Engineering construction pipeline transfer equipment

By designing a construction pipeline transfer equipment including support base, load-bearing rod, load-bearing hanger, buffer damper and high-strength steel wire rope, the displacement and fracture problems caused by inertial forces and bumps in heavy pipeline transportation are solved, and the problem of displacement and fracture caused by inertial forces and bumps is achieved. More stable and safe pipeline transportation.

CN222479641UActive Publication Date: 2025-02-14TIANJIN LINHAI CONSTR ENG GRP
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421066580.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-16
Publication Date
2025-02-14
Estimated Expiration
2034-05-16

AI Technical Summary

Technical Problem

Existing pipeline transfer equipment is prone to moving equipment due to inertia forces when transporting heavy pipelines, causing pipeline displacement; at the same time, bumps in the road surface will cause impact force to cause pipeline breakage.

Method used

A construction pipeline transfer equipment was designed, using supporting base, load-bearing rod, load-bearing hanger, buffer damper, self-locking air pressure adjustment seat and high-strength steel wire rope and other components to fix the water pipe through support stop seat and limit screw , use high-strength steel wire rope to share the weight of the water pipe to reduce bumps and impact.

Benefits of technology

It effectively avoids pipeline displacement and fracture caused by inertial forces, improves the stability and safety of pipeline transportation, and enhances the equipment's bump resistance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222479641U_ABST
    Figure CN222479641U_ABST
Patent Text Reader

Abstract

The utility model provides engineering construction pipeline transfer equipment which comprises a supporting base, a plurality of supporting plates fixedly installed at the top of the supporting base, bearing rods fixedly installed at the four corners of the top of each supporting plate, a bearing hanging bracket arranged at the tops of the bearing rods, a plurality of buffering dampers arranged at the tops of the supporting plates, and a bearing supporting plate arranged at the tops of the buffering dampers. Self-locking type air pressure adjusting seats are arranged on the two sides of the bearing hanging bracket, air pressure rods are arranged at the bottoms of the self-locking type air pressure adjusting seats, limiting pressing plates are arranged at the bottoms of the air pressure rods, sliding grooves are formed in the two sides of the supporting plate, and supporting blocking seats are connected into the sliding grooves in a sliding mode. The high-strength steel wire lifting rope is wound around the bottom of the water pipe, the two ends of the high-strength steel wire lifting rope are fixed to the steel cable U-shaped clamps, the water pipe is lifted through the high-strength steel wire lifting rope, the weight of the water pipe is shared through supporting force of the bearing rod and the bearing lifting frame, and the stability of the water pipe during transportation is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of pipeline transfer equipment, and in particular relates to engineering construction pipeline transfer equipment. Background Art

[0002] The existing pipeline transportation equipment needs to use large equipment to lift the pipeline for transportation. Only one pipeline can be transported on one side, which has low work efficiency. At the same time, the sizes of various pipelines are different. Each transportation needs to use equipment to re-fix pipelines of different sizes for transportation, which is very inconvenient. Among them, the "Pipeline Transportation Device for Water Conservancy Construction" disclosed in the application number "CN202321292021.6" is also an increasingly mature technology. The anti-slip rubber pad fixedly connected to the inner side of the upper arc plate and the rubber convex block fixedly connected to the inner side of the lower arc plate can prevent the surface of the pipeline from slipping. The function is to prevent the pipeline from sliding during transportation. By setting three groups of upper arc plates and lower arc plates, the working efficiency of pipeline transportation can be improved, and the problem that the lower fixed plate and the upper fixed plate can only transport one pipeline at a time is solved, thereby improving the transportation efficiency. However, the device still has the following defects: when transporting the pipeline, the pipeline is heavy. After moving to the designated position, it is easy for the transportation equipment to generate forward inertia force, causing the equipment to move, resulting in displacement of the fixed pipeline. At the same time, when the equipment is transporting the pipeline, the bumpy road surface can easily cause the fixed water pipe to be subjected to impact forces in different directions, resulting in pipeline rupture. Utility Model Content

[0003] The utility model aims to provide a pipeline transfer device for engineering construction, aiming to solve the problem in the prior art that when transferring pipelines, the pipelines are heavy, and after being moved to a designated position, the transfer equipment is likely to generate a forward inertia force, causing the equipment to move, resulting in displacement of the fixed pipelines; at the same time, when the equipment is transferring pipelines, the bumpy road surface is likely to cause the fixed water pipes to be subjected to impact forces in different directions, resulting in pipeline rupture.

