Fence for water conservancy project

By designing cleaning racks, collection frames and filters in the fences for water conservancy projects, and using the cooperation of the drive mechanism and the adjustment mechanism, the automatic collection and removal of garbage is achieved, solving the problem of inconvenient garbage cleaning in the existing technology, and improving the convenience and stability of maintenance.

CN222614116UActive Publication Date: 2025-03-14CHONGQING LIHE ENGINEERING SUPERVISION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421209716.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-30
Publication Date
2025-03-14
Estimated Expiration
2034-05-30

AI Technical Summary

Technical Problem

When the existing fences of water conservancy projects are cleaned up, they cannot effectively concentrate and collect garbage, resulting in inconvenience to staff maintenance.

Method used

A fence for water conservancy projects is designed, including a cleaning rack, a collection frame and a filter. Through the cooperation of the driving mechanism and the adjustment mechanism, the automatic collection and removal of garbage is achieved.

Benefits of technology

Automatic garbage collection and removal of fences for water conservancy projects has been realized, simplified the maintenance of staff, and improved the convenience and stability of operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222614116U_ABST
    Figure CN222614116U_ABST
Patent Text Reader

Abstract

The fence for the water conservancy project comprises a first fence frame, one side of the first fence frame is fixedly connected with a transverse rod, one side of the transverse rod is fixedly connected with a second fence frame, one side of the second fence frame is fixedly connected with a driving mechanism, and the top of the second fence frame is movably connected with a first lead screw in a penetrating mode. The top of the first lead screw is fixedly connected with a first transmission wheel, the outer side of the first lead screw is movably connected with a first nut seat in a threaded mode, a fence frame is movably connected between the first fence frame and the second fence frame, the inner side of the fence frame is fixedly connected with a fence net, and the front faces of the first fence frame and the second fence frame are fixedly connected with a lifting frame. A lifting groove is formed in the inner side of the lifting frame, a cleaning frame is movably connected to the inner side of the lifting frame through the lifting groove, a collecting frame is fixedly connected to the back face of the cleaning frame, and the cleaning frame, the collecting frame and the filter screen are arranged, so that the fence for the water conservancy project can automatically collect garbage and remove the garbage on the fence; therefore, workers can conveniently maintain the fence for the water conservancy project.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model is a fence for water conservancy projects and relates to the field of water conservancy projects. Background Art

[0002] A water conservancy project is a project built to control and allocate natural surface water and groundwater to achieve the purpose of eliminating harm and promoting benefits. It is also called a water project. Water is a valuable resource indispensable to human production and life, but its natural state does not fully meet human needs. Only by building water conservancy projects can we control water flow, prevent floods and waterlogging disasters, and regulate and distribute water to meet the people's needs for water resources in life and production.

[0003] Although the existing water conservancy project fences can intercept garbage during use, the garbage in the water will still be concentrated on the fences. When the garbage on the fences needs to be cleaned, the fences cannot concentrate and collect the garbage, which makes it inconvenient for the staff to clean the garbage on the fences. Utility Model Content

[0004] In view of the deficiencies in the prior art, the utility model aims to provide a fence for water conservancy projects to solve the problems raised in the above-mentioned background technology. The utility model is easy to use, easy to operate, good in stability and high in reliability.

[0005] In order to achieve the above-mentioned purpose, the utility model is realized through the following technical scheme: a fence for water conservancy projects, comprising a first fence frame, a cross bar is fixedly connected to one side of the first fence frame, a second fence frame is fixedly connected to one side of the cross bar, a driving mechanism is fixedly connected to one side of the second fence frame, a first screw rod is movably connected to the top of the second fence frame, a first transmission wheel is fixedly connected to the top of the first screw rod, a first nut seat is movably threadedly connected to the outside of the first screw rod, a fence frame is movably connected between the first fence frame and the second fence frame, a fence net is fixedly connected to the inner side of the fence frame, a lifting frame is fixedly connected to the front side of the first fence frame and the second fence frame, a lifting slot is provided on the inner side of the lifting frame, a cleaning frame is movably connected to the inner side of the lifting frame through the lifting slot, a collecting frame is fixedly connected to the back side of the cleaning frame, an adjusting mechanism is fixedly connected to one side of the lifting frame, a second screw rod is movably connected to the top of the lifting frame, and a second transmission wheel is fixedly connected to the top of the second screw rod.

[0006] Furthermore, installation grooves are provided on the inner sides of the first and second fence frames and on the top of the cross bar. The first and second fence frames have the same length. The first and second fence frames and the cross bar are movably connected to the fence frame through the installation grooves.

[0007] Furthermore, the driving mechanism includes a first motor frame, a first driving motor and a first driving gear, the first motor frame is fixedly connected to one side of the second fence frame, the top of the first motor frame is fixedly connected to the first driving motor, the driving end of the first driving motor is fixedly connected to the first driving gear, and the first driving gear is meshed with the first transmission wheel.

