By designing the anti-seepage support device of the formwork bracket in the top plate, and using the steel bar support and water stop ring structure, the problems of long construction cycle and poor anti-seepage performance of multi-layered water treatment facilities in traditional construction are solved, and one-time pouring and high efficiency are achieved Anti-seepage effect.

CN222314596UActive Publication Date: 2025-01-07HEBEI SECOND CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421140200.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-23
Publication Date
2025-01-07
Estimated Expiration
2034-05-23

AI Technical Summary

Technical Problem

When constructing traditional reinforced concrete structures, the construction period of multi-layered water treatment facilities is long, and it is difficult to ensure the integrity and permeability of the pool body, especially when it is poured on one-time, it is susceptible to construction joints and secondary casting factors.

Method used

Design a waterproof support device for the inner formwork bracket of the top plate, including steel pipes and steel bar support connected to the top plate formwork. The support forms a "soil" font structure, equipped with a steel plate water stop ring and a removable PVC sleeve, support Place it in the concrete pad, and the pad is equipped with a "ten" shaped slot to ensure the overall stiffness and deformation of the template.

Benefits of technology

One-time pouring of multi-layer concrete structures has been achieved, shortening the construction cycle, ensuring the seepage resistance of concrete and the integrity of the pool body, and is suitable for the construction of multi-layered structures such as pools, canals, and pipeline corridors.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222314596U_ABST
    Figure CN222314596U_ABST
Patent Text Reader

Abstract

The utility model discloses a top plate inner formwork support anti-seepage supporting device which comprises a steel pipe connected with an (N + 1) th layer of top plate formwork support, a steel bar support is arranged below the steel pipe in a sleeved mode and comprises a steel bar top support, a steel bar stand column and two steel bar bottom supports, and the steel bar top support, the steel bar stand column and one steel bar bottom support are welded to form a structure shaped like a Chinese character'tu '. A steel plate water stop ring is welded to the steel bar stand column, the two steel bar bottom supports are welded to form a cross-shaped structure on the plane, the lower portion of the steel bar support is placed in the concrete cushion block, and the concrete cushion block is provided with a cross-shaped clamping groove used for containing the cross-shaped structure. And the concrete cushion block is placed in the steel bar grid on the Nth layer of top plate bottom template. According to the utility model, the multi-layer concrete structure engineering can be poured at one time, the construction period is effectively shortened, the template does not displace and deform, and the poured concrete is good in impermeability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of construction engineering, in particular to an anti-seepage support device for a top plate inner formwork bracket, especially for supporting the top plate formwork during one-time pouring of multi-layer superimposed structure buildings such as canals, pipe corridors, canals, etc. Background Art

[0002] In the context of the increasingly serious negative impact of the construction industry on the environment, in order to ensure the sustainable development of my country's construction industry, it is particularly important to implement the "four savings and one environmental protection". With the gradual deepening of the concept of "four savings and one environmental protection", the design of water plants at this stage tends to be superimposed and intensively arranged. The design of multiple pools has gradually matured, and the construction unit must strengthen the improvement and improvement of the cast-in-place construction technology of reinforced concrete in superimposed structures. In the construction of traditional reinforced concrete structures, after the bottom plate is cast, water-stopping measures are set on the pool wall and then the top plate concrete is cast to control the integrity and impermeability of the pool. The superimposed pools, canals, pipe corridors and other water treatment facilities are arranged in multiple layers. The traditional construction process has a long construction period and requires a construction process of cyclic steel bar binding-formwork support-concrete pouring. The construction progress is slow and is easily affected by factors such as construction joints and secondary pouring, resulting in the integrity and impermeability of the pool not meeting the requirements. Utility Model Content

[0003] The technical problem to be solved by the utility model is to provide an anti-seepage support device for a top plate inner formwork bracket, which can enable a multi-story concrete structure project to be poured in one go, and effectively shorten the construction period, ensure that the formwork does not move or deform, and the poured concrete has good anti-seepage properties.

