Expressway water damage repairing device
By combining the solid soil module and compacted pipe of the highway water damage repair device, the problem of unsustainable highway water damage repair in the existing technology is solved, and the stability and fixation of the roadbed and road surface is achieved, reducing the possibility of water damage is ensured. Long-term traffic capacity of expressways.
Patent Information
- Application Number
- CN202420635721.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-29
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-03-29
AI Technical Summary
The existing highway water damage repair methods are used to treat the symptoms but not the root cause, resulting in water damage on the highway again, affecting normal use.
The highway water damage repair device including pile columns and soil solid modules is adopted. The roadbed is nailed into the roadbed through pile columns and embedded in the soil solid module, so that it is formed integrally with the concrete filler in the compacted pipe to form a stable road surface and reduce the water damage of the roadbed and road surfaces. possibilities.
Effectively cure the roadbed and pavement, reduce the possibility of water damage, and ensure the long-term and stable use of the expressway.
Smart Images

Figure CN222083236U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of highway maintenance, in particular to a highway water damage repair device. Background Art
[0002] Expressways, or highways for short, are roads designed for high-speed driving of cars. Expressways have different regulations in different countries, regions, eras, and scientific research fields. According to China's Highway Engineering Technical Standards (JTG B01-2014), expressways are multi-lane roads designed for cars to drive in different directions and lanes, with full access control. The average annual daily design traffic volume of expressways should be more than 15,000 passenger cars, with a design speed of 80 to 120 kilometers per hour.
[0003] Highways are damaged by water every year. In mild cases, the roadbed and pavement are damaged, affecting the highway's traffic capacity. In severe cases, bridges are washed away, interrupting traffic, and the resulting losses are quite serious.
[0004] Highway water damage is often caused by loose soil on the roadbed and slopes, unsuitable soil or roadbed filling materials, long-term water accumulation on the roadbed, softening of the roadbed soil when exposed to water, causing roadbed settlement and collapse, and then road water damage. The existing method of repairing highway water damage is generally to re-compact the water-damaged section and pour new pavement, but this repair method only treats the symptoms and not the root cause. The re-compacted pavement will soften again after being exposed to water for a long time, causing the highway to be water damaged again, affecting the normal use of the highway. Utility Model Content
[0005] In order to solve the above technical problems, a highway water damage repair device is provided.
[0006] In order to achieve the above purpose, the following scheme is provided: a highway water damage repair device, comprising a pile column and a plurality of soil-fixing modules, each of the soil-fixing modules is evenly installed on the side of the pile column, the pile column comprises a top head and a tamping tube, the top head is fixedly installed at one end of the tamping tube, the tamping tube is a hollow tubular structure, and a plurality of through holes are evenly arranged on the side wall of the tamping tube, the soil-fixing module is installed at the through hole, the soil-fixing module comprises a movable hammer, a connecting cable and a limit block, the movable hammer is fixedly connected to one end of the connecting cable, the other end of the connecting cable is fixedly connected to the limit block, the limit block is located in the tamping tube, and the connecting cable passes through the through hole.
[0007] Furthermore, the sizes of the limit block and the movable hammer are both larger than the size of the through hole, and the limit block is a flat long strip structure.
[0008] Furthermore, the movable hammer is in a spherical structure.
[0009] Furthermore, the top head is in a conical or pyramidal structure.
[0010] Furthermore, the tamping tube is filled with concrete filler.
[0011] The working principle and advantages of the utility model are as follows: by installing multiple highway water damage repair devices on the water-damaged section of the highway, the devices are nailed into the water-damaged section, and the soil-fixing module of the device can move with the address of the land, so that the soil-fixing module is embedded in the soil around the tamping tube, thereby fixing the roadbed soil of the highway. At the same time, the concrete pouring pavement of the highway and the concrete filler filled in the tamping tube are integrally formed, so that the highway pavement can be firmly poured on the roadbed, and under the coordinated action of each tamping tube, the roadbed is tightened, effectively reducing the possibility of water damage to the roadbed and the road surface. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is the front view of the utility model;
[0013] Figure 2 It is a top view of the utility model;
[0014] Figure 3 This is a structural diagram of the tamping pipe of the utility model;
[0015] Figure 4 This is a structural diagram of the soil consolidation module of the utility model.
[0016] The reference numerals in the drawings of the specification include:
[0017] 1. Top head, 2. Ramming pipe, 3. Through hole, 4. Movable hammer, 5. Connecting rope, 6. Limit block, 7. Concrete filler. DETAILED DESCRIPTION
[0018] The following is a further detailed description through specific implementation methods:
[0019] like Figures 1 to 4 As shown:
[0020] A highway water damage repair device, which mainly consists of a pile column and a plurality of soil-fixing modules, each soil-fixing module is evenly installed on the side of the pile column, so that when the pile column is nailed into the roadbed, each soil-fixing module can be embedded in the roadbed, so that in the process of geological movement of the soil of the roadbed in the later stage, the soil-fixing module is gradually embedded in the soil around the pile column, thereby realizing the soil-fixing function; the pile column is mainly composed of a top head 1 and a tamping tube 2, and the top head 1 of the fixed installation rod at one end of the tamping tube 2 is convenient for the tamping tube 2 to be nailed into the roadbed, and the tamping tube 2 can squeeze the soil inside the roadbed, thereby achieving the squeezing and compacting of the roadbed, and the tamping tube 2 is filled with concrete filler 7, and the concrete filler 7 is integrally formed with the cast road surface, so that the road The surface can be cast on the roadbed more firmly, reducing the possibility of road damage; the compacting tube 2 is a tubular structure and a plurality of through holes 3 are opened on its side wall. The through holes 3 are used to install the soil consolidation module. At the same time, the concrete filler 7 filled in the compacting tube 2 can flow out of the outside of the compacting tube 2 from the through holes 3 and mix with the soil to make the soil more solid; the soil consolidation module is composed of a movable hammer 4, a connecting cable 5 and a limit block 6. The movable hammer 4 and the limit block 6 are respectively fixedly mounted at the two ends of the connecting cable 5, and the connecting cable 5 is connected to the middle of the limit block 6. The connecting cable 5 is made of anti-corrosion and wear-resistant material. The limit block 6 can pass through the through hole 3 and be inserted into the compacting tube 2, reducing the possibility of the soil consolidation module detaching from the compacting tube 2.