[0004] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0005] A construction engineering pipeline transfer equipment comprises a support base, a plurality of support plates are fixedly installed on the top of the support base, load-bearing rods are fixedly installed at the four corners of the top of the support plate, a load-bearing hanger is provided on the top of the load-bearing rod, a plurality of buffer dampers are provided on the top of the support plate, a load-bearing support plate is provided on the top of the buffer damper, self-locking gas pressure regulating seats are provided on both sides of the load-bearing hanger, a gas pressure rod is provided at the bottom of the self-locking gas pressure regulating seat, a limit pressure plate is provided at the bottom of the gas pressure rod, slide grooves are opened on both sides of the support plate, and support blocks are slidably connected in the slide grooves.

[0006] In an implementation scheme of the engineering construction pipeline transfer equipment of the utility model, a limiting screw is provided on one side of the inner wall of the slide groove, a movable groove is opened at the bottom of the support block seat, the limiting screw is inserted and connected in the movable groove, and a fastening screw is provided at one end of the limiting screw.

[0007] In this solution, after placing the cement pipe on the load-bearing support plate, the support block is installed into the slide groove, and the limiting screw is passed through the movable groove. The L-shaped limiting hook plate is used to support the two ends of the water pipe, the fastening screw is used to support the support block, and the support block is used to support the two ends of the water pipe to prevent the water pipe from falling off due to the forward impact after the water pipe stops moving.

[0008] In an implementation scheme of the engineering construction pipeline transfer equipment of the utility model, an adjusting screw is provided on one side of the support block, an L-shaped limiting hook plate is sleeved on the outside of the adjusting screw, and a nut is provided at one end of the adjusting screw.

[0009] In this solution, the L-shaped limit hook plate is moved, the L-shaped limit hook plate is hung on the side of the water pipe, and the nut is installed to fix the position of the L-shaped limit hook plate.

[0010] In an implementation scheme of the engineering construction pipeline transfer equipment of the utility model, steel cable U-shaped clamps are arranged at the four corners of the load-bearing hanger, and high-strength steel wire ropes are arranged inside the steel cable U-shaped clamps.

[0011] In this solution, a high-strength steel wire rope is wrapped around the bottom of the water pipe and both ends are fixed to the steel cable U-clamp. The water pipe is lifted by the high-strength steel wire rope, and the weight of the water pipe is shared by the supporting force of the load-bearing rod and the load-bearing hanger, thereby improving the stability of the water pipe during transportation.

[0012] In an implementation scheme of the engineering construction pipeline transfer equipment of the utility model, a traction hook is provided on one side of the support base.

[0013] In this solution, the traction hook is installed with the external traction equipment to facilitate large-scale movement and fixation of the rear water pipe.

[0014] In an implementation scheme of the engineering construction pipeline transfer equipment of the utility model, anti-slip pads are provided on the top of the load-bearing support plate and the bottom of the limiting pressure plate.

[0015] In this solution, the friction of the contact surface is increased by the anti-skid pads on the load-bearing support plate and the limiting pressure plate to prevent the water pipe from moving after being fixed.

[0016] In an implementation scheme of the engineering construction pipeline transfer equipment of the utility model, first threaded holes are provided at the four corners of the top of the load-bearing hanger, and a second threaded hole is provided at the top of the load-bearing rod, and the first threaded hole and the second threaded hole are threadedly connected by a screw.

[0017] In this solution, the water pipe is lifted and placed on a load-bearing support plate, and a load-bearing hanger is installed. When the first threaded hole is aligned with the second threaded hole, it is fixed with a screw to cap the top of the water pipe.

[0018] In an implementation scheme of the engineering construction pipeline transfer equipment of the utility model, a brake universal wheel is provided at the bottom of the support base.

[0019] In this solution, the support base is moved by braking the universal wheels.

[0020] Compared with the prior art, the beneficial effects of the utility model are:

[0021] 1. For the construction of pipeline transfer equipment in this project, the support block is installed into the slide slot, and the limit screw is passed through the movable slot. The support block is supported by the fastening screw, and the L-shaped limit hook plate is moved. The L-shaped limit hook plate is hung on the side of the water pipe, and the nut is installed to fix the position of the L-shaped limit hook plate. The L-shaped limit hook plate is used to support both ends of the water pipe to prevent the water pipe from falling off due to the forward impact after the water pipe stops moving;

[0022] 2. The pipeline transfer equipment constructed in this project is equipped with a high-strength steel wire rope that is wrapped around the bottom of the water pipe and fixed at both ends on the steel cable U-clamp. The water pipe is lifted by the high-strength steel wire rope, and the weight of the water pipe is shared by the supporting force of the load-bearing rod and the load-bearing hanger, thereby improving the stability of the water pipe during transportation. At the same time, the buffer damper is used to reduce the impact force caused by the bumps during the transportation of the water pipe to avoid damage to the water pipe. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0024] Figure 1 It is a structural schematic diagram of the utility model;

[0025] Figure 2 This is a schematic diagram of the load-bearing hanger structure of the utility model;

[0026] Figure 3 This is a schematic diagram of the slide structure of the utility model.

