Rapid construction device for wall surface aluminum square tube
By introducing a quick installation mechanism and a fixed clamping mechanism into the aluminum square rapid construction device, using components such as limit balls, movable columns and springs, the problem of cumbersome bolt fixation during aluminum square installation is solved, and the aluminum square network is realized Quick installation and disassembly improve construction efficiency.
Patent Information
- Application Number
- CN202323586669.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2033-12-27
AI Technical Summary
When installing the aluminum square tube on the fixing plate, it requires multiple bolts to fix it, which causes the staff to spend a lot of energy and time, and the operation is cumbersome, which reduces the construction efficiency.
A wall aluminum square-pass rapid construction device is designed, adopting a quick installation mechanism and a fixed clamping mechanism, including plug sockets, plug cylinders, limit balls, movable columns, springs and movable limit blocks, through these components In conjunction with the rapid installation and fixing of aluminum square passes and fixing plates.
The installation process of aluminum square pipes has been simplified, the construction efficiency has been improved, and the staff can quickly complete the installation and disassembly of aluminum square pipes has been greatly improved.
Smart Images

Figure CN222044821U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of aluminum square tubes, in particular to a rapid construction device for wall aluminum square tubes. Background Art
[0002] Aluminum square tube is one of the ceiling materials produced in recent years. It has an open view, ventilation, air permeability, bright and neat lines, distinct layers, reflecting a simple and clear modern style, and is easy to install and disassemble. It has become a major product that has swept the decoration market in recent years. When installing aluminum square tubes, you need to first install the fixing plate on the wall, and then fix the aluminum square tube on the fixing plate.
[0003] However, in the prior art, when the aluminum square tube is installed on the fixing plate, it needs to be fixed with multiple bolts. The staff needs to spend a lot of energy and time on tightening the bolts. The operation is very cumbersome, which reduces the construction efficiency. In view of the above problems, a quick construction device for wall aluminum square tubes is proposed. Utility Model Content
[0004] The purpose of the utility model is to solve the problem in the prior art that when the aluminum square tube is installed on the fixing plate, it needs to be fixed with multiple bolts, the staff needs to spend a lot of energy and time on tightening the bolts, the operation is very cumbersome, and the construction efficiency is reduced. A quick construction device for wall aluminum square tubes is proposed to solve the problem that
[0005] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a wall aluminum square tube quick construction device, including an aluminum square tube body and a fixed plate, a plurality of quick installation mechanisms are arranged at both ends of the aluminum square tube body, the quick installation mechanism includes a plug-in sleeve and a plug-in tube, a through hole is provided at the top of the plug-in sleeve, two limit holes are penetrated through the outer surface of the plug-in sleeve, the inner wall of the limit hole is slidably connected with a limit ball, the inner wall of the through hole is slidably connected with a movable column, the outer surface of the movable column is provided with a No. 1 spring, and a limit groove is provided inside the plug-in tube.
[0006] Preferably, a fixed clamping mechanism is provided at one end of the fixed plate, and the fixed clamping mechanism includes a fixed column, and the outer surface of the fixed column is slidably connected to two movable limit blocks, a No. 2 spring is provided between the two movable limit blocks, and a No. 1 slot is opened at the other end of the fixed plate.
[0007] Preferably, a second slot is provided at the bottom end of the fixed plate and near the edge of the other end, and a movable block is slidably connected to the inner wall of the second slot.
[0008] Preferably, the top end of the No. 1 spring is fixedly connected to the outer surface of the movable column, and the bottom end of the No. 1 spring is fixedly connected to the inner wall of the through hole.
[0009] Preferably, the inner wall of the No. 2 spring is movably sleeved with the outer surface of the fixed column, and the two ends of the No. 2 spring are movably arranged with one end of the two movable limit blocks.
[0010] Preferably, the bottom end of the plug sleeve is fixedly mounted to one end of the aluminum square tube body, and the bottom end of the plug tube is fixedly mounted to the top end of the fixing plate.
