Anti-floating recyclable hanging bar

By using anti-floating and recycling hanging bars in drilling pile construction, the fixed structure of the pull rod and the stressed beam should be used to prevent the steel cage from floating, and the concrete will be separated after initial settling, the problems of floating and resource waste of steel cages will be solved. Efficient construction and cost control are achieved.

CN222313976UActive Publication Date: 2025-01-07KUNMING RAILWAY CONSTR COMPANY OF CHINA RAILWAY NO 8 ENG GRP +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420712280.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-08
Publication Date
2025-01-07
Estimated Expiration
2034-04-08

AI Technical Summary

Technical Problem

During the construction of drilling piles, the steel cage is easy to float when concrete is poured, and the existing technology is difficult to effectively prevent, and anti-floating measures are difficult to reuse, resulting in high construction costs and difficult to control the elevation of the pile top.

Method used

A recyclable suspending rib with anti-floating, including a stress beam and a pull rod, is designed to connect to the stress beam through a pull rod, fix the steel cage, and a detachable fixed structure is set at the bottom of the pull rod to avoid floating, while allowing the concrete to begin After condensed, it is separated for recycling.

Benefits of technology

It effectively prevents the floating of the steel cage during concrete pouring, ensures the quality of piles, and realizes the recycling of hanging ribs through a detachable design, reduces construction costs and improves the control accuracy of pile top elevation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222313976U_ABST
    Figure CN222313976U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of capital construction, in particular to an anti-floating recyclable hanging bar which comprises a stress beam and a pull rod. The stress beam is located at the top of the pile hole, and the two ends of the stress beam are erected on the ground. The pull rod is vertically arranged, and a fixing structure is arranged at the bottom end of the pull rod and detachably connected with the reinforcement cage; a connecting part is arranged on the pull rod and is connected with the stress beam; an auxiliary stabilizing structure is arranged on the pull rod and detachably connected with the pile casing. The steel reinforcement cage has the advantages that the steel reinforcement cage is connected with the stress beam through the pull rod, so that the steel reinforcement cage is fixed, and the cage floating phenomenon is prevented; and the pull rods are detachably connected with the reinforcement cage, and the hanging bars can be detached after initial setting of concrete, so that repeated utilization is realized, and the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of infrastructure construction, in particular to an anti-floating and recyclable hanging rod. Background Art

[0002] The current engineering construction uses a large number of bored cast-in-place pile technologies. Bored cast-in-place piles refer to piles made by mechanically drilling in the foundation soil at the construction site, placing a steel cage inside and pouring concrete. According to the pile-making process, they are divided into dry-operation bored cast-in-place piles, mud-wall bored cast-in-place piles and full-casing bored cast-in-place piles. Among them, during the concrete pouring process of the mud-wall bored cast-in-place piles, the concrete will form a force that causes the steel cage to float, which is prone to "floating cage" accidents. At the least, it affects the quality of the pile and the strength of the pile body, and at the worst, it will cause the pile to be abandoned. Therefore, it is extremely important to solve the problem of the floating of the steel cage caused by the concrete pouring during the construction of bored cast-in-place piles.

[0003] The existing technology has some disadvantages. Some construction sites increase the diameter and number of hanging bars, and add counterweights at the wellhead or weld them to the casing to prevent the steel cage from floating up. The process is complicated and takes up construction time. The steel cage hanging bars and anti-floating measures in the existing technology are difficult to reuse, resulting in a large amount of steel waste and increased construction costs. The existing technology is difficult to achieve subtle adjustments to the position of the steel cage, and can only significantly displace the steel cage, and the pile top elevation is difficult to control. Utility Model Content

[0004] The utility model aims to overcome the shortcomings of the prior art and provide an anti-floating and recyclable hanging rod to solve at least one of the above technical problems.