[0027] In the figure: 1. Support base; 2. Support plate; 3. Load-bearing rod; 4. Load-bearing hanger; 5. Buffer damper; 6. Load-bearing support plate; 7. Self-locking gas pressure adjustment seat; 8. Gas pressure rod; 9. Limit pressure plate; 10. Slide groove; 11. Support stop seat; 12. Limit screw; 13. Movable groove; 14. Fastening screw; 15. Adjusting screw; 16. L-shaped limit hook plate; 17. Steel cable U-shaped clamp; 18. High-strength steel wire rope; 19. Towing hook; 20. First threaded hole; 21. Second threaded hole; 22. Brake universal wheel. DETAILED DESCRIPTION

[0028] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0029] See also Figure 1-3 The utility model provides the following technical solutions: a construction pipeline transfer equipment, including a support base 1, a plurality of support plates 2 are fixedly installed on the top of the support base 1, load-bearing rods 3 are fixedly installed at the four corners of the top of the support plate 2, a load-bearing hanger 4 is arranged on the top of the load-bearing rod 3, a plurality of buffer dampers 5 are arranged on the top of the support plate 2, a load-bearing support plate 6 is arranged on the top of the buffer damper 5, self-locking air pressure regulating seats 7 are arranged on both sides of the load-bearing hanger 4, a gas pressure rod 8 is arranged at the bottom of the self-locking gas pressure regulating seat 7, a limit pressure plate 9 is arranged at the bottom of the gas pressure rod 8, slide grooves 10 are opened on both sides of the support plate 2, and a support stopper 11 is slidably connected in the slide groove 10.

[0030] For a specific embodiment of the engineering construction pipeline transfer equipment, please refer to Figure 3 A limiting screw 12 is provided on one side of the inner wall of the slide groove 10, a movable groove 13 is provided at the bottom of the support block seat 11, the limiting screw 12 is inserted and connected in the movable groove 13, and a fastening screw 14 is provided at one end of the limiting screw 12.

[0031] See also Figure 3 : After placing the cement pipe on the load-bearing support plate 6, install the support block 11 into the slide groove 10, and pass the limiting screw 12 through the movable groove 13, use the L-shaped limiting hook plate 16 to support the two ends of the water pipe, use the fastening screw 14 to support the support block 11, and use the support block 11 to support the two ends of the water pipe to prevent the water pipe from falling off due to the forward impact after the water pipe stops moving.

[0032] For a specific embodiment of the engineering construction pipeline transfer equipment, please refer to Figure 3An adjusting screw 15 is provided on one side of the support block 11, an L-shaped limiting hook plate 16 is sleeved on the outside of the adjusting screw 15, and a nut is provided on one end of the adjusting screw 15.

[0033] See also Figure 3 : Move the L-shaped limit hook plate 16, hang the L-shaped limit hook plate 16 on the side of the water pipe, and install the nut to fix the position of the L-shaped limit hook plate 16.

[0034] For a specific embodiment of the engineering construction pipeline transfer equipment, please refer to Figure 1 : The four corners of the load-bearing hanger 4 are provided with steel cable U-shaped clamps 17, and high-strength steel wire ropes 18 are arranged in the steel cable U-shaped clamps 17.

[0035] See also Figure 1 : Wrap the high-strength steel wire rope 18 around the bottom of the water pipe and fix both ends on the steel cable U-shaped clamp 17, use the high-strength steel wire rope 18 to lift the water pipe, use the supporting force of the load-bearing rod 3 and the load-bearing hanger 4 to share the weight of the water pipe, and improve the stability of the water pipe during transportation.

[0036] For a specific embodiment of the engineering construction pipeline transfer equipment, please refer to Figure 1 : A traction hook 19 is provided on one side of the supporting base 1.

[0037] See also Figure 1 : Install the traction hook 19 with the external traction equipment to facilitate large-scale mobile and fixed rear water pipes.

[0038] For a specific embodiment of the engineering construction pipeline transfer equipment, please refer to Figure 2 : The top of the load-bearing support plate 6 and the bottom of the limiting pressure plate 9 are both provided with anti-slip pads.

[0039] See also Figure 2 : The friction of the contact surface is increased by the anti-skid pads on the load-bearing support plate 6 and the limiting pressure plate 9 to prevent the water pipe from moving after being fixed.

[0040] For a specific embodiment of the engineering construction pipeline transfer equipment, please refer to Figure 2 : The four corners of the top of the load-bearing hanger 4 are provided with first threaded holes 20, and the top of the load-bearing rod 3 is provided with a second threaded hole 21, and the first threaded hole 20 and the second threaded hole 21 are threadedly connected by a screw.