[0011] Preferably, the No. 1 slot is connected to the No. 2 slot.
[0012] Compared with the prior art, the advantages and positive effects of the utility model are:
[0013] 1. In the utility model, by setting a quick installation mechanism, through the cooperation between the limiting ball, the limiting hole and the limiting groove, it is convenient for workers to quickly install the aluminum square tube body and the fixed plate, the operation is simple, and the construction efficiency is improved.
[0014] 2. In the utility model, by setting a fixed clamping mechanism, the installation between the two fixed plates is realized by utilizing the cooperation between the two movable limit blocks and the No. 1 slot, which is easy to operate and further improves the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 The utility model provides a three-dimensional structural schematic diagram of a wall aluminum square tube rapid construction device;
[0016] Figure 2 The utility model provides a partial structural explosion diagram of a wall aluminum square tube rapid construction device;
[0017] Figure 3 This utility model provides a schematic cross-sectional view of the internal structure of a quick installation mechanism of a wall aluminum square tube quick construction device;
[0018] Figure 4 The utility model provides a three-dimensional structural diagram of a fixing and clamping mechanism of a wall aluminum square tube rapid construction device;
[0019] Figure 5 The utility model provides a bottom schematic diagram of a wall aluminum square tube rapid construction device after partial structural decomposition.
[0020] Legend: 1. Aluminum square tube body; 2. Fixed plate; 3. Quick installation mechanism; 301. Plug-in sleeve; 302. Through hole; 303. Limit hole; 304. Limit ball; 305. Movable column; 306. No. 1 spring; 307. Plug-in tube; 308. Limit groove; 4. Fixed clamping mechanism; 401. Fixed column; 402. Movable limit block; 403. No. 2 spring; 5. No. 1 slot; 6. No. 2 slot; 7. Movable block. DETAILED DESCRIPTION
[0021] In order to more clearly understand the above-mentioned purpose, features and advantages of the utility model, the utility model is further described below in conjunction with the accompanying drawings and embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.
[0022] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways than those described herein. Therefore, the present invention is not limited to the specific embodiments of the following disclosure.
[0023] Embodiment 1
[0024] like Figure 1-5 As shown, the utility model provides a wall aluminum square tube rapid construction device, including an aluminum square tube body 1 and a fixed plate 2, a plurality of rapid installation mechanisms 3 are arranged at both ends of the aluminum square tube body 1, the rapid installation mechanism 3 includes a plug-in sleeve 301 and a plug-in cylinder 307, a through hole 302 is provided at the top of the plug-in sleeve 301, two limiting holes 303 are penetrated through the outer surface of the plug-in sleeve 301, the inner wall of the limiting hole 303 is slidably connected to the limiting ball 304, the inner wall of the through hole 302 is slidably connected to a movable column 305, the outer surface of the movable column 305 is provided with a No. 1 spring 306, a limiting groove 308 is arranged inside the plug-in cylinder 307, the top of the No. 1 spring 306 is fixedly connected to the outer surface of the movable column 305, the bottom end of the No. 1 spring 306 is fixedly connected to the inner wall of the through hole 302, the bottom end of the plug-in sleeve 301 is fixedly installed with one end of the aluminum square tube body 1, and the bottom end of the plug-in cylinder 307 is fixedly installed with the top of the fixed plate 2.
[0025] The following is a detailed description of the specific settings and functions of this embodiment. When installing the aluminum square tube body 1 and the fixed plate 2, the staff first places the aluminum square tube body 1 at a suitable position on the fixed plate 2 so that the four plug-in sleeves 301 are aligned with the plug-in cylinder 307. Then the staff inserts the plug-in sleeve 301 into the plug-in cylinder 307. At this time, the limiting ball 304 is inside the inclined surface of the movable column 305, so that the limiting ball 304 will not be exposed from the limiting hole 303. After the preliminary installation is completed, the staff flips the aluminum square tube body 1 and the fixed plate 2. At this time, the movable column 305 will be under the action of gravity. The two limiting balls 304 will be squeezed and pushed out of a part of the limiting hole 303. At this time, the two limiting balls 304 and the limiting grooves 308 are engaged. The two limiting balls 304 will engage the plug-in sleeve 301 in the plug-in tube 307. In this way, the quick installation between the aluminum square tube body 1 and the fixed plate 2 is realized. When disassembly is required, the staff presses the movable column 305 to extend it into the plug-in tube 307. At this time, the No. 1 spring 306 produces elastic deformation and generates elastic force. After that, the elastic force of the No. 1 spring 306 will facilitate the rebound of the movable column 305.
