Piling device for cofferdam wharf construction

By introducing soil softening, reinforcement and clamping devices into the pile driving device for cofferdam dock construction, the accuracy problems caused by device shaking and dry and cracked soil are solved, and higher pile driving stability and convenience are achieved.

CN222083546UActive Publication Date: 2024-11-29HANGZHOU FUSHIDE GEOTECHNICAL TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202322927693.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-10-31
Publication Date
2024-11-29
Estimated Expiration
2033-10-31

AI Technical Summary

Technical Problem

The existing pile driving device for cofferdam wharf construction is prone to deviating from position or angle due to shaking during use, and the soil is dry and hard in hot weather, making it difficult to drive piles, which affects the accuracy and working efficiency of the device.

Method used

A pile driving device for cofferdam terminal construction including a soil softening device, a reinforcement device and a clamping device is designed. The soil softening device humidifies and softens the soil through a water tank, a water pump and a water spray board, the reinforcement device increases stability through a support column and a fixed plate, and the clamping device ensures the accuracy of the position of the wooden piles through a power motor and a track.

Benefits of technology

Through the combination of soil softening, reinforcement and clamping devices, the accuracy and stability of pile driving are achieved, preventing position or angle deviation, and improving the functionality and working efficiency of the device, especially the convenience of pile driving under dry and cracked soil conditions .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222083546U_ABST
    Figure CN222083546U_ABST
Patent Text Reader

Abstract

The utility model discloses a pile driving device for cofferdam wharf construction, which relates to the technical field of pile driving for cofferdam wharf construction and comprises a main body, a first supporting column is arranged at the upper end of the main body, a supporting plate is arranged at the upper end of the first supporting column, a motor box is arranged at the upper end of the supporting plate, and a pile driving column is arranged at the lower end of the supporting plate. A clamping device is arranged on the right side of the main body, a reinforcing device is arranged at the lower end of the main body, and a soil softening device is arranged on the left side of the main body. According to the device, soil at the piling position can be humidified and softened, piling of the device is easier and more accurate, firmness of the device is improved, connection between the devices is firmer and more stable, the device is prevented from shaking during piling, stability of the device is improved, the device can be clamped by clamping a timber pile, and the device is more convenient to use. And the timber piles are limited in the transverse direction, position or angle deviation is prevented when the device is used for piling, and the functionality of the device is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of piling for cofferdam wharf construction, in particular to a piling device for cofferdam wharf construction. Background Art

[0002] A pile driver is a type of equipment commonly used in building construction and bridge engineering. It is mainly used to drive reinforced concrete piles or wooden piles into the ground to fix buildings or bridge structures. The pile driver uses the gravity of a heavy hammer to hit the piles through the principle of free fall to achieve depth and fixation effect. Specifically, the heavy hammer of the pile driver is lifted upward by the control of the oil cylinder, and then falls freely by gravity, hitting the reinforced concrete pile or wooden pile, and then rebounds, and repeats this process until the reinforced concrete pile or wooden pile is completely underground or fixed. The following problems exist in the prior art:

[0003] 1. The existing piling device for cofferdam wharf construction may cause the wood pile to deviate from the required piling position or the angle of the wood pile due to the shaking of the device during piling, which affects the accuracy of the device, making it impossible for workers to complete subsequent work and reducing the working efficiency of the device;

[0004] 2. The existing piling device for cofferdam wharf construction, when in use, when the device is driving piles, the weather is hot for a long time, resulting in the soil at the piling location being hard and dry, making it difficult to drive wooden piles. Utility Model Content

[0005] In order to solve the above technical problems, the technical solution adopted by the utility model is:

[0006] A piling device for cofferdam wharf construction comprises a main body, a first supporting column is arranged at the upper end of the main body, a supporting plate is arranged at the upper end of the first supporting column, a motor box is arranged at the upper end of the supporting plate, a piling column is arranged at the lower end of the supporting plate, a clamping device is arranged on the right side of the main body, a reinforcing device is arranged at the lower end of the main body, and a soil softening device is arranged on the left side of the main body.