[0005] The purpose of the utility model is achieved through the following technical solutions: an anti-floating recyclable hanger, comprising a load-bearing beam and a tension rod; the load-bearing beam is located at the top of the pile hole, and the two ends of the load-bearing beam are erected on the ground; the tension rod is vertically arranged, and a fixed structure is arranged at the bottom end of the tension rod, and the fixed structure is detachably connected to the steel cage; a connecting component is arranged on the tension rod, and the connecting component is connected to the load-bearing beam; an auxiliary stabilizing structure is arranged on the tension rod, and the auxiliary stabilizing structure is detachably connected to the casing.

[0006] The utility model fixes the steel cage on the load-bearing beam by using a tie rod, thereby preventing the steel cage from floating up during concrete pouring and ensuring the quality of pile formation. At the same time, by arranging a fixing structure detachably connected to the steel cage at the bottom of the tie rod, after the concrete pouring is completed and the initial setting, the tie rod can be separated from the steel cage, and the suspension rod can be recovered so that the suspension rod can be reused.

[0007] In some embodiments, the connecting component includes a connecting sleeve and a connecting sleeve mounting plate arranged on one side of the connecting sleeve, the connecting sleeve is sleeved on the stress beam, and the connecting sleeve mounting plate is connected to the pull rod. The pull rod can be quickly fixed to the stress beam through the connecting component.

[0008] In some embodiments, the cross section of the stress beam is rectangular, and the inner contour of the connecting sleeve is a rectangle corresponding to the cross section of the stress beam. The stress beam is set to a rectangle, and the connecting sleeve is set to a rectangle at the same time, so that after the connecting sleeve is set on the stress beam, the connecting sleeve is prevented from rotating circumferentially around the stress beam.

[0009] In some embodiments, the auxiliary stabilizing structure includes a stabilizing structure mounting plate and a clamping plate arranged on the stabilizing structure mounting plate, the stabilizing structure mounting plate is connected to the pull rod, two clamping plates are arranged on the stabilizing structure mounting plate at intervals, a downward bayonet is formed between the two clamping plates, and the bayonet is used to clamp the top of the casing. Through the two clamping plates, the auxiliary stabilizing structure can be quickly clamped on the top of the casing.

[0010] In some embodiments, one of the clamping plates is provided with a set bolt, and the set bolt is used to abut the casing. The top of the casing is abutted against the clamping plate by the set bolt to improve stability.

[0011] In some embodiments, the pull rod includes a threaded screw rod, the threaded screw rod is passed through the connecting sleeve mounting plate, and the threaded screw rod is provided with first adjustment nuts on both sides of the connecting sleeve mounting plate, and the two first adjustment nuts are used to adjust the position of the connecting sleeve mounting plate on the threaded screw rod. By adjusting the position of the two first adjustment bolts on the pull rod, the axial position of the connecting sleeve on the pull rod is adjusted, and then the height of the steel cage is adjusted.

[0012] In some embodiments, the threaded screw is passed through the stabilizing structure mounting plate, and second adjusting nuts are provided on both sides of the threaded screw on the stabilizing structure mounting plate, and the two second adjusting nuts are used to adjust the position of the stabilizing structure mounting plate on the threaded screw. After the height of the steel cage is adjusted, a second adjusting nut is provided so that the auxiliary stabilizing structure can be connected to the casing. By adjusting the position of the second adjusting nut on the pull rod, the position of the auxiliary stabilizing structure on the pull rod is adjusted so that the auxiliary stabilizing structure can be connected to the top of the casing.

[0013] In some embodiments, the fixing structure includes two clips, which are arranged at intervals at the bottom end of the pull rod, and the gap between the two clips is used to clamp the annular stirrups of the steel cage. The two clips facilitate the direct insertion of the annular stirrups of the steel cage, and after the initial setting of the concrete, the two clips can be easily detached from the steel cage to recover the hanger bars.