[0026] Embodiment 2
[0027] like Figure 1 , Figure 4 and Figure 5 As shown, a fixed clamping mechanism 4 is provided at one end of the fixed plate 2, and the fixed clamping mechanism 4 includes a fixed column 401, and the outer surface of the fixed column 401 is slidably connected to two movable limit blocks 402, and a No. 2 spring 403 is provided between the two movable limit blocks 402. A No. 1 slot 5 is provided at the other end of the fixed plate 2, and a No. 2 slot 6 is provided at the bottom end of the fixed plate 2 and near the edge of the other end, and a movable block 7 is slidably connected to the inner wall of the No. 2 slot 6, and the inner wall of the No. 2 spring 403 is movably sleeved with the outer surface of the fixed column 401, and both ends of the No. 2 spring 403 are movably arranged with one end of the two movable limit blocks 402, and the No. 1 slot 5 is connected to the No. 2 slot 6.
[0028] The effect achieved by the entire embodiment is that when installing the two fixed plates 2, the staff first pulls the movable block 7 out of the No. 2 slot 6, and then pushes the side of one fixed plate 2 provided with the fixed clamping mechanism 4 toward the side of the other fixed plate 2 provided with the No. 1 slot 5. Two side plates should be provided at the opening of the No. 1 slot 5. During the pushing process, the two movable limit blocks 402 will be squeezed by the two side plates of the No. 1 slot 5, and then the two movable limit blocks 402 will move closer and squeeze the No. 2 spring 403, and the No. 2 spring 403 will produce elastic deformation and generate elastic force. After the front end part of the limit block 402 is separated from the side plate, the two movable limit blocks 402 are reset under the action of the elastic force of the No. 2 spring 403, and the front end will clamp the two side plates, thus realizing the quick installation between the two fixed plates 2. When disassembly is required, the staff will reinsert the movable block 7 into the No. 2 slot 6, and the inclined surface of the movable block 7 will squeeze the two movable limit blocks 402, and the two movable limit blocks 402 will be pushed and brought together again until the total length of the two movable limit blocks 402 is less than the opening length of the No. 1 slot 5, so that the staff can separate the two fixed plates 2.