[0041] See also Figure 2 : Lift the water pipe and place it on the load-bearing support plate 6, install the load-bearing hanger 4, and fix it with a screw when the first threaded hole 20 is aligned with the second threaded hole 21 to cap the top of the water pipe.

[0042] For a specific embodiment of the engineering construction pipeline transfer equipment, please refer to Figure 1 : A brake universal wheel 22 is provided at the bottom of the supporting base 1.

[0043] See also Figure 1 : The support base 1 is moved by braking the universal wheel 22.

[0044] The utility model provides a construction pipeline transfer equipment, and the specific use method is as follows: lift the water pipe and place it on the load-bearing support plate 6, install the load-bearing hanger 4, and fix it with a screw when the first threaded hole 20 is aligned with the second threaded hole 21, cap the top of the water pipe, wind the high-strength steel wire rope 18 around the bottom of the water pipe and fix both ends on the steel cable U-shaped clamp 17, lift the water pipe with the high-strength steel wire rope 18, share the weight of the water pipe with the supporting force of the load-bearing rod 3 and the load-bearing hanger 4, improve the stability of the water pipe during transportation, and operate the self-locking The rocker on the air pressure regulating seat 7 extends the air pressure rod 8, and the limit pressure plate 9 is used to press against the top of the water pipe, and the water pipe is clamped between the limit pressure plate 9 and the load-bearing support plate 6, and the support block seat 11 is installed into the slide groove 10, and the limit screw 12 is passed through the movable groove 13, and the fastening screw 14 is used to press against the support block seat 11, and the L-shaped limit hook plate 16 is moved, and the L-shaped limit hook plate 16 is hung on the side of the water pipe, and the nut is installed to fix the position of the L-shaped limit hook plate 16, and the L-shaped limit hook plate 16 is used to press against both ends of the water pipe to prevent the water pipe from falling off due to the forward impact after the water pipe stops moving.

[0045] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A construction pipeline transfer device, comprising a support base (1), characterized in that: A plurality of support plates (2) are fixedly mounted on the top of the support base (1), a load-bearing rod (3) is fixedly mounted at the four corners of the top of the support plate (2), a load-bearing hanger (4) is arranged on the top of the load-bearing rod (3), a plurality of buffer dampers (5) are arranged on the top of the support plate (2), a load-bearing support plate (6) is arranged on the top of the buffer damper (5), self-locking gas pressure regulating seats (7) are arranged on both sides of the load-bearing hanger (4), a gas pressure rod (8) is arranged at the bottom of the self-locking gas pressure regulating seat (7), a limit pressure plate (9) is arranged at the bottom of the gas pressure rod (8), and a slide groove (10) is opened on both sides of the support plate (2), and a support stopper (11) is slidably connected in the slide groove (10).

2. The engineering construction pipeline transfer equipment according to claim 1, characterized in that: A limiting screw (12) is provided on one side of the inner wall of the slide groove (10), a movable groove (13) is provided at the bottom of the support stopper (11), the limiting screw (12) is inserted and connected in the movable groove (13), and a fastening screw (14) is provided at one end of the limiting screw (12).

3. The engineering construction pipeline transfer equipment according to claim 1, characterized in that: An adjusting screw (15) is provided on one side of the support stopper (11), an L-shaped limiting hook plate (16) is sleeved on the outside of the adjusting screw (15), and a nut is provided on one end of the adjusting screw (15).

4. The engineering construction pipeline transfer equipment according to claim 1, characterized in that: Steel cable U-shaped clamps (17) are provided at the four corners of the load-bearing hanger (4), and a high-strength steel wire rope (18) is provided inside the steel cable U-shaped clamp (17).

5. The engineering construction pipeline transfer equipment according to claim 1, characterized in that: A traction hook (19) is provided on one side of the support base (1).

6. The engineering construction pipeline transfer equipment according to claim 1, characterized in that: The top of the load-bearing support plate (6) and the bottom of the limiting pressure plate (9) are both provided with anti-slip pads.

7. The engineering construction pipeline transfer equipment according to claim 1, characterized in that: The four corners of the top of the load-bearing hanger (4) are provided with first threaded holes (20), the top of the load-bearing rod (3) is provided with a second threaded hole (21), and the first threaded hole (20) and the second threaded hole (21) are threadedly connected via a screw.

8. The engineering construction pipeline transfer equipment according to claim 1, characterized in that: The bottom of the support base (1) is provided with a brake universal wheel (22).

Citation Information

Patent Citations

  • Pipeline transfer device for water conservancy construction

    CN219969733U