Construction traffic plan optimizing method in dam project construction process

A technology of construction process and optimization method, applied in design optimization/simulation, prediction, instrument, etc., can solve problems such as lack of judgment basis for whether construction plan is reasonable, difficult to accurately express the dynamic change process of engineering construction traffic, complex construction plan, etc.

Active Publication Date: 2018-02-23
CHENGDU XIMENG TEKE TECH DEV CO LTD
View PDF5 Cites 7 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] At present, there is no method for simulating the construction process of the gravel soil core rockfill dam project according to the designed construction plan before construction. Due to the large scale of the project and the complexity of the construction plan, it is difficult for the existing techn

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction traffic plan optimizing method in dam project construction process
  • Construction traffic plan optimizing method in dam project construction process
  • Construction traffic plan optimizing method in dam project construction process

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0146] Embodiments of the present invention are described in detail below, examples of which are shown in the drawings, wherein the same or similar reference numerals designate the same or similar elements or elements having the same or similar functions throughout. The embodiments described below by referring to the figures are exemplary only for explaining the present invention and should not be construed as limiting the present invention.

[0147] In describing the present invention, it should be understood that the terms "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", The orientation or positional relationship indicated by "horizontal", "top", "bottom", "inner", "outer", etc. are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than Nothing indicating or implying that a referenced device or elem...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a construction traffic plan optimizing method in dam project construction process. The construction traffic plan optimizing method comprises the following steps of S1, accordingto a trunk road plan of a dam project, establishing parameters of a construction trunk road network, and setting information of each road; S2, adding the information of a dam climbing traffic accessing point in the modeling of the dam project, and a material conveying traffic accessing point in the modeling of raw materials of a material yard; S3, according to the data of the accessing points, setting the number of vehicles, transportation capacity, and material transportation time, so as to establish a traffic transportation data model. The construction traffic plan optimizing method has theadvantages that according to the applicable construction traffic parameters, the accurate and efficient modeling is performed, the construction period is shortened, and the efficiency of the dam project is improved.

Description

technical field [0001] The invention relates to the field of computer-aided design, in particular to a construction traffic planning optimization method in the construction process of a dam project. Background technique [0002] At present, there is no method for simulating the construction process of the gravel soil core rockfill dam project according to the designed construction plan before construction. Due to the large scale of the project and the complexity of the construction plan, it is difficult for the existing technology to accurately express the dynamic changes of traffic in the project construction Process, construction traffic material consumption, traffic flow status, traffic road information and vehicle configuration. There is no effective basis for judging whether the designed construction scheme is reasonable or not. This just needs those skilled in the art to solve corresponding technical problem badly. Contents of the invention [0003] The present inv...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): G06F17/50G06Q10/04G06Q50/08
CPCG06Q10/047G06Q50/08G06F30/20
Inventor 杨兴国刘飞虎李洪涛姚强陈思迪辜斌
Owner CHENGDU XIMENG TEKE TECH DEV CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products