Railway bridge construction support device
By designing the railway bridge construction bracket device, using the mobile mechanism connecting cylinder, I-steel and Bere frame, the problem of inconvenience in disassembly and transportation of the steel pipe column Bere beam combination bracket in the prior art is solved, and rapid disassembly and efficient transportation is achieved. Improve construction efficiency.
Patent Information
- Application Number
- CN202420696818.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-07
- Publication Date
- 2025-01-10
- Estimated Expiration
- 2034-04-07
AI Technical Summary
The existing steel pipe column Bere beam combination bracket is inconvenient during disassembly and transportation after construction, and requires manual recombination, resulting in large workload and troublesome transportation.
A railway bridge construction bracket device is designed, including connecting cylinders, I-steel and Bere frame moving mechanisms, which can be quickly disassembled and moved through bolted connections and jack drives. Bere frame can be quickly disassembled into parts for easy transportation and through Threaded rods and moving beads improve disassembly efficiency.
It realizes rapid disassembly and convenient transportation of brackets, reduces the workload of manual combination and transportation, and improves construction efficiency.
Smart Images

Figure CN222332486U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of bridge supports, in particular to a railway bridge construction support device. Background Art
[0002] When the number of reinforced concrete beam spans is small, the cast-in-place method is used to eliminate foundation settlement and inelastic deformation of the support to avoid cracks in the beam concrete, and then the steel pipe column Bailey beam combined support is used for construction.
[0003] In practice, steel pipe column Bailey beam combination support construction is very commonly used. When using this construction support, the steel pipe support is welded by connecting rods, which is troublesome to disassemble. After the construction of the existing Bailey beam, there is a built bridge on the upper side, and the Bailey frame close to the lower side of the bridge is difficult to be transported by crane due to its position. If the Bailey frame is disassembled into Bailey pieces, it is convenient for transportation, but the workload is large, and when the Bailey frame is needed again, it is still necessary to manually reassemble the Bailey pieces, and the whole Bailey frame is troublesome to transport. Generally, it will be disassembled into partial Bailey frames for easy transportation and convenient reassembly and reuse next time, but disassembling into partial Bailey frames is still not convenient.
[0004] Therefore, the utility model provides a railway bridge construction support device to solve the above problems. Utility Model Content
[0005] In view of the deficiencies in the prior art, the utility model provides a railway bridge construction support device to solve the above-mentioned problems.
[0006] In order to achieve the above objectives, the present invention is implemented through the following technical solutions:
[0007] A railway bridge construction support device includes a connecting cylinder, the top of which is fixedly connected to an I-beam, and a cylinder disassembly mechanism is provided on the connecting cylinder. The cylinder disassembly mechanism includes a fixed ring and a connecting ring, the fixed ring is fixedly connected to the outside of the connecting cylinder, the connecting ring is fixedly connected to the outside of the connecting cylinder by bolts, the connecting ring is arranged between the fixed rings, and the connecting ring port is fixedly connected to a connecting fixture by bolts.
[0008] Preferably, a Bailey frame moving mechanism is provided on the I-beam, and the Bailey frame moving mechanism includes a moving plate, which is arranged in the notch of the I-beam, the upper side of the moving plate is fixedly connected to the jack, the upper side of the jack is fixedly connected to the second support plate, the upper side of the second support plate is fixedly connected to the first support plate, and both ends of the moving plate are fixedly connected to fixed blocks.
[0009] Preferably, a threaded rod is provided on the upper side of the fixed block, a manual swivel is fixedly connected to the outer side of the threaded rod, a third support plate is fixedly connected to the upper end of the threaded rod, and a plurality of movable balls are provided at the bottom of the fixed block.
[0010] Preferably, a Bailey frame quick-detachment mechanism is provided on the upper side of the first support plate, and the Bailey frame quick-detachment mechanism includes a Bailey plate, which is fixedly connected to the upper side of the first support plate, and a plurality of support plates are bolted to the side wall of the Bailey plate, and a connecting rod is fixedly connected to the side wall of the support plate, a second connecting hole is provided in the middle of the support plate, and a fixing plate is provided on the support plate.
[0011] Preferably, first connecting holes are provided on both sides of the fixing plate, and the fixing plate is connected to the supporting sheet via connecting pins.
