Hoisting tool

By designing a lifting tool for field pipeline installation, the combination of support beams, fixing devices and support devices is used to solve the problems of lifting and docking in field pipeline installation, and a safe and fast installation effect is achieved.

CN222616187UActive Publication Date: 2025-03-14SICHUAN GUANGAN POWER GENERATION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421509901.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-28
Publication Date
2025-03-14
Estimated Expiration
2034-06-28

AI Technical Summary

Technical Problem

During the installation of metal pipes in the field, due to geographical location limitations, it is difficult to set up a crane or scaffolding, which makes it difficult to effectively lift and connect the pipes, which increases the installation difficulty and danger.

Method used

A lifting tool including supporting beams, fixing devices and support devices is designed. The pipe is hoisted by supporting beams. The fixing device is sleeved with fixed pipes, and the support device abuts against the pipes, and the pipes are connected by leverage.

Benefits of technology

The tool simplifies the field pipeline installation process, reduces dependence on large crane tools, improves installation safety and speed, and reduces work costs and labor requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222616187U_ABST
    Figure CN222616187U_ABST
Patent Text Reader

Abstract

The utility model discloses a hoisting tool and belongs to the technical field of hoisting. The hoisting tool comprises a supporting cross beam, a fixing device and a supporting device, wherein one end of the supporting cross beam is used for hoisting a pipeline; the fixing device is arranged at the other end of the supporting cross beam and is used for sleeving a pipeline; one end of the supporting device is connected with the middle of the supporting cross beam, and the other end of the supporting device abuts against a pipeline. The hoisting tool disclosed by the embodiment of the utility model is simple in structure, low in manufacturing cost, simple and convenient to operate, efficient and flexible, the convenience of field pipeline mounting operation is improved, the use of large hoisting tools such as cranes is reduced, the risk of hoisting operation is reduced, the working cost and the working manpower can be effectively reduced, and the working efficiency is improved. And the effect of safe and rapid installation operation is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of hoisting, in particular to a hoisting tool. Background Art

[0002] The installation of metal pipes in the field is limited by the geographical location, so it is difficult to use cranes or set up scaffolding. Pipes can weigh tens of kilograms or hundreds or even thousands of kilograms, and are difficult to move with manpower alone. Pipes are tilted or staggered, which increases the center deviation of the interfaces between pipes and makes pipe connection more difficult. Utility Model Content

[0003] The utility model aims to solve at least one of the technical problems existing in the prior art. To this end, the utility model proposes a lifting tool, which improves the convenience of field pipeline installation operations, reduces the use of large lifting tools such as cranes, reduces the danger of lifting operations, effectively reduces work costs and manpower, and plays a role in safe and rapid installation operations.

[0004] According to the lifting tool of the embodiment of the utility model, it includes a supporting beam, a fixing device and a supporting device, one end of the supporting beam is used for lifting the pipe; the fixing device is arranged at the other end of the supporting beam, and the fixing device is used for sleeve-mounting the pipe; one end of the supporting device is connected to the middle part of the supporting beam, and the other end is used for abutting the pipe.

[0005] According to the lifting tool of the embodiment of the utility model, by such a setting, at least the following beneficial effects can be achieved: the fixing device is sleeved on the fixed pipe, and at the same time, one end of the supporting device is in contact with the upper end surface of the fixed pipe. At this time, the supporting crossbeam is used to lift the pipe to be installed at one end of the lifting pipe. Through the lever effect, the pipe to be installed can be easily pulled to complete the docking of the pipe to be installed with the fixed pipe, so that the center lines of the pipe openings of the two pipes are aligned. At this time, the two pipes can be welded or clamps can be installed to connect the two pipes to each other. According to the lifting tool of the embodiment of the utility model, the structure is simple, the cost is low, the operation is simple, and the two pipes are efficient and flexible. It improves the convenience of field pipeline installation operations, reduces the use of large lifting tools such as cranes, reduces the danger of lifting operations, can effectively reduce work costs and manpower, and plays a role in safe and fast installation operations.

[0006] According to some embodiments of the utility model, the fixing device includes a first connecting rod and a clamping device, one end of the first connecting rod is connected to the supporting beam, and the other end is connected to the clamping device, and the clamping device is used to sleeve the pipeline.

[0007] According to some embodiments of the present invention, the first connecting rod is rotatably connected to the supporting beam.

