Steel wire rope flexible operation platform for aloft work in hollow area of building

By designing a flexible wire rope operation platform for high altitude operations in the hollow building area, the problems of unsuitable erection height, high destructiveness to building structures and low efficiency of high altitude strapping and fixing in the prior art are solved, and high flexibility and safety are achieved Improvement of performance and construction efficiency.

CN222478099UActive Publication Date: 2025-02-14YUNNAN CONSTR INVESTMENT HLDG GRP CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420384084.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-29
Publication Date
2025-02-14
Estimated Expiration
2034-02-28

AI Technical Summary

Technical Problem

The prior art has difficulty in construction in high-altitude operations in hollow buildings, including unsuitable erection heights, high destructiveness to the main structure of the building, and low efficiency of high-altitude strapping and fixing.

Method used

A flexible operating platform for high-altitude operations in the hollow area of ​​the building was designed. The cross-arranged steel cables were used to form a rope mesh structure, and the nylon pocket mesh and laminated plates were laid on the steel cables. , use movable lever and flower basket bolts to fix it.

Benefits of technology

A flexible operating platform with a height adjustment as needed is realized, reducing damage to the main structure of the building and improving the safety and construction efficiency of high-altitude operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222478099U_ABST
    Figure CN222478099U_ABST
Patent Text Reader

Abstract

The utility model discloses a steel wire rope flexible operation platform for aloft work in a hollow area of a building, which comprises a plurality of steel corbels, each steel corbel is fixed on the outer side of a stand column on the periphery of the hollow area through an anchor bolt, and a plurality of cross beams are arranged on the steel corbels on the outer sides of the stand columns on the periphery of the hollow area. A sliding groove is formed in the side, close to the hollow area, of the beam. A plurality of movable pull rods are slidably arranged on the sliding groove, and drag hooks are arranged at the front ends of the movable pull rods. Steel cables are arranged in a hollow area of the building and comprise a plurality of transverse steel cables and a plurality of longitudinal steel cables, the transverse steel cables and the longitudinal steel cables are arranged in a crossed mode to form a net-shaped structure, two ends of the transverse steel cables and the longitudinal steel cables are connected to the drag hooks through turn buckles, and steel cable fixing seats are arranged at crossed positions of the transverse steel cables and the longitudinal steel cables.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of operating platforms, in particular to a steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings. Background Art

[0002] In the design of public buildings, there are usually hollow areas above halls or large light wells, and high-altitude construction such as steel structure hoisting or glass dome is usually required above this area, which is difficult to construct. Usually, this area needs to be equipped with ground-based or cantilevered full-hall operating scaffolding to assist in high-altitude construction. However, if this method is used for construction, on the one hand, the construction period of full-hall scaffolding is long, which is not conducive to the control of construction period; on the other hand, if the scaffolding is set up too high, the danger will be greatly increased, and the amount of materials input will increase, resulting in an increase in unnecessary construction costs.

[0003] In the existing flexible operating platform, for example, the Chinese utility model patent with patent number CN201120079160.1 discloses a cable suspension flexible construction platform, which includes transverse cables and longitudinal cables arranged parallel to the horizontal plane, the transverse cables and longitudinal cables are arranged vertically and crosswise to form a mesh structure, the two ends of the transverse cables and longitudinal cables are fixed to the crossbeam by anchor bolts, and the working surface is laid on the mesh structure. The front ends of the transverse cables and longitudinal cables are heart-shaped ring structures, and the heart-shaped rings are connected to the anchor bolts by a basket bolt. The patent also has the following problems:

[0004] 1. The transverse cables and longitudinal cables of the patent are fixed on the crossbeam, but the height of the crossbeam and the design spacing of the top steel structure or glass dome in the hollow area are not fixed. The height of the crossbeam may not be suitable for the height of the operating platform. If the crossbeam is too low or too high, it will be difficult for the operators to construct the top steel structure or glass dome after the construction platform of the patent is erected.

[0005] 2. The spacing between the transverse cables and the longitudinal cables does not exceed 1m, while both ends of the transverse cables and the longitudinal cables of this patent are anchored to the beams by chemical anchors. It is necessary to drill a row of anchor holes with a spacing of less than 1m on the beams in advance. The large number of holes is very destructive to the beam structure and may seriously affect the safety of the main structure of the building.