[0012] Beneficial Effects
[0013] The utility model provides a railway bridge construction support device. Compared with the prior art, it has the following beneficial effects:
[0014] (1) A railway bridge construction support device, wherein a connecting ring is fixedly connected to a cylinder by bolts, and then a connecting fixture is fixedly connected by bolts, and the cylinder is fixed by the connecting fixture, and the subsequent support is quickly disassembled.
[0015] (2) A railway bridge construction support device, which facilitates the movement of the Bailey frame at the bottom of the bridge to the crane working area through the Bailey frame moving mechanism, so that the subsequent crane can transport the Bailey frame to the designated location.
[0016] (3) A railway bridge construction support device, in which a worker quickly removes a connecting pin, cancels the connection between a supporting plate and a fixing plate, and then manually removes the fixing plate, thereby realizing rapid disassembly of the Bailey frame, so that the Bailey frame can be disassembled into partial Bailey frames, which is convenient for reinstallation when the Bailey frame is needed later. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is the overall side view structure diagram of the utility model;
[0018] Figure 2 It is a structural diagram of the cylindrical disassembly mechanism of the utility model;
[0019] Figure 3 This is a structural diagram of the Bailey frame quick disassembly mechanism of the utility model;
[0020] Figure 4 This is a partial structural diagram of the Bailey frame quick disassembly mechanism of the utility model;
[0021] Figure 5 This is an oblique side structural diagram of the Bailey frame moving mechanism of the utility model;
[0022] Figure 6 This is a rear structural diagram of the Bailey frame moving mechanism of the utility model;
[0023] Figure 7 This is a connection structure diagram of the Bailey frame quick disassembly mechanism of the utility model;
[0024] Figure 8 It is a connection ring diagram of the utility model.
[0025] In the figure, 1 is a cylinder; 2 is an I-beam;
[0026] Cylinder disassembly mechanism: 31. Connecting ring; 32. Connecting fixing piece; 33. Fixing ring;
[0027] Bailey frame moving mechanism: 41, moving plate; 42, jack; 43, first support plate; 44, second support plate; 45, threaded rod; 46, manual swivel; 47, third support plate; 48, fixed block; 49, moving ball;
[0028] Bailey frame quick disassembly mechanism: 51, Bailey plate; 52, fixing plate; 53, supporting plate; 54, connecting rod; 55, first connecting hole; 56, second connecting hole; 57, connecting pin. DETAILED DESCRIPTION
[0029] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0030] Embodiment 1:
[0031] See also Figure 1-8 A railway bridge construction support device includes a connecting cylinder 1, an I-beam 2 is fixedly connected to the top of the connecting cylinder 1, and a cylinder disassembly mechanism is arranged on the connecting cylinder 1.
[0032] The cylinder disassembly mechanism includes a fixed ring 33 and a connecting ring 31. The fixed ring 33 is fixedly connected to the outside of the connecting cylinder 1. The connecting ring 31 is fixedly connected to the outside of the connecting cylinder 1 by bolts. The connecting ring 31 is arranged between the fixed rings 33. The port of the connecting ring 31 is fixedly connected to a connecting fixture 32 by bolts.
[0033] Working process: When the bracket needs to be disassembled, the connecting fixture 32 is removed from the cylinder 1 by removing the bolts, which facilitates the quick removal of the connecting fixture 32. Then, the bolts on the connecting fixture 32 are removed to loosen the connecting fixture 32 on the cylinder 1, which facilitates the quick removal of the connecting fixture 32, making the overall disassembly of the cylinder 1 convenient.
[0034] Embodiment 2:
[0035] See also Figure 1-8 This embodiment provides a technical solution for a railway bridge construction support device based on the first embodiment:
[0036] A Bailey frame moving mechanism is provided on the I-beam 2, and the Bailey frame moving mechanism includes a moving plate 41, which is provided in the notch of the I-beam 2, and the upper side of the moving plate 41 is fixedly connected to the jack 42, and the upper side of the jack 42 is fixedly connected to the second support plate 44, and the upper side of the second support plate 44 is fixedly connected to the first support plate 43, and both ends of the moving plate 41 are fixedly connected to fixed blocks 48.
[0037] A threaded rod 45 is disposed on the upper side of the fixing block 48 , a manual swivel 46 is fixedly connected to the outer side of the threaded rod 45 , a third support plate 47 is fixedly connected to the upper end of the threaded rod 45 , and a plurality of movable balls 49 are disposed at the bottom of the fixing block 48 .