[0007] A further improvement of the technical solution of the utility model is that the soil softening device includes a water tank, a water outlet is provided at the lower end of the water tank, a water pump is provided on the right side of the water outlet, a first fixing plate is provided on both sides of the water pump, first fixing nuts are provided on both sides of the first fixing plate, a water pipe is provided on the right side of the first fixing plate, and a water spray plate is provided on the right side of the upper end of the water pipe.

[0008] A further improvement of the technical solution of the utility model is that: the lower right end of the water tank is fixedly connected to the left side of the water outlet, the right side of the water outlet is fixedly connected to the left side of the first fixed plate, the upper and lower sides of the first fixed plate are fixedly connected to the left side of the water pump through the first fixing nut, and the lower left end of the water pipe is fixedly connected to the right side of the water pump.

[0009] A further improvement of the technical solution of the utility model is that: the reinforcement device includes a second support column, second fixing plates are arranged on both sides of the second support column, a third support column is arranged on one side of the second fixing plate, a first connecting plate is arranged at the lower end of the second support column, pin holes are arranged on both sides of the first connecting plate, a pin nail is arranged in the middle of the pin hole, and one side of the second fixing plate is fixedly connected to one side of the second fixing nut.

[0010] A further improvement of the technical solution of the utility model is that: a second fixing plate is fixedly connected to both sides of the third support column, the lower end of the second support column is fixedly connected to the upper end of the first connecting plate, and pin holes are fixedly connected to the middle parts of both sides of the first connecting plate, and the middle part of the pin hole is pin-connected to the outer end of the pin nail.

[0011] A further improvement of the technical solution of the utility model is that the clamping device includes a power motor, a crawler track is arranged on the right side of the power motor, a threaded column is arranged on the upper end of the crawler track, rotors are arranged on both sides of the threaded column, a sliding block is arranged in the middle of the threaded column, a connecting column is arranged on the upper end of one side of the sliding block, a sliding shaft is arranged in the middle of the connecting column, a second connecting plate is arranged on the outside of the sliding shaft, a clamping plate is arranged on one side of the upper end of the connecting column, and a roller is arranged in the middle of the clamping plate.

[0012] A further improvement of the technical solution of the utility model is that: the right side of the power motor is movably connected to the track, the upper end of the track is movably connected to the threaded column, both sides of the threaded column are movably connected to one side of the rotor, the middle part of the threaded column is slidably connected to the middle part of the sliding block, the middle part of the connecting column is fixedly connected to the middle part of the sliding shaft, the outer end of the sliding shaft is slidably connected to the middle part of the second connecting plate, one side of the upper end of the connecting column is fixedly connected to one side of the clamping plate, and the middle part of the clamping plate is slidably connected to one side of the roller.

[0013] Due to the adoption of the above technical solution, the utility model has achieved the following technical progress compared with the prior art:

[0014] The utility model provides a piling device for cofferdam wharf construction. Through the joint action of a water tank, a water pump, a water pipe, a water spray plate, a water outlet, a first fixing plate and a first fixing nut, the device can humidify the soil at the piling position to soften the soil, so that the device can piling more easily and accurately, and prevent the soil from being relatively dry and hard on a sunny day, causing the piling position of the device to shift and affecting the accuracy of the device. When the soil needs to be softened, the water pump is started to extract water from the inside of the water tank, and the water flows out from the water outlet at the lower end of the water tank. The first fixing plate at one end of the water pipe is fixed to one end of the water pump through the first fixing nut, so that the water pump can inject water into the water spray plate through the water pipe, so that the water flows out from the water spray plate, and the water is sprayed onto the wooden piles, so that the water flows down from the outer wall of the wooden piles, so that the hard soil at the lower end of the wooden piles is softened, which is beneficial for the device to quickly drive the wooden piles into the soil, thereby increasing the functionality and convenience of the device.

