Concrete shear wall steel bar positioning device
By using adjustable installation base and positioning fixture in the shear wall steel bar positioning device, the problem of low steel bar deviation and binding efficiency in the prior art is solved, accurate positioning and stable installation of steel bars are achieved, and concrete pouring is improved Quality and binding efficiency.
Patent Information
- Application Number
- CN202420359002.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-27
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-02-27
AI Technical Summary
The existing shear wall reinforcement positioning cards have fixed type and simple binding methods, which can easily lead to steel bar deviation and affect the concrete pouring quality and binding efficiency.
Using a concrete shear wall rebar positioning device including mounting base and positioning fixture, the semi-arc clamp hole and hook are provided through an adjustable mounting support and clamp structure, combined with screw and rotary cap, to ensure accurate positioning of the rebar mesh and Stable installation.
It effectively avoids the deviation caused by external forces when the steel bars are poured into concrete, improves the quality of concrete casting and the efficiency of steel bar binding, and is suitable for concrete and steel bar sizes of different thicknesses.
Smart Images

Figure CN222066194U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building construction, and in particular relates to a concrete shear wall reinforcement positioning device. Background Art
[0002] Shear walls, also known as wind-resistant walls or earthquake-resistant walls, are a type of wall in a building structure that is mainly used to withstand horizontal loads caused by external forces such as earthquakes or strong winds to prevent lateral displacement of the building. In high-rise or super-high-rise buildings, shear walls have become a very important structural component due to the large floor heights and large horizontal loads. Shear walls are usually made of reinforced concrete and have high strength and rigidity. They can effectively resist horizontal loads and ensure the stability and safety of the building.
[0003] In shear walls, horizontal and vertical bars are the most common types of reinforcement, which are mainly used to bear horizontal and vertical loads, transfer loads and maintain the stability of the structure. Tie bars are used to connect the inner and outer reinforcements of the shear wall to enhance the integrity and stability of the structure.
[0004] In shear wall construction, the bundled steel bar components must first be installed in place, and then the molds and other parts must be installed, and finally the concrete must be poured. The installation of the steel bars in place is related to whether the subsequent concrete pouring meets the design requirements. In the prior art, the steel bar positioning tool uses a steel bar positioning card. By placing the positioning card on the shear wall formwork and inserting the steel bar into the positioning card according to the positioning diagram, the position of the steel bar can be ensured to be accurate. However, this type of positioning card has the problem of being fixed, with a simple binding method, and is prone to causing problems such as steel bar offset. Utility Model Content
[0005] The utility model aims to provide a concrete shear wall reinforcement positioning device, which changes the structure of a traditional positioning card so that the positioning card is more suitable for auxiliary operation during reinforcement binding, and can optimize the reinforcement binding operation and improve the binding efficiency.
[0006] In order to achieve the above purpose, the technical solution adopted by the utility model is specifically as follows:
[0007] A concrete shear wall reinforcement positioning device comprises a mounting base connected to a template and a plurality of positioning clamps connected below the mounting base; the mounting base comprises two mounting support rods arranged in the same direction as the template, and a positioning clamp mounting plate arranged between the two mounting support rods; each positioning clamp comprises at least two clamping plates, each clamping plate is provided with a plurality of semi-arc clamping holes adapted to the size of the reinforcement, and a screw rod is connected between the two clamping plates, and a rotating cap is rotatably connected to one end of the screw rod.
[0008] Furthermore, one of the clamping plates is fixed to the two mounting support rods by bolts.
[0009] Furthermore, a plurality of connecting hooks are arranged at intervals on the mounting support rod.
[0010] Furthermore, the size of the elbow of the connecting hook is adapted to the thickness of the template.
[0011] Furthermore, a plurality of grouting holes are provided on the fixture mounting plate.
[0012] Furthermore, reinforcing ribs are provided between the mounting support rods and the template.
[0013] Compared with the prior art, the advantages of the utility model are: the utility model adopts the use of an installation base and a positioning clamp connected to the base to position the steel mesh to be installed, and the positioning clamp is quickly clamped to effectively position the installed steel mesh, and can avoid the problem of displacement of the steel mesh due to external force factors when pouring concrete, effectively improve the quality of concrete pouring, and can also reduce the requirements for steel bar binding and improve binding efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.
[0015] Figure 1 The utility model is a structural schematic diagram of a concrete shear wall reinforcement positioning device provided by the utility model.
[0016] Figure 2 The utility model is a schematic diagram of the structure of a clamping plate of a concrete shear wall reinforcement positioning device.
[0017] Reference numerals:
[0018] 1. Template; 2. Clamp mounting plate; 3. Mounting support rod; 4. Reinforcement ribs; 5. Clamp plate; 6. Rotating cap; 7. Semi-arc clamp hole; 8. Screw; 9. Grouting hole. DETAILED DESCRIPTION
[0019] In order to make the purpose, technical solution and advantages of the embodiment of the utility model clearer, the technical solution in the embodiment of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiment of the utility model. Obviously, the described embodiment is a part of the embodiment of the utility model, not all of the embodiments. Based on the embodiment of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0020] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0021] In the description of the present utility model, it should be noted that if the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the accompanying drawings, or is the orientation or position relationship in which the utility model product is usually placed when used. It is only for the convenience of describing the utility model and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model.
[0022] In addition, the terms “first”, “second”, “third”, etc., if used, are merely used to distinguish between the descriptions and should not be understood as indicating or implying relative importance.
[0023] In addition, the terms "horizontal", "vertical", "overhanging", etc. do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.
