Pipe gallery system capable of achieving modular construction

By designing a modular construction pipeline system, using the combination of pipeline framework, pipeline units, pipeline columns, pipeline support and fixtures, the problems of many high-altitude operations and unstable pipeline limits during installation of pipeline systems are solved, and a safer and more efficient construction process is achieved.

CN222525150UActive Publication Date: 2025-02-25LIAOCHENG LUXI CHEM ENG DESIGN
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421193042.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-29
Publication Date
2025-02-25
Estimated Expiration
2034-05-29

AI Technical Summary

Technical Problem

There are many high-altitude operations when installing the existing pipeline system, and it is not clear how to firmly limit the pipeline to the support frame, resulting in the pipeline being easily dropped during the lifting process.

Method used

A modular construction pipeline system is designed, including multiple pipeline corridor submodules, each module consisting of pipeline corridor frame, pipeline units, pipeline columns, pipeline support and fixtures. The pipe gallery frame is fixedly connected to the pipe unit through a fixing device. The pipe gallery column is a detachable column unit. The fixing device includes a pipe support and a fixing member for a stable limit on the pipe unit.

Benefits of technology

Through the modular construction of the pipeline corridor system, the time and risks of high-altitude operations are reduced, ensuring that the pipeline does not fall during the lifting process, and improving construction safety and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222525150U_ABST
    Figure CN222525150U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of pipe gallery construction, in particular to a pipe gallery system capable of achieving modular construction, which comprises a plurality of pipe gallery sub-modules, each pipe gallery sub-module comprises a pipe gallery frame, each pipe gallery frame is fixedly connected with a pipeline unit through a fixing device, and the bottom of each pipe gallery frame is fixedly connected with a pipe gallery stand column; the pipeline units between the adjacent pipe gallery sub-modules are connected in a welded mode, and each pipe gallery stand column comprises a plurality of stand column units which are detachably and fixedly connected. The pipe gallery frame comprises a plurality of transverse frames and longitudinal frames, and intervals are arranged between the adjacent transverse frames. The fixing device comprises a pipe support and a fixing piece, and the two ends of the pipeline unit are not aligned with the transverse frame in the vertical direction. The vertical columns are a plurality of detachable vertical column units, the pipe gallery frame and the vertical columns can be constructed separately, high-altitude operation is reduced, and higher safety is achieved; and by arranging the pipe supports and the fixing pieces, the two pipelines can be stably limited and cannot fall off in the hoisting process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pipe gallery construction, in particular to a pipe gallery system capable of modular construction. Background Art

[0002] Many pipelines in a chemical plant are concentrated together and arranged along the outside of the device or factory building to connect the chemical devices and equipment to form a circulating system. These concentrated pipeline corridors are called pipe galleries. Pipe galleries are generally open-air and overhead, supported by concrete or steel supports to form corridor-like passages. A clear height of more than 4.5 meters is generally left under the pipe gallery to ensure that fire trucks can pass smoothly when there is a fire road under the pipe gallery.

[0003] The patent with application number 201520390474.1 discloses an integrated modular pipe gallery system, wherein each pipe gallery submodule includes a pipe gallery, a support frame and a support frame, wherein the support frame is fixed on the support frame, and the support frame includes a horizontal pipe support and a vertical pipe support, wherein the horizontal pipe support and the vertical pipe support are vertically fixed to each other to form a multi-layer frame structure, wherein each layer of the frame structure forms a pipe gallery for placing pipes, and a plurality of rows of positioning rings are provided in the pipe gallery.

[0004] The problems with the patent solution with application number 201520390474.1 are: 1. There are still many high-altitude operations in the installation of the pipeline corridor system; 2. It is unclear how to firmly limit the pipeline on the support frame so that the pipeline will not fall during the lifting process. Utility Model Content

[0005] The main purpose of the utility model is to provide a pipe gallery system capable of modular construction, so as to solve the problems in the prior art that there are still many high-altitude operations in the installation of the pipe gallery system and it is unclear how to stably limit the pipelines on the supporting frame.

[0006] In order to achieve the above-mentioned purpose, the utility model provides a pipeline gallery system that can be constructed in a modular manner, including multiple pipeline gallery sub-modules, the pipeline gallery sub-modules include a pipeline gallery frame, the pipeline gallery frame is fixedly connected to the pipeline unit by a fixing device, and the bottom of the pipeline gallery frame is fixedly connected to the pipeline gallery column; the pipeline units between adjacent pipeline gallery sub-modules are welded, and the pipeline gallery columns include multiple detachable and fixedly connected column units.