[0015] The utility model provides a piling device for cofferdam wharf construction, through the joint action of the second support column, the third support column, the first connecting plate, the second fixing plate, the second fixing nut, the pin hole and the pin nail, the device can be reinforced at the bottom to prevent the device from being unstable during piling, the device shaking during piling, causing the wooden pile to deviate, affecting the accuracy of the device, and increasing the firmness of the device. When piling is required, the lower end of the second support column is fixedly connected to the first connecting plate, and the two ends of the third support column pass through the second fixing plate to fix the second support column and the first connecting plate through the second fixing nut, and the two sides of the second support column are supported by the third support column, and the second support column and the third support columns on both sides of the second support column form a triangular structure, and the stability of the triangle is utilized to make the connection between the devices more firm and stable, and the pin nail is inserted into the pin hole and deeply inserted into the ground, so as to prevent the device from shaking during piling, causing the piling position of the device to deviate, affecting the accuracy of the device, and increasing the stability of the device.

[0016] The utility model provides a piling device for cofferdam wharf construction. Through the joint action of a second connecting plate, a sliding shaft, a clamping plate, a connecting column, a power motor, a crawler, a sliding block, a threaded column, a rotor and a roller, the device can clamp the wooden pile to determine the piling position, thereby preventing the position or angle from being offset when the device is driving the pile, thereby affecting the accuracy of the device's piling and increasing the functionality of the device. When the device is driving the pile, the power motor is started, and the power motor drives the threaded column to rotate through the crawler. The threads on both sides of the middle of the threaded column are opposite, and the threaded column rotates in the middle of the rotor to make the sliding block The moving block moves toward the middle, and the sliding block drives the sliding shaft of the connecting column to move toward each other on the second connecting plate, so that the clamping plates move toward each other, clamp the pile, and determine the piling position. The roller can roll freely in the middle of the clamping plate, so that the pile can move up and down in the vertical direction, and limit the pile in the horizontal direction to prevent the position angle of the pile from shifting when the device is piling, which affects the accuracy of the device's piling. When the device completes piling, the power motor drives the crawler to move in the opposite direction of the upper direction, so that the clamping plate leaves the pile and gives up clamping the pile, thereby increasing the functionality of the device. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a structural schematic diagram of a piling device for cofferdam wharf construction of the utility model.

[0018] Figure 2 It is a structural schematic diagram of the soil softening device of the utility model.

[0019] Figure 3 It is a structural schematic diagram of the stabilizing device of the utility model.

[0020] Figure 4 It is a structural schematic diagram of the clamping device of the utility model.

[0021] In the figure: 1. main body; 2. soil softening device; 3. reinforcement device; 4. support plate; 5. motor box; 6. pile column; 7. first support column; 8. clamping device; 21. water tank; 22. water pump; 23. water pipe; 24. water spray plate; 25. water outlet; 26. first fixing plate; 27. first fixing nut; 31. second support column; 32. third support column; 33. first connecting plate; 34. second fixing plate; 35. second fixing nut; 36. pin hole; 37. pin; 81. second connecting plate; 82. sliding shaft; 83. clamping plate; 84. connecting column; 85. power motor; 86. crawler; 87. sliding block; 88. threaded column; 89. rotor; 810. roller. DETAILED DESCRIPTION

[0022] The present invention is further described in detail below in conjunction with the embodiments: Example 1

[0023] like Figure 1-4 As shown, the utility model provides a piling device for cofferdam wharf construction, including a main body 1, a first supporting column 7 is arranged at the upper end of the main body 1, a supporting plate 4 is arranged at the upper end of the first supporting column 7, a motor box 5 is arranged at the upper end of the supporting plate 4, a piling column 6 is arranged at the lower end of the supporting plate 4, a clamping device 8 is arranged on the right side of the main body 1, a reinforcing device 3 is arranged at the lower end of the main body 1, and a soil softening device 2 is arranged on the left side of the main body 1. Example 2

[0024] like Figure 1-4 As shown, on the basis of Example 1, the utility model provides a technical solution: preferably, the soil softening device 2 includes a water tank 21, a water outlet 25 is provided at the lower end of the water tank 21, a water pump 22 is provided on the right side of the water outlet 25, first fixing plates 26 are provided on both sides of the water pump 22, first fixing nuts 27 are provided on both sides of the first fixing plate 26, a water pipe 23 is provided on the right side of the first fixing plate 26, a water spray plate 24 is provided on the right side of the upper end of the water pipe 23, the lower right end of the water tank 21 is fixedly connected to the left side of the water outlet 25, the right side of the water outlet 25 is fixedly connected to the left side of the first fixing plate 26, the upper and lower sides of the first fixing plate 26 are fixedly connected to the left side of the water pump 22 through the first fixing nut 27, and the left side of the lower end of the water pipe 23 is fixedly connected to the right side of the water pump 22.