[0014] The utility model has the following advantages:

[0015] By connecting the tie rod to the load-bearing beam and then utilizing the fixing structure at the bottom of the tie rod to detachably connect the tie rod to the steel cage, the height of the steel cage is fixed to prevent the steel cage from floating when concrete is poured; at the same time, since the tie rod is detachably connected to the steel cage through the fixing mechanism, the tie rod can be removed after the initial setting of the concrete is completed for subsequent recycling; and the position of the connecting sleeve on the tie rod can be adjusted through the first adjusting nut, thereby adjusting the height of the steel cage. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a schematic diagram of the installation of the anti-floating recyclable suspension rod of the utility model;

[0017] Figure 2 It is a structural schematic diagram of the pull rod of the utility model;

[0018] In the figure: 1. load-bearing beam; 2. pull rod; 3. connecting component; 31. connecting sleeve; 32. connecting sleeve mounting plate; 4. auxiliary stabilizing structure; 41. stabilizing structure mounting plate; 42. clamping plate; 43. tightening bolt; 5. clamping piece; 6. first adjusting nut; 7. second adjusting nut. DETAILED DESCRIPTION

[0019] In order to make the purpose, technical scheme and advantages of the utility model clearer, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the utility model and are not used to limit the utility model, that is, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. The components of the embodiments of the utility model described and shown in the drawings can be arranged and designed in various different configurations.

[0020] The present invention is further described below in conjunction with the accompanying drawings, but the protection scope of the present invention is not limited to the following description.

[0021] like Figure 1 and Figure 2 As shown, an anti-floating recyclable hanger bar comprises a load-bearing beam 1 and a tension rod 2; the load-bearing beam 1 is located at the top of the pile hole, and both ends of the load-bearing beam 1 are erected on the ground; the tension rod 2 is vertically arranged, and a fixed structure is arranged at the bottom end of the tension rod 2, and the fixed structure is detachably connected to the steel cage; a connecting component 3 is arranged on the tension rod 2, and the connecting component 3 is connected to the load-bearing beam 1; an auxiliary stabilizing structure 4 is arranged on the tension rod 2, and the auxiliary stabilizing structure 4 is detachably connected to the casing.

[0022] Specifically, in this embodiment, the load-bearing beam 1 is a square wood, the load-bearing beam 1 is placed on the top of the pile hole, and the two ends are fixed on the ground. The middle section of the load-bearing beam 1 is suspended at the top of the pile hole, and the tie rod 2 is in a vertical state. The tie rod 2 is connected to the load-bearing beam 1 through a connecting component 3 and is located at the edge of the pile hole near the edge of the casing. The fixed structure at the bottom of the tie rod 2 is located at the annular stirrup of the steel cage; the auxiliary stabilizing structure 4 is located at the bottom of the connecting component 3, and the auxiliary stabilizing structure 4 is detachably connected to the casing. When applying this embodiment, the tie rod 2 is first connected to the load-bearing beam 1 through a connecting piece, and then the fixed structure at the bottom of the tie rod 2 is connected to the annular stirrup of the steel cage, and finally the auxiliary stabilizing structure 4 is connected to the casing, so that the entire suspension bar is more stable. The steel cage and the load-bearing beam 1 are fixed by the tie rod 2 to prevent the steel cage from floating during the pouring of concrete; at the same time, by utilizing the detachable connection between the fixed structure at the bottom of the tie rod 2 and the steel cage, the tie rod 2 can be removed after the initial setting of the concrete, so that the suspension bar can be recycled and reused.

[0023] Preferably, the connecting member 3 includes a connecting sleeve 31 and a connecting sleeve mounting plate 32 arranged on one side of the connecting sleeve 31, the connecting sleeve 31 is sleeved on the load-bearing beam 1, and the connecting sleeve mounting plate 32 is connected to the pull rod 2. The connecting sleeve 31 is directly sleeved on the load-bearing beam 1 to ensure that the connecting sleeve 31 will not be separated from the load-bearing beam 1.

[0024] Preferably, the cross section of the load-bearing beam 1 is a rectangle, and the inner contour of the connecting sleeve 31 is a rectangle corresponding to the cross section of the load-bearing beam 1. Due to the rectangular cross section of the load-bearing beam 1 and the rectangular inner contour of the connecting sleeve 31, when the connecting sleeve 31 is sleeved on the load-bearing beam 1, the connecting sleeve 31 will not rotate circumferentially around the load-bearing beam 1, thereby preventing the tie rod 2 from rotating circumferentially around the load-bearing beam 1, and when the tie rod 2 is connected to the steel cage through the fixed structure, no unnecessary shaking will occur, thereby increasing stability.