[0007] Furthermore, the pipe gallery frame includes a plurality of horizontal frames and vertical frames, and intervals are provided between adjacent horizontal frames.

[0008] Furthermore, the fixing device includes a pipe support and a fixing piece, the pipe support is fixedly connected to the pipe gallery frame by bolts; the fixing piece includes 2 bolt and nut assemblies and 2 teardrop-shaped clamps, the bolt and nut assemblies are fixedly connected to the cross frame, and are used to limit the left and right sides of the pipeline unit, the teardrop-shaped clamps are fixedly connected to the pipeline unit, and the teardrop-shaped clamps are clamped on both sides of the cross frame, and are used to limit the front and back sides of the pipeline unit.

[0009] Furthermore, both ends of the pipe unit are not aligned with the cross frame in the up-down direction.

[0010] The beneficial effects of the utility model are:

[0011] 1. The columns are multiple detachable column units. The pipe gallery frame and the columns can be constructed separately and then assembled together at the end. Therefore, the construction of the pipe gallery frame is no longer a high-altitude operation and is safer;

[0012] 2. Some of the pipes in the pipe gallery frame need to be connected with pipe supports, while some do not. By setting pipe supports and fixings, both types of pipes can be firmly limited and will not fall during the hoisting process.

[0013] 3. The two ends of the pipe unit are not aligned with the cross frame in the vertical direction, so that there is enough space for pipe welding. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The drawings in the specification, which constitute a part of the present application, are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention.

[0015] Figure 1 It is a schematic diagram of the local structure of the pipe gallery system capable of modular construction in the embodiment;

[0016] Figure 2 This is a schematic diagram of the side structure of the pipe gallery submodule in the embodiment;

[0017] Figure 3 This is a front view structural diagram of the pipe gallery submodule in the embodiment;

[0018] Figure 4 This is a schematic diagram of the top view of the pipe gallery submodule in the embodiment;

[0019] Figure 5 This is a schematic diagram of the structure of the fixing member in the embodiment;

[0020] Figure 6 Schematic diagram of the pipe support structure in the embodiment.

[0021] In the figure: 1. Pipe gallery frame; 101. Horizontal frame; 102. Vertical frame; 2. Pipe unit; 3. Pipe gallery column; 4. Pipe support; 5. Fixing piece; 501. Bolt and nut assembly; 502. Tear-drop type clamp. DETAILED DESCRIPTION

[0022] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present utility model will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0023] Engineering construction company B undertook a new construction project P. The length of the pipeline corridor connecting the periphery of the device is 500 meters. The pipeline corridor is divided into 3 layers, with the lowest layer being 6 meters high. 20 pipes are laid above the pipeline corridor, with a total length of approximately 10,000 meters. Company B used a pipeline corridor system that can be constructed in a modular manner to construct this project.

[0024] like Figures 1 to 6 As shown, a pipe gallery system capable of modular construction includes multiple pipe gallery sub-modules, and the pipe gallery sub-module includes a pipe gallery frame 1, the pipe gallery frame 1 is fixedly connected to a pipe unit 2 by a fixing device, and a pipe gallery column 3 is fixedly connected to the bottom of the pipe gallery frame 1; the pipe units 2 between adjacent pipe gallery sub-modules are welded, and the pipe gallery columns 3 include column units connected by bolts.

[0025] The pipe gallery frame 1 includes a plurality of horizontal frames 101 and vertical frames 102 , and intervals are provided between adjacent horizontal frames 101 .

[0026] like Figure 5 and Figure 6 As shown, the fixing device includes a pipe support 4 and a fixing member 5. The pipe support 4 is fixedly connected to the pipe gallery frame 1 by bolts. The pipe support 4 can hold the pipe unit 2 tightly to limit the pipe unit 2; the fixing member 5 includes two bolt and nut assemblies 501 and two teardrop-shaped clamps 502. The bolt and nut assemblies 501 are fixedly connected to the cross frame 101 and are used to limit the left and right sides of the pipe unit 2. The teardrop-shaped clamps 502 are fixedly connected to the pipe unit 2. The teardrop-shaped clamps 502 are clamped on both sides of the cross frame 101 and are used to limit the front and back sides of the pipe unit 2. During the lifting process, the pipe unit 2 has a very small upward and downward movement range, so there is no need to limit its upward and downward directions.