[0025] In this embodiment, the device can humidify the soil at the piling position to soften the soil, making it easier and more accurate for the device to drive piles, and preventing the soil from being relatively dry and hard on sunny days, causing the device to deviate from the piling position and affecting the accuracy of the device. When the soil needs to be softened, the water pump 22 is started to extract water from the inside of the water tank 21, and the water flows out from the water outlet 25 at the lower end of the water tank 21. The first fixing plate 26 at one end of the water pipe 23 is fixed to one end of the water pump 22 by the first fixing nut 27, so that the water pump 22 can inject water into the water spray plate 24 through the water pipe 23, so that the water flows out from the water spray plate 24, and the water is sprayed onto the piles, so that the water flows down from the outer wall of the piles, so that the hard soil at the lower end of the piles is softened, which is beneficial for the device to quickly drive the piles into the soil, thereby increasing the functionality and convenience of the device. Example 3

[0026] like Figure 1-4As shown, on the basis of Example 1, the utility model provides a technical solution: preferably, the reinforcement device 3 includes a second support column 31, second fixing plates 34 are arranged on both sides of the second support column 31, a third support column 32 is arranged on one side of the second fixing plate 34, a first connecting plate 33 is arranged at the lower end of the second support column 31, pin holes 36 are arranged on both sides of the first connecting plate 33, a pin nail 37 is arranged in the middle of the pin hole 36, one side of the second fixing plate 34 is fixedly connected to one side of the second fixing nut 35, the second fixing plates 34 are fixedly connected to both sides of the third support column 32, the lower end of the second support column 31 is fixedly connected to the upper end of the first connecting plate 33, the middle parts of both sides of the first connecting plate 33 are fixedly connected with pin holes 36, and the middle parts of the pin holes 36 are pin-connected to the outer ends of the pin nails 37.

[0027] In this embodiment, the device can be reinforced at the bottom to prevent the device from being unstable during piling, the device shaking during piling, causing the piles to shift, affecting the accuracy of the device, and increasing the firmness of the device. When piling is required, the lower end of the second support column 31 is fixedly connected to the first connecting plate 33, and the two ends of the third support column 32 are fixedly connected to the second support column 31 and the first connecting plate 33 through the second fixing nut 35 through the second fixing plate 34. The two sides of the second support column 31 are supported by the third support column 32. The second support column 31 and the third support columns 32 on both sides thereof form a triangular structure. The stability of the triangle is utilized to make the connection between the devices more firm and stable. The pin 37 is inserted into the pin hole 36 and deeply inserted into the ground to prevent the device from shaking during piling, causing the piling position of the device to shift, affecting the accuracy of the device, and increasing the stability of the device. Example 4

[0028] like Figure 1-4As shown, on the basis of Example 1, the utility model provides a technical solution: preferably, the clamping device 8 includes a power motor 85, a crawler 86 is arranged on the right side of the power motor 85, a threaded column 88 is arranged on the upper end of the crawler 86, rotors 89 are arranged on both sides of the threaded column 88, a sliding block 87 is arranged in the middle of the threaded column 88, a connecting column 84 is arranged on the upper end of one side of the sliding block 87, a sliding shaft 82 is arranged in the middle of the connecting column 84, a second connecting plate 81 is arranged on the outside of the sliding shaft 82, a clamping plate 83 is arranged on one side of the upper end of the connecting column 84, and the clamping A roller 810 is provided in the middle of the holding plate 83, the right side of the power motor 85 is movably connected to the track 86, the upper end of the track 86 is movably connected to the threaded column 88, the two sides of the threaded column 88 are movably connected to one side of the rotor 89, the middle of the threaded column 88 is slidably connected to the middle of the sliding block 87, the middle of the connecting column 84 is fixedly connected to the middle of the sliding shaft 82, the outer end of the sliding shaft 82 is slidably connected to the middle of the second connecting plate 81, one side of the upper end of the connecting column 84 is fixedly connected to one side of the clamping plate 83, and the middle of the clamping plate 83 is slidably connected to one side of the roller 810.