[0008] According to some embodiments of the present utility model, the clamping device includes a first connecting member and a second connecting member, and both ends of the first connecting member and the second connecting member are connected to each other for sleeve-mounting the pipe therein.

[0009] According to some embodiments of the utility model, the first connecting member includes a first arc-shaped plate, connecting plates are provided at both ends of the first arc-shaped plate, and bolt holes are opened on the connecting plates; the second connecting member includes a second arc-shaped plate, screws are provided at both ends of the second arc-shaped plate; the first connecting member and the second connecting member are connected through the screws and the bolt holes.

[0010] According to some embodiments of the utility model, the supporting device includes a second connecting rod and a supporting plate, one end of the second connecting rod is connected to the supporting beam, and the other end is connected to the supporting plate, and the supporting plate is used to abut against the pipeline.

[0011] According to some embodiments of the present invention, the second connecting rod is rotatably connected to the supporting beam.

[0012] According to some embodiments of the present invention, the support plate is an arc-shaped plate structure, and the inner concave surface of the support plate is used to abut against the pipeline.

[0013] According to some embodiments of the utility model, the supporting device includes a second connecting rod and a clamping assembly, one end of the second connecting rod is connected to the supporting beam, and the other end is used to abut the pipe; a driving motor and an adjusting screw are arranged in the second connecting rod, and the clamping assembly includes two movable gears and a clamping claw symmetrically arranged along the axial direction of the adjusting screw, the gear teeth of the two movable gears are meshed with the threads of the adjusting screw, and the clamping claw is connected to the movable gear, and the driving motor drives the adjusting screw to rotate so that the movable gear rotates, thereby driving the clamping claw to rotate synchronously to grasp the pipe.

[0014] According to some embodiments of the utility model, a hoisting part and a hand chain hoist are also included. The hoisting part is arranged at one end of the supporting beam. A hoisting hole is opened on the hoisting part. The hand chain hoist is hung on the hoisting hole. The pipes are pulled by the hand chain hoist to connect the pipes.

[0015] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The above additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:

[0017] Figure 1 It is a structural schematic diagram of a lifting tool according to an embodiment of the utility model;

[0018] Figure 2 It is a schematic diagram of the coordination structure of the lifting tool and the pipeline according to an embodiment of the utility model;

[0019] Figure 3 It is a structural schematic diagram of a supporting device for a lifting tool according to an embodiment of the utility model.

[0020] Reference numerals:

[0021] Support beam 100, first connecting rod 210, first connecting member 220, first arc plate 221, connecting plate 222, second connecting member 230, second arc plate 231, screw 232, nut 233, second connecting rod 310, support plate 320, lifting part 400, lifting hole 410, hand hoist 500, pipe A610, pipe B620, drive motor 710, adjusting screw 720, movable gear 730, clamping claw 740. DETAILED DESCRIPTION

[0022] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0023] In the description of the present invention, it should be understood that descriptions involving orientation, such as up, down, front, back, left, right, etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0024] In the description of the present utility model, "several" means one or more, "more" means more than two, "greater than", "less than", "exceed" etc. are understood to exclude the number itself, and "above", "below", "within" etc. are understood to include the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.

[0025] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.

[0026] Reference below Figures 1 to 3 To describe the lifting tool according to the embodiment of the utility model.

[0027] According to the lifting tool of the embodiment of the utility model, it includes a supporting beam 100, a fixing device and a supporting device. One end of the supporting beam 100 is used for lifting the pipe; the fixing device is arranged at the other end of the supporting beam 100, and the fixing device is used for sleeve-mounting the pipe; one end of the supporting device is connected to the middle part of the supporting beam 100, and the other end is used for abutting the pipe.

[0028] For example Figure 1 and Figure 2 As shown, the lifting tool is provided with a supporting beam 100, and the fixing device and the supporting device are connected to the bottom of the supporting beam 100. One end of the supporting beam 100 is used for lifting the pipe, and the other end is provided with a fixing device for sleeve installation of the pipe. The supporting device is located in the middle of the supporting beam 100 to form a lever, for example Figure 2 As shown in the given embodiment, the pipe A610 is already installed and fixed, and the fixed pipe A610 is sleeved by the fixing device, and the bottom of the supporting device is in contact with the upper end surface of the pipe A610, so as to support the supporting crossbeam 100. At this time, the other end of the supporting crossbeam 100 lifts the pipe B620, and through the lever effect, the pipe B620 can be easily pulled to complete the docking of the pipe B620 with the already fixed pipe A610, so that the center lines of the pipe openings of the two pipes are aligned, and the two pipes can be welded or clamps can be installed to connect the two pipes to each other.