[0038] A Bailey frame quick-detachment mechanism is provided on the upper side of the first support plate 43, and the Bailey frame quick-detachment mechanism includes a Bailey plate 51, which is fixedly connected to the upper side of the first support plate 43, and a plurality of support plates 53 are bolted to the side wall of the Bailey plate 51, and a connecting rod 54 is fixedly connected to the side wall of the support plate 53, a second connecting hole 56 is provided in the middle of the support plate 53, and a fixing plate 52 is provided on the support plate 53.
[0039] First connection holes 55 are provided on both sides of the fixing plate 52 , and the fixing plate 52 is connected to the supporting sheet 53 via connection pins 57 .
[0040] Working process: when it is necessary to move the Bailey plate 51 to a specified position, manually rotate the manual swivel 46 to lower the threaded rod 45. The lowering of the threaded rod 45 drives the third support plate 47 to move downward, so that the third support plate 47 releases its support for the inner upper wall of the I-beam 2, making it easier for the jack 42 to move as a whole.
[0041] At the same time, the jack 42 is used manually, so that the jack 42 drives the second support plate 44 to move upward, and the upward movement of the second support plate 44 drives the first support plate 43 to move upward, and the first support plate 43 presses against the Bailey plate 51, so that the Bailey plate 51 is separated from the I-beam 2, and a plurality of movable balls 49 are provided at the bottom of the fixed block 48 to facilitate subsequent staff to push the Bailey plate 51 to the specified position. The overall Bailey plate 51 is transformed from sliding friction to rolling friction, so that the overall Bailey plate 51 is easy to move.
[0042] When the bracket needs to be removed quickly, the connecting pin 57 is manually removed to release the fixing plate 52 and the supporting plate 53, and then the fixing plate 52 is removed to facilitate the Bailey bracket to be released, and then the Bailey bracket moving mechanism is used to quickly disassemble the Bailey bracket.
[0043] Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.
[0044] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0045] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A railway bridge construction support device, comprising a connecting column (1), characterized in that: The top end of the connecting cylinder (1) is fixedly connected to an I-beam (2), and a cylinder disassembly mechanism is provided on the connecting cylinder (1); The cylindrical disassembly mechanism comprises a fixing ring (33) and a connecting ring (31), wherein the fixing ring (33) is fixedly connected to the outside of the connecting cylinder (1), and the connecting ring (31) is fixedly connected to the outside of the connecting cylinder (1) by bolts, and the connecting ring (31) is arranged between the fixing rings (33), and a connecting fixture (32) is fixedly connected to the port of the connecting ring (31) by bolts.
2. A railway bridge construction support device according to claim 1, characterized in that: The I-beam (2) is provided with a Bailey frame moving mechanism, the Bailey frame moving mechanism comprising a moving plate (41), the moving plate (41) being arranged in a notch of the I-beam (2), the upper side of the moving plate (41) being fixedly connected to a jack (42), the upper side of the jack (42) being fixedly connected to a second support plate (44), the upper side of the second support plate (44) being fixedly connected to a first support plate (43), and both ends of the moving plate (41) being fixedly connected to fixed blocks (48).
3. A railway bridge construction support device according to claim 2, characterized in that: A threaded rod (45) is disposed on the upper side of the fixed block (48), a manual swivel (46) is fixedly connected to the outer side of the threaded rod (45), a third support plate (47) is fixedly connected to the upper end of the threaded rod (45), and a plurality of movable balls (49) are disposed on the bottom of the fixed block (48).
4. A railway bridge construction support device according to claim 2, characterized in that: A Bailey frame quick-detachment mechanism is arranged on the upper side of the first support plate (43), the Bailey frame quick-detachment mechanism comprising a Bailey plate (51), the Bailey plate (51) being fixedly connected to the upper side of the first support plate (43), a plurality of support plates (53) being bolted to the side wall of the Bailey plate (51), a connecting rod (54) being fixedly connected to the side wall of the support plate (53), a second connecting hole (56) being arranged in the middle of the support plate (53), and a fixing plate (52) being arranged on the support plate (53).
5. A railway bridge construction support device according to claim 4, characterized in that: First connection holes (55) are provided on both sides of the fixing plate (52), and the fixing plate (52) and the supporting plate (53) are connected via a connection pin (57).