[0008] Furthermore, the adjusting mechanism includes a second motor frame, a second drive motor and a second drive gear, the second motor frame is fixedly connected to one side of the lifting frame, the top of the second motor frame is fixedly connected to the second drive motor, the driving end of the second drive motor is fixedly connected to the second drive gear, and the second drive gear is meshed with the second transmission wheel.

[0009] Furthermore, the outer side of the second screw rod is threadedly connected to a second nut seat, and the second nut seat is fixedly connected to the cleaning frame.

[0010] Furthermore, filters are fixedly connected to the inner sides of the cleaning rack and the collecting frame.

[0011] The beneficial effects of the utility model include: through the provided cleaning rack, collecting frame and filter screen, when the water passes through the fence net on the fence frame, the garbage in the water will be intercepted by the fence net; when there is too much garbage, the staff starts the second drive motor, the second drive motor drives the second drive gear to rotate, and the second drive gear drives the second transmission wheel to rotate, at this time the second screw rod will rotate clockwise, and the second nut seat will drive the cleaning rack to move upward due to the rotation direction of the second screw rod, at this time the collecting frame will collect the garbage intercepted by the fence net, and the water will be filtered out by the filter screen, and at the same time the collecting frame will rise out of the water, at this time the staff only needs to clean the garbage in the collecting frame, so that the water conservancy project fence can automatically collect garbage and remove garbage on the fence, thus facilitating the staff to maintain the water conservancy project fence. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Other features, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings:

[0013] Figure 1 This is a schematic diagram of the overall structure of the utility model water conservancy project fence;

[0014] Figure 2 It is a partial structural schematic diagram of the cleaning rack in the fence for water conservancy projects of the utility model;

[0015] Figure 3 It is a cross-sectional view of the second fence frame in the utility model of the fence for water conservancy engineering;

[0016] Figure 4 It is a cross-sectional view of the lifting frame in the fence for water conservancy projects of the utility model.

[0017] In the figure: 1-first fence frame, 2-mounting groove, 3-second fence frame, 4-first screw rod, 401-first nut seat, 5-first transmission wheel, 6-first motor frame, 7-first drive motor, 8-first drive gear, 9-fence frame, 10-fence net, 11-lifting frame, 12-lifting groove, 13-cleaning frame, 1301-collecting frame, 14-filter screen, 15-second motor frame, 16-second drive motor, 17-second drive gear, 18-second screw rod, 19-second transmission wheel, 20-second nut seat, 21-cross bar. DETAILED DESCRIPTION

[0018] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.

[0019] See also Figure 1-Figure 4 The utility model provides a technical solution: a fence for a water conservancy project, comprising a first fence frame 1, a cross bar 21 is fixedly connected to one side of the first fence frame 1, a second fence frame 3 is fixedly connected to one side of the cross bar 21, a driving mechanism is fixedly connected to one side of the second fence frame 3, a first screw rod 4 is movably connected to the top of the second fence frame 3, a first transmission wheel 5 is fixedly connected to the top of the first screw rod 4, a first nut seat 401 is movably threadedly connected to the outer side of the first screw rod 4, and the first fence frame 1 and the second fence frame 3 are movably connected. A fence frame 9, the inner side of which is fixedly connected with a fence net 10, a lifting frame 11 is fixedly connected to the front sides of the first fence frame 1 and the second fence frame 3, a lifting slot 12 is provided on the inner side of the lifting frame 11, a cleaning frame 13 is movably connected to the inner side of the lifting frame 11 through the lifting slot 12, a collecting frame 1301 is fixedly connected to the back side of the cleaning frame 13, an adjusting mechanism is fixedly connected to one side of the lifting frame 11, a second screw rod 18 is movably connected to the top of the lifting frame 11, and a second transmission wheel 19 is fixedly connected to the top of the second screw rod 18.

[0020] Specific implementation method: The inner sides of the first fence frame 1 and the second fence frame 3 and the top of the cross bar 21 are provided with installation grooves 2, the first fence frame 1 and the second fence frame 3 have the same length, the first fence frame 1 and the second fence frame 3 and the cross bar 21 are movably connected to the fence frame 9 through the installation grooves 2, so that the fence frame 9 can be fixed more firmly and will not be washed away by water.

[0021] Specific implementation: The driving mechanism includes a first motor frame 6, a first driving motor 7 and a first driving gear 8. The first motor frame 6 is fixedly connected to one side of the second fence frame 3. The top of the first motor frame 6 is fixedly connected to the first driving motor 7. The driving end of the first driving motor 7 is fixedly connected to the first driving gear 8. The first driving gear 8 is meshingly connected with the first transmission wheel 5. By starting the first driving motor 7, the first driving motor 7 drives the first driving gear 8 to rotate, and the first driving gear 8 drives the first screw rod 4 to rotate through the first transmission wheel 5. At this time, the first nut seat 401 will drive the fence frame 9 to move up and down due to the rotation direction of the first screw rod 4.

