Civil engineering square pile forming equipment
By designing civil square pile forming equipment including base, telescopic sleeve, motor and extrusion plate, the bubble problem in cement pouring is solved, the molding quality and flatness of square piles are improved, and the use needs are met.
Patent Information
- Application Number
- CN202420681464.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-03
- Publication Date
- 2024-12-06
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing civil engineering square pile forming equipment has bubbles during cement pouring, resulting in poor quality after forming and unable to meet the usage needs.
A civil pile forming equipment is designed, including base, telescopic sleeve, motor, hoist frame and extrusion plate. The vibration of the hoist frame is used to drive the hoist frame to eliminate air bubbles in the cement and improve the pressure plate by adjusting and tightening the pressure plate. The surface flatness of the square pile.
It effectively eliminates bubbles inside the square pile, improves the quality and surface flatness after forming, and meets the use needs.
Smart Images

Figure CN222115437U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of earthwork square piles, in particular to earthwork square pile forming equipment. Background Art
[0002] Civil engineering refers to the planning, construction and maintenance of all infrastructure related to water, soil and culture. Square piles are hollow cylindrical slender concrete prefabricated components made by prestressing technology and centrifugal forming. They are mainly composed of square pile bodies, end plates and steel hoops. They are generally used in large quantities in civil engineering projects. Square pile forming equipment is required to pour and shape cement before the square piles are put into use.
[0003] During the cement pouring process of the existing civil engineering square pile forming equipment, many bubbles will be present inside the cement, causing the square pile to become hollow, which will deteriorate the overall quality of the square pile after it is formed, affecting the quality of the square pile and failing to meet the use requirements. Utility Model Content
[0004] In view of the deficiencies in the prior art, the utility model provides a civil engineering square pile forming device, which has the advantages of high production quality and solves the problems in the above-mentioned background technology.
[0005] In order to achieve the above-mentioned purpose of high production quality, the utility model provides the following technical solutions: a civil engineering square pile forming equipment, including a base, the inner bottom wall of the base is fixedly connected with a telescopic sleeve and a spring, the front of the base is fixedly connected with a motor, the output shaft of the motor is fixedly connected with a main shaft through a coupling, the outer wall of the main shaft is fixedly connected with a lifting frame and a main gear, and the outer wall of the main gear is movably connected with a secondary gear.
[0006] The inner wall of the secondary gear is fixedly connected with a secondary shaft, one end of the telescopic sleeve is fixedly connected with a model box, one side of the model box is movably connected with a baffle, one side of the baffle is fixedly connected with a positioning seat, the front of the positioning seat is movably connected with a positioning block, and the inner wall of the positioning seat is movably connected with a plug plate. After the cement is poured in the model box, the model box can be lifted up to vibrate when the jacking frame is driven by a motor to swing, so that the bubbles in the cement disappear under the action of vibration, preventing the square pile from being hollow due to many bubbles inside after the square pile is formed, effectively improving the quality of the square pile after forming, and further meeting the use requirements.
[0007] Preferably, a transverse plate is fixedly connected to the top of the plug plate, an adjusting rod is movably connected to the inner wall of the transverse plate, one end of the adjusting rod is movably connected to a movable seat, the bottom of the movable seat is fixedly connected to an extrusion plate, and the top of the extrusion plate is fixedly connected to a weighting block. After the cement is poured in the model box, the extrusion plate at one end can be adjusted by rotating the adjusting rod to move into the model box to tighten the poured square piles, thereby improving the flatness of the surface of the square piles after molding, and further improving the quality of the formed square piles.
[0008] Preferably, the front side of the baffle is fixedly connected with a connecting plate, the back side of the connecting plate is fixedly connected with a clamping block, a groove is provided on the top of the model box, and the inner wall of the groove is movably connected with the outer wall of the clamping block, so as to facilitate cement pouring and unloading after the square pile is formed.
[0009] Preferably, the inner wall of the transverse plate is provided with a screw ring, and the transverse plate is movably connected to the adjusting rod through the screw ring, and the outer wall of the adjusting rod is provided with a thread, so that the extrusion plate can be adjusted to move when rotating, and the poured cement can be extruded.
[0010] Preferably, a bearing is provided on the inner wall of the movable seat, and the inner ring of the bearing is fixedly connected to one end of the adjusting rod, and the movable seat is movably connected to the adjusting rod through the bearing, so that the extrusion plate can be driven to move linearly downward when the adjusting rod is rotated, and avoid rotating simultaneously with the adjusting rod.
[0011] Preferably, a mounting groove is provided at the bottom of the positioning seat, and a connecting shaft is provided on the inner wall of the mounting groove, and the positioning seat is movably connected to the positioning block via the connecting shaft, so as to facilitate the movable rotation of the positioning block, thereby enabling the assembly and disassembly of the plug board.
[0012] Preferably, a card slot is provided on one side of the plug plate, and the plug plate is connected to the positioning block through the card slot, which can connect and position the cross plate and enable the cross plate to be installed and disassembled from the model box.
[0013] Compared with the prior art, the utility model provides a civil engineering square pile forming device, which has the following beneficial effects:
[0014] 1. The civil engineering square pile forming equipment, through a base, a telescopic sleeve, a spring, a motor, a main shaft, a jacking frame, a main gear, a sub-gear and a sub-shaft, can, after pouring cement into a model box, drive the jacking frame to swing through a motor to jack up the model box for vibration, so that bubbles in the cement disappear under the action of vibration, preventing the square pile from being hollow due to many bubbles inside after forming, effectively improving the quality of the square pile after forming, and further meeting the use requirements.
[0015] 2. The civil engineering square pile forming equipment, through the cross plate, the adjusting rod, the movable seat, the extrusion plate and the weight block, can adjust the extrusion plate at one end to move into the model box by rotating the adjusting rod after the cement is poured into the model box to tighten the poured square pile, thereby improving the flatness of the surface of the square pile after forming, and further improving the quality of the square pile after forming. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0017] Figure 1 This is a schematic diagram of the front view structure of the utility model;
[0018] Figure 2 This is a schematic diagram of the base structure of the utility model;
[0019] Figure 3 For this utility model Figure 1 Enlarged view of point A in the middle;
[0020] Figure 4 This is a schematic diagram of the structure of the transverse plate and the extruded plate of the utility model;
[0021] Figure 5 This is a schematic diagram of the structure of the model box of the utility model.
[0022] In the figure: 1. base; 2. telescopic sleeve; 3. spring; 4. motor; 5. main shaft; 6. lifting frame; 7. main gear; 8. secondary gear; 9. secondary shaft; 10. model box; 11. baffle; 12. clamping block; 13. connecting plate; 14. positioning seat; 15. positioning block; 16. plug-in plate; 17. cross plate; 18. adjusting rod; 19. movable seat; 20. extrusion plate; 21. weight block; 22. slot. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model. Example 1
[0024] The preferred embodiment of the earthwork square pile forming equipment provided by the utility model is as follows Figures 1 to 5As shown: a civil engineering square pile forming equipment, including a base 1, the inner bottom wall of the base 1 is fixedly connected with a telescopic sleeve 2 and a spring 3, the front of the base 1 is fixedly connected with a motor 4, the output shaft of the motor 4 is fixedly connected with a main shaft 5 through a coupling, the outer wall of the main shaft 5 is fixedly connected with a jacking frame 6 and a main gear 7, and the outer wall of the main gear 7 is movably connected with a sub-gear 8.
[0025] The inner wall of the secondary gear 8 is fixedly connected to the secondary shaft 9, one end of the telescopic sleeve 2 is fixedly connected to the model box 10, one side of the model box 10 is movably connected to a baffle 11, one side of the baffle 11 is fixedly connected to a positioning seat 14, the front of the positioning seat 14 is movably connected to a positioning block 15, and the inner wall of the positioning seat 14 is movably connected to a plug plate 16. After the cement is poured into the model box 10, the motor 4 drives the jacking frame 6 to swing and can lift the model box 10 upward to vibrate, so that the bubbles in the cement disappear under the action of vibration, preventing the square pile from being hollow due to many bubbles inside after the square pile is formed, effectively improving the quality of the square pile after forming, and further meeting the use requirements.
[0026] In this embodiment, the top of the plug plate 16 is fixedly connected to a horizontal plate 17, the inner wall of the horizontal plate 17 is movably connected to an adjusting rod 18, one end of the adjusting rod 18 is movably connected to a movable seat 19, the bottom of the movable seat 19 is fixedly connected to an extrusion plate 20, and the top of the extrusion plate 20 is fixedly connected to a weight block 21. After the cement is poured in the model box 10, the extrusion plate 20 at one end can be adjusted by rotating the adjusting rod 18 to move into the model box 10 to tighten the poured square piles, thereby improving the flatness of the surface of the square piles after molding, and further improving the quality of the formed square piles. Example 2
[0027] On the basis of Example 1, a preferred embodiment of the earthwork square pile forming equipment provided by the utility model is as follows: Figures 1 to 5 As shown: the front of the baffle 11 is fixedly connected with a connecting plate 13, the back of the connecting plate 13 is fixedly connected with a clamping block 12, a groove is provided on the top of the model box 10, and the inner wall of the groove is movably connected to the outer wall of the clamping block 12, which is convenient for cement pouring and easy for material unloading after the square pile is formed.
[0028] In this embodiment, the inner wall of the horizontal plate 17 is provided with a screw ring, and the horizontal plate 17 is movably connected to the adjusting rod 18 through the screw ring, and the outer wall of the adjusting rod 18 is provided with a thread, which can adjust the extrusion plate 20 to move when rotating, and can extrude the poured cement.
[0029] Furthermore, a bearing is provided on the inner wall of the movable seat 19, and the inner ring of the bearing is fixedly connected to one end of the adjusting rod 18, and the movable seat 19 is movably connected to the adjusting rod 18 through the bearing, which can drive the extrusion plate 20 to move linearly downward when the adjusting rod 18 is rotated, and avoid rotating simultaneously with the adjusting rod 18.
[0030] Furthermore, a mounting groove is provided at the bottom of the positioning seat 14, and a connecting shaft is provided on the inner wall of the mounting groove. The positioning seat 14 is movably connected to the positioning block 15 via the connecting shaft, so that the positioning block 15 can be rotated movably, thereby enabling the insertion plate 16 to be assembled and disassembled.
[0031] In addition, a slot 22 is provided on one side of the plug plate 16 , and the plug plate 16 is engaged with the positioning block 15 through the slot 22 , which can connect and position the cross plate 17 , and at the same time enable the cross plate 17 to be installed and removed from the model box 10 .
[0032] When in use, first pour cement into the model box 10, then start the motor 4 to drive the main shaft 5 to rotate, and while the main shaft 5 rotates, the jacking frame 6 and the main gear 7 on the outer wall rotate synchronously, and the main gear 7 is meshed with the sub-gear 8, so that the sub-shaft 9 and the main shaft 5 rotate at the same time, and the jacking frame 6 rotates and swings, and the model box 10 can be repeatedly jacked up to make it vibrate under the action force, and the bubbles in the cement can disappear during the vibration, thereby improving the quality of the square pile after molding, and after vibration, the cross plate 17 can be placed on the model box 10, so that the bottom plug plate 16 is inserted into the positioning seat 14 and limited by the positioning block 15, and then the adjusting rod 18 is rotated to adjust the bottom extrusion plate 20 to move downward into the model box 10 and contact the surface of the poured cement, and the extrusion plate 20 is provided with a weighting block 21, which can increase the extrusion force of the extrusion plate 20, thereby improving the flatness of the surface of the square pile after molding, and further improving the quality of the square pile molding.
[0033] In summary, the civil engineering square pile forming equipment can make the bubbles in the cement disappear under the action of vibration after the cement is poured into the model box 10, thereby preventing the square pile from being hollow due to the presence of many bubbles inside the square pile after it is formed, effectively improving the quality of the formed square pile, and can tighten the poured square pile after the cement is poured into the model box 10, thereby improving the flatness of the surface of the formed square pile, further improving the quality of the formed square pile.
[0034] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0035] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A civil engineering pile forming device, comprising a base (1), characterized in that: The inner bottom wall of the base (1) is respectively fixedly connected with a telescopic sleeve (2) and a spring (3); the front surface of the base (1) is fixedly connected with a motor (4); the output shaft of the motor (4) is fixedly connected with a main shaft (5) via a coupling; the outer wall of the main shaft (5) is respectively fixedly connected with a jacking frame (6) and a main gear (7); the outer wall of the main gear (7) is movably connected with a secondary gear (8); The inner wall of the secondary gear (8) is fixedly connected to a secondary shaft (9), one end of the telescopic sleeve (2) is fixedly connected to a model box (10), one side of the model box (10) is movably connected to a baffle (11), one side of the baffle (11) is fixedly connected to a positioning seat (14), the front side of the positioning seat (14) is movably connected to a positioning block (15), and the inner wall of the positioning seat (14) is movably connected to a plug plate (16).
2. The earthwork pile forming equipment according to claim 1, characterized in that: The top of the plug plate (16) is fixedly connected to a transverse plate (17), the inner wall of the transverse plate (17) is movably connected to an adjusting rod (18), one end of the adjusting rod (18) is movably connected to a movable seat (19), the bottom of the movable seat (19) is fixedly connected to an extrusion plate (20), and the top of the extrusion plate (20) is fixedly connected to a weight block (21).
3. The earthwork pile forming equipment according to claim 1, characterized in that: The front side of the baffle (11) is fixedly connected to a connecting plate (13), the back side of the connecting plate (13) is fixedly connected to a clamping block (12), and a groove is formed on the top of the model box (10), and the inner wall of the groove is movably connected to the outer wall of the clamping block (12).
4. The earthwork pile forming equipment according to claim 2, characterized in that: The inner wall of the transverse plate (17) is provided with a screw ring, and the transverse plate (17) is movably connected to the adjustment rod (18) via the screw ring, and the outer wall of the adjustment rod (18) is provided with a thread.
5. The earthwork pile forming equipment according to claim 2, characterized in that: A bearing is provided on the inner wall of the movable seat (19), and the inner ring of the bearing is fixedly connected to one end of the adjusting rod (18), and the movable seat (19) is movably connected to the adjusting rod (18) via the bearing.
6. The earthwork pile forming equipment according to claim 1, characterized in that: The bottom of the positioning seat (14) is provided with a mounting groove, and the inner wall of the mounting groove is provided with a connecting shaft, and the positioning seat (14) is movably connected to the positioning block (15) via the connecting shaft.
7. The earthwork pile forming equipment according to claim 1, characterized in that: A slot (22) is provided on one side of the plug plate (16), and the plug plate (16) is engaged and connected with the positioning block (15) via the slot (22).