[0029] After the two pipes are connected, the fixture can be moved, and the fixture and the supporting device can be moved to the pipe B620, and then the next pipe can be installed.

[0030] The lifting tool according to the embodiment of the utility model has a simple structure, low cost, easy operation, high efficiency and flexibility, improves the convenience of field pipeline installation operations, reduces the use of large lifting tools such as cranes, reduces the danger of lifting operations, can effectively reduce work costs and manpower, and plays a role in safe and fast installation operations. With the help of this tool, the lifting and jointing of larger pipelines can be completed at a relatively low cost, greatly reducing the maintenance cost and maintenance time.

[0031] In some specific embodiments of the present invention, the fixing device includes a first connecting rod 210 and a clamping device. One end of the first connecting rod 210 is connected to the supporting beam 100, and the other end is connected to the clamping device. The clamping device is used to sleeve the pipeline.

[0032] For example Figure 1 and Figure 2As shown, the fixing device includes a first connecting rod 210 and a clamping device, one end of the first connecting rod 210 is connected to the supporting beam 100, and the other end is connected to the clamping device, and the clamping device is used to sleeve the pipe A610. Through the arrangement of the first connecting rod 210, there is a certain distance between the clamping device and the supporting beam 100, which facilitates the supporting beam 100 to play the role of a lever.

[0033] The clamping device is used to cover the pipe. The shape of the clamping device is consistent with the shape of the pipe. According to the size of the pipe, you can choose clamping devices of different sizes to cover the pipe and cover the pipe. Because the pipe is generally cylindrical, the clamping device is also circular, so that the pipe can be framed in it.

[0034] The clamping device can be designed in a circular shape and inserted into one end of the pipe A610, or it can be designed as two semicircular connecting pieces and connected through the two semicircular connecting pieces.

[0035] In some specific embodiments of the present invention, the first connecting rod 210 is rotatably connected to the supporting beam 100 .

[0036] For example Figure 1 As shown, the first connecting rod 210 and the supporting beam 100 are rotatably connected. The rotatable connection makes the use of the lifting tool more convenient. After the clamping device is clamped around the installed and fixed pipe A610, the supporting beam 100 can be easily rotated, so that the supporting device is placed on the pipe A610 to form a stable lever structure. The pipe B620 is hoisted with the other end of the supporting beam 100 so that the center lines of the two pipe openings are aligned. At this time, the two pipes can be welded or clamps can be installed to connect the two pipes to each other.

[0037] In some specific embodiments of the present invention, the clamping device includes a first connecting member 220 and a second connecting member 230. Both ends of the first connecting member 220 and the second connecting member 230 are connected to each other for sleeves of the pipes.

[0038] For example Figure 1 and Figure 2 As shown, the clamping device includes a first connecting member 220 and a second connecting member 230, and both ends of the first connecting member 220 and the second connecting member 230 are connected to each other, so that the pipe A610 is sleeved therein.

[0039] In some specific embodiments of the present invention, the first connecting member 220 includes a first curved plate 221, connecting plates 222 are provided at both ends of the first curved plate 221, and bolt holes are opened on the connecting plates 222; the second connecting member 230 includes a second curved plate 231, screws 232 are provided at both ends of the second curved plate 231; the first connecting member 220 and the second connecting member 230 are connected through the screws 232 and the bolt holes.

[0040] For example Figure 1 and Figure 2 As shown, the first connecting member 220 includes a first curved plate 221, and connecting plates 222 are provided at both ends of the first curved plate 221, and bolt holes are provided on the connecting plates 222. The second connecting member 230 includes a second curved plate 231, and screw rods 232 are provided at both ends of the second curved plate 231. When installing, the first curved plate 221 is first placed on the upper end surface of the pipe A610, so that the inner concave surface of the first curved plate 221 abuts against the pipe A610. At this time, the screw rods 232 at both ends of the second curved plate 231 are aligned with the bolt holes on the connecting plate 222 and inserted into the connecting plate 222, so that the inner concave surface of the second curved plate 231 abuts against the lower end surface of the pipe A610. At this time, the screw rods 232 are fixed by nuts 233, so that the first connecting member 220 and the second connecting member 230 can stably hold the pipe A610.

