A construction method for a post-mounted retaining wall drain hole

A construction method and technology for retaining walls, which are applied in water conservancy projects, soil protection, artificial islands, etc., can solve the problems of affecting the layout effect of decorative tiles on the wall body during the decoration stage, unable to ensure accurate positioning, and affecting the efficiency of backfilling. Conducive to finished product protection, fast construction, and convenient reinforcement

Active Publication Date: 2021-01-26
中建五局第三建设有限公司
View PDF10 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

This construction method has the following disadvantages: (1) Since the drain pipe protrudes out of the retaining wall, it is necessary to open holes in the formwork on both sides, and the drain pipe extends out of the formwork to ensure that the wall formwork is straight. The efficiency is low, and it is easy to cause damage to the drain pipe during the reinforcement and removal of the formwork; (2) The embedding of the drain pipe in the main stage cannot ensure accurate positioning, which affects the layout effect of the wall decoration bricks in the decoration stage; (3) Since the drain pipe protrudes out of the wall , in the earthwork backfill stage, it is necessary to manually backfill and tamp one by one, which affects the backfill efficiency on the one hand, and easily causes damage to the drain pipe on the other hand

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A construction method for a post-mounted retaining wall drain hole

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0030] Below in conjunction with accompanying drawing, describe a kind of construction method of post type retaining wall weep hole in detail.

[0031] see figure 1 , a construction method for a post-mounted retaining wall drain hole, the construction process: wall reinforcement binding - casing pre-embedded - formwork support - concrete pouring - retaining wall backfill - earth reverse Excavation - burial of drain pipes - installation of filter bags - backfilling - plastering - tiling - installation of sleeves

[0032] During the construction, the "jumping warehouse method" is used to carry out the construction of each section of the retaining wall structure, and a certain strength foam board is used at the deformation joint to isolate from the foundation of the two adjacent retaining walls to the top of the wall. The specific construction steps are as follows:

[0033] 1. Binding of steel bars on the wall

[0034] After the concrete pouring of the foundation of the retain...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a construction method of a post-mounted retaining wall drain hole, which consists of two parts: a wall drainage pipe and a reverse filter layer. It can be achieved by pre-burying the casing during the construction stage of the retaining wall structure, first filling the soil and then back excavating to install the drain pipe and the reverse filter bag, laying the large face bricks of the retaining wall first, and then laying the face bricks at the drain holes, etc. The formwork of the retaining wall is easy to reinforce, the backfilling efficiency is high, and the drain pipe is not easy to be damaged. At the same time, it can ensure the accurate positioning of the drain pipe and ensure the beautiful paving of the bricks.

Description

technical field [0001] The invention relates to a construction method of a rear-mounted retaining wall drain hole. Background technique [0002] At present, the traditional retaining wall drainage pipe is buried during the construction of the retaining wall structure, and a length is reserved on both sides of the retaining wall. On the backfill side of the earthwork, use a reverse filter bag to wrap the protruding drain pipe. This construction method has the following disadvantages: (1) Since the drain pipe protrudes out of the retaining wall, it is necessary to open holes in the formwork on both sides, and the drain pipe protrudes out of the formwork to ensure that the wall formwork is straight, which makes it inconvenient to reinforce the formwork. The efficiency is low, and it is easy to cause damage to the drain pipe during the reinforcement and removal of the formwork; (2) The embedding of the drain pipe in the main stage cannot ensure accurate positioning, which affec...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D29/02E02D3/10
CPCE02D3/10E02D29/0275E02D2250/0007E02D2250/0023
Inventor 宋鑫李果覃川黎罗
Owner 中建五局第三建设有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products