[0004] In order to solve the above technical problems, the technical solution adopted by the utility model is: a top plate internal formwork support anti-seepage support device, including a steel pipe connected to the N+1-th layer top plate formwork support, a steel bar support is sleeved under the steel pipe, the steel bar support includes a steel bar top support, a steel bar column and two steel bar bottom supports, the steel bar top support, the steel bar column and one steel bar bottom support are welded into a "earth" shape structure, a steel plate water stop ring is welded on the steel bar column, and two steel bar bottom supports are welded on the plane into a "cross" structure, the bottom of the steel bar support is placed in a concrete pad, the concrete pad is provided with a "cross" shaped slot for placing the "cross" structure, and the concrete pad is placed in the steel grid on the bottom formwork of the N-th layer top plate.

[0005] A further improvement of the technical solution of the utility model is that a detachable sleeve is sleeved on the outer side of the steel pipe.

[0006] A further improvement of the technical solution of the utility model is that the sleeve is made of PVC material.

[0007] A further improvement of the technical solution of the utility model is that the distances from the steel plate water stop ring to the steel bar top support and the steel bar bottom support are the same.

[0008] Due to the adoption of the above technical solution, the technical progress achieved by the utility model is:

[0009] 1. The utility model replaces the traditional layered pouring construction method, avoids the need to set up water-stop steel plates in layers for layered pouring, solves the technical problem of one-time pouring of multi-layer structures, reduces the technical interval time of concrete construction, shortens the construction period, realizes that the template does not move or deform, and the poured concrete has good impermeability;

[0010] 2. The anti-seepage support device of the bracket of the utility model is installed in the top plate, without leakage risk, ensuring the anti-seepage performance of the pool body, and is suitable for the construction of multi-layer superimposed pool structures such as pools, canals, and pipe galleries. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0012] Figure 2 This is a schematic diagram of the steel bar support structure of the utility model;

[0013] Figure 3 It is a schematic diagram of the overall structure of the use scenario of the utility model;

[0014] Figure 4 This utility model Figure 3 Front view at A in the middle;

[0015] Among them, 1. casing, 2. steel pipe, 3. steel bar column, 4. steel bar top support, 5. steel bar bottom support, 6. steel plate water stop ring, 7. concrete pad, 8. steel bar support. DETAILED DESCRIPTION

[0016] The present invention is further described in detail below in conjunction with the embodiments:

[0017] like Figure 1-Figure 2As shown, a top plate internal formwork support anti-seepage support device includes a steel pipe 2 connected to the N+1th layer top plate formwork support, where N is a natural number greater than or equal to 1. The outer side of the steel pipe 2 is sleeved with a detachable sleeve 1 made of PVC material, which can make the steel pipe 2 smoothly dismantled and recycled. A steel support 8 is sleeved below the steel pipe 2, and the steel support 8 includes a steel top support 4, a steel column 3 and two steel bottom supports 5. The steel top support 4, the steel column 3 and one steel bottom support 5 are welded into a "earth"-shaped structure. A steel plate water stop ring 6 is welded on the steel column 3, and the spacing between the steel plate water stop ring 6 and the steel top support 4 and the steel bottom support 5 is the same. The two steel bottom supports 5 are welded into a "cross"-shaped structure on the plane, and the bottom of the steel support 8 is placed in a concrete pad 7, which is prefabricated with concrete of the same grade. The concrete pad 7 is provided with a "cross"-shaped slot for placing the "cross"-shaped structure, which effectively ensures the overall rigidity of the formwork system and can achieve that the formwork does not move or deform when pouring concrete. The concrete pad 7 is placed in the steel grid on the bottom formwork of the Nth layer top plate.

[0018] Combination Figure 3-Figure 4 The following is a method for using the anti-seepage support device for the internal formwork support of the utility model:

[0019] 1. Prefabricated components:

[0020] According to the construction plan, a concrete pad 7 with a "cross"-shaped groove is prefabricated on the surface layer, and the strength of the concrete pad 7 is consistent with the structural strength; a steel support 8 welded from a steel top support 4, a steel column 3, a steel bottom support 5, and a water stop ring 6 is prefabricated and properly placed for use after prefabrication.

