Fabricated energy-saving factory building of steel structure
By adopting square annular diversion pipe and equidistant air outlet design in steel structure factories, uniform distribution and rapid cooling of air conditioners are achieved, and the problems of uneven distribution of air conditioners and slow cooling effect in the existing technology are solved, energy saving effect is improved and the environment is protected.
Patent Information
- Application Number
- CN202420488963.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-13
- Publication Date
- 2025-02-28
- Estimated Expiration
- 2034-03-13
AI Technical Summary
In summer, the existing steel structure factory buildings are wasteful and have poor energy saving due to uneven air conditioning distribution and slow cooling effect.
A prefabricated energy-saving factory with steel structure is designed, using square ring-distributed diversion pipes and equidistant air outlets. The cold air is evenly distributed into the factory through the air collection box and connecting pipe, and an exhaust fan and purification mechanism are installed at the heat dissipation ports, and an activated carbon layer and an odor removal layer are used to treat the odor air.
It realizes uniform distribution of air conditioners in the factory, quickly reduces temperature, improves energy-saving effects, and removes odors through purification mechanisms to protect the environment.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of steel structure factory buildings, in particular to an assembled energy-saving factory building with a steel structure. Background Art
[0002] With the progress and development of society, the light steel structure frame system with the characteristics of "green, environmental protection, energy saving, industrialization, and recyclability", namely "green building", is playing an increasingly important role in building layout. Steel structures are widely used in industrial plants, gymnasiums and other buildings.
[0003] During the use of existing steel structure factories, the interior of the factories will be very hot and stuffy in the summer. If air conditioning is used for cooling, the cold air inside the factories will be unevenly distributed and the cooling effect will be slow, which will cause energy waste and poor energy-saving effect. Therefore, we have launched a new steel structure assembled energy-saving factory. Utility Model Content
[0004] The main purpose of the utility model is to provide a steel structure assembled energy-saving factory building, which can effectively solve the problems in the background technology.
[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0006] A steel structure assembled energy-saving factory building includes columns, wherein a plurality of columns are provided, and side panels are commonly provided between the four longitudinal columns, and the side panels in the middle of the left side and the side panels in the middle of the right side are fixedly connected to the opposite surfaces thereof, and a ceiling is commonly provided on the upper ends of the plurality of columns, and heat dissipation ports are provided at the front and rear upper ends of the ceiling, and exhaust fans are provided in the two heat dissipation ports, and fixed seats are fixedly connected at the front and rear upper ends of the columns, and four cross slots are provided at the upper ends of the two fixed seats, and purification mechanisms are snap-connected to the upper ends of the two fixed seats.
[0007] Preferably, the ventilation mechanism includes an air collecting box, an air inlet pipe is fixedly connected to the middle part of the left end of the air collecting box, a No. 1 connecting pipe is fixedly connected to the upper outer surface and the lower outer surface of the air collecting box, a No. 2 connecting pipe is fixedly connected to the front outer surface and the rear outer surface of the air collecting box, two No. 1 connecting pipes are fixedly connected to one end away from the air collecting box and two No. 2 connecting pipes are fixedly connected to a diversion pipe at one end away from the air collecting box, and a plurality of air outlets are fixedly connected to the right outer surface of the diversion pipe.
[0008] Preferably, the left end of the air collecting box is fixedly connected to the side plate in the middle of the left side, and the air inlet pipe is interlacedly connected to the side plate in the middle of the left side.
[0009] Preferably, the air collecting box is connected to the interior of the diversion pipe through two No. 1 connecting pipes and two No. 2 connecting pipes, and the plurality of air outlets are distributed at equal distances.
[0010] Preferably, the purification mechanism comprises a purification cylinder, an activated carbon layer and an odor removal layer are fixedly connected to the inner wall of the purification cylinder, a sealing ring is fixedly connected to the lower end of the purification cylinder, and four cross blocks are fixedly connected to the lower end of the purification cylinder.
[0011] Preferably, the lower end of the sealing ring is tightly fitted with the fixing seat, and the four cross clamping blocks are respectively engaged and connected with four cross clamping grooves.
