheet body is fitted with the second first T-slot of the adjacent sheet pile body to form an I-shaped groove, the I-shaped plate is inserted into the I-shaped groove formed by the two sheet pile bodies, and the above steps are repeated, so that the multiple sheet pile bodies are quickly connected and installed, and the connecting rod is inserted into the U-shaped plate on the corresponding sheet pile body. The connecting rod can support the two opposite sheet pile bodies. At the same time, the baffle on the sheet pile body can prevent the sheet pile body from tilting inward when it is subjected to the pressure of the side wall of the foundation pit. This process realizes a process that is easy to fix, improves work efficiency, and thus enhances practicality.

[0010] Preferably, the protection mechanism comprises two protection fences, a plurality of insertion rods are fixedly mounted on the bottom ends of the two protection fences, slots are formed on the top ends of the plurality of sheet pile bodies, and the plurality of insertion rods are respectively clamped in the plurality of slots.

[0011] By adopting the above technical solution, after multiple sheet pile bodies are connected and installed, the rods on the guardrail are inserted into the slots, and the guardrail is installed on the sheet pile body to prevent passers-by from falling into the foundation pit, thereby enhancing safety.

[0012] Preferably, top ends of the plurality of first T-slots and second T-slots are all configured as slope structures.

[0013] By adopting the above technical solution, the slope structure can make the I-shaped plate better inserted into the first T-slot and the second T-slot, thereby enhancing practicality.

[0014] Preferably, a plurality of the I-shaped plates are provided with semicircular grooves, and support rods are fixedly installed in the plurality of semicircular grooves.

[0015] By adopting the above technical solution, workers can install the I-shaped board by holding the support rod, thereby enhancing the convenience of use.

[0016] Preferably, a plurality of the baffles are fixedly mounted with triangular plates, and the plurality of triangular plates are respectively fixedly connected to the plurality of sheet pile bodies.

[0017] By adopting the above technical solution, the triangular plate can strengthen the connection between the baffle plate and the sheet pile body, thereby enhancing stability.

[0018] Beneficial Effects

[0019] Compared with the prior art, the present application provides a concrete sheet pile construction structure, which has the following beneficial effects:

[0020] Insert the anchor rods on multiple sheet pile bodies into the bottom of the foundation pit in turn, fit the multiple sheet pile bodies together, fit the second T-slot of one pile sheet body with the second first T-slot of the adjacent sheet pile body to form an I-shaped groove, insert the I-shaped plate into the I-shaped groove formed by the two sheet pile bodies, repeat the above steps, and quickly connect and install the multiple sheet pile bodies, insert the connecting rod into the U-shaped plate on the corresponding sheet pile body, the connecting rod can support the two opposite sheet pile bodies, and at the same time, the baffle on the sheet pile body can prevent the sheet pile body from tilting inward when it is subjected to the pressure of the side wall of the foundation pit. This process realizes the process of facilitating fixing, improves work efficiency, and thus enhances practicality. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a schematic diagram of the shaft side structure of the utility model;

[0022] Figure 2 It is a schematic diagram of the axial side cross-sectional structure of the utility model;

[0023] Figure 3 It is a structural schematic diagram of the connection between the support rod and the I-shaped plate of the utility model;

[0024] Figure 4 It is a structural schematic diagram of the connection between the sheet pile body and the support rod of the utility model.

[0025] Markings in the attached drawings: 1. sheet pile body; 2. connecting rod; 3. anchor rod; 4. first T-slot; 5. second T-slot; 6. I-shaped plate; 7. baffle; 8. U-shaped plate; 9. guardrail; 10. insertion rod; 11. slope structure; 12. support rod; 13. triangle plate. DETAILED DESCRIPTION

[0026] Example

[0027] See also Figure 1-Figure 4A concrete sheet pile construction structure comprises a plurality of sheet pile bodies 1, a connecting mechanism comprises a plurality of connecting rods 2, anchor rods 3 are fixedly installed at the bottom ends of the plurality of sheet pile bodies 1, a first T-slot 4 and a second T-slot 5 are provided on the plurality of sheet pile bodies 1, two sheet pile bodies 1 located on the same vertical plane are connected at their joints by an I-shaped plate 6, baffle plates 7 are fixedly installed at the inner ends of the plurality of sheet pile bodies 1, a U-shaped plate 8 is fixedly installed on the plurality of sheet pile bodies 1, both ends of the connecting rod 2 are respectively slidably mounted on the two U-shaped plates 8 located on the same vertical plane, a protective mechanism comprises two guardrails 9, a plurality of plugging rods 10 are fixedly installed at the bottom ends of the two guardrails 9, slots are provided on the top ends of the plurality of sheet pile bodies 1, and the plurality of plugging rods 10 are respectively mounted on the plurality of slots, the anchor rods 3 on the plurality of sheet pile bodies 1 are inserted into the bottom of the foundation pit in sequence, and the plurality of sheet piles The main body 1 is fitted, the second T-slot 5 of a pile sheet body is fitted with the second first T-slot 4 of the adjacent sheet pile body 1 to form an I-shaped groove, the I-shaped plate 6 is inserted into the I-shaped groove formed by the two sheet pile bodies 1, and the above steps are repeated to quickly connect and install multiple sheet pile bodies 1, and the connecting rod 2 is inserted into the U-shaped plate 8 on the corresponding sheet pile body 1. The connecting rod 2 can support the two opposite sheet pile bodies 1. At the same time, the baffle 7 on the sheet pile body 1 can prevent the sheet pile body 1 from tilting inward when it is subjected to the pressure of the side wall of the foundation pit. After the connection and installation of multiple sheet pile bodies 1 are completed, the insertion rod 10 on the guardrail 9 is inserted into the slot, and the guardrail 9 is installed on the sheet pile body 1 to prevent passers-by from falling into the foundation pit. This process realizes a process that is easy to fix, improves work efficiency, and thus enhances practicality.