[0024] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", "connection", etc. should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0025] It should be noted that, in the absence of conflict, the features in the embodiments of the present invention may be combined with each other.
[0026] like Figure 1-Figure 2As shown, a concrete shear wall reinforcement positioning device includes a mounting base connected to a template 1 and a plurality of positioning clamps connected below the mounting base; the mounting base includes two mounting support rods 3 arranged in the same direction as the template 1, and a positioning clamp mounting plate 2 arranged between the two mounting support rods 3; each positioning clamp includes at least two clamping plates 5, each clamping plate 5 is provided with a plurality of semi-arc clamping holes 7 adapted to the size of the reinforcement, and a screw rod 8 is connected between the two clamping plates 5, and a rotating cap 6 is rotatably connected to one end of the screw rod 8.
[0027] Compared with the prior art, in the prior art, ordinary positioning cards need to be made according to the grade, model and size of the steel bars. When the column bars are inserted and temporarily fixed, the positioning cards are installed to temporarily fix the steel bars before pouring. On the one hand, this type of positioning card also determines the installation position of the template 1 and the pouring thickness of the concrete by its radius. That is to say, for concrete of different design thicknesses, a large number of positioning cards of different diameters need to be equipped. This type of positioning card is inconvenient to store and has poor adaptability to different scenes. In the present utility model, a mounting base is set to be installed on the template 1, and the mounting support rods 3 of the mounting base are installed by installing a clamping plate 5, and the length of the clamping plate 5 is adjustable, so that the spacing between the mounting support rods 3 can be adjusted as needed, and it can be applicable to concrete of different thicknesses, and there is no need to customize positioning cards for concrete of different thicknesses. The two clamping plates 5 are driven to move closer and apart by the rotation of the screw rod 8, so that the semi-arc clamping holes 7 on the two clamping plates 5 can be clamped by matching, and the screw rod 8 has a strong anti-retraction effect to avoid loosening due to external force factors during pouring.
[0028] One of the clamping plates 5 is fixed to the two mounting rods 3 by bolts. By fixing one end and moving the other end, the steel bars can be clamped quickly, which has a significant effect on reducing the binding style and difficulty of the steel bars and improves work efficiency.
[0029] A plurality of connecting hooks are arranged at intervals on the mounting support rod 3. The size of the elbow of the connecting hook is adapted to the thickness of the template 1. The mounting support rod 3 is hooked on the template 1 through the connecting hooks, which is simple and quick.
[0030] A plurality of grouting holes 9 are provided on the fixture mounting plate 2. Grouting grooves can also be provided to avoid blocking the original grouting position after the positioning device provided by the utility model is installed.
[0031] A reinforcing rib 4 is provided between the mounting support rod 3 and the template 1. One end of the reinforcing rib 4 is against the template 1, and the other end is against the bottom of the mounting support rod 3 to strengthen the supporting force.
[0032] Specifically, when in use, the two mounting rods 3 are preferably installed on both sides of the template 1, and the reinforcing ribs 4 are used for auxiliary fixing, the bottom of the reinforcing ribs 4 are pressed against the outer surface of the template 1, and the other end of the reinforcing ribs 4 is pressed against the lower end of the mounting rods 3, and the overall fixing is completed. Then the fixture positioning plate is installed, the fixture mounting plate 2 is installed on the inner side of the template 1, and fixedly connected between the two already installed mounting rods 3; the fixture mounting plate 2 is mainly positioned by screws passing through the mounting rods 3, and the position of the fixture mounting plate 2 in the template 1 is adjusted by the length of the screws extending into the template 1. After the fixture mounting plate 2 is in place, two clamping plates 5 are installed. One of the clamping plates 5 is fixed to the fixture mounting plate 2 at both ends by screws. The two clamping plates 5 are movably connected by a screw rod 8, and the operation of the two clamping plates 5 moving in and out of contact is controlled by driving the screw rod 8, so that the two clamping plates 5 can be installed to temporarily clamp the steel mesh. The screw rod 8 is not easy to retreat, and the position of the steel bar can be kept without shaking during grouting. In addition, the structure can be suitable for concrete walls of different thicknesses and steel bars of different sizes and thicknesses, and the structure is more flexible and variable.
[0033] As described above, the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A concrete shear wall reinforcement positioning device, characterized in that: It comprises a mounting base connected to a template (1) and a plurality of positioning clamps connected below the mounting base; the mounting base comprises two mounting support rods (3) arranged in the same direction as the template (1), and a positioning clamp mounting plate (2) arranged between the two mounting support rods (3); each positioning clamp comprises at least two clamping plates (5), each clamping plate (5) is provided with a plurality of semi-arc clamping holes (7) adapted to the size of the steel bars, a screw rod (8) is connected between the two clamping plates (5), and a rotating cap (6) is rotatably connected to one end of the screw rod (8).
2. The concrete shear wall reinforcement positioning device according to claim 1 is characterized in that: One of the clamping plates (5) is fixed to the two mounting support rods (3) by means of bolts.
3. The concrete shear wall reinforcement positioning device according to claim 2 is characterized in that: A plurality of connecting hooks are arranged at intervals on the mounting support rod (3).
4. The concrete shear wall reinforcement positioning device according to claim 3 is characterized in that: The size of the elbow of the connecting hook is adapted to the thickness of the template (1).
5. The concrete shear wall reinforcement positioning device according to claim 1, characterized in that: The fixture mounting plate (2) is provided with a plurality of grouting holes (9).
6. The concrete shear wall reinforcement positioning device according to claim 1, characterized in that: A reinforcing rib (4) is provided between the mounting support rod (3) and the template (1).