Anti-seismic support used for providing support for pipeline

By setting up an adjustable length support frame between the seismic support bodies, the problem of excessive cost when the seismic support is used for pipe support is solved, and the effect of reducing costs and improving stability is achieved.

CN222297194UActive Publication Date: 2025-01-03JIANGSU JINTAN FIRST CONSTR & INSTALLATION ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421237662.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-30
Publication Date
2025-01-03
Estimated Expiration
2034-05-30

AI Technical Summary

Technical Problem

When existing seismic support is used for pipeline support, if the fixed cost of the entire line is too high, the demand cannot be met.

Method used

A support frame with adjustable length is arranged between two adjacent seismic support bodies, including a fixed sleeve rod, a U-shaped rod and a fixing mechanism. The adjustment and fixation of the support frame is achieved through the sliding groove, spring and hook, thereby reducing the seismic support body quantity.

Benefits of technology

The number of seismic support bodies required to fix the pipeline is reduced, the cost is reduced, and the stability and scope of application of the pipeline are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222297194U_ABST
    Figure CN222297194U_ABST
Patent Text Reader

Abstract

The utility model discloses an anti-seismic support for supporting a pipeline, and relates to the technical field of anti-seismic supports, the anti-seismic support comprises a pipeline body and a plurality of anti-seismic support bodies installed on a ceiling and used for resisting shock of the pipeline body, and a supporting frame which is used for providing extra support for the pipeline body and is adjustable in length is arranged between every two adjacent anti-seismic support bodies. The supporting frame comprises two sets of fixing sleeve rods arranged at the position of a ceiling and U-shaped rods arranged between the bottom ends of the two adjacent fixing sleeve rods in a sliding mode and used for lifting a pipeline body, and fixing mechanisms used for fixing the moved U-shaped rods are arranged on the outer sides of the fixing sleeve rods. The supporting frames are arranged between every two adjacent anti-seismic support bodies, the number of the anti-seismic support bodies needed for fixing the pipeline can be reduced while additional supporting is provided for the pipeline body, and therefore cost needed for fixing the pipeline is reduced, the rubber shock pads in the supporting frames can conduct shock absorption on the pipeline body, and the pipeline body is prevented from being damaged. And the pipeline fixing stability can be improved to a certain extent.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of earthquake-resistant brackets, in particular to an earthquake-resistant bracket for supporting pipelines. Background Art

[0002] Seismic brackets are structural components used to improve the seismic performance of buildings. They can enhance the stability and rigidity of building structures, reduce the impact of earthquake forces on buildings, and thus improve the seismic resistance of buildings. Seismic brackets are widely used in various types of buildings. They can increase the rigidity and stability of buildings, improve the seismic resistance of buildings, and protect the lives and property of people. With the continuous development of earthquake engineering technology, seismic brackets are increasingly used in building structure design and engineering practice.

[0003] Existing earthquake-resistant brackets are generally used to provide support for pipelines. However, if the entire pipeline is fixed with earthquake-resistant brackets, the cost is too high, so it cannot meet the requirements of existing technologies. Utility Model Content

[0004] The utility model aims at the disadvantage that the existing seismic support is generally used to support the pipeline, but if the entire pipeline is fixed with the seismic support, the cost is too high. The utility model provides a seismic support for supporting the pipeline. The specific technical solution is as follows:

[0005] An earthquake-resistant support for providing support for a pipeline comprises a pipeline body, and a plurality of earthquake-resistant support bodies installed on a ceiling and used for earthquake-resistant the pipeline body. A support frame with an adjustable length for providing additional support to the pipeline body is provided between two adjacent earthquake-resistant support bodies. The support frame comprises two groups of fixed sleeve rods provided on the ceiling, and a U-shaped rod slidably provided between the bottom ends of two adjacent fixed sleeve rods for lifting the pipeline body. A fixing mechanism for fixing the U-shaped rod after movement is provided on the outer side of the fixed sleeve rod.

[0006] By adopting the above technical solution, a support frame is arranged between two adjacent seismic support bodies, which can provide additional support to the pipeline body while reducing the number of seismic support bodies required to fix the pipeline, thereby reducing the cost required to fix the pipeline.