[0029] In this embodiment, the device can clamp the pile to determine the piling position, prevent the position or angle deviation when the device is piling, and affect the accuracy of the device piling, thereby increasing the functionality of the device. When the device is piling, the power motor 85 is started, and the power motor 85 drives the threaded column 88 to rotate through the crawler 86. The threads on both sides of the middle of the threaded column 88 are opposite. The threaded column 88 rotates in the middle of the rotor 89, so that the sliding block 87 moves toward the middle, and the sliding block 87 drives the sliding shaft 82 of the connecting column 84 to rotate on the second connecting plate 8 1 moves toward each other, so that the clamping plates 83 move toward each other, clamp the wood pile, and determine the piling position. The roller 810 can roll freely in the middle of the clamping plate 83, so that the wood pile can move up and down in the vertical direction, and limit the wood pile in the horizontal direction to prevent the wood pile position angle from deviating during the piling, which affects the accuracy of the piling of the device. When the piling of the device is completed, the power motor 85 drives the crawler 86 to move in the opposite direction from the upper direction, so that the clamping plate 83 leaves the wood pile and gives up clamping the wood pile, thereby increasing the functionality of the device.

[0030] The working principle of the piling device used in the cofferdam wharf construction is described in detail below.

[0031] like Figure 1-4As shown, the device can humidify the soil at the piling position to soften the soil, making it easier and more accurate for the device to drive the pile, and preventing the soil from being dry and hard on sunny days, causing the device to deviate from the piling position and affecting the accuracy of the device. When the soil needs to be softened, the water pump 22 is started to extract water from the inside of the water tank 21, and the water flows out from the water outlet 25 at the lower end of the water tank 21. The first fixing plate 26 at one end of the water pipe 23 is fixed to one end of the water pump 22 through the first fixing nut 27, so that the water pump 22 can inject water into the water spray plate 24 through the water pipe 23, so that the water flows out from the water spray plate 24, and the water is sprayed onto the pile, so that the water flows down from the outer wall of the pile, making the lower end of the pile hard. The hard soil is softened, which is conducive to the device to quickly drive the wood piles into the soil, increasing the functionality and convenience of the device. The device can be reinforced at the bottom to prevent the device from being unstable when driving piles. The device shakes during driving piles, causing the wood piles to deviate, affecting the accuracy of the device, and increasing the firmness of the device. When it is necessary to drive piles, the lower end of the second support column 31 is fixedly connected to the first connecting plate 33, and the two ends of the third support column 32 are fixedly connected to the second support column 31 and the first connecting plate 33 through the second fixing nut 35 through the second fixing plate 34. The two sides of the second support column 31 are supported by the third support column 32, and the second support column 31 and the third support columns on both sides of it are fixedly connected. 32 forms a triangular structure, and the stability of the triangle is utilized to make the connection between the devices more firm and stable. The pin 37 is inserted into the pin hole 36 and deeply inserted into the ground to prevent the device from shaking during piling, causing the piling position of the device to deviate and affect the accuracy of the device, thereby increasing the stability of the device. The device can clamp the wooden pile to determine the piling position, thereby preventing the position or angle from deviating during piling, thereby affecting the accuracy of the piling of the device and increasing the functionality of the device. When the device is piling, the power motor 85 is started, and the power motor 85 drives the threaded column 88 to rotate through the crawler 86. The threads on both sides of the middle of the threaded column 88 are opposite, and the threaded column 88 is The middle part of the rotor 89 rotates, causing the sliding block 87 to move toward the middle part. The sliding block 87 drives the sliding shaft 82 of the connecting column 84 to move toward each other on the second connecting plate 81, causing the clamping plates 83 to move toward each other, clamping the piles and determining the piling position. The roller 810 can roll freely in the middle part of the clamping plate 83, allowing the piles to move up and down in the vertical direction, limiting the piles in the horizontal direction, preventing the position angle of the piles from shifting when the device is piling, thereby affecting the accuracy of the piling. When the device completes piling, the power motor 85 drives the crawler 86 to move in the opposite direction from the upper direction, causing the clamping plate 83 to leave the piles and give up clamping the piles, thereby increasing the functionality of the device.