[0025] Preferably, the auxiliary stabilizing structure 4 comprises a stabilizing structure mounting plate 41 and a clamping plate 42 arranged on the stabilizing structure mounting plate 41, the stabilizing structure mounting plate 41 is connected to the pull rod 2, two clamping plates 42 are arranged at intervals on the stabilizing structure mounting plate 41, a downward bayonet is formed between the two clamping plates 42, and the bayonet is used to clamp the top of the casing. Specifically, in this embodiment, the stabilizing structure mounting plate 41 is arranged horizontally, and the two clamping plates 42 are arranged vertically at the bottom of the stabilizing structure mounting plate 41. The two clamping plates 42 are arranged at one end of the stabilizing structure mounting plate 41 away from the pull rod 2, and the two clamping plates 42 are arranged at intervals, and there is a gap between the two clamping plates 42, forming a bayonet opening downward, and the bayonet is used to clamp the top of the casing. Through the auxiliary stabilizing structure 4 located at the bottom of the connecting component 3, the pull rod 2 is connected to the load-bearing beam 1 while also connecting to the casing, so that the pull rod 2 is more stable and not easy to shake, and the pull rod 2 is ensured to be stably connected to the steel cage.

[0026] Preferably, a fixing bolt 43 is provided on one of the clamping plates 42, and the fixing bolt 43 is used to abut the casing. Specifically, in this embodiment, a hole for the fixing bolt 43 to pass through is provided on one of the clamping plates 42, a nut is welded on one side of the hole, the fixing bolt 43 is threadedly connected with the nut and passes through the hole to between the two clamping plates 42, and the casing between the two clamping plates 42 is tightened by the fixing bolt 43, and the pull rod 2 and the casing are completely fixed to improve stability.

[0027] Preferably, the pull rod 2 includes a threaded screw, which is passed through the connecting sleeve mounting plate 32. The threaded screw is provided with first adjustment nuts 6 on both sides of the connecting sleeve mounting plate 32, and the two first adjustment nuts 6 are used to adjust the position of the connecting sleeve mounting plate 32 on the threaded screw. Specifically, when it is necessary to adjust the height of the casing, first loosen one of the first adjustment nuts 6 so that the connecting sleeve mounting plate 32 can move along the pull rod 2, thereby adjusting the height of the steel cage. When the position between the connecting sleeve mounting plate 32 and the pull rod 2 is adjusted appropriately, tighten the two first adjustment nuts 6 so that the two first adjustment nuts 6 clamp the connecting sleeve mounting plate 32 to lock the position of the connecting sleeve 31; through the two first adjustment nuts 6, it is convenient to make subtle adjustments to the height of the steel cage and accurately control the pile top elevation.

[0028] Preferably, the threaded screw is passed through the stabilizing structure mounting plate 41, and the threaded screw is provided with second adjusting nuts 7 on both sides of the stabilizing structure mounting plate 41, and the two second adjusting nuts 7 are used to adjust the position of the stabilizing structure mounting plate 41 on the threaded screw. In this embodiment, after adjusting the height of the steel cage by the first adjusting nut 6, it is necessary to adjust the height of the auxiliary stabilizing structure 4 so that the auxiliary stabilizing structure can be connected to the casing. When adjusting the height position of the auxiliary stabilizing structure 4, first loosen one of the second adjusting nuts 7 so that the auxiliary stabilizing structure 4 can move axially on the pull rod 2, move the auxiliary stabilizing structure 4 to a position where it can be connected to the casing, and make the top of the casing stuck between the two clamping plates 42 of the auxiliary stabilizing structure 4, and then tighten the two second adjusting nuts 7 so that the two second adjusting nuts 7 clamp the auxiliary stabilizing structure 4 to lock the position of the auxiliary stabilizing structure 4.

