Channel ecological isolation belt and construction method and application thereof

By imitating the natural island chain and densely planted aquatic plants, an ecological isolation zone is formed, which solves the problem that traditional bank protection structures cannot block ship waves and soil erosion, and achieves effective pollution control and landscape improvement.

CN118774068AInactive Publication Date: 2024-10-15POWERCHINA HUADONG ENG CORP LTD

Patent Information

Application Number
CN202411003853.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-10-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional waterway bank protection structures cannot effectively block ship waves and echoes, resulting in the death of underwater vegetation, cannot effectively inhibit soil erosion and water pollution, and cannot effectively intercept silt, floating garbage and algae in the water.

Method used

An ecological isolation zone that imitates a natural island chain with terrestrial and aquatic plants is used to form a protective barrier through the island chain. Combined with densely planted aquatic plants, including emergent, floating and submerged plants, the design parameters of the island chain ensure the growth and stability of vegetation. characteristics, and ensure the success rate and operability of the ecological isolation zone through specific construction methods.

Benefits of technology

It effectively prevents ship waves from scouring the shore protection, extends the life of the shore, improves water transparency, reduces noise pollution, forms a stable water-land interface, and improves the ecological environment and landscape aesthetics of the waterway.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774068A_ABST
    Figure CN118774068A_ABST
Patent Text Reader

Abstract

The invention provides a channel ecological isolation belt and a construction method and application thereof, and relates to the technical field of ship pollution control, the channel ecological isolation belt comprises an island chain configured in a near-shore area and vegetation planted in the island chain; wherein the vegetation comprises emergent aquatic plants such as reeds and submerged plants such as vallisneria natans and hydrilla verticillata; the island chain comprises a nature-imitated island chain and can be at least one of a willow-leaf-shaped island chain, an oval island chain and a spindle-shaped island chain. The technical problem that a single structural mode of a traditional channel bank is difficult to effectively block scouring of ship waves to a revetment is solved, and the technical effects that scouring of the ship waves to the revetment can be effectively blocked, wave flow of a water and soil boundary layer can be effectively slowed down, and therefore water and soil loss is restrained are achieved; the purposes of absorbing the influence of ship traveling waves and echoes, effectively prolonging the service life of the revetment, improving the transparency of a water body and forming a more stable channel land and water interlaced zone are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of ship pollution prevention and control, and in particular to a waterway ecological isolation zone and a construction method and application thereof. Background Art

[0002] At present, in order to prevent scouring, traditional waterway banks often use hardened revetments combined with near-shore underwater vegetation planting. However, ship waves and echoes will still accelerate the death of underwater vegetation, resulting in little effect.

[0003] The single structural model of traditional revetment combined with aquatic plants planted in the water area around the revetment is not only unable to effectively prevent the scouring of the revetment by ship waves, but also cannot effectively prevent silt, floating garbage and water hyacinth in the water.

[0004] In view of this, the present invention is proposed. Summary of the invention

[0005] One of the purposes of the present invention is to provide a waterway ecological isolation zone that can effectively prevent the scouring of ship waves on the revetment, and at the same time can effectively inhibit soil erosion, thereby effectively extending the life of the bank and forming a more stable waterway water-land interlaced zone.

[0006] The second purpose of the present invention is to provide a method for constructing a waterway ecological isolation zone, which has strong operability, high success rate and is suitable for promotion.

[0007] The third purpose of the present invention is to provide an application of a waterway ecological isolation zone, which can effectively alleviate waterway pollution and improve water transparency.

[0008] In order to achieve the above-mentioned purpose of the present invention, the following technical solutions are particularly adopted:

[0009] In the first aspect, a waterway ecological isolation zone includes an island chain configured in a nearshore area, and vegetation planted in the island chain;

[0010] Said vegetation includes terrestrial plants and aquatic plants;

[0011] The island chain includes an imitation natural island chain;

[0012] The simulated natural island chain includes at least one of a willow-leaf island chain, an oval island chain and a spindle-shaped island chain.