[0006] 3. After laying, the dense mesh and nylon net need to be fixed on the transverse and longitudinal cables. The patent does not disclose the structural features of fixing the dense mesh and nylon net. The traditional method is to fix them by tying them with ropes, but the high-altitude tying and fixing method is more troublesome and inefficient, which affects the construction progress. Summary of the invention

[0007] The technical problem to be solved by the utility model is to overcome the deficiencies of the prior art and provide a steel wire rope flexible operating platform for high-altitude operations in the hollow area of ​​a building.

[0008] The utility model is realized by the following technical solutions:

[0009] A steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings, comprising:

[0010] A plurality of steel brackets (1), each of which is fixed to the outside of a column (9) around the hollow area by anchor bolts, for auxiliary support of the crossbeam (2);

[0011] A plurality of cross beams (2) are respectively arranged on the steel brackets (1) outside the upright columns (9) around the hollow area, and a slide groove (211) is arranged on one side of the cross beam (2) close to the hollow area. The cross beam (2) is used to bear the tension of the steel cable (4);

[0012] A plurality of movable pull rods (3), the tails of which are slidably arranged on the slide grooves (211), and the front ends of the movable pull rods (3) are provided with pull hooks (31);

[0013] The steel cable (4) comprises a plurality of transverse steel cables (41) and a plurality of longitudinal steel cables (42) arranged crosswise in a mesh structure, and both ends of the transverse steel cables (41) and the longitudinal steel cables (42) are connected to the draw hook (31) via a turnbuckle bolt (43);

[0014] A plurality of steel cable fixing seats (5) are respectively fixed at the intersection of the transverse steel cable (41) and the longitudinal steel cable (42) and are used to lock the transverse steel cable (41) and the longitudinal steel cable (42).

[0015] Furthermore, the crossbeam (2) is fixed to the column (9) via a crossbeam fixing assembly (6), and the fixing assembly (6) comprises:

[0016] A fixed cross bar (61) is transversely arranged on one side of the column (9) close to the hollow area, and waist-shaped holes are arranged on both sides of the fixed cross bar (61);

[0017] The two crossbeam pull rods (62) are provided with threads at the front ends and are slidably arranged in the slide grooves (211). The front ends of the two crossbeam pull rods (62) respectively pass through the waist-shaped holes on both sides of the fixed cross bar (61) and are fixed by nuts.

[0018] Furthermore, the fixed cross bar (61) is a strip-shaped structure or a U-shaped structure.

[0019] Furthermore, at least one layer of nylon net (7) is laid above the steel cable (4), and a layer of board (8) is laid at the construction position and the walking route above the nylon net (7).

[0020] Furthermore, the steel cable fixing seat (5) comprises:

[0021] A connecting plate (51), wherein the connecting plate (51) is provided with four through holes;

[0022] A cross positioning groove (52) is arranged below the connecting plate (51), and the intersection of the transverse steel cable (41) and the longitudinal steel cable (42) is positioned in the cross positioning groove (52). A steel cable (5) located below is respectively passed through four through holes on the connecting plate (51) by two U-shaped bolts (53) and is fixed to the connecting plate (51) by nuts.

[0023] Furthermore, a net fixing ring (54) is provided above the connecting plate (51), and the nylon net (7) is connected to the net fixing ring (54) via a net buckle (55).

[0024] Furthermore, the crossbeam (2) is a Bailey truss, which is composed of several single-section Bailey beams (21) connected end to end, and the single-section Bailey beam (21) includes two Bailey plates (22) arranged in parallel up and down and a vertical connecting plate (23) connecting the ends of the two Bailey plates (22), and the gap formed by the two channel steels on both sides of the Bailey plate (22) is a slide groove (211).

[0025] Furthermore, a limiting plate (32) is arranged at the tail of the movable pull rod (3) perpendicular to the axis of the pull rod, the front end of the movable pull rod (3) passes through the slide groove (211) and is connected to the basket bolt (43), and the movable pull rod (3) is limited on the slide groove (211) by the limiting plate (32).

[0026] Furthermore, a temporary staircase platform is arranged outside the cross beam (2) on one side of the hollow area of ​​the building, and the bottom of the temporary staircase platform is erected on the ground or on the roof of the building on one side of the hollow area. The temporary staircase platform is erected using steel pipes and steel pipe fasteners.

[0027] Furthermore, the middle part of the steel cable (4) is suspended on the top steel structure of the hollow area of ​​the building through a steel wire rope.