[0029] Preferably, the fixing structure includes two clips 5, which are arranged at intervals at the bottom end of the tie rod 2, and the gap between the two clips 5 is used to clamp the annular stirrups of the steel cage. Specifically, in this embodiment, the two clips 5 are arranged horizontally and welded to the tie rod 2. When this embodiment is applied, the annular stirrups of the steel cage are arranged to be clamped into the gap between the two clips 5 to achieve a detachable connection between the fixing structure and the steel cage. After the concrete is initially set, the tie rod 2 only needs to be moved to one side to separate the steel cage from the tie rod 2, and the suspension bar can be recovered for recycling.

[0030] The above is only a preferred embodiment of the utility model, and does not limit the utility model in any form. Any technician familiar with the field can make many possible changes and modifications to the technical solution of the utility model by using the above-mentioned technical content without departing from the scope of the technical solution of the utility model, or modify it into an equivalent embodiment of equivalent changes. Therefore, any changes, modifications, equivalent changes and modifications made to the above embodiments based on the technology of the utility model without departing from the content of the technical solution of the utility model shall fall within the protection scope of the technical solution of the utility model.

Claims

1. An anti-floating recyclable suspension rod, characterized in that: include: A load-bearing beam (1), the load-bearing beam (1) is located at the top of the pile hole, and both ends of the load-bearing beam (1) are erected on the ground; A pull rod (2), the pull rod (2) being arranged vertically, a fixing structure being arranged at the bottom end of the pull rod (2), and the fixing structure being detachably connected to the steel cage; The pull rod (2) is provided with a connecting component (3), and the connecting component (3) is connected to the load-bearing beam (1); The pull rod (2) is provided with an auxiliary stabilizing structure (4), and the auxiliary stabilizing structure (4) is detachably connected to the casing.

2. The anti-floating recyclable suspension rod according to claim 1, characterized in that: The connecting component (3) comprises a connecting sleeve (31) and a connecting sleeve mounting plate (32) arranged on one side of the connecting sleeve (31); the connecting sleeve (31) is sleeved on the load-bearing beam (1); and the connecting sleeve mounting plate (32) is connected to the pull rod (2).

3. The anti-floating recyclable suspension rod according to claim 2, characterized in that: The cross section of the load-bearing beam (1) is a rectangle, and the internal contour of the connecting sleeve (31) is a rectangle corresponding to the cross-sectional shape of the load-bearing beam (1).

4. The anti-floating recyclable suspension rod according to claim 2, characterized in that: The auxiliary stabilizing structure (4) comprises a stabilizing structure mounting plate (41) and a clamping plate (42) arranged on the stabilizing structure mounting plate (41); the stabilizing structure mounting plate (41) is connected to the pull rod (2); two clamping plates (42) are arranged on the stabilizing structure mounting plate (41) at intervals; a downward bayonet is formed between the two clamping plates (42), and the bayonet is used to clamp the top of the casing.

5. The anti-floating recyclable suspension rod according to claim 4, characterized in that: A fixing bolt (43) is arranged on one of the clamping plates (42), and the fixing bolt (43) is used for abutting against the casing.

6. The anti-floating recyclable suspension rod according to claim 4, characterized in that: The pull rod (2) includes a threaded screw, which is inserted into the connecting sleeve mounting plate (32). The threaded screw is provided with first adjustment nuts (6) on both sides of the connecting sleeve mounting plate (32). The two first adjustment nuts (6) are used to adjust the position of the connecting sleeve mounting plate (32) on the threaded screw.

7. The anti-floating recyclable suspension rod according to claim 6, characterized in that: The threaded screw is inserted into the stabilizing structure mounting plate (41), and second adjustment nuts (7) are provided on both sides of the threaded screw on the stabilizing structure mounting plate (41), and the two second adjustment nuts (7) are used to adjust the position of the stabilizing structure mounting plate (41) on the threaded screw.

8. The anti-floating recyclable suspension rod according to claim 1, characterized in that: The fixing structure comprises two clips (5), the two clips (5) are arranged at intervals at the bottom end of the pull rod (2), and the gap between the two clips (5) is used to clamp the annular stirrups of the steel cage.