[0022] Specific implementation method: The adjustment mechanism includes a second motor frame 15, a second drive motor 16 and a second drive gear 17. The second motor frame 15 is fixedly connected to one side of the lifting frame 11. The top of the second motor frame 15 is fixedly connected to the second drive motor 16. The driving end of the second drive motor 16 is fixedly connected to the second drive gear 17. The second drive gear 17 is meshed and connected with the second transmission wheel 19. By starting the second drive motor 16, the second drive motor 16 drives the second drive gear 17 to rotate, and the second drive gear 17 will drive the second transmission wheel 19 to rotate. At this time, the second screw rod 18 will rotate clockwise, and the second nut seat 20 will drive the cleaning frame 13 to move upward due to the rotation direction of the second screw rod 18. At this time, the collecting frame 1301 will collect the garbage intercepted by the fence net 10.

[0023] Specific implementation: The outer side of the second screw rod 18 is threadedly connected with a second nut seat 20 , and the second nut seat 20 is fixedly connected to the cleaning frame 13 , so that the second nut seat 20 can drive the cleaning frame 13 to move up and down according to the rotation direction of the second screw rod 18 .

[0024] Specific implementation method: The inner sides of the cleaning rack 13 and the collecting frame 1301 are fixedly connected with a filter 14, so that the cleaning rack 13 and the collecting frame 1301 can filter out excess water.

[0025] Working principle: When using the fence for water conservancy projects, when water passes through the fence net 10 on the fence frame 9, the garbage in the water will be intercepted by the fence net 10. When there is too much garbage, the staff starts the second drive motor 16, and the second drive motor 16 drives the second drive gear 17 to rotate, and the second drive gear 17 will drive the second transmission wheel 19 to rotate. At this time, the second screw rod 18 will rotate clockwise, and the second nut seat 20 will drive the cleaning frame 13 to move upward due to the rotation direction of the second screw rod 18. At this time, the collecting frame 1301 will collect the garbage intercepted by the fence net 10, and the water will be filtered out by the filter net 14. At the same time, the collecting frame 1301 will rise above the water surface. At this time, the staff only needs to clean the garbage in the collecting frame 1301.

[0026] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A fence for a water conservancy project, comprising a first fence frame (1), characterized in that: One side of the first fence frame (1) is fixedly connected to a cross bar (21), one side of the cross bar (21) is fixedly connected to a second fence frame (3), one side of the second fence frame (3) is fixedly connected to a driving mechanism, a first screw rod (4) is movably connected through the top of the second fence frame (3), a first transmission wheel (5) is fixedly connected to the top of the first screw rod (4), a first nut seat (401) is movably threadedly connected to the outer side of the first screw rod (4), a fence frame (9) is movably connected between the first fence frame (1) and the second fence frame (3), and the inner side of the fence frame (9) is fixedly connected to A fence net (10) is provided, wherein a lifting frame (11) is fixedly connected to the front of the first fence frame (1) and the second fence frame (3), a lifting slot (12) is provided on the inner side of the lifting frame (11), a cleaning frame (13) is movably connected to the inner side of the lifting frame (11) through the lifting slot (12), a collecting frame (1301) is fixedly connected to the back side of the cleaning frame (13), an adjusting mechanism is fixedly connected to one side of the lifting frame (11), a second screw rod (18) is movably connected to the top of the lifting frame (11), and a second transmission wheel (19) is fixedly connected to the top of the second screw rod (18).

2. The water conservancy project fence according to claim 1, characterized in that: The inner sides of the first fence frame (1) and the second fence frame (3) and the top of the cross bar (21) are provided with mounting grooves (2); the first fence frame (1) and the second fence frame (3) have the same length; the first fence frame (1), the second fence frame (3) and the cross bar (21) are movably connected to the fence frame (9) via the mounting grooves (2).

3. The water conservancy project fence according to claim 1, characterized in that: The driving mechanism comprises a first motor frame (6), a first driving motor (7) and a first driving gear (8); the first motor frame (6) is fixedly connected to one side of the second fence frame (3); the top of the first motor frame (6) is fixedly connected to the first driving motor (7); the driving end of the first driving motor (7) is fixedly connected to the first driving gear (8); and the first driving gear (8) is meshedly connected to the first transmission wheel (5).

4. The water conservancy project fence according to claim 1, characterized in that: The adjustment mechanism comprises a second motor frame (15), a second drive motor (16) and a second drive gear (17); the second motor frame (15) is fixedly connected to one side of the lifting frame (11); the top of the second motor frame (15) is fixedly connected to the second drive motor (16); the driving end of the second drive motor (16) is fixedly connected to the second drive gear (17); and the second drive gear (17) is meshedly connected to the second transmission wheel (19).

5. The water conservancy project fence according to claim 1, characterized in that: The outer side of the second screw rod (18) is threadedly connected to a second nut seat (20), and the second nut seat (20) is fixedly connected to the cleaning frame (13).

6. The water conservancy project fence according to claim 1, characterized in that: The inner sides of the cleaning frame (13) and the collecting frame (1301) are both fixedly connected with a filter screen (14).