Engineering pile capable of draining water
By introducing a gravel seepage filter layer and a dense mesh into the engineering piles, combined with the design of a fixed connection of protective top net, the problem of the lack of drainage function and the non-fixed connection of protective nets in the existing engineering piles is solved, and effective drainage and construction safety is achieved Sex improvement.
Patent Information
- Application Number
- CN202421182587.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-28
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-05-28
AI Technical Summary
The existing engineering piles lack drainage function, and additional drainage wells need to be excavated during construction, and the protective net is not fixedly connected to the engineering piles, which poses safety hazards.
A drainable engineering pile including foundation, pile hole, engineering pile concrete body, steel cage body, gravel seepage filter layer, dense mesh net, protective top net and connecting components were designed, and the gravel water seepage filter layer and dense mesh net were passed through the gravel water seepage filter layer and dense mesh net. The water infiltration and extraction is achieved, and the protective top mesh is fixed to the main body of the steel cage through fixing nuts and screws to ensure its stability.
The drainage function is achieved without the need for additional excavation of drainage wells. Multiple engineering piles jointly meet the drainage needs of the construction site, and the stability and safety of the protective net are improved through fixed connections.
Smart Images

Figure CN222065434U_ABST
Abstract
Description
Technical Field
[0001] The utility model specifically relates to a drainage engineering pile, belonging to the technical field of engineering piles. Background Art
[0002] Engineering piles are piles used in engineering projects and are ultimately subjected to stress in buildings and structures. They can be embedded in the ground by hammering, extrusion or drilling to provide better bearing capacity and stability. Engineering piles are widely used in civil engineering, marine engineering, pipelines and transmission lines, geological exploration and testing, and environmental protection. For example, in civil engineering, engineering piles can be used to support the thrust on the side of the soil; in marine engineering, they can be used to support structures and resist natural forces such as waves, tides and currents; in pipeline and transmission line construction, they can be used as support and protection for pipelines; in geological exploration and testing, they can be used to support and fix underground detection instruments; in environmental protection, engineering piles also have their specific uses.
[0003] Engineering pile structures are generally divided into solid piles and hollow piles. Solid piles are cast concrete structures, with the solid pile part extending into the bearing layer. The hollow pile has not been poured with concrete, and is only a circular steel frame, or has no steel bars. Engineering piles generally play a compressive role, and the existing engineering piles do not have a drainage function. When draining water during the excavation stage of the project, it is generally necessary to dig additional drainage wells and pump out the water to prevent the water from affecting the foundation. After the construction of the engineering piles, a protective net is generally set on the top. The protective net is generally covered on the top of the engineering piles, and the protective net is not connected to the engineering piles when in use.
[0004] In view of this, a drainage engineering pile is proposed. Utility Model Content
[0005] The purpose of the utility model is to provide a drainage engineering pile in order to solve the above-mentioned problem. The pile has a drainage function and does not need to dig additional drainage wells. The protective net is fixedly connected to the main body of the engineering pile reinforcement cage.
[0006] The utility model achieves the above-mentioned purpose through the following technical scheme: a drainable engineering pile, comprising a foundation body, a pile hole is arranged on the foundation body, the pile hole is provided with an engineering pile concrete body, the top of the engineering pile concrete body is fixedly connected with an engineering pile steel cage body, the outer side wall of the engineering pile steel cage body is fixedly connected with a dense mesh, a gravel seepage filter layer is filled between the engineering pile steel cage body and the pile hole, a protective top net is arranged on the top of the engineering pile steel cage body, a through hole is arranged on the protective top net, a connecting component is arranged on the protective top net, and a shielding component for shielding the through hole is arranged on the top of the protective top net.
[0007] Furthermore, in order to fix the fixing nuts to the main body of the engineering pile reinforcement cage, the connection assembly includes fixing nuts, and the fixing nuts are fixedly installed on the top of the main body of the engineering pile reinforcement cage in a circular array.
[0008] Furthermore, in order to connect the fixing screw to the protective top net, the protective top net is provided with first threaded holes in a circumferential array, and the fixing screw is threadedly connected in the first threaded hole.
[0009] Furthermore, in order to connect the fixing screw with the fixing nut, one end of the fixing screw is screwed into the fixing nut.