[0007] Optionally, a mounting plate is fixedly provided on the top of the fixed sleeve rod, and the mounting plate is fixedly installed on the ceiling. A sliding groove is opened in the fixed sleeve rod, and the two ends of the top of the U-shaped rod are respectively slidably connected in the sliding grooves of two adjacent fixed sleeve rods, and a rubber shock-absorbing pad is fixedly provided on the bottom inner side of the U-shaped rod and abuts against the bottom surface of the pipe body.

[0008] By adopting the above technical solution, the U-shaped rod at the bottom end of the moving fixed sleeve rod can adjust the overall length of the support frame, making it easier for the support frame to support pipelines of different heights.

[0009] Optionally, a spring is fixed to the outer wall of the bottom end of the fixed sleeve rod, a connecting plate is fixed to one end of the spring, and a number of positioning holes are opened at both ends of the top of the U-shaped rod. The fixing mechanism includes a positioning rod fixed to the side of the connecting plate close to the spring, and one end of the positioning rod passes through the fixed sleeve rod and is inserted into the positioning hole.

[0010] By adopting the above technical solution, under the pulling force of the spring, in conjunction with the connection between the positioning rod and the spring by the connecting plate, the positioning rod can be pulled into the fixed sleeve rod, so that one end of the positioning rod is inserted into the corresponding positioning hole to fix the moved U-shaped rod and fix the length of the support frame after adjustment.

[0011] Optionally, a connecting assembly is provided between the fixing mechanisms of the support frame, and the connecting assembly includes a vertical hook and a horizontal hook which are rotatably arranged on one side of two adjacent connecting plates respectively.

[0012] By adopting the above technical solution, two adjacent fixing mechanisms in the support frame can be connected by using a vertical hook to hang the horizontal hook, so that people do not need to pull the fixing mechanism by hand all the time when adjusting the length of the support frame.

[0013] In summary, the present invention has at least one of the following beneficial effects:

[0014] 1. By setting a support frame between two adjacent seismic support bodies, it is possible to provide additional support to the pipeline body while reducing the number of seismic support bodies required to fix the pipeline, thereby reducing the cost required to fix the pipeline. The rubber shock-absorbing pad in the support frame can reduce the shock of the pipeline body and improve the stability of pipeline fixation to a certain extent.

[0015] 2. By moving the U-shaped rod at the bottom end of the fixed sleeve rod, the overall length of the support frame can be adjusted, which is convenient for the support frame to support pipes of different heights and increase its scope of application. The moved U-shaped rod can be fixed by the fixing mechanism, thereby fixing the length of the support frame after adjustment. By connecting the vertical hook and the horizontal hook, two adjacent fixing mechanisms in the support frame can be connected, so that people do not need to hold the fixing mechanism by hand all the time when adjusting the length of the support frame, which is convenient to use. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a front view of the overall structure of the utility model;

[0017] Figure 2 It is a side view of the pipeline body and the support frame of the utility model;

[0018] Figure 3 It is a side cross-sectional view of the pipeline body and the support frame of the utility model;

[0019] Figure 4 The utility model Figure 3 A magnified view of the structure in the middle.

[0020] Explanation of the reference numerals in the accompanying drawings: 1. Pipe body; 2. Earthquake-resistant bracket body; 3. Support frame; 31. Fixed sleeve rod; 32. U-shaped rod; 33. Mounting plate; 34. Slide groove; 35. Rubber shock-absorbing pad; 36. Positioning hole; 4. Spring; 41. Connecting plate; 42. Positioning rod; 43. Vertical hook; 44. Horizontal hook. DETAILED DESCRIPTION

[0021] The following is combined with Figure 1-4 The utility model is described in further detail.