[0028] The working principle of this utility model:

[0029] The utility model utilizes a cross-pull of a transverse steel cable (41) and a longitudinal steel cable (42) to form a steel cable (4) rope net as a bearing platform for high-altitude operations in a hollow area of ​​a building; the cross-section of the transverse steel cable (41) and the longitudinal steel cable (42) is fixed by a steel cable fixing seat (5); a double-layer nylon bag net (7) is fully laid on the steel cable (4) rope net, and the nylon bag net (7) is hung and buckled on a bag net fixing ring (54) above the steel cable fixing seat (5) by a bag net buckle (71); and a layer board (8) is laid above the nylon bag net (7) according to the construction position and the walking route of the construction personnel.

[0030] When the steel cable fixing seat (5) is installed, the intersection of the transverse steel cable (41) and the longitudinal steel cable (42) is positioned in the cross positioning groove (52), and a steel cable (5) located at the bottom passes through four through holes on the connecting plate (51) respectively through two U-shaped bolts (53) and is fixed to the connecting plate (51) through nuts.

[0031] The two ends of the steel cable (4) are bolted and fixed to the hook (31) at the front end of the movable pull rod (3), and a basket bolt (43) is used to tighten one end of the steel cable (4) and the hook (31). The transverse steel cables (41) and longitudinal steel cables (42) of the entire steel wire rope flexible operating platform are arranged at a spacing of 0.8m. The tail of the movable pull rod (3) is slidably installed on the slide groove (211) of the cross beam (2), and the cross beam (2) is assembled by connecting multiple sections of Bailey beams (21) end to end. The Bailey beam (21) is connected and assembled by two Bailey plates (22) and two connecting plates (23), and the slide groove (211) is arranged on both sides of the Bailey plates (22); the cross beam (2) is installed above the steel bracket (1), and the steel bracket (1) is installed on the outer side of the frame column (9) of the upper main building structure in the hollow area through expansion bolts; the cross beam (2) is fixed to the column (9) by using a fixing component (6) at the position where the cross beam (2) contacts the column (9).

[0032] When installing the fixing assembly (6), the tails of the two crossbeam pull rods (62) are respectively installed on the slide grooves (211) of the crossbeam (2) on both sides of the column (9), and the front ends of the two crossbeam pull rods (62) pass through the waist-shaped holes on both sides of the fixed crossbar (61) and are fixed by nuts.

[0033] Compared with the prior art, the utility model has the following beneficial effects:

[0034] The utility model supports and fixes the cross beam (2) through the steel bracket (1) and the fixing assembly (6), thereby forming a double fixing protection for the cross beam (2), and the steel bracket (1) and the fixing assembly (6) can adjust their fixing heights according to the erection height of the flexible platform, so the utility model is easy to use and has high safety.

[0035] The crossbeam (2) of the utility model is made in the style of a Bailey beam (21) and has high strength. The Bailey beam (21) is detachable and convenient for turnover and transportation.

[0036] The movable pull rod (3) and the crossbeam pull rod (62) of the fixed assembly (6) of the utility model can slide on the slide groove (211) of the crossbeam (2) to adjust the position, so that the staff can adjust the spacing between the transverse steel cable (41) and the longitudinal steel cable (42) conveniently.

[0037] The utility model provides a net fixing ring (54) on the steel cable fixing seat (5), and the nylon net (7) can be hung and buckled on the net fixing ring (54) by means of the net buckle (71). The nylon net (7) is easy to install and operate, and the installation efficiency of the double-layer nylon net (7) is greatly improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 It is a three-dimensional structural schematic diagram of the utility model;

[0039] Figure 2 It is an exploded view of the Bailey beam of the utility model;

[0040] Figure 3 This is a schematic diagram of the assembly of the Bailey beam of the utility model;

[0041] Figure 4 This is a schematic diagram of the structure of the utility model in which the crossbeam is installed on a square column;

[0042] Figure 5 This is a schematic diagram of the structure of the utility model in which the crossbeam is installed on a circular column;

[0043] Figure 6 This is a schematic diagram of the connection between the steel cable and the Bailey beam of the utility model;

[0044] Figure 7 It is a structural schematic diagram of the movable pull rod of the utility model;

[0045] Figure 8 This is a diagram of the use status of the steel cable net of the utility model;

[0046] Fig. 9 This is one of the structural schematic diagrams of the steel cable fixing seat of the utility model;

[0047] Fig.10 This is the second structural schematic diagram of the steel cable fixing seat of the utility model;

[0048] Fig.11 This is a schematic diagram of the installation of the nylon net of the utility model;

[0049] Fig.12 This is a cross-sectional view of the nylon net and layer board of the utility model in use.