[0041] Furthermore, the bending radius of the first arc plate 221 and the second arc plate 231 is the same as the end surface radius of the pipe, so that they can be well fitted on the surface of the pipe.

[0042] Furthermore, the first arc plate 221 and the second arc plate 231 are both semicircular, so that the first arc plate 221 and the second arc plate 231 can form a complete circle to frame the pipe A610, making the connection between the clamping device and the pipe A610 more stable.

[0043] In some specific embodiments of the present invention, the supporting device includes a second connecting rod 310 and a supporting plate 320. One end of the second connecting rod 310 is connected to the supporting beam 100, and the other end is connected to the supporting plate 320. The supporting plate 320 is used to abut against the pipeline.

[0044] For example Figure 1 and Figure 2 As shown, the support device includes a second connecting rod 310 and a support plate 320. The second connecting rod 310 connects the support beam 100 and the support plate 320, so that when the support plate 320 abuts against the pipe A610, the second connecting rod 310 can act as a fulcrum of the lever, which is beneficial for lifting the pipe B620 at the other end of the support beam 100, so that the center lines of the pipe openings of the two pipes are aligned. At this time, the two pipes can be welded or clamps can be installed to connect the two pipes to each other.

[0045] In some specific embodiments of the present invention, the second connecting rod 310 is rotatably connected to the supporting beam 100 .

[0046] For example Figure 1 As shown, the top end of the second connecting rod 310 is rotatably connected to the supporting beam 100, so that the supporting plate 320 can be easily rotated through the second connecting rod 310, so as to be placed above the pipe A610 and abut against the upper surface of the pipe A610.

[0047] In some specific embodiments of the present invention, the support plate 320 is an arc-shaped plate structure, and the inner concave surface of the support plate 320 is used to abut against the pipeline.

[0048] For example Figure 1 As shown, the support plate 320 is an arc-shaped structure, and the inner concave surface of the support plate 320 abuts against the pipe A610, so that the support plate 320 can stably abut against the pipe A610, so that the second connecting rod 310 and the support plate 320 can act as a fulcrum, which is convenient for the lifting tool to achieve a lever effect through the second connecting rod 310 and the support plate 320, and it is convenient to lift the pipe B620 and connect it with the pipe A610.

[0049] In some specific embodiments of the utility model, the supporting device includes a second connecting rod 310 and a clamping assembly, one end of the second connecting rod 310 is connected to the supporting beam 100, and the other end is used to abut the pipeline; a driving motor 710 and an adjusting screw 720 are arranged in the second connecting rod 310, and the clamping assembly includes two movable gears 730 and a clamping claw 740 symmetrically arranged along the axial direction of the adjusting screw 720, the gear teeth of the two movable gears 730 are meshed with the threads of the adjusting screw 720, and the clamping claw 740 is connected to the movable gear 730, and the driving motor 710 drives the adjusting screw 720 to rotate so that the movable gear 730 rotates, thereby driving the clamping claw 740 to rotate synchronously to grasp the pipeline.

[0050] For example Figure 3As shown, the top end of the second connecting rod 310 is connected to the supporting beam 100, and the other end is in contact with the pipe A610 and supported on the pipe A610. The driving motor 710, the adjusting screw rod 720 and the movable gear 730 are built in the second connecting rod 310, and the clamping claw 740 is fixedly connected with the movable gear 730, extending from the second connecting rod 310 and clamped on the outer wall of the pipe A610. When working, the second connecting rod 310 supports the supporting beam 100, and the driving motor 710 rotates at the same time, thereby driving the adjusting screw rod 720 to rotate, and the thread of the adjusting screw rod 720 is meshed with the gear teeth of the movable gear 730, so that the rotation of the adjusting screw rod 720 can drive the movable gear 730 to rotate. The clamping claw 740 is fixedly connected with the movable gear 730, and the rotation of the movable gear 730 drives the clamping claw 740 to rotate, so that the pipe A can be grasped, so that the second connecting rod 310 can stably support the supporting beam 100 without shaking.

[0051] Furthermore, the portion where the clamping claw 740 contacts the pipe is provided with an anti-slip pad, which enables the clamping claw 740 to grip the pipe more firmly, making the supporting device more stable and less prone to shaking.