[0021] 2. Construction of one layer of formwork support:

[0022] A top slab formwork support is set up above a layer of already cast bottom slab. After qualified acceptance, the top slab formwork and top slab reinforcement are installed and the acceptance is completed.

[0023] 3. Construction of second-layer formwork support:

[0024] Place the prefabricated concrete pad 7 in the steel grid on the bottom formwork of the first top plate according to the plan, place the steel support 8 above the concrete pad 7, align the steel support 8 with the first layer of risers, and place the sleeve 1 and the steel pipe 2 on the steel support 8. When placing the steel pipe 2, two people are required to cooperate to complete the installation of the second-layer formwork support. After the formwork support installation is completed and accepted, the top plate formwork and top plate steel bars are installed and the acceptance is completed.

[0025] 4. Construction of three-layer formwork support:

[0026] Place the prefabricated concrete pad 7 in the steel grid on the bottom formwork of the second-floor top plate according to the plan, place the steel support 8 above the concrete pad 7, align the steel support 8 with the second-floor riser, and place the sleeve 1 and the steel pipe 2 on the steel support 8. When placing the steel pipe 2, two people are required to cooperate to complete the installation of the second-floor formwork support. After the formwork support installation is completed and accepted, install the top plate formwork and top plate steel bars and complete the acceptance.

[0027] 5. Multi-layer structure concrete pouring:

[0028] The installation of the pool wall formwork is interspersed with the above steps. After completion, the concrete pouring of the multi-layer structure begins. The pouring method is to pour the side wall first, then the top plate, from bottom to top, and in a reciprocating manner. When the first layer of the pool wall is poured to the first layer of the top plate, the rod workers and the plastering and finishing personnel will enter the top plate to vibrate and finish the surface. The plastering personnel will circulate back and forth in different areas to carry out the plastering work. When the top plate is initially solidified in one area, the second layer of the pool wall and the top plate will be poured in this area. When pouring to the second layer of the top plate, the rod workers and the plastering and finishing personnel will enter the top plate of the second layer of the top plate to vibrate and finish the surface. When the second layer of the top plate is initially solidified in one area, the third layer of the pool wall and the top plate will be poured in this area. This cycle will continue until the pouring work is successfully completed.

[0029] 6. Follow-up work:

[0030] After the concrete pouring is completed and the concrete reaches the demoulding strength, the template can be removed; the steel pipe 2 is recycled, the steel support 8 remains in the concrete, and the holes left by the removal of the steel pipe 2 are filled with concrete of the same grade mixed with a micro-expansion agent.

Claims

1. A roof internal formwork support anti-seepage support device, characterized in that: The invention comprises a steel pipe (2) connected to a support for a top plate formwork of the N+1th layer, a steel bar support (8) is sleeved below the steel pipe (2), the steel bar support (8) comprises a top steel bar support (4), a steel bar column (3) and two bottom steel bar supports (5), the top steel bar support (4), the steel bar column (3) and one bottom steel bar support (5) are welded into a "earth"-shaped structure, a steel plate water stop ring (6) is welded to the top steel bar column (3), the two bottom steel bar supports (5) are welded on a plane into a "cross"-shaped structure, the bottom of the steel bar support (8) is placed in a concrete pad (7), the concrete pad (7) is provided with a "cross"-shaped slot for placing the "cross"-shaped structure, and the concrete pad (7) is placed in a steel bar grid on the bottom formwork of the top plate of the Nth layer.

2. The anti-seepage support device for the roof inner formwork support according to claim 1, characterized in that: The outer side of the steel pipe (2) is sleeved with a detachably connected sleeve (1).

3. The anti-seepage support device for the roof inner formwork support according to claim 2, characterized in that: The sleeve (1) is made of PVC material.

4. The anti-seepage support device for the roof inner formwork support according to claim 1, characterized in that: The distances between the steel plate water stop ring (6) and the steel bar top support (4) and the steel bar bottom support (5) are the same.