[0050] Numbers in the figure:

[0051] 1-Steel corbel;

[0052] 2-crossbeam, 21-Bailey beam, 211-slideway, 22-Bailey plate, 23-connecting plate;

[0053] 3-movable pull rod, 31-hook, 32-limiting plate;

[0054] 4- steel cable, 41- transverse steel cable, 42- longitudinal steel cable, 43- turnbuckle bolt;

[0055] 5-wire fixing seat, 51-connecting plate, 52-cross positioning groove, 53-U-bolt, 54-net fixing ring;

[0056] 6-fixed assembly, 61-fixed crossbar, 62-crossbeam tie rod;

[0057] 7-nylon net, 71-net buckle;

[0058] 8-layer board;

[0059] 9- Pillar. DETAILED DESCRIPTION

[0060] In order to enable those skilled in the art to better understand the technical solution of the utility model, its specific implementation method is described in detail below with reference to the accompanying drawings.

[0061] like Figure 1-12 As shown, a flexible wire rope operation platform for high-altitude operations in the hollow area of ​​a building comprises several steel corbels 1, each of which is fixed to the outside of a column 9 around the hollow area by anchor bolts, several cross beams 2 are arranged on the steel corbels 1 on the outside of the columns 9 around the hollow area, and a slide groove 211 is arranged on the side of the cross beam 2 close to the hollow area; several movable pull rods 3 are slidably arranged on the slide groove 211, and a hook 31 is arranged at the front end of the movable pull rod 3; a steel cable 4 is arranged in the hollow area of ​​the building, including several transverse steel cables 41 and several longitudinal steel cables 42 which are cross-arranged in a mesh structure, and both ends of the transverse steel cables 41 and the longitudinal steel cables 42 are connected to the hook 31 by basket bolts 43, and a steel cable fixing seat 5 is arranged at the intersection of the transverse steel cables 41 and the longitudinal steel cables 42.

[0062] In an embodiment, Figure 4 , 5 As shown, the crossbeam 2 is fixed to the column 9 by a crossbeam fixing assembly 6, and the fixing assembly 6 includes a fixed cross bar 61 which is transversely arranged on one side of the column 9 close to the hollow area, and waist-shaped holes are arranged on both sides of the fixed cross bar 61; two crossbeam pull rods 62 with threads at the front end are slidably arranged on the slide groove 211, and the front ends of the two crossbeam pull rods 62 respectively pass through the waist-shaped holes on both sides of the fixed cross bar 61 and are fixed by nuts.

[0063] The fixed cross bar 61 is a strip-shaped structure or a U-shaped structure. The fixed cross bar 61 with a strip-shaped structure is used to adapt to the shape of the square column 9; the fixed cross bar 61 with a U-shaped structure is used to adapt to the shape of the circular column 9.

[0064] In an embodiment, Figure 1As shown, two layers of nylon nets 7 are laid above the steel cables 4, and layers 8 are laid at the construction position and walking route above the nylon nets 7; the nylon nets 7 are used to prevent workers from falling from the gap between the transverse steel cables 41 and the longitudinal steel cables 42, thereby improving the safety of high-altitude operations.

[0065] In an embodiment, Figure 9-12 As shown, the steel cable fixing seat 5 includes a connecting plate 51, and four through holes are arranged on the connecting plate 51; a cross positioning groove 52 is arranged below the connecting plate 51, and the intersection of the transverse steel cable 41 and the longitudinal steel cable 42 is positioned in the cross positioning groove 52, and a steel cable 4 located below is respectively passed through the four through holes on the connecting plate 51 by two U-shaped bolts 53, and is fixed to the connecting plate 51 by nuts; a net fixing ring 54 is arranged above the connecting plate 51, and the nylon net 7 is connected to the net fixing ring 54 by a net buckle 55.

[0066] In an embodiment, Figure 2 , 3 As shown, the crossbeam 2 is a Bailey truss, which is composed of several single-section Bailey beams 21 connected end to end. The single-section Bailey beam 21 includes two Bailey plates 22 arranged in parallel up and down and a vertical connecting plate 23 connecting the ends of the two Bailey plates 22. The gap formed by the two channel steels on both sides of the Bailey plate 22 is a slide groove 211.

[0067] In an embodiment, Figure 6 , 7 As shown, a limiting plate 32 is arranged perpendicularly to the axis of the movable pull rod at the tail end of the movable pull rod 3 , and the front end of the movable pull rod 3 passes through the slide groove 211 and is connected to the basket bolt 43 , and the movable pull rod 3 is limited on the slide groove 211 by the limiting plate 32 .