[0052] In some specific embodiments of the present invention, a hoisting portion 400 is further included. The hoisting portion 400 is disposed at one end of the supporting beam 100. A hoisting hole 410 is opened on the hoisting portion 400. The hoisting hole 410 is used for hoisting the pipeline.

[0053] For example Figure 2 As shown, a hoisting part 400 is provided at one end of the support beam 100 away from the fixing device, and a hoisting hole 410 is provided on the hoisting part 400, through which the pipe B620 can be hoisted to achieve docking with the pipe A610. A hand chain hoist 500 is hung on the hoisting hole 410, and the hand chain hoist 500 is connected to the pipe B620. The operator can adjust the up, down, left, and right positions of the pipe B620 by pulling the hand chain of the hand chain hoist 500 until the center lines of the two pipe openings of the pipe B620 and the pipe A610 are aligned, and then welding or installing a clamp can be performed.

[0054] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0055] Although the embodiments of the present invention have been shown and described, those skilled in the art will appreciate that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.

Claims

1. A lifting tool, characterized in that: include: A supporting beam (100), one end of which is used for hoisting a pipeline; A fixing device, the fixing device being arranged at the other end of the supporting crossbeam (100), the fixing device being used for sleeve-mounting a pipeline; A supporting device, one end of which is connected to the middle portion of the supporting beam (100), and the other end of which is used to abut against the pipeline.

2. The lifting tool according to claim 1, characterized in that: The fixing device comprises a first connecting rod (210) and a clamping device, wherein one end of the first connecting rod (210) is connected to the supporting crossbeam (100), and the other end is connected to the clamping device, and the clamping device is used for sleeve installation of the pipeline.

3. The lifting tool according to claim 2, characterized in that: The first connecting rod (210) is rotatably connected to the supporting crossbeam (100).

4. The lifting tool according to claim 2, characterized in that: The clamping device comprises a first connecting member (220) and a second connecting member (230), wherein both ends of the first connecting member (220) and the second connecting member (230) are connected to each other and are used to sleeve the pipeline therein.

5. The lifting tool according to claim 4, characterized in that: The first connecting member (220) comprises a first arc-shaped plate (221), connecting plates (222) are arranged at both ends of the first arc-shaped plate (221), and bolt holes are opened on the connecting plates (222); the second connecting member (230) comprises a second arc-shaped plate (231), screw rods (232) are arranged at both ends of the second arc-shaped plate (231); the first connecting member (220) and the second connecting member (230) are connected via the screw rods (232) and the bolt holes.

6. The lifting tool according to claim 1, characterized in that: The supporting device comprises a second connecting rod (310) and a supporting plate (320); one end of the second connecting rod (310) is connected to the supporting beam (100), and the other end is connected to the supporting plate (320); the supporting plate (320) is used to abut against the pipeline.

7. The lifting tool according to claim 6, characterized in that: The second connecting rod (310) is rotatably connected to the supporting beam (100).

8. The lifting tool according to claim 6, characterized in that: The support plate (320) is an arc-shaped plate structure, and the inner concave surface of the support plate (320) is used to abut against the pipeline.

9. The lifting tool according to claim 1, characterized in that: The supporting device comprises a second connecting rod (310) and a clamping assembly, wherein one end of the second connecting rod (310) is connected to the supporting crossbeam (100), and the other end is used to abut against the pipeline; a driving motor (710) and an adjusting screw (720) are arranged inside the second connecting rod (310), and the clamping assembly comprises two movable gears (730) and a clamping claw (740) symmetrically arranged along the axial direction of the adjusting screw (720), the gear teeth of the two movable gears (730) are meshed with the threads of the adjusting screw (720), and the clamping claw (740) is connected to the movable gear (730), and the driving motor (710) drives the adjusting screw (720) to rotate so that the movable gear (730) rotates, thereby driving the clamping claw (740) to rotate synchronously to grasp the pipeline.

10. The lifting tool according to claim 1, characterized in that: It also includes a hoisting part (400) and a hand chain hoist (500), wherein the hoisting part (400) is arranged at one end of the supporting crossbeam (100), a hoisting hole (410) is opened on the hoisting part (400), and the hand chain hoist (500) is hung on the hoisting hole (410), and the pipes are pulled by the hand chain hoist (500) so that the pipes are connected.