[0013] Furthermore, the highest point of the island chain is not less than 20 cm below the normal water level.

[0014] Furthermore, the width of the island chain above the normal water level is not less than 2 m.

[0015] Furthermore, the terrestrial plants include at least one of reed, Phragmites australis and Reed.

[0016] Further, the aquatic plants include at least one of emergent plants, floating plants and submerged plants;

[0017] The emergent plants include reeds;

[0018] The submerged plants include at least one of Vallisneria and Hydrilla.

[0019] Furthermore, the aquatic plants are densely planted on the island chain;

[0020] The planting density of the dense planting is 70 to 90 plants / m 2 ;

[0021] The lowest point of the aquatic plant planting should not be deeper than 100 cm below the normal water level.

[0022] In a second aspect, a method for constructing a waterway ecological isolation zone as described in any one of the above items comprises the following steps:

[0023] (a) Build cofferdams and regulate the water level in the operation area;

[0024] (b) Clean the work area and ensure that the bottom of the water is clean;

[0025] (c) First, lay out the island chain according to its outline, then reinforce it with pine piles according to the outline, and then pile up soil to stabilize the island chain terrain;

[0026] (d) covering with soil and planting vegetation;

[0027] (e) Maintain the area to form a stable ecological isolation zone and gradually remove the cofferdam.

[0028] Furthermore, the deepest area of ​​the working area after water level control is no more than 30 cm.

[0029] Furthermore, the planting of vegetation includes the following steps:

[0030] Plant terrestrial plants first, then aquatic plants;

[0031] Before planting aquatic plants, water should be replenished. First, a submerged plant community should be built. After maintenance for 3 to 5 months, water should be replenished to the normal water level, and then emergent plants and floating plants can be planted.

[0032] A third aspect is the application of a waterway ecological isolation zone as described in any of the above items in preventing and controlling ship pollution.

[0033] Compared with the prior art, the present invention has at least the following beneficial effects:

[0034] The waterway ecological isolation zone provided by the present invention can, through the ecological island chain model, on the one hand, expand the water-land junction protection zone, form a protective barrier with the island chain as the main body, and absorb the impact of ship waves and echoes; on the other hand, it can intercept underwater garbage, floating objects on the water, and algae caused by ships in the water body of the waterway, avoiding direct impact on the revetment; at the same time, the present invention uses green and ecological design methods, which not only effectively beautifies the ecological environment and enhances the image of the nearshore landscape, but also effectively reduces ship noise pollution. In short, the waterway ecological isolation zone of the present invention can effectively block the scouring of the revetment by ship waves, and can effectively inhibit soil erosion, thereby effectively extending the life of the bank and forming a more stable waterway water-land junction.

[0035] The method for constructing a waterway ecological isolation zone provided by the present invention has strong operability, high success rate and is suitable for promotion.

[0036] The application of the waterway ecological isolation zone provided by the present invention can effectively alleviate waterway pollution and improve water transparency. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0038] Figure 1 A schematic plan view of a waterway ecological isolation zone provided in one embodiment of the present invention;

[0039] Figure 2 A schematic diagram of water wave flow diversion and absorption provided in one embodiment of the present invention;

[0040] Figure 3 A schematic cross-sectional view of a waterway ecological isolation zone provided for one embodiment of the present invention. DETAILED DESCRIPTION

[0041] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0042] According to a first aspect of the present invention, there is provided a waterway ecological isolation zone, comprising an island chain arranged in a nearshore area, and vegetation planted in the island chain;

[0043] Among them, vegetation includes terrestrial plants and aquatic plants;

[0044] The island chain refers to an imitation of a natural island chain, including at least one of a willow-leaf island chain, an oval island chain and a spindle-shaped island chain.

[0045] In the present invention, the simulated natural island chain refers to artificially created continents, beaches and islands whose shapes conform to the characteristics of naturally formed island chains and have the function of absorbing ship waves.

[0046] The waterway ecological isolation zone of