[0068] In the embodiment, a temporary staircase platform is arranged outside the crossbeam 2 on one side of the hollow area of ​​the building. The bottom of the temporary staircase platform is erected on the ground or on the roof of the building on one side of the hollow area. The temporary staircase platform is erected with steel pipes and steel pipe fasteners, and is erected in sections with an erection width of 1.5m. The erection height is subject to the actual situation on site. The frame beam position is reinforced with a beam, the first section of the platform is reinforced with a diagonal brace, and the vertical pole reinforcement uses steel pipe fasteners with a step distance of 1.5m.

[0069] In the embodiment, the middle part of the steel cable 4 is hung on the top steel structure of the hollow area of ​​the building through a steel wire rope, and four hanging points are set on each main steel beam and one hanging point is set on the secondary steel beam to lift the rope net of the steel cable 4.

[0070] Working mode of the utility model:

[0071] When setting up a flexible platform:

[0072] Step 1: Install steel corbels 1 on the frame columns 9 of the upper main building structure in the hollow area. Install 1-2 steel corbels 1 on the outside of each frame column 9. The installation height of the steel corbels 1 is 0.4m below the main steel beam.

[0073] Step 2: After assembling the Bailey pieces 22 and the connecting pieces 23 into a plurality of single-section Bailey beams 21, the multiple sections of Bailey beams 21 are connected end to end to form a crossbeam 2 according to the dimensions of the hollow area, and the crossbeam 2 is hoisted onto the steel corbel 1 by a lifting device, and the crossbeam 2 is fixed to the column 9 by a fixing assembly 6 at the position where the crossbeam 2 contacts the column 9;

[0074] When installing the fixing assembly 6, the tails of the two beam pull rods 62 are respectively installed on the slide grooves 211 of the beam 2 on both sides of the column 9, and the front ends of the two beam pull rods 62 pass through the waist-shaped holes on both sides of the fixed crossbar 61 and are fixed by nuts.

[0075] Step 3: Use 6*19M-FC steel wire ropes with a diameter of 9.3mm to set them crosswise and vertically, slide the tails of several movable pull rods 3 on the slide groove 211 of the crossbeam 2, tighten and fix the two sides of the steel cable 4 on the hook 31 at the front end of the movable pull rod 3, and use 20# basket bolts 43 to tighten one end of the steel cable 4 and the hook 31. The transverse steel cables 41 and longitudinal steel cables 42 of the entire steel wire rope flexible operating platform are arranged at a spacing of 0.8m, and the basket bolts need to be symmetrically staggered.

[0076] Step 4: The intersection of the steel cables 4 is fastened with a steel cable fixing seat 5, and the intersection of the transverse steel cables 41 and the longitudinal steel cables 42 is positioned in the cross positioning groove 52. The steel cable 4 located below passes through the four through holes on the connecting plate 51 through two U-bolts 53 and is fixed to the connecting plate 51 by nuts.

[0077] Step 5: Fully spread the double-layer nylon bag net 7 on the rope net of the steel cable 4, and use the bag net buckle 71 to hang the nylon bag net 7 on the bag net fixing ring 54 above the steel cable fixing seat 5.

[0078] Step 6: Lay the layer board 8 on the top of the nylon net 7 according to the construction location and the walking route of the construction workers. The four corners of the layer board 8 are tied and fixed with 14# black iron wire and steel cable 4.

[0079] Step 7: After the main steel beam at the top of the hollow area is hoisted into place, add 4 lifting points on each main steel beam and 1 lifting point on the secondary steel beam to lift the 4-rope net of the steel cable; the added lifting points are fastened with basket bolts and the connection between the wire rope and the basket bolts is protected by chicken core rings.

[0080] Step 8: Build a staircase platform on the outside of the beam 2 on one side of the hollow area. The bottom of the temporary staircase platform is built on the ground or on the roof of the building on one side of the hollow area. The temporary staircase platform is built with steel pipes and steel pipe fasteners, and is built in sections with a width of 1.5m.

[0081] Step 9: Use safety nets to protect the edges around the operating platform. Use 8# expansion hooks to fix the safety nets at the top and bottom to achieve the edge protection effect.

[0082] It should be noted that the above detailed introduction of the technical solution of the utility model and the description of the principle of the utility model are provided, and the above description of the working principle is only used to help understand the core idea of ​​the utility model. It should be pointed out that for ordinary technicians in this technical field, without departing from the principle of the utility model, the utility model can also be improved and modified, and these improvements and modifications also fall within the scope of protection of the claims of the utility model.