[0010] Furthermore, in order to facilitate the installation and use of the vertical plate, the shielding assembly includes a vertical plate, the vertical plate is fixedly installed on the top of the protective top net, and a side groove is provided on one side of the vertical plate.
[0011] Furthermore, in order to enable the sliding block to slide in the side groove, a sliding block is slidably clamped in the side groove, one end of the sliding block is connected to a circular shielding plate, and the circular shielding plate is located at the top of the through hole.
[0012] Furthermore, in order to make the driving screw rod cooperate with the sliding block, a driving screw rod is rotatably installed in the side groove, a second threaded hole is provided on the sliding block, and one end of the driving screw rod is inserted into the second threaded hole.
[0013] Furthermore, in order to operate the driving screw rod through the handle, one end of the driving screw rod passes through the vertical plate, and a handle is installed and connected to one end of the driving screw rod.
[0014] Technical effects and advantages of the utility model:
[0015] The utility model is provided with a gravel water seepage filter layer, a close-mesh net and a protective top net. When the project is under construction, water in the foundation body can penetrate into the main body of the engineering pile steel cage through the gravel water seepage filter layer and the close-mesh net. Thereafter, the water inside the main body of the engineering pile steel cage can be extracted through an external pumping device. Since more engineering piles need to be arranged during the engineering construction, drainage of multiple engineering piles together can also meet the drainage requirements of the construction site. The protective top net is fixedly connected to the main body of the steel cage to prevent others from arbitrarily shifting the protective top net. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0017] Figure 2 It is a schematic diagram of the cross-sectional structure of the engineering pile concrete body and the engineering pile steel cage body in the utility model;
[0018] Figure 3 It is a schematic diagram of the connection between the engineering pile concrete body and the engineering pile steel cage body in the utility model;
[0019] Figure 4 It is an explosion diagram of the protective top net and the main body of the engineering pile reinforcement cage in the utility model;
[0020] Figure 5 It is a structural schematic diagram of the protective top net in the utility model;
[0021] In the figure: 1. foundation body; 2. engineering pile concrete body; 3. engineering pile steel cage body; 4. fine mesh; 5. gravel seepage filter layer; 6. protective top net; 7. through hole; 8. connection assembly; 801. fixing nut; 802. fixing screw; 9. shielding assembly; 901. vertical plate; 902. sliding block; 903. circular shielding plate; 904. driving screw; 905. handle. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] See also Figure 1-Figure 5 As shown, a drainable engineering pile comprises a foundation body 1, a pile hole is arranged on the foundation body 1, an engineering pile concrete body 2 is arranged on the pile hole, an engineering pile steel cage body 3 is fixedly connected to the top of the engineering pile concrete body 2, a dense mesh 4 is fixedly connected to the outer wall of the engineering pile steel cage body 3, the dense mesh 4 is permeable to water but not to mud, a gravel seepage filter layer 5 is filled between the engineering pile steel cage body 3 and the pile hole, a protective top net 6 is arranged on the top of the engineering pile steel cage body 3, the protective top net 6 can prevent others from falling, a through hole 7 is arranged on the protective top net 6, a connecting component 8 is arranged on the protective top net 6, and a shielding component 9 for shielding the through hole 7 is arranged on the top of the protective top net 6.
[0024] The connecting assembly 8 includes a fixing nut 801, which is fixedly installed in a circular array on the top of the engineering pile reinforcement cage body 3. The protective top net 6 is provided with a first threaded hole in a circular array, and a fixing screw 802 is threadedly connected in the first threaded hole. One end of the fixing screw 802 is screwed into the fixing nut 801. Since the protective top net 6 is fixed to the top of the engineering pile reinforcement cage body 3 by means of the fixing screw 802 and the fixing nut 801, it prevents others from arbitrarily displacing the protective top net 6, thereby improving safety.