[0028] See also Figure 1-Figure 4 The tops of the plurality of first T-slots 4 and the second T-slots 5 are all arranged with a slope structure 11. The slope structure 11 can make the I-shaped plate 6 better inserted into the first T-slots 4 and the second T-slots 5, thereby enhancing the practicality.

[0029] See also Figure 1-Figure 3 A plurality of I-shaped plates 6 are provided with semicircular grooves, and support rods 12 are fixedly installed in the plurality of semicircular grooves. The staff can hold the support rods 12 to install the I-shaped plates 6. A plurality of baffles 7 are fixedly installed with triangular plates 13, and the plurality of triangular plates 13 are respectively fixedly connected to a plurality of sheet pile bodies 1. The triangular plates 13 can strengthen the connection between the baffles 7 and the sheet pile bodies 1, thereby enhancing practicality.

[0030] The utility model provides a concrete sheet pile construction structure. When working, the anchor rods 3 on multiple sheet pile bodies 1 are inserted into the bottom of the foundation pit in sequence, and the multiple sheet pile bodies 1 are fitted together. The second T-slot 5 of one pile sheet body is fitted with the second first T-slot 4 of the adjacent sheet pile body 1 to form an I-shaped groove, and the I-shaped plate 6 is inserted into the I-shaped groove formed by the two sheet pile bodies 1. The above steps are repeated to quickly connect and install the multiple sheet pile bodies 1, and the connecting rod 2 is inserted into the U-shaped plate 8 on the corresponding sheet pile body 1. The connecting rod 2 can support the two opposite sheet pile bodies 1. At the same time, the baffle 7 on the sheet pile body 1 can prevent the sheet pile body 1 from tilting inward when it is subjected to the pressure of the side wall of the foundation pit. After the multiple sheet pile bodies 1 are connected and installed, the insertion rod 10 on the guardrail 9 is inserted into the slot, and the guardrail 9 is installed on the sheet pile body 1 to prevent passers-by from falling into the foundation pit. This process realizes a process that is easy to fix.

[0031] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A concrete sheet pile construction structure, comprising a plurality of sheet pile bodies (1), characterized in that , also includes: A connecting mechanism, the connecting mechanism comprising a plurality of connecting rods (2), anchor rods (3) are fixedly installed at the bottom ends of the plurality of sheet pile bodies (1), a first T-shaped groove (4) and a second T-shaped groove (5) are opened on the plurality of sheet pile bodies (1), the joints of two sheet pile bodies (1) located on the same vertical plane are connected by an I-shaped plate (6), baffle plates (7) are fixedly installed at the inner ends of the plurality of sheet pile bodies (1), U-shaped plates (8) are fixedly installed on the plurality of sheet pile bodies (1), and both ends of the connecting rod (2) are respectively slidably clamped with the two U-shaped plates (8) located on the same vertical plane; A protection mechanism is installed on the sheet pile body (1) and is used to protect the sheet pile body (1).

2. A concrete sheet pile construction structure as claimed in claim 1, characterized in that: The protection mechanism comprises two protection fences (9), a plurality of insertion rods (10) are fixedly mounted at the bottom ends of the two protection fences (9), a plurality of sheet pile bodies (1) are provided with slots at the top ends, and the plurality of insertion rods (10) are respectively clamped in the plurality of slots.

3. A concrete sheet pile construction structure as claimed in claim 1, characterized in that: The top ends of the plurality of first T-shaped slots (4) and second T-shaped slots (5) are all arranged as slope structures (11).

4. A concrete sheet pile construction structure as claimed in claim 1, characterized in that: A plurality of I-shaped plates (6) are each provided with a semicircular groove, and a support rod (12) is fixedly installed in each of the semicircular grooves.

5. A concrete sheet pile construction structure as claimed in claim 1, characterized in that: A triangular plate (13) is fixedly mounted on each of the plurality of baffles (7), and the plurality of triangular plates (13) are respectively fixedly connected to the plurality of sheet pile bodies (1).