[0083] The technical personnel in the technical field of the utility model can make modifications or supplements to the specific embodiments described or replace them in a similar manner, as long as they do not deviate from the structure of the utility model or exceed the scope defined by the claims, which shall fall within the protection scope of the utility model. Therefore, the protection scope of the utility model patent shall be based on the attached claims.

Claims

1. A steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings, characterized in that: include: A plurality of steel brackets (1), each of which is fixed to the outside of a column (9) around the hollow area by anchor bolts, for auxiliary support of the crossbeam (2); A plurality of cross beams (2) are respectively arranged on the steel brackets (1) outside the upright columns (9) around the hollow area, and a slide groove (211) is arranged on one side of the cross beam (2) close to the hollow area. The cross beam (2) is used to bear the tension of the steel cable (4); A plurality of movable pull rods (3), the tails of which are slidably arranged on the slide grooves (211), and the front ends of the movable pull rods (3) are provided with pull hooks (31); The steel cable (4) comprises a plurality of transverse steel cables (41) and a plurality of longitudinal steel cables (42) arranged crosswise in a mesh structure, and both ends of the transverse steel cables (41) and the longitudinal steel cables (42) are connected to the draw hook (31) via a turnbuckle bolt (43); A plurality of steel cable fixing seats (5) are respectively fixed at the intersection of the transverse steel cable (41) and the longitudinal steel cable (42) and are used to lock the transverse steel cable (41) and the longitudinal steel cable (42).

2. The steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings according to claim 1 is characterized by: The crossbeam (2) is fixed to the column (9) via a crossbeam fixing assembly (6), and the fixing assembly (6) comprises: A fixed cross bar (61) is transversely arranged on one side of the column (9) close to the hollow area, and waist-shaped holes are arranged on both sides of the fixed cross bar (61); The two crossbeam pull rods (62) are provided with threads at the front ends and are slidably arranged in the slide grooves (211). The front ends of the two crossbeam pull rods (62) respectively pass through the waist-shaped holes on both sides of the fixed cross bar (61) and are fixed by nuts.

3. The steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings according to claim 2 is characterized by: The fixed cross bar (61) is a strip-shaped structure or a U-shaped structure.

4. The steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings according to claim 1 is characterized by: At least one layer of nylon net (7) is laid above the steel cable (4), and a layer board (8) is laid at the construction position and the walking route above the nylon net (7).

5. The steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings according to claim 4 is characterized by: The steel cable fixing seat (5) comprises: A connecting plate (51), wherein the connecting plate (51) is provided with four through holes; A cross positioning groove (52) is arranged below the connecting plate (51), and the intersection of the transverse steel cable (41) and the longitudinal steel cable (42) is positioned in the cross positioning groove (52). A steel cable (4) located below is respectively passed through four through holes on the connecting plate (51) by two U-shaped bolts (53) and is fixed to the connecting plate (51) by nuts.

6. The steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings according to claim 5 is characterized by: A net fixing ring (54) is arranged above the connecting plate (51), and the nylon net (7) is connected to the net fixing ring (54) via a net buckle (55).

7. The steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings according to claim 1 is characterized by: The crossbeam (2) is a Bailey truss, which is composed of several single-section Bailey beams (21) connected end to end. The single-section Bailey beam (21) includes two Bailey plates (22) arranged in parallel up and down and a vertical connecting plate (23) connecting the ends of the two Bailey plates (22). The gap formed by the two channel steels on both sides of the Bailey plate (22) is a slide groove (211).

8. The steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings according to claim 7 is characterized by: A limiting plate (32) is arranged at the tail of the movable pull rod (3) perpendicular to the pull rod axis, the front end of the movable pull rod (3) passes through the slide groove (211) and is connected to the basket bolt (43), and the movable pull rod (3) is limited on the slide groove (211) by the limiting plate (32).

9. The steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings according to claim 1 is characterized by: A temporary staircase platform is arranged outside the crossbeam (2) on one side of the hollow area of ​​the building. The bottom of the temporary staircase platform is erected on the ground or on the roof of the building on one side of the hollow area. The temporary staircase platform is erected using steel pipes and steel pipe fasteners.

10. The steel wire rope flexible operating platform for high-altitude operations in hollow areas of buildings according to claim 1 is characterized by: The middle part of the steel cable (4) is hung on the top steel structure of the hollow area of ​​the building through a steel wire rope.

Citation Information

Patent Citations

  • Flexible construction platform for suspension cable

    CN201962931U