[0027] Some of the pipe units 2 in the pipe gallery frame 1 need to be connected using pipe supports, while some of the pipe units 2 are larger in size and do not need to be connected using pipe supports. However, both types of pipe units 2 need to be limited to prevent the pipe units 2 from moving during hoisting. By providing pipe supports 4 and fixings 5, both types of pipe units 2 can be firmly limited and will not fall during the hoisting process. The fixings 5 ​​have a lower cost and are suitable for limiting the larger pipe units 2 that do not need to be connected using pipe supports.

[0028] like Figure 3 and Figure 4 As shown, the two ends of the pipe unit 2 are not aligned with the cross frame 101 in the up-down direction, so that there is enough space when the pipes are welded.

[0029] The construction method of the pipe gallery system capable of modular construction includes the following steps:

[0030] S1. Process the pipe gallery frame 1, pipe unit 2, column unit, pipe support 4 and fixing piece 5 in the factory, and use the pipe support 4 and fixing piece 5 to fix the pipe unit 2 at the designated position of the pipe gallery frame 1 to form a first assembly; if the pipe unit 2 needs to be painted or needs to be covered with a heat-insulating or cold-insulating sleeve, the construction is carried out in the factory; during the construction, a distance needs to be left at the welding points at both ends of the pipe unit 2 to prevent damage to the paint, heat-insulating sleeve or cold-insulating sleeve during welding; the operations in this step are all completed on the ground, which is safer;

[0031] S2, loading the first assembly and the column unit onto a truck, and transporting them to the construction site for unloading; the pipe support 4 and the fixing member 5 can ensure that the pipe unit 2 will not fall during the loading and unloading of the first assembly;

[0032] S3, start installation, first install the column unit into the corridor column 3 and stand it up and fix it, then hoist the first assembly onto the corridor column 3, and fix the corridor column 3 to the first assembly; weld the pipe units 2 of adjacent corridor sub-modules; after welding the pipe units 2 of adjacent corridor sub-modules, spray paint or cover the reserved distance with insulation or cold-keeping sleeves; complete the construction in two times, avoiding damage to the paint, insulation sleeve or cold-keeping sleeve during welding, and most of the work is completed on the ground, reducing the time of high-altitude operations and ensuring the construction quality.

[0033] A total of 100 construction workers were involved in the construction, including 20 high-altitude workers and 80 factory and ground prefabrication and service personnel. The construction was carried out under a normal working environment, and it took a total of 100 days to complete the project and deliver it to the construction unit. The costs of labor, materials, machinery, etc. were 22 million yuan. This construction method reduces the number of high-altitude workers by 75%, and the duration of high-altitude work is only about 25 days, a reduction of 83.3%. The safety hazards and accident rate are reduced by more than 85%. The cost of hiring lifting vehicles is reduced by 83.3%, the project investment cost is reduced by 26.7%, the construction period is shortened by 44.4%, the work efficiency is high, and there are few factors affecting the construction quality. It has an absolute competitive advantage in the industry.

[0034] The above description is only the preferred embodiment of the utility model, and is not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A pipe gallery system capable of modular construction, comprising a plurality of pipe gallery sub-modules, wherein the pipe gallery sub-modules comprise a pipe gallery frame (1), wherein the pipe gallery frame (1) is fixedly connected to a pipeline unit (2) via a fixing device, and a pipe gallery column (3) is fixedly connected to the bottom of the pipe gallery frame (1); characterized in that: The pipeline units (2) between adjacent pipe gallery submodules are connected by welding, and the pipe gallery columns (3) comprise a plurality of detachably fixedly connected column units.

2. The pipe gallery system capable of modular construction as claimed in claim 1, characterized in that: The pipe gallery frame (1) comprises a plurality of transverse frames (101) and longitudinal frames (102), and intervals are provided between adjacent transverse frames (101).

3. The pipe gallery system capable of modular construction as claimed in claim 2, characterized in that: The fixing device comprises a pipe support (4) and a fixing member (5); the pipe support (4) is fixedly connected to the pipe gallery frame (1) by means of bolts; the fixing member (5) comprises two bolt and nut assemblies (501) and two teardrop-shaped clamps (502); the bolt and nut assemblies (501) are fixedly connected to the cross frame (101) and are used to limit the left and right positions of the pipe unit (2); the teardrop-shaped clamps (502) are fixedly connected to the pipe unit (2); the teardrop-shaped clamps (502) are clamped on both sides of the cross frame (101) and are used to limit the front and rear positions of the pipe unit (2).

4. The pipe gallery system capable of modular construction as claimed in claim 3, characterized in that: Both ends of the pipeline unit (2) are not aligned with the cross frame (101) in the up-down direction.

Citation Information

Patent Citations

  • Integrated module piping lane system

    CN204785046U