[0021] The sizes of the limit block 6 and the movable hammer 4 are both larger than the size of the through hole 3, preventing the limit block 6 and the movable hammer 4 from passing through the through hole 3 at will. The limit block 6 is a flat, long strip structure. The length of the limit block 6 is larger than the size of the through hole 3, and its width is slightly smaller than the size of the through hole 3, so that the limit block 6 can penetrate into the through hole 3 without escaping from the through hole 3 at will.
[0022] The movable hammer 4 is in a spherical structure, so that the movable hammer 4 can move in the soil along with the soil.
[0023] The top head 1 is in a conical or pyramidal structure, which is convenient for nailing the compaction pipe 2 into the roadbed.
[0024] The specific implementation process is as follows:
[0025] When using the highway water damage repair device, first install each soil consolidation module at the through hole 3 on the side of the tamping tube 2 as needed, insert the soil consolidation module limit block 6 into the through hole 3, and then nail multiple devices into the water-damaged section of the highway. Due to the presence of the top head 1, the tamping tube 2 can be more easily inserted into the roadbed of the water-damaged section; the tamping tube 2 is inserted into the roadbed to squeeze and compact the roadbed, and at the same time, the tamping tube 2 drives the soil consolidation module to be buried in the roadbed together, and then the roadbed is leveled and the road surface is poured on the roadbed, and the concrete filler 7 At the same time, it enters the compacting tube 2, so that the concrete filler 7 in the compacting tube 2 is formed as one piece with the road surface, and multiple highway water damage repair devices are fixed to the roadbed with the road surface, so that the connection between the roadbed and the road surface is more firm. At the same time, each compacting tube 2 works synergistically with the concrete filler inside to fix the roadbed and reduce the occurrence of water damage to the roadbed; and when the geological activity of the roadbed occurs, the movable hammer 4 and the connecting cable 5 can gradually move and embed into the soil around the compacting tube 2, thereby consolidating the soil and filler of the roadbed and reducing the possibility of water damage to the roadbed.
[0026] By installing multiple highway water damage repair devices on the water-damaged section of the highway, the device is nailed into the water-damaged section. The soil consolidation module of the device can move with the ground address, so that the soil consolidation module is embedded in the soil around the tamping tube 2, and then the roadbed soil of the highway is consolidated. At the same time, the concrete pouring pavement of the highway and the concrete filler 7 filled into the tamping tube 2 are integrally formed, so that the highway pavement can be firmly cast on the roadbed. Under the coordinated action of each tamping tube 2, the roadbed is tightened, effectively reducing the possibility of water damage to the roadbed and pavement.
[0027] The above is only an embodiment of the utility model. The common sense such as the known specific structure and characteristics in the scheme is not described in detail here. The ordinary technicians in the relevant field know all the common technical knowledge in the technical field of the utility model before the application date or priority date, can obtain all the existing technologies in the field, and have the ability to apply the conventional experimental means before that date. The ordinary technicians in the relevant field can improve and implement this scheme in combination with their own abilities under the enlightenment given by this application. Some typical known structures or known methods should not become obstacles for ordinary technicians in the relevant field to implement this application. It should be pointed out that for the technicians in this field, without departing from the structure of the utility model, several deformations and improvements can be made, which should also be regarded as the protection scope of the utility model, which will not affect the effect of the implementation of the utility model and the applicability of the patent. The protection scope required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to explain the content of the claims.
Claims
1. A highway water damage repair device, characterized by: It includes a pile column and several soil-fixing modules, each of the soil-fixing modules is evenly installed on the side of the pile column, the pile column includes a top head and a tamping tube, the top head is fixedly installed at one end of the tamping tube, the tamping tube is a hollow tubular structure, and several through holes are evenly arranged on the side wall of the tamping tube, the soil-fixing module is installed at the through hole, the soil-fixing module includes a movable hammer, a connecting cable and a limit block, the movable hammer is fixedly connected to one end of the connecting cable, the other end of the connecting cable is fixedly connected to the limit block, the limit block is located in the tamping tube, and the connecting cable passes through the through hole.
2. The highway water damage repair device according to claim 1 is characterized by: The sizes of the limit block and the movable hammer are both larger than the size of the through hole, and the limit block is in a flat long strip structure.
3. The highway water damage repair device according to claim 2 is characterized by: The movable hammer is in a spherical structure.
4. The highway water damage repair device according to claim 1 is characterized by: The top head is in a conical or pyramidal structure.
5. The highway water damage repair device according to claim 1 is characterized by: The tamping tube is filled with concrete filler.
Citation Information
Cited By
A device for repairing water-damaged roadbeds