Tubular pile reinforcement cage
By putting a connecting sleeve on the longitudinal steel bars of the pipe pile steel cage and welding the inner support ring, combining the reinforcement design of the positioning bar, positioning sleeve and reinforcement brace, the problems of welding damage and impact deformation are solved, and the strength of the steel cage is improved and stability.
Patent Information
- Application Number
- CN202323645615.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-29
- Publication Date
- 2025-02-11
- Estimated Expiration
- 2033-12-29
AI Technical Summary
The existing pipe pile steel cages are prone to damage longitudinal steel bars during welding, and are easily affected by impact deformation when pouring concrete, which affects the use effect.
A pipe pile steel cage was designed. By putting a connecting sleeve on the longitudinal steel bar and welding an inner support ring on the inner side of the connecting sleeve, it is reinforced by positioning ribs, positioning sleeves and reinforcement braces, and positioning rods and pads at the thickness of the protective layer. With the help of the plate, prevent the steel cage from touching the side wall of the pile hole.
It effectively avoids damage at the welding of longitudinal steel bars, improves the overall strength and stability of the steel bar cage, reduces the risk of deformation when pouring concrete, and extends the service life.
Smart Images

Figure CN222456557U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of steel bar cages, in particular to a pipe pile steel bar cage. Background Art
[0002] The main function of the steel cage is the same as the stress on the longitudinal steel bars of the column. It mainly plays a tensile role. The compressive strength of concrete is high but the tensile strength is very low. It restrains the concrete of the pile body and enables it to withstand a certain axial tension.
[0003] The pipe pile reinforcement cage has the following disadvantages: 1. The pipe pile reinforcement cage cannot avoid the existing inner support ring being directly welded on the longitudinal reinforcement, causing damage to the longitudinal reinforcement welding part, affecting the strength of the longitudinal reinforcement, and is easily deformed after being impacted during concrete pouring. To this end, we propose a pipe pile reinforcement cage. Utility Model Content
[0004] In view of the problems in the prior art, the utility model provides a pipe pile reinforcement cage, which can avoid the existing inner support ring being directly welded to the longitudinal reinforcement, causing damage to the welding joint of the longitudinal reinforcement and affecting the strength of the longitudinal reinforcement, and is not easily deformed by impact when pouring concrete.
[0005] The utility model solves the technical problem by adopting the following technical solution: a pipe pile steel cage, comprising a steel cage main part, the steel cage main part is composed of longitudinal steel bars, spiral stirrups and inner support rings, the longitudinal steel bars are sleeved with connecting sleeves at equal distances and the inner side of the connecting sleeves is welded with inner support rings;
[0006] A positioning rib is arranged at the axis center of the inner support ring, and a positioning sleeve is sleeved on the positioning rib at equal distances, and a reinforcing support is welded between the positioning sleeve and the inner support ring.
[0007] Furthermore, a protective layer thickness positioning rod is welded on the outer side of the connecting sleeve facing the reinforcing support, and three groups of protective layer thickness positioning rods and reinforcing supports on the same layer are provided.
[0008] Furthermore, a pad is welded to the outer side of the protective layer thickness positioning rod, which effectively prevents the main part of the steel cage from touching the side wall of the pile hole, causing the protective layer thickness of the main part of the steel cage to decrease, affecting the use effect.
[0009] Furthermore, spiral stirrups with a circular cross-section are welded around the outer side of the longitudinal steel bars, and the spiral stirrups connect the longitudinal steel bars into a whole, so that the bearing capacity of the pile body after casting is stronger.
[0010] Furthermore, the diameter of the positioning reinforcement is twice that of the longitudinal reinforcement.
[0011] Compared with the prior art, the utility model has the following beneficial effects:
[0012] The inner support ring is welded to the connecting sleeve and the connecting sleeve is set on the longitudinal steel bar. The inner support ring is used to play a supporting effect and can avoid the problem that the existing inner support ring is directly welded to the longitudinal steel bar, causing damage to the welding part of the longitudinal steel bar, affecting the strength of the longitudinal steel bar and reducing the overall strength of the steel cage.
[0013] The positioning bars, positioning sleeves and reinforcing braces are used to reinforce the main parts of the overall steel cage, greatly improving the strength and stability, avoiding large impact forces during concrete pouring, which would cause deformation and damage to the pipe pile steel cage and affect the use effect. The protective layer thickness positioning rods and pads are used to effectively prevent the main parts of the steel cage from touching the side walls of the pile hole, causing the protective layer thickness of the main parts of the steel cage to decrease and affect the use effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the overall structure of the utility model.
[0015] Figure 2 It is a bottom view of the utility model.
[0016] Figure 3 This is a large-scale drawing of point A of the utility model.
[0017] In the figure: 1. Main part of the steel cage; 101. Longitudinal steel bars; 102. Spiral stirrups; 103. Inner support ring; 2. Positioning bars; 3. Positioning sleeves; 4. Reinforcement support; 5. Connecting sleeves; 6. Protective layer thickness positioning rods; 7. Pads. DETAILED DESCRIPTION
[0018] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.