[0029] The use method and working principle of the device: When installing the aluminum square tube body 1 and the fixing plate 2, the staff first places the aluminum square tube body 1 at a suitable position on the fixing plate 2, so that the four plug sleeves 301 are aligned with the plug cylinder 307, and then the staff inserts the plug sleeve 301 into the plug cylinder 307. At this time, the limit ball 304 is inside the inclined surface of the movable column 305, so that the limit ball 304 will not be exposed from the limit hole 303. After the preliminary installation is completed, the staff turns over the aluminum square tube body 1 and the fixing plate 2. At this time, the movable column 305 is moved under the action of gravity. The two limiting balls 304 will be squeezed and pushed out of a part of the limiting hole 303. At this time, the two limiting balls 304 and the limiting grooves 308 are connected. The two limiting balls 304 will clamp the plug-in sleeve 301 in the plug-in cylinder 307, so that the quick installation between the aluminum square tube body 1 and the fixed plate 2 is realized. When disassembly is required, the staff presses the movable column 305 to extend it into the plug-in cylinder 307. At this time, the No. 1 spring 306 produces elastic deformation and generates elastic force. Later, due to the elastic force of the No. 1 spring 306, it is convenient to The movable column 305 rebounds; when installing the two fixed plates 2, the staff first pulls the movable block 7 out of the No. 2 slot 6, and then pushes the side of one fixed plate 2 provided with the fixed clamping mechanism 4 toward the side of the other fixed plate 2 provided with the No. 1 slot 5. Two side plates should be provided at the opening of the No. 1 slot 5. During the pushing process, the two movable limit blocks 402 will be squeezed by the two side plates of the No. 1 slot 5, and then the two movable limit blocks 402 will move closer and squeeze the No. 2 spring 403. The No. 2 spring 403 produces elastic deformation and generates elastic force. After the front end part of block 402 is separated from the side plate, the two movable limit blocks 402 are reset under the action of the elastic force of the No. 2 spring 403, and the front end will clamp the two side plates, thus realizing the rapid installation between the two fixed plates 2. When disassembly is required, the staff will reinsert the movable block 7 into the No. 2 slot 6, and the inclined surface of the movable block 7 will squeeze the two movable limit blocks 402, and the two movable limit blocks 402 will be pushed and brought together again until the total length of the two movable limit blocks 402 is less than the opening length of the No. 1 slot 5, so that the staff can separate the two fixed plates 2.
[0030] The above description is only a preferred embodiment of the present invention and does not limit the present invention in other forms. Any technician familiar with the profession may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes and apply it to other fields. However, any simple modification, equivalent change and modification made to the above embodiment based on the technical essence of the present invention without departing from the content of the technical solution of the present invention still falls within the protection scope of the technical solution of the present invention.
Claims
1. A quick construction device for wall aluminum square tubes, comprising an aluminum square tube body (1) and a fixing plate (2), characterized in that: A plurality of quick installation mechanisms (3) are provided at both ends of the aluminum square tube body (1), and the quick installation mechanisms (3) include a plug-in sleeve (301) and a plug-in tube (307). A through hole (302) is provided at the top of the plug-in sleeve (301), and two limiting holes (303) are provided through the outer surface of the plug-in sleeve (301). The inner wall of the limiting hole (303) is slidably connected to a limiting ball (304), and the inner wall of the through hole (302) is slidably connected to a movable column (305). A No. 1 spring (306) is provided on the outer surface of the plug-in tube (307). A limiting groove (308) is provided inside.
2. A wall aluminum square tube rapid construction device according to claim 1, characterized in that: A fixed clamping mechanism (4) is provided at one end of the fixed plate (2), the fixed clamping mechanism (4) comprising a fixed column (401), the outer surface of the fixed column (401) being slidably connected to two movable limit blocks (402), a No. 2 spring (403) being provided between the two movable limit blocks (402), and a No. 1 slot (5) is provided at the other end of the fixed plate (2).
3. A rapid construction device for aluminum square tubes for walls according to claim 2, characterized in that: A second slot (6) is provided on one side of the fixed plate (2) near the edge of the other end, and a movable block (7) is slidably connected to the inner wall of the second slot (6).
4. A wall aluminum square tube rapid construction device according to claim 1, characterized in that: The top end of the No. 1 spring (306) is fixedly connected to the outer surface of the movable column (305), and the bottom end of the No. 1 spring (306) is fixedly connected to the inner wall of the through hole (302).
5. The rapid construction device for aluminum square tubes for walls according to claim 2 is characterized by: The inner wall of the No. 2 spring (403) is movably sleeved with the outer surface of the fixed column (401), and the two ends of the No. 2 spring (403) are movably arranged with one end of the two movable limit blocks (402).
6. A wall aluminum square tube rapid construction device according to claim 1, characterized in that: The bottom end of the plug sleeve (301) is fixedly mounted on one end of the aluminum square tube body (1), and the bottom end of the plug tube (307) is fixedly mounted on the top end of the fixing plate (2).
7. The rapid construction device for wall aluminum square tube according to claim 3 is characterized by: The first slot (5) and the second slot (6) are connected.