[0022] The utility model embodiment discloses a seismic support for supporting a pipeline, referring to Figure 1 , including a pipeline body 1, and several earthquake-resistant bracket bodies 2 installed on the ceiling and used to earthquake-resistant the pipeline body 1. The earthquake-resistant bracket body 2 is fixed on the ceiling by expansion bolts. The earthquake-resistant bracket body 2 can support and earthquake-resistant the pipeline body 1 at the bottom. The earthquake-resistant bracket body 2 is an existing earthquake-resistant bracket, and its internal structure and principle have been disclosed, so no further details will be given here.

[0023] Reference Figure 1 A support frame 3 with adjustable length for providing additional support to the pipeline body 1 is provided between two adjacent seismic support bodies 2. The support frame 3 is combined with the seismic support body 2 to form a seismic support for supporting the pipeline. The support frame 3 is provided between two adjacent seismic support bodies 2. While providing additional support to the pipeline body 1, the number of seismic support bodies 2 required for fixing the pipeline can be reduced, thereby reducing the cost required for fixing the pipeline.

[0024] Reference Figure 1-3 The support frame 3 includes two groups of fixed sleeve rods 31 arranged on the ceiling, and a U-shaped rod 32 slidably arranged between the bottom ends of two adjacent fixed sleeve rods 31 for supporting the pipeline body 1. A mounting plate 33 is fixedly provided on the top of the fixed sleeve rod 31. The mounting plate 33 is fixedly installed on the ceiling. The mounting plate 33 can be fixed to the ceiling by expansion bolts to support and fix the fixed sleeve rod 31 and other components.

[0025] Reference Figure 1-3 A sliding groove 34 is provided in the fixed sleeve rod 31, and the two ends of the top of the U-shaped rod 32 are respectively slidably connected in the sliding grooves 34 of the two adjacent fixed sleeve rods 31. The two adjacent fixed sleeve rods 31 can connect and limit the U-shaped rod 32 through the sliding groove 34. After the U-shaped rod 32 slides up and down at the bottom of the fixed sleeve rod 31, the overall length of the support frame 3 will be adjusted.

[0026] Reference Figure 2-3A rubber shock-absorbing pad 35 is fixedly provided at the inner bottom of the U-shaped rod 32 and abuts against the bottom surface of the pipe body 1. The U-shaped rod 32 can lift and support the pipe body 1 through the rubber shock-absorbing pad 35. The rubber shock-absorbing pad 35 can reduce the shock of the supported pipe body 1, which can improve the stability of the pipe fixation to a certain extent.

[0027] Reference Figure 2-4 A spring 4 is fixedly arranged on the outer wall of the bottom end of the fixed sleeve rod 31 , and a connecting plate 41 is fixedly arranged on one end of the spring 4 . Under the pulling force of the spring 4 , the connecting plate 41 will be pulled toward the side of the fixed sleeve rod 31 .

[0028] Reference Figure 2-4 A fixing mechanism is provided on the outside of the fixing sleeve rod 31 for fixing the U-shaped rod 32 after movement. A plurality of positioning holes 36 are provided at both ends of the top of the U-shaped rod 32. The fixing mechanism includes a positioning rod 42 fixedly arranged on the side of the connecting plate 41 close to the spring 4. One end of the positioning rod 42 passes through the fixing sleeve rod 31 and is inserted into the positioning hole 36. Under the pulling force of the spring 4, the connecting plate 41 cooperates with the connection between the positioning rod 42 and the spring 4, so that the positioning rod 42 can be pulled into the fixing sleeve rod 31, so that one end of the positioning rod 42 is inserted into the corresponding positioning hole 36 to fix the U-shaped rod 32 after movement and fix the length of the support frame 3 after adjustment.

[0029] Reference Figure 2-4 A connecting assembly is provided between the fixing mechanisms of the support frame 3, and the connecting assembly includes a vertical hook 43 and a horizontal hook 44 which are respectively rotatably arranged on one side of two adjacent connecting plates 41, the vertical hook 43 is a hook in the vertical direction, and the horizontal hook 44 is a hook in the horizontal direction. When people pull the two connecting plates 41 in the support frame 3 away from the fixing sleeve rod 31, the positioning rod 42 will be disengaged from the positioning hole 36, and then people can hang the vertical hook 43 and the horizontal hook 44 to connect the two adjacent fixing mechanisms in the support frame 3, so that people do not need to pull the fixing mechanism with their hands all the time when adjusting the length of the support frame 3.