[0032] The above generally describes the present invention in detail, but it is obvious to a person skilled in the art that some modifications or improvements can be made to the present invention. Therefore, modifications or improvements that do not deviate from the spirit of the present invention are within the scope of protection of the present invention.

Claims

1. A piling device for cofferdam wharf construction, comprising a main body (1), characterized in that: The upper end of the main body (1) is provided with a first support column (7), the upper end of the first support column (7) is provided with a support plate (4), the upper end of the support plate (4) is provided with a motor box (5), the lower end of the support plate (4) is provided with a pile driving column (6), the right side of the main body (1) is provided with a clamping device (8), the lower end of the main body (1) is provided with a reinforcement device (3), the left side of the main body (1) is provided with a soil softening device (2), the clamping device (8) includes a power motor (85), the right side of the power motor (85) is provided with a crawler (86), the upper end of the crawler (86) is provided with a threaded column (88), both sides of the threaded column (88) are provided with rotors (89), the middle part of the threaded column (88) is provided with a sliding block (87), the upper end of one side of the sliding block (87) is provided with a connecting column (84), the middle part of the connecting column (84) is provided with A sliding shaft (82) is provided, a second connecting plate (81) is provided outside the sliding shaft (82), a clamping plate (83) is provided on one side of the upper end of the connecting column (84), a roller (810) is provided in the middle of the clamping plate (83), the right side of the power motor (85) is movably connected to the crawler (86), the upper end of the crawler (86) is movably connected to the threaded column (88), and both sides of the threaded column (88) are connected to the rotor (89). One side is movably connected, the middle part of the threaded column (88) is slidably connected to the middle part of the sliding block (87), the middle part of the connecting column (84) is fixedly connected to the middle part of the sliding shaft (82), the outer end of the sliding shaft (82) is slidably connected to the middle part of the second connecting plate (81), one side of the upper end of the connecting column (84) is fixedly connected to one side of the clamping plate (83), and the middle part of the clamping plate (83) is slidably connected to one side of the roller (810).

2. A piling device for cofferdam wharf construction according to claim 1, characterized in that: The soil softening device (2) comprises a water tank (21), a water outlet (25) is arranged at the lower end of the water tank (21), a water pump (22) is arranged on the right side of the water outlet (25), first fixing plates (26) are arranged on both sides of the water pump (22), first fixing nuts (27) are arranged on both sides of the first fixing plate (26), a water pipe (23) is arranged on the right side of the first fixing plate (26), and a water spray plate (24) is arranged on the right side of the upper end of the water pipe (23).

3. A piling device for cofferdam wharf construction according to claim 2, characterized in that: The lower right end of the water tank (21) is fixedly connected to the left side of the water outlet (25), the right side of the water outlet (25) is fixedly connected to the left side of the first fixing plate (26), the upper and lower sides of the first fixing plate (26) are fixedly connected to the left side of the water pump (22) via a first fixing nut (27), and the left side of the lower end of the water pipe (23) is fixedly connected to the right side of the water pump (22).

4. A piling device for cofferdam wharf construction according to claim 1, characterized in that: The reinforcing device (3) comprises a second supporting column (31), second fixing plates (34) are arranged on both sides of the second supporting column (31), a third supporting column (32) is arranged on one side of the second fixing plate (34), a first connecting plate (33) is arranged at the lower end of the second supporting column (31), pin holes (36) are arranged on both sides of the first connecting plate (33), a pin nail (37) is arranged in the middle of the pin hole (36), and one side of the second fixing plate (34) is fixedly connected to one side of a second fixing nut (35).

5. A piling device for cofferdam wharf construction according to claim 4, characterized in that: The second fixing plates (34) are fixedly connected to both sides of the third support column (32), the lower end of the second support column (31) is fixedly connected to the upper end of the first connecting plate (33), the middle parts of both sides of the first connecting plate (33) are fixedly connected to the plug holes (36), and the middle parts of the plug holes (36) are plug-connected to the outer ends of the plug pins (37).