[0012] Compared with the prior art, the utility model has the following beneficial effects:
[0013] 1. The external cold air source is sent into the air collecting box through the air inlet pipe, and the cold air in the air collecting box is sent into the shunt pipe through two No. 1 connecting pipes and two No. 2 connecting pipes, and then sent into the factory through several air outlets on the shunt pipe. Since the shunt pipe is distributed in the factory in a square ring shape, and several air outlets are distributed at equal distances, the cold air can be evenly distributed in the factory, and the temperature inside the factory can be quickly reduced, so that the energy saving effect is good;
[0014] 2. In summer, odors are prone to appear inside the factory, and the air inside the factory needs to be dissipated for ventilation. The gas inside the factory is discharged from the heat dissipation port through the drainage fan, and the gas is discharged through the activated carbon layer and the odor removal layer. The activated carbon layer can adsorb impurities in the gas, and the odor removal layer can remove odors in the gas, thereby avoiding the exhaust gas from polluting the external environment and improving environmental protection. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is a schematic diagram of the overall structure of a steel structure assembled energy-saving factory building of the utility model;
[0016] Figure 2 This is a schematic diagram of the disassembled structure of a steel structure assembled energy-saving factory building of the utility model;
[0017] Figure 3 This is a schematic diagram of the overall structure of a ventilation mechanism of a steel structure assembled energy-saving factory building of the utility model;
[0018] Figure 4 This is a schematic diagram of the overall structure of a purification mechanism of a steel structure assembled energy-saving factory building of the utility model.
[0019] In the figure: 1. column; 2. side panel; 3. ventilation mechanism; 4. ceiling; 5. heat dissipation port; 6. exhaust fan; 7. fixing seat; 8. cross slot; 9. purification mechanism; 10. air collecting box; 11. air inlet pipe; 12. No. 1 connecting pipe; 13. No. 2 connecting pipe; 14. diverter pipe; 15. air outlet; 16. purification cylinder; 17. activated carbon layer; 18. deodorization layer; 19. sealing ring; 20. cross block. DETAILED DESCRIPTION
[0020] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.
[0021] In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "two ends", "one end", "the other end" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.
[0022] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "connected", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0023] See also Figure 1-4 , the utility model provides a technical solution:
[0024] A steel structure assembled energy-saving factory building includes a column 1. A plurality of columns 1 are provided. Side panels 2 are commonly provided between the four longitudinal columns 1. The side panels 2 in the middle of the left side and the side panels 2 in the middle of the right side are fixedly connected to the opposite surfaces thereof. A ceiling 4 is commonly provided on the upper ends of the plurality of columns 1. Heat dissipation openings 5 are provided at the front and rear ends of the upper ends of the ceiling 4. Exhaust fans 6 are provided in the two heat dissipation openings 5. Fixed seats 7 are fixedly connected at the front and rear ends of the upper ends of the columns 1. Four cross slots 8 are provided at the upper ends of the two fixed seats 7. Purification mechanisms 9 are snap-connected to the upper ends of the two fixed seats 7.
[0025] In this embodiment, the ventilation mechanism 3 includes an air collecting box 10, an air inlet pipe 11 is fixedly connected to the middle of the left end of the air collecting box 10, a No. 1 connecting pipe 12 is fixedly connected to the upper and lower outer surfaces of the air collecting box 10, a No. 2 connecting pipe 13 is fixedly connected to the front and rear outer surfaces of the air collecting box 10, the two No. 1 connecting pipes 12 are fixedly connected to one end away from the air collecting box 10 and the two No. 2 connecting pipes 13 are fixedly connected to the ends of the air collecting box 10, and a plurality of air outlet pipes 14 are fixedly connected to the right outer surface of the air collecting box 10. The left end of the air collecting box 10 is fixedly connected to the side panel 2 in the middle of the left side, the air inlet pipe 11 is connected through the side panel 2 in the middle of the left side, the air collecting box 10 is connected to the inside of the diverter pipe 14 through two No. 1 connecting pipes 12 and two No. 2 connecting pipes 13, and a plurality of air outlets 15 are distributed at equal distances. Since the diverter pipes 14 are distributed in a square ring shape inside the factory building, and a plurality of air outlets 15 are distributed at equal distances, the cold air can be evenly distributed inside the factory building, and the temperature inside the factory building can be quickly reduced, resulting in a good energy-saving effect.