[0025] The shielding assembly 9 includes a vertical plate 901, which is fixedly installed on the top of the protective top net 6. A side groove is provided on one side of the vertical plate 901, and a sliding block 902 is slidably engaged in the side groove. One end of the sliding block 902 is connected to a circular shielding plate 903, and the circular shielding plate 903 is located at the top of the through hole 7. A driving screw rod 904 is rotatably installed in the side groove. A second threaded hole is provided on the sliding block 902, and one end of the driving screw rod 904 is penetrated in the second threaded hole. One end of the driving screw rod 904 passes through the vertical plate 901, and a handle 905 is installed and connected to one end of the driving screw rod 904. When the through hole 7 is not in use, the through hole 7 can be blocked by the circular shielding plate 903 to prevent others from placing garbage and other items into the interior of the engineering pile steel cage body 3. When it is necessary to pump water from the inside of the engineering pile steel cage body 3, the user can raise the circular shielding plate 903, and then the water pumping pipe on the external water pumping device can be placed into the interior of the engineering pile steel cage body 3 through the through hole 7.
[0026] When the utility model is in use, during engineering construction, it is necessary to extend a part of the engineering pile concrete body 2 into the bearing layer, and the engineering pile steel cage body 3 is connected to the top of the engineering pile concrete body 2, so that the water source in the foundation body 1 can penetrate into the engineering pile steel cage body 3 through the stone seepage filter layer 5 and the dense mesh 4. When it is necessary to pump water inside the engineering pile steel cage body 3, the user can rotate the driving screw 904 through the handle 905, so as to drive the sliding block 902 and the circular shielding plate 903 to rise. After the circular shielding plate 903 rises, the through hole 7 can be exposed. Then the user can place the pumping pipe on the external pumping device through the through hole 7 on the protective top net 6 into the interior of the engineering pile steel cage body 3. After the external pumping device works, the water source inside the engineering pile steel cage body 3 can be extracted. Since more engineering piles need to be set during engineering construction, the drainage of multiple engineering piles together can also meet the drainage needs of the construction site. The protective top net 6 is fixedly connected to the steel cage body to prevent others from arbitrarily shifting the protective top net 6.
[0027] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.
[0028] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A drainable engineering pile, comprising a foundation body (1), wherein the foundation body (1) is provided with a pile hole, wherein the pile hole is provided with an engineering pile concrete body (2), and the top of the engineering pile concrete body (2) is fixedly connected with an engineering pile steel cage body (3), characterized in that: A dense mesh (4) is fixedly connected to the outer wall of the engineering pile reinforcement cage body (3); a gravel water seepage filter layer (5) is filled between the engineering pile reinforcement cage body (3) and the pile hole; a protective top mesh (6) is arranged on the top of the engineering pile reinforcement cage body (3); a through hole (7) is arranged on the protective top mesh (6); a connecting component (8) is arranged on the protective top mesh (6); and a shielding component (9) for shielding the through hole (7) is arranged on the top of the protective top mesh (6).
2. The drainable engineering pile according to claim 1, characterized in that: The connection assembly (8) comprises fixing nuts (801), and the fixing nuts (801) are fixedly mounted on the top of the engineering pile reinforcement cage body (3) in a circular array.
3. The drainable engineering pile according to claim 2, characterized in that: The protective top net (6) is provided with first threaded holes in a circumferential array, and a fixing screw (802) is threadedly connected in the first threaded holes.
4. The drainable engineering pile according to claim 3, characterized in that: One end of the fixing screw (802) is screwed into the fixing nut (801).
5. The drainable engineering pile according to claim 1, characterized in that: The shielding assembly (9) comprises a vertical plate (901), wherein the vertical plate (901) is fixedly mounted on the top of the protective top net (6), and a side groove is provided on one side of the vertical plate (901).
6. The drainable engineering pile according to claim 5, characterized in that: A sliding block (902) is slidably engaged in the side groove, one end of the sliding block (902) is connected to a circular shielding plate (903), and the circular shielding plate (903) is located at the top of the through hole (7).
7. The drainable engineering pile according to claim 6, characterized in that: A driving screw rod (904) is rotatably installed in the side groove, a second threaded hole is provided on the sliding block (902), and one end of the driving screw rod (904) is inserted into the second threaded hole.
8. The drainable engineering pile according to claim 7, characterized in that: One end of the driving screw rod (904) passes through the vertical plate (901), and a handle (905) is installed and connected to one end of the driving screw rod (904).