Method for constructing upper step middle partition wall of shallow-buried excavation tunnel
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- HANGZHOU TIANHENG INVESTMENT CONSTR MANAGEMENT
- Publication Date
- 2015-05-13
Smart Images
Figure 1
Abstract
Description
technical field
[0001] The invention belongs to the technical field of tunnel construction, and in particular relates to a construction method for a partition wall in an upper step of a shallow-buried tunnel. Background technique
[0002] The CRD method and the double-side-wall pilot-pit method are often used in the construction of shallow-buried tunnels with weak surrounding rocks. These methods are based on the idea of block excavation, and the excavation and temporary support are removed to disturb the surrounding rock many times. The process transformation is complicated and the operation Small space is not conducive to the use of large mechanical equipment, slow construction progress, long construction period, high cost, poor excavation stability and safety, and is not suitable for low rock strength, developed rock mass structural planes, rock mass endowment The excavation of the two-lane tunnel cannot be carried out due to rock formations with poor storage environmen...