[0026] In this embodiment, the purification mechanism 9 includes a purification cylinder 16, and the inner wall of the purification cylinder 16 is fixedly connected with an activated carbon layer 17 and an odor removal layer 18. The lower end of the purification cylinder 16 is fixedly connected with a sealing ring 19, and the lower end of the purification cylinder 16 is fixedly connected with four cross blocks 20. The lower end of the sealing ring 19 is tightly fitted with the fixed seat 7, and the four cross blocks 20 are respectively engaged with four cross slots 8. The activated carbon layer 17 can absorb impurities in the gas, and the odor removal layer 18 can remove odors in the gas, thereby preventing the discharged gas from polluting the external environment and improving environmental protection.
[0027] It should be noted that the utility model is a steel structure assembled energy-saving factory building. During use, the external cold air source is sent into the air collecting box 10 through the air inlet pipe 11, and the cold air in the air collecting box 10 is sent into the shunt pipe 14 through two No. 1 connecting pipes 12 and two No. 2 connecting pipes 13, and then sent into the factory building through a plurality of air outlets 15 on the shunt pipe 14. Since the shunt pipe 14 is distributed in the factory building in a square ring shape, and the plurality of air outlets 15 are distributed at equal distances, the cold air can be partially discharged in the factory building. The air inside the factory is evenly distributed and can quickly reduce the temperature inside the factory, so that the energy-saving effect is good. In summer, odor is easy to appear inside the factory, and the air inside the factory needs to be dispersed for ventilation. The gas inside the factory is discharged from the heat dissipation port 5 through the exhaust fan 6, and the gas is discharged through the activated carbon layer 17 and the deodorizing layer 18. The activated carbon layer 17 can adsorb impurities in the gas, and the deodorizing layer 18 can remove the odor in the gas, so as to avoid the exhaust gas from polluting the external environment and improve environmental protection.
[0028] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.
Claims
1. A steel structure assembled energy-saving factory building, comprising a column (1), characterized in that: A plurality of the columns (1) are provided, and a side panel (2) is commonly provided between the four longitudinal columns (1), and the opposite surfaces of the side panel (2) in the middle of the left side and the side panel (2) in the middle of the right side are fixedly connected with a ventilation mechanism (3), and a ceiling (4) is commonly provided at the upper ends of the plurality of columns (1), and a heat dissipation port (5) is provided at the front and rear upper ends of the ceiling (4), and exhaust fans (6) are provided in the two heat dissipation ports (5), and a fixing seat (7) is fixedly connected at the front and rear upper ends of the columns (1), and four cross slots (8) are provided at the upper ends of the two fixing seats (7), and a purification mechanism (9) is snap-connected at the upper ends of the two fixing seats (7); The ventilation mechanism (3) comprises an air collecting box (10), an air inlet pipe (11) is fixedly connected to the middle of the left end of the air collecting box (10), a No. 1 connecting pipe (12) is fixedly connected to the upper and lower outer surfaces of the air collecting box (10), a No. 2 connecting pipe (13) is fixedly connected to the front and rear outer surfaces of the air collecting box (10), one end of the two No. 1 connecting pipes (12) away from the air collecting box (10) and one end of the two No. 2 connecting pipes (13) away from the air collecting box (10) are fixedly connected to a shunt pipe (14), and a plurality of air outlets (15) are fixedly connected to the right outer surface of the shunt pipe (14).
2. The steel structure assembled energy-saving factory building according to claim 1 is characterized by: The left end of the air collecting box (10) is fixedly connected to the side plate (2) in the middle of the left side, and the air inlet pipe (11) is interlacedly connected to the side plate (2) in the middle of the left side.
3. The steel structure assembled energy-saving factory building according to claim 1 is characterized by: The air collecting box (10) is connected to the interior of the flow distribution pipe (14) through two No. 1 connecting pipes (12) and two No. 2 connecting pipes (13), and a plurality of air outlets (15) are distributed at equal distances.
4. The steel structure assembled energy-saving factory building according to claim 1 is characterized by: The purification mechanism (9) comprises a purification cylinder (16), the inner wall of which is fixedly connected to an activated carbon layer (17) and an odor removal layer (18), the lower end of which is fixedly connected to a sealing ring (19), and the lower end of which is fixedly connected to four cross-shaped blocks (20).
5. The steel structure assembled energy-saving factory building according to claim 4 is characterized by: The lower end of the sealing ring (19) is tightly fitted with the fixing seat (7), and the four cross clamping blocks (20) are respectively clamped and connected with the four cross clamping grooves (8).