Field prefabrication and installation method for groove cover plate in tunnel
A technology for prefabricated installation and in-tunnel application in mining equipment, earth-moving drilling, manufacturing tools, etc. It can solve the problems of high land occupation cost, long site occupation time, and high product transportation cost for prefabricated sites, so as to save costs and speed up Construction progress and the effect of slow water evaporation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0020] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0021] like figure 1 As shown, an embodiment of the on-site prefabricated installation method of the trench cover plate in the tunnel of the present invention comprises the following steps:
[0022] S1: Combined with the construction period plan, according to the design size requirements, customize the plastic mold of the trench cover plate;
[0023] S2: Place the plastic mold, flat vibrator, backing plate and steel mesh in the tunnel;
[0024] S3: Place the backing plate flat on the slot of the groove, place the plastic mold neatly on the backing plate, and place the steel mesh in the plastic mold;
[0025] S4: Produce concrete according to the established ratio and deliver it to the site;
[0026] S5: Concrete pouring in plastic molds, using a flat vibrator to vibrate and compact;
[0027] S6: Use geotextile to cover the poured ...