[0019] In order to avoid the existing inner support ring being directly welded to the longitudinal reinforcement, which may cause damage to the longitudinal reinforcement welding part and affect the strength of the longitudinal reinforcement, and it is not easy to be deformed after impact during concrete pouring, such as Figure 1-3 As shown, a pipe pile reinforcement cage includes a reinforcement cage main part 1, the reinforcement cage main part 1 is composed of longitudinal reinforcement 101, spiral stirrups 102 and inner support rings 103, the longitudinal reinforcement 101 is sleeved with connecting sleeves 5 at equal distances, and the inner side of the connecting sleeves 5 is welded with the inner support ring 103;
[0020] A positioning rib 2 is provided at the axis of the inner support ring 103 , and a positioning sleeve 3 is sleeved on the positioning rib 2 at an equal distance, and a reinforcing support 4 is welded between the positioning sleeve 3 and the inner support ring 103 .
[0021] Among them, a protective layer thickness positioning rod 6 is welded on the outer side of the connecting sleeve 5 facing the reinforcing support 4, and three groups of protective layer thickness positioning rods 6 and reinforcing support 4 on the same layer are provided.
[0022] In this embodiment, Figure 1 As shown, the reinforcing brace 4 improves the stability of the main steel cage component 1 and reduces deformation.
[0023] Wherein, a pad 7 is welded to the outer side of the protective layer thickness positioning rod 6 .
[0024] In this embodiment, Figure 1 As shown, the main part 1 of the steel cage is effectively prevented from touching the side wall of the pile hole, causing the thickness of the protective layer of the main part 1 of the steel cage to be reduced, thus affecting the use effect.
[0025] The outer side of the longitudinal steel bar 101 is wrapped and welded with a spiral stirrup 102 with a circular cross section.
[0026] In this embodiment, Figure 1 As shown, the spiral stirrups 102 connect the longitudinal reinforcements 101 into a whole, so that the bearing capacity of the pile body after pouring is stronger.
[0027] The diameter of the positioning rib 2 is specifically twice that of the longitudinal reinforcement 101 .
[0028] In this embodiment, Figure 3 As shown, the strength of the positioning rib 2 is increased, thereby improving the supporting effect.
[0029] It should be noted that the utility model is a pipe pile steel cage. When working, the inner support ring 103 is welded to the connecting sleeve 5 and the connecting sleeve 5 is sleeved on the longitudinal steel bar 101. The inner support ring 103 is used to play a supporting role, and the existing inner support ring 103 can be avoided from being directly welded to the longitudinal steel bar 101, causing damage to the welding part of the longitudinal steel bar 101, affecting the strength of the longitudinal steel bar 101, and reducing the overall strength of the steel cage. The positioning ribs 2, positioning sleeves 3 and reinforcing braces 4 are used to reinforce the overall steel cage main component 1, and the strength and stability are greatly improved, avoiding a large impact force during concrete pouring, causing deformation and damage to the pipe pile steel cage, affecting the use effect, and using the protective layer thickness positioning rod 6 and pad 7 to effectively prevent the steel cage main component 1 from touching the side wall of the pile hole, causing the protective layer thickness of the steel cage main component 1 to be reduced, affecting the use effect.
[0030] In the description of the present utility model, it should be understood that the terms "upper", "lower", "top", "bottom", "inside", "outside", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, or are the orientations or positional relationships in which the utility model product is conventionally placed when in use, or are the orientations or positional relationships conventionally understood by those skilled in the art. They are only for the convenience of describing the present utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present utility model.
[0031] In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. In the present utility model, unless otherwise clearly specified and limited, the terms "install", "set", "connect", "fix", "screw" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection or an electrical connection;
[0032] The above embodiments are only preferred embodiments of the present invention and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A pipe pile reinforcement cage, comprising a reinforcement cage main part (1), characterized in that: The steel cage main part (1) is composed of longitudinal steel bars (101), spiral stirrups (102) and an inner support ring (103); the longitudinal steel bars (101) are sleeved with connecting sleeves (5) at equal distances, and the inner side of the connecting sleeves (5) is welded with an inner support ring (103); A positioning rib (2) is provided at the axis of the inner support ring (103), and a positioning sleeve (3) is sleeved on the positioning rib (2) at an equal distance, and a reinforcing support (4) is welded between the positioning sleeve (3) and the inner support ring (103).
2. The pipe pile reinforcement cage according to claim 1, characterized in that: A protective layer thickness positioning rod (6) is welded on the outside of the connecting sleeve (5) facing the reinforcing support (4), and three groups of protective layer thickness positioning rods (6) and reinforcing support (4) on the same layer are provided.
3. A pipe pile reinforcement cage according to claim 2, characterized in that: A backing plate (7) is welded to the outer side of the protective layer thickness positioning rod (6).
4. The pipe pile reinforcement cage according to claim 1, characterized in that: The outer side of the longitudinal steel bar (101) is welded with a spiral stirrup (102) with a circular cross section.
5. The pipe pile reinforcement cage according to claim 1, characterized in that: The diameter of the positioning rib (2) is specifically twice that of the longitudinal reinforcement (101).