Connecting structure for excavation and filling interface of fill in mountainous area
By designing inclined steps in mountain fill project, the filling and excavation interface connection structure of geogrid and micro steel pipe piles is solved, the hidden dangers of the excavation and filling interface are improved, and the construction quality is reduced and the foundation deformation is reduced. Effective prevention and control of uneven settlement, cracks and sliding.
Patent Information
- Application Number
- CN202420757475.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-12
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-12
AI Technical Summary
In mountainous fill projects, common problems in the excavation and filling interface, such as uneven settlement, cracks and sliding, lead to project quality hazards, and existing geogrid reinforcement methods cannot effectively solve these problems.
Design a mountainous area filling and excavation interface connection structure, forming inclined steps starting from the filling slope foot, each step is equipped with geogrid and micro steel pipe piles, the surface is filled with gravel layers, and the micro steel pipe piles are placed on the micro steel pipe piles Reinforced concrete connection beams are installed on the top, the micro steel pipe piles are arranged in plum blossom shape, and the step surface is chiseled to improve friction resistance.
It effectively improves the construction quality, reduces the foundation deformation of the fill project, and prevents and controls common diseases at the interface of excavation and filling, such as uneven settlement, cracks and sliding, and the structure is simple and easy to implement.
Smart Images

Figure CN222065414U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of excavation-filling interface processing in filling engineering, in particular to an excavation-filling interface connection structure for filling in mountainous areas. Background Art
[0002] As the contradiction between the huge demand for construction land in mountainous areas and the shortage of available land resources becomes increasingly prominent, a large number of land reclamation projects have been formed by cutting mountains and filling ditches. The increasing number of high-fill projects has achieved certain results, but also generated many new technical, theoretical and engineering problems. Issues related to the cut-fill interface are one of the main geotechnical engineering problems in the construction of fill projects. Common diseases at the cut-fill interface include uneven settlement, cracks and sliding at the cut-fill interface, which pose a major hidden danger to the quality of fill projects.
[0003] At present, geogrid reinforcement is mainly used for the interface between excavation and filling in fill projects. However, this method cannot effectively solve the common diseases at the interface between excavation and filling in fill projects. Utility Model Content
[0004] The technical problem to be solved by the utility model is to provide a connection structure for the interface between filling and excavation in mountainous areas, which can improve the construction quality.
[0005] In order to solve the above problems, the utility model discloses a connection structure of the cut-fill interface in mountainous area, including a cut-fill interface, which is characterized in that: the cut-fill interface forms steps upward from the foot of the fill slope, and each step is provided with a geogrid and a plurality of micro steel pipe piles; the surface of the geogrid is fixedly filled with a gravel layer, and the excavated soil is filled above the gravel layer; and a reinforced concrete connecting beam is provided on the top of the micro steel pipe pile.
[0006] The step is arranged obliquely, and the heights of the inner and outer sides of the step are different.
[0007] The inclination angle of the step is less than 30 degrees.
[0008] The height of the outer side of the step is greater than the height of the inner side.
[0009] The surface of the step is in a rough state.
[0010] Several of the micro steel pipe piles are arranged in a plum blossom shape.
[0011] Compared with the prior art, the utility model has the following advantages:
[0012] 1. The utility model effectively improves the construction quality of the excavation-fill joint of the filling project by setting up geogrids and micro steel pipe piles, plays a positive role in preventing and controlling common diseases at the excavation-fill interface, such as uneven settlement, cracks and sliding at the excavation-fill interface, and effectively reduces the foundation deformation of the filling project.
[0013] 2. The utility model has a simple structure and is easy to implement. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] The specific implementation of the utility model is further described in detail below with reference to the accompanying drawings.
[0015] Figure 1 It is a structural schematic diagram of the utility model.
[0016] Figure 2 This is a schematic diagram of the arrangement of micro steel pipe piles of the utility model.
[0017] In the figure: 1—interface between cut and fill; 2—step; 3—geogrid; 4—gravel layer; 5—micro steel pipe piles; 6—reinforced concrete connecting beam. DETAILED DESCRIPTION
[0018] like Figure 1~2 As shown, a connection structure of a cut-fill interface in a mountainous area includes a cut-fill interface 1. The cut-fill interface 1 forms a step 2 upward from the foot of the fill slope, and a geogrid 3 is provided at each step 2. At the same time, a plurality of micro steel pipe piles 5 are provided to improve the rigidity; a crushed stone layer 4 is fixedly filled on the surface of the geogrid 3, and the excavated soil is filled above the crushed stone layer 4 to reduce the fill settlement; a reinforced concrete connecting beam 6 is provided on the top of the micro steel pipe pile 5 to improve the integrity.
[0019] Among them: the step 2 is inclined, and the inclination angle is less than 30 degrees. At the same time, the heights of the inner and outer sides of the step 2 are not equal, and usually the height of the outer side of the step 2 is greater than the height of the inner side, presenting a reverse slope structure.
[0020] In order to increase the friction resistance with the filler, the surface of the step 2 is subjected to a series of roughening treatments to present a rough state.
[0021] In order to improve the rigidity, several micro steel pipe piles 5 are arranged in a plum blossom shape. Such micro steel pipe piles 5 have the characteristics of small construction machinery, flexible construction and fast progress.
[0022] Geogrid 3 includes various types, such as plastic geogrid, welded geogrid and steel-plastic geogrid, etc. The specific type can be selected according to the site conditions.
Claims
1. A cut-fill interface connection structure in a mountainous area, comprising a cut-fill interface (1), characterized in that: The cut-fill interface (1) forms steps (2) from the foot of the fill slope upwards, and each step (2) is provided with a geogrid (3) and a plurality of micro steel pipe piles (5); the surface of the geogrid (3) is fixedly filled with a crushed stone layer (4), and the top of the crushed stone layer (4) is filled with excavated soil; and a reinforced concrete connecting beam (6) is provided on the top of the micro steel pipe piles (5).
2. A connection structure for the cut-and-fill interface in a mountainous area as claimed in claim 1, characterized in that: The step (2) is arranged obliquely, and the heights of the inner and outer sides of the step (2) are different.
3. A mountain area fill cut and fill interface connection structure as claimed in claim 2, characterized in that: The inclination angle of the step (2) is less than 30 degrees.
4. A connection structure for the cut-and-fill interface in a mountainous area as claimed in claim 2, characterized in that: The height of the outer side of the step (2) is greater than the height of the inner side.