[0030] The implementation principle of the seismic support for supporting the pipeline in the embodiment of the utility model is:

[0031] When in use, people can install the support frame 3 and the earthquake-resistant support body 2 on the ceiling, and the support frame 3 and the earthquake-resistant support body 2 support the pipeline body 1. The support frame 3 located between two adjacent earthquake-resistant support bodies 2 can provide additional support to the pipeline body 1 while reducing the number of earthquake-resistant support bodies 2 required to fix the pipeline, thereby reducing the cost required to fix the pipeline;

[0032] When people need to use the support frame 3 to support the pipeline body 1 at different heights, people can pull the two connecting plates 41 in the support frame 3 away from the fixing sleeve rod 31, so that the positioning rod 42 will be separated from the positioning hole 36, and then people can hang the vertical hook 43 and the horizontal hook 44, so as to connect and fix the two adjacent positioning rods 42, so that people do not need to keep pulling the fixing mechanism and the connecting plate 41 by hand when adjusting the length of the support frame 3;

[0033] Then people can move the U-shaped rod 32 at the bottom of the fixed sleeve rod 31 to adjust the overall length of the support frame 3, so that the support frame 3 after the length adjustment can lift and support the pipeline body 1. When the length of the support frame 3 is adjusted, people separate the hanging vertical hook 43 and the horizontal hook 44. At this time, under the pulling force of the spring 4, one end of the positioning rod 42 can be inserted into the corresponding positioning hole 36 to fix the U-shaped rod 32 after moving, and fix the length of the support frame 3 after adjustment.

[0034] The above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. An anti-seismic bracket for supporting a pipeline, comprising a pipeline body (1), and a plurality of anti-seismic bracket bodies (2) installed on a ceiling and used for providing anti-seismic protection for the pipeline body (1), characterized in that: A support frame (3) with adjustable length for providing additional support to the pipeline body (1) is provided between two adjacent anti-seismic support bodies (2), the support frame (3) comprising two sets of fixed sleeve rods (31) provided at the ceiling, and a U-shaped rod (32) slidably provided between the bottom ends of the two adjacent fixed sleeve rods (31) for supporting the pipeline body (1), and a fixing mechanism for fixing the U-shaped rod (32) after movement is provided on the outer side of the fixed sleeve rod (31).

2. The seismic support for supporting a pipeline according to claim 1, characterized in that: A mounting plate (33) is fixedly provided on the top end of the fixed sleeve rod (31), and the mounting plate (33) is fixedly mounted on the ceiling.

3. The seismic support for supporting a pipeline according to claim 1, characterized in that: A sliding groove (34) is provided in the fixed sleeve rod (31), and the two ends of the top of the U-shaped rod (32) are respectively slidably connected in the sliding grooves (34) of two adjacent fixed sleeve rods (31).

4. The seismic support for supporting a pipeline according to claim 1, characterized in that: A rubber shock-absorbing pad (35) is fixedly provided on the inner bottom of the U-shaped rod (32) and is in contact with the bottom surface of the pipe body (1).

5. The seismic support for supporting a pipeline according to claim 1, characterized in that: A spring (4) is fixedly provided on the outer wall of the bottom end of the fixed sleeve rod (31), and a connecting plate (41) is fixedly provided on one end of the spring (4).

6. The seismic support for supporting a pipeline according to claim 5, characterized in that: A plurality of positioning holes (36) are formed at both ends of the top of the U-shaped rod (32). The fixing mechanism comprises a positioning rod (42) fixed to a side of the connecting plate (41) close to the spring (4). One end of the positioning rod (42) passes through the fixing sleeve rod (31) and is inserted into the positioning hole (36).

7. The seismic support for supporting a pipeline according to claim 6, characterized in that: A connecting assembly is provided between the fixing mechanisms of the support frame (3), and the connecting assembly comprises a vertical hook (43) and a horizontal hook (44) which are rotatably arranged on one side of two adjacent connecting plates (41).