Fabricated steel sheet pile
Through the prefabricated steel sheet pile structure, the connection of pull-plate and anchor plate is used to set up drainage holes and water absorption holes, combined with rubber seal strips and filters, the problem of insufficient water stop and support in deep foundation pits is solved, achieving high efficiency The support effect of steel sheet piles is suitable for large-scale deep foundation pit projects.
Patent Information
- Application Number
- CN202422602216.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-28
- Publication Date
- 2024-12-10
- Estimated Expiration
- 2034-10-28
AI Technical Summary
The traditional U-shaped steel pile has a thin cross-sectional thickness, and the joints between the steel sheet piles and the steel sheet piles are large, which is not conducive to water stop. The adhesion of the soil outside the steel sheet pile is not fully utilized, and it is difficult to remove, making it difficult to be in a deep foundation pit. Use alone.
Adopt the prefabricated steel sheet pile structure, including the straight section steel sheet pile and the corner section steel sheet pile, connected by pull-up plate and anchor plate, drainage holes and water absorption holes are set, rubber seal strips and filter mesh are used, and the steel sheet pile support structure and surrounding purlins are combined. , achieve firm connection and effective drainage.
It has achieved convenient installation and disassembly and reusable, high stiffness, good seepage resistance, small joints, good water stopping effect, and can give full play to the supporting role of steel sheet piles. It is suitable for large-scale deep foundation pit support projects, improving construction efficiency and engineering reliability.
Smart Images

Figure CN222139999U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of foundation pit support, in particular to an assembled steel sheet pile. Background Art
[0002] Steel sheet piles are a commonly used foundation pit support structure. Compared with traditional support methods such as cast-in-place piles, steel sheet piles are usually constructed through piling equipment, and have the characteristics of fast construction speed and high degree of mechanization. However, the cross-sectional thickness of traditional U-shaped steel piles is relatively thin, and the joints between steel sheet piles are relatively large, which is not conducive to water stopping, and it is impossible to remove groundwater outside the steel sheet piles. The corner interface is relatively weak, and the cohesive force of the soil outside the steel sheet piles is not fully utilized. At the same time, when laying out the perimeter purlins, they are usually connected to the steel sheet piles by welding, which is difficult to dismantle and not conducive to recycling. The contact surface between the steel sheet piles and the perimeter purlins is insufficient, and the supporting function cannot be fully exerted. Therefore, it is difficult to use it alone in deep foundation pits, and its application has certain limitations. Utility Model Content
[0003] The purpose of the utility model is to provide an assembled steel sheet pile to solve the technical problems existing in the background technology.
[0004] In order to achieve the above purpose, the technical solution adopted by the utility model is as follows:
[0005] An assembled steel sheet pile comprises a steel sheet pile frame structure formed by a plurality of straight section steel sheet piles and a plurality of corner section steel sheet piles;
[0006] The straight section steel sheet pile comprises a straight section retaining plate, a first pull plate and a first anchor plate, one end of the first pull plate is connected to the straight section retaining plate, and the other end is connected to the first anchor plate, and the straight section retaining plate has a first concave socket end and a first convex socket end;
[0007] The corner section steel sheet pile comprises a corner section retaining plate, a second pull plate and a second anchor plate, one end of the second pull plate is connected to the corner section retaining plate, and the other end is connected to the second anchor plate, and the corner section retaining plate has a second concave socket end and a second convex socket end;
[0008] Among them, the first concave socket end is used for snap-fitting with the first convex socket end or the second convex socket end; the second concave socket end is used for snap-fitting with the first convex socket end.
[0009] Furthermore, it also includes a steel sheet pile supporting structure arranged on the inner side of the steel sheet pile frame structure, the steel sheet pile supporting structure includes a plurality of steel sheet pile purlins and a plurality of steel sheet pile supports, and the plurality of steel sheet pile purlins are correspondingly clamped and arranged on the inner side of the steel sheet pile frame structure, and are clamped and matched one by one with the plurality of straight steel sheet piles included in the steel sheet pile frame structure, and the plurality of steel sheet pile supports are correspondingly hinged and arranged on the inner side of the steel sheet pile frame structure, and both ends of each steel sheet pile support are correspondingly hinged with a group of parallel and oppositely arranged steel sheet pile purlins.
[0010] Furthermore, the first concave socket end of the straight section retaining plate is provided with a first groove, and the first convex socket end is provided with a first convex head;
[0011] The second concave socket end of the corner section retaining plate is provided with a second groove, and the second convex socket end is provided with a second convex head;
[0012] The first groove is used to engage with the first convex head or the second convex head;
[0013] The second groove is used for snap-fitting with the first protrusion.
[0014] Furthermore, a first pile tip is provided at the bottom of the straight section retaining plate; and a second pile tip is provided at the bottom of the corner section retaining plate.
[0015] Further, a plurality of first drainage holes are arranged on one side of the straight section retaining plate close to the first anchor plate, a plurality of first water absorption holes are arranged on the top of the straight section retaining plate, and the plurality of first drainage holes are communicated with the plurality of first water absorption holes;
[0016] A plurality of second drainage holes are arranged on one side of the corner section retaining plate close to the second anchor plate, a plurality of second water absorption holes are arranged on the top of the corner section retaining plate, and the plurality of second drainage holes are communicated with the plurality of second water absorption holes.
[0017] Furthermore, a limiting groove composed of at least two limiting blocks is provided on the front side of the straight section steel sheet pile, and the limiting groove is used to clamp the steel sheet pile surrounding purlin.
[0018] Furthermore, the steel sheet pile purlin includes a purlin steel plate and a hinge support, the purlin steel plate is clamped in the limiting groove, and the hinge support is fixed on the front side of the purlin steel plate and is hinged to the steel sheet pile support.
[0019] Furthermore, the steel sheet pile support includes a steel pipe column and hinged shafts arranged at both ends of the steel pipe column, and the steel pipe column is hinged to the hinge support of the steel sheet pile purlin through the hinged shaft.
[0020] Furthermore, rubber sealing strips are provided inside the first groove and the second groove.
[0021] Furthermore, filter screens are provided at the openings of the first drainage hole and the second drainage hole.
[0022] Compared with the prior art, the advantages of the present invention are as follows: (1) it is easy to install and disassemble, and can be reused; (2) it has high rigidity and good impermeability, and can fully utilize the cohesion of the soil behind the retaining board, and can take into account the dual functions of retaining and drainage; (3) the joints are small and the water-stopping effect is good; (4) the contact surface between the steel sheet pile purlin and the steel sheet pile is large, and the support function of the steel sheet pile can be fully exerted; (5) the groundwater behind the retaining board can be pumped out in time, which is suitable for large-scale deep foundation pit support projects, and can effectively improve construction efficiency, shorten construction period, and increase project reliability. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the technical solution in this embodiment, the following is a brief introduction to the drawings required for use in the description of the embodiment. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0024] Figure 1 It is an axonometric schematic diagram of an assembled steel sheet pile provided in an embodiment of the utility model;
[0025] Figure 2 It is a top view schematic diagram of the assembled steel sheet pile provided by the embodiment of the utility model;
[0026] Figure 3 This is an axonometric diagram of a straight section of steel sheet pile from one perspective;
[0027] Figure 4 This is an axonometric diagram of a straight section of steel sheet pile from another perspective;
[0028] Figure 5 This is an axonometric diagram of the steel sheet pile at the corner section from one of the viewing angles;
[0029] Figure 6 This is an axonometric diagram of the steel sheet piles at the corner section from another perspective;
[0030] Figure 7 It is an axonometric diagram of the steel sheet pile purlin;
[0031] Figure 8 It is an axonometric diagram of the steel sheet pile support;
[0032] Fig. 9 yes Figure 1 A partial enlarged view of the assembled steel sheet pile in the embodiment;
[0033] Explanation of reference numerals: 100, steel sheet pile frame structure; 101, straight section steel sheet pile; 1011, straight section retaining plate; 1012, first pull plate; 1013, first anchor plate; 1014, first groove; 1015, first protrusion; 1016, first pile tip; 1017, first drainage hole; 1018, first water absorption hole; 1019, limit block; 102, corner section steel sheet pile; 1021, corner section retaining plate Plate; 1022, second pull plate; 1023, second anchor plate; 1024, second groove; 1025, second protrusion; 1026, second pile tip; 1027, second drainage hole; 1028, second water absorption hole; 200, steel sheet pile supporting structure; 201, steel sheet pile surrounding purlin; 2011, surrounding purlin steel plate; 2012, hinged bearing; 202, steel sheet pile support; 2021, steel pipe column; 2022, hinged shaft. DETAILED DESCRIPTION
[0034] In order to make the purpose, technical solution and advantages of the utility model clearer, the technical solution in the embodiment of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiment of the utility model. Obviously, the described embodiment is a part of the embodiment of the utility model, not all of the embodiments. The components of the embodiment of the utility model described and shown in the drawings here can be arranged and designed in various different configurations.
[0035] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the present invention to be protected, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0036] In the description of the embodiments of the present utility model, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present utility model can be understood according to specific circumstances.
[0037] The utility model is further described below in conjunction with the accompanying drawings:
[0038] See also Figures 1 to 9 As shown, an embodiment of the utility model provides an assembled steel sheet pile, comprising a steel sheet pile frame structure 100 formed by a plurality of straight section steel sheet piles 101 and a plurality of corner section steel sheet piles 102;
[0039] The straight section steel sheet pile 101 comprises a straight section earth retaining plate 1011, a first tension plate 1012 and a first anchor plate 1013. One end of the first tension plate 1012 is connected to the straight section earth retaining plate 1011, and the other end is connected to the first anchor plate 1013. The straight section earth retaining plate 1011 has a first concave socket end and a first convex socket end.
[0040] The corner section steel sheet pile 102 comprises a corner section retaining plate 1021, a second pull plate 1022 and a second anchor plate 1023. One end of the second pull plate 1022 is connected to the corner section retaining plate 1021, and the other end is connected to the second anchor plate 1023. The corner section retaining plate 1021 has a second concave socket end and a second convex socket end.
[0041] The first concave socket end is used for snapping and matching with the first convex socket end or the second convex socket end; the second concave socket end is used for snapping and matching with the first convex socket end;
[0042] When in use, the straight section steel sheet pile 101 is snap-fitted with the first convex socket end of the adjacent straight section steel sheet pile 101 through the first concave socket end, or is snap-fitted with the second convex socket end of the adjacent corner section steel sheet pile 102; the corner section steel sheet pile 102 is snap-fitted with the first convex socket end of the adjacent straight section steel sheet pile 101 through the second concave socket end; at the same time, the straight section retaining plate 1011 is anchored to the earth behind the steel sheet pile through the first anchor plate 3; the corner section retaining plate 1021 is anchored to the earth behind the steel sheet pile through the second anchor plate 1023; in this way, by arranging corresponding pull plates and anchor plates behind the straight section retaining plate 1011 and the corner section retaining plate 1021, the cohesion of the earth behind the steel sheet pile can be fully utilized, thereby ensuring the firmness of the connection between the steel sheet pile and the rear soil, and thus greatly improving the reliability of the assembled steel sheet pile provided by the utility model when in use.
[0043] Specifically, the prefabricated steel sheet piles provided in the embodiment of the utility model also include a steel sheet pile supporting structure 200 arranged on the inner side of the steel sheet pile frame structure 100, the steel sheet pile supporting structure 200 includes a plurality of steel sheet pile purlins 201 and a plurality of steel sheet pile supports 202, and the plurality of steel sheet pile purlins 201 are all correspondingly clamped and arranged on the inner side of the steel sheet pile frame structure 100, and are clamped and matched one by one with the plurality of straight section steel sheet piles 101 included in the steel sheet pile frame structure 100, the plurality of steel sheet pile supports 202 are all correspondingly hinged and arranged on the inner side of the steel sheet pile frame structure 100, and both ends of each steel sheet pile support 202 are correspondingly hinged to a group of steel sheet pile purlins 201 arranged in parallel and opposite to each other.
[0044] Specifically, in the assembled steel sheet piles provided in the embodiment of the utility model, the first concave socket end of the straight section retaining plate 1011 is provided with a first groove 1014, and the first convex socket end is provided with a first protrusion 1015; the second concave socket end of the corner section retaining plate 1021 is provided with a second groove 1024, and the second convex socket end is provided with a second protrusion 1025; wherein the first groove 1014 is used to be snap-fitted with the first protrusion 1015 or the second protrusion 1025; and the second groove 1024 is used to be snap-fitted with the first protrusion 1015.
[0045] Specifically, in order to facilitate the steel sheet pile to be driven into the earth during pile driving, in the assembled steel sheet pile provided in the embodiment of the utility model, the bottom of the straight section retaining plate 1011 is provided with a first pile tip 1016; the bottom of the corner section retaining plate 1021 is provided with a second pile tip 1026. The provision of the first pile tip 1016 is conducive to quickly driving the straight section steel sheet pile 101 into the earth; the provision of the second pile tip 1026 is conducive to quickly driving the corner section steel sheet pile 102 into the earth. The lengths of the first pile tip 1016 and the second pile tip 1026 can be set according to actual needs.
[0046] Specifically, in order to facilitate the drainage of groundwater behind the steel sheet pile, in the assembled steel sheet pile provided in the embodiment of the utility model, a plurality of first drainage holes 1017 are provided on one side of the straight section retaining plate 1011 close to the first anchor plate 1013, and a plurality of first water absorption holes 1018 are provided on the top of the straight section retaining plate 1011, and the plurality of first drainage holes 1017 are communicated with the plurality of first water absorption holes 1018. By providing the first drainage holes 1017 and the first water absorption holes 1018, the groundwater behind the straight section retaining plate 1011 can be pumped out in time.
[0047] Similarly, in the assembled steel sheet pile provided in the embodiment of the utility model, a plurality of second drainage holes 1027 are provided on one side of the corner retaining plate 1021 close to the second anchor plate 1023, and a plurality of second water absorption holes 1028 are provided on the top of the corner retaining plate 1021, and the plurality of second drainage holes 1027 are communicated with the plurality of second water absorption holes 1028. By providing the second drainage holes 1027 and the second water absorption holes 1028, the groundwater behind the corner retaining plate 1021 can be pumped out in time.
[0048] In actual use, one end of the pumping hose can be connected to the water suction hole on the top of the steel sheet pile, and the other end can be connected to the pumping equipment. Then, by starting the pumping equipment, the groundwater outside the steel sheet pile can be discharged.
[0049] Specifically, in order to facilitate the installation of the steel sheet pile purlin 201 and increase the contact surface between the steel sheet pile purlin 201 and the straight section steel sheet pile 101, in the prefabricated steel sheet pile provided in the embodiment of the utility model, a limiting groove composed of two limiting blocks 1019 is provided on the front side of the straight section steel sheet pile 101, and this limiting groove is used for clamping and setting the steel sheet pile purlin 201.
[0050] Specifically, in the prefabricated steel sheet piles provided in the embodiment of the utility model, the steel sheet pile purlin 201 includes a purlin steel plate 2011 and a hinge support 2012, wherein the purlin steel plate 2011 is clamped in a limiting groove formed by two limiting blocks 1019, and the hinge support 2012 is fixed on the front side of the purlin steel plate 2011 and is hinged to the steel sheet pile support 202.
[0051] Specifically, in the prefabricated steel sheet piles provided in the embodiment of the utility model, the steel sheet pile support 202 includes a steel pipe column 2021 and hinged shafts 2022 arranged at both ends of the steel pipe column 2021, wherein the steel pipe column 2021 is hinged to the hinge support 2012 of the steel sheet pile purlin 201 through the hinged shaft 2022.
[0052] Furthermore, in order to prevent external moisture from entering the steel pipe column 2021 and causing the steel pipe column 2021 to rust, blind plates are used to seal both ends of the steel pipe column 2021, and the hinged shafts 2022 located at both ends of the steel pipe column 2021 are set on the blind plates at both ends.
[0053] Specifically, in order to prevent groundwater from seeping out from the joints of the steel sheet piles, in the assembled steel sheet piles provided in the embodiment of the utility model, rubber sealing strips (not shown in the figure) are arranged inside the first groove 1014 and the second groove 1024. The shape of the rubber sealing strip can be set according to actual needs, as long as the first protrusion 1015 can be sealed with the first groove 1014, the second groove 1024, and the second protrusion 1025 can be sealed with the first groove 1014. By setting the rubber sealing strip, the joints between two adjacent sections of steel sheet piles can be well blocked to prevent groundwater on the rear side of the steel sheet pile from seeping out from the joints.
[0054] Specifically, in order to prevent the mud in the groundwater from clogging the drainage holes, in the assembled steel sheet pile provided in the embodiment of the utility model, a filter screen (not shown in the figure) is provided at the opening of the first drainage hole 1017 and the second drainage hole 1027. The filter screen can effectively filter out the mud in the groundwater, prevent the mud from entering the drainage hole and clogging the drainage hole, thereby affecting the discharge of groundwater.
[0055] Specifically, the lengths of the first pull plate 1012 and the first anchor plate 1013 are shorter than the corresponding straight section retaining plate 1011 ; the lengths of the second pull plate 1022 and the second anchor plate 1023 are shorter than the corresponding corner section retaining plate 1021 .
[0056] The steps for using the assembled steel sheet pile provided in the embodiment of the utility model are as follows
[0057] The first step is to pre-mark the steel sheet pile positioning line before the large-scale excavation, and then use the piling equipment to drive the steel sheet piles into the four corners of the foundation pit in sequence. Figure 5 and Figure 6 The corner section steel sheet piles 102 shown are driven until the corner section steel sheet piles 102 at the four corners are driven to a predetermined elevation;
[0058] In the second step, after the corner steel sheet piles 102 at the four corners are driven to the predetermined elevation, the steel sheet piles 102 are hoisted. Figure 3 and Figure 4 The first straight section steel sheet pile 101 shown in the figure, after the first straight section steel sheet pile 101 is hoisted to a predetermined height, align it with the pre-drawn steel sheet pile positioning line, and align the convex head (or groove) of the first straight section steel sheet pile 101 with the groove (or convex head) of one of the corner section steel sheet piles 102, after the alignment, start sinking the pile downward, after the first straight section steel sheet pile 101 is driven to a predetermined elevation, the first straight section steel sheet pile 101 will be completely embedded with the connected corner section steel sheet pile 102;
[0059] The third step is to hoist the second straight section steel sheet pile 101. After the second straight section steel sheet pile 101 is hoisted to a predetermined height, align it with the pre-drawn positioning line, and align the convex head (or groove) of the second straight section steel sheet pile 101 with the groove or convex head of the first straight section steel sheet pile 101 that has been piled. After the alignment, start sinking the pile downward. After the second straight section steel sheet pile 101 is driven to a predetermined elevation, the second straight section steel sheet pile 101 will be completely embedded with the first straight section steel sheet pile 101.
[0060] Step 4: Repeat step 3 to sequentially hoist the remaining straight steel sheet piles 101 until all straight steel sheet piles 101 are driven to form a continuous retaining wall.
[0061] Step 5. When drainage is required, one end of the water pumping hose can be connected to the water suction holes (including the first water suction hole 1018 and the second water suction hole 1028) on the top of the steel sheet pile (including the straight section steel sheet pile 101 and the corner section steel sheet pile 102), and then the other end of the water pumping hose can be connected to the pumping equipment, and then the water can be pumped out through the pumping equipment to achieve the purpose of drainage.
[0062] Step 6: dig out the earth in the steel sheet pile frame structure 100 (enclosed by a plurality of straight steel sheet piles 101 and four corner steel sheet piles 102) and Figure 7 The steel sheet pile purlin 201 shown is placed inside the steel sheet pile frame structure 100, and then the steel sheet pile purlin 201 is placed inside the steel sheet pile frame structure 100 by a lifting machine. Figure 8 The steel sheet pile support 202 shown is hoisted into the excavated foundation pit, and the hinged shafts 2022 at both ends of the steel sheet pile support 202 are hinged together with the hinged supports 2012 on the steel sheet pile purlins 201 at both ends, and then the excavation is continued until the foundation pit is excavated to a predetermined elevation; the assembled steel sheet pile structure after installation is completed, as shown in FIG. Figure 1 and Figure 2 shown.
[0063] Finally, it should be noted that the above description is only an embodiment of the present utility model, and does not limit the patent scope of the present utility model. Any equivalent structure or equivalent process transformation made using the contents of the present utility model specification and drawings, or directly or indirectly used in other related technical fields, are also included in the patent protection scope of the present utility model.
Claims
1. An assembled steel sheet pile, characterized in that: It comprises a steel sheet pile frame structure (100) formed by enclosing a plurality of straight section steel sheet piles (101) and a plurality of corner section steel sheet piles (102); The straight section steel sheet pile (101) comprises a straight section earth retaining plate (1011), a first tension plate (1012) and a first anchor plate (1013); one end of the first tension plate (1012) is connected to the straight section earth retaining plate (1011), and the other end is connected to the first anchor plate (1013); the straight section earth retaining plate (1011) has a first concave socket end and a first convex socket end; The corner section steel sheet pile (102) comprises a corner section retaining plate (1021), a second pull plate (1022) and a second anchor plate (1023); one end of the second pull plate (1022) is connected to the corner section retaining plate (1021), and the other end is connected to the second anchor plate (1023); the corner section retaining plate (1021) has a second concave socket end and a second convex socket end; Among them, the first concave socket end is used for snap-fitting with the first convex socket end or the second convex socket end; the second concave socket end is used for snap-fitting with the first convex socket end.
2. The assembled steel sheet pile according to claim 1, characterized in that: The invention also comprises a steel sheet pile supporting structure (200) arranged inside the steel sheet pile frame structure (100), wherein the steel sheet pile supporting structure (200) comprises a plurality of steel sheet pile purlins (201) and a plurality of steel sheet pile supports (202), and the plurality of steel sheet pile purlins (201) are correspondingly arranged inside the steel sheet pile frame structure (100) and are correspondingly engaged with a plurality of straight steel sheet piles (101) included in the steel sheet pile frame structure (100), and the plurality of steel sheet pile supports (202) are correspondingly hingedly arranged inside the steel sheet pile frame structure (100), and both ends of each steel sheet pile support (202) are correspondingly hingedly connected to a group of steel sheet pile purlins (201) arranged in parallel and opposite to each other.
3. The assembled steel sheet pile according to claim 1, characterized in that: The first concave socket end of the straight section retaining plate (1011) is provided with a first groove (1014), and the first convex socket end is provided with a first convex head (1015); The second concave socket end of the corner section retaining plate (1021) is provided with a second groove (1024), and the second convex socket end is provided with a second convex head (1025); The first groove (1014) is used to engage with the first protrusion (1015) or the second protrusion (1025); The second groove (1024) is used for snap-fitting with the first protrusion (1015).
4. The assembled steel sheet pile according to claim 1, characterized in that: A first pile tip (1016) is provided at the bottom of the straight section retaining plate (1011); A second pile tip (1026) is provided at the bottom of the corner section retaining plate (1021).
5. The assembled steel sheet pile according to claim 1, characterized in that: A plurality of first drainage holes (1017) are arranged on one side of the straight section retaining plate (1011) close to the first anchor plate (1013), and a plurality of first water absorption holes (1018) are arranged on the top of the straight section retaining plate (1011), wherein the plurality of first drainage holes (1017) are in communication with the plurality of first water absorption holes (1018); A plurality of second drainage holes (1027) are provided on one side of the corner section retaining plate (1021) close to the second anchor plate (1023), and a plurality of second water absorption holes (1028) are provided on the top of the corner section retaining plate (1021), wherein the plurality of second drainage holes (1027) are in communication with the plurality of second water absorption holes (1028).
6. The assembled steel sheet pile according to claim 2, characterized in that: A limiting groove composed of at least two limiting blocks (1019) is provided on the front side of the straight section steel sheet pile (101), and the limiting groove is used for clamping the steel sheet pile surrounding purlin (201).
7. The assembled steel sheet pile according to claim 6, characterized in that: The steel sheet pile purlin (201) comprises a purlin steel plate (2011) and a hinge support (2012), wherein the purlin steel plate (2011) is clamped inside a limiting groove, and the hinge support (2012) is fixed to the front side of the purlin steel plate (2011) and is hinged to the steel sheet pile support (202).
8. The assembled steel sheet pile according to claim 7, characterized in that: The steel sheet pile support (202) comprises a steel pipe column (2021) and hinged shafts (2022) arranged at both ends of the steel pipe column (2021); the steel pipe column (2021) is hingedly connected to a hinge support (212) of the steel sheet pile purlin (201) via the hinged shaft (2022).
9. The assembled steel sheet pile according to claim 3, characterized in that: Rubber sealing strips are provided inside the first groove (1014) and the second groove (1024).
10. The assembled steel sheet pile according to claim 5, characterized in that: Filter screens are provided at the openings of the first drainage hole (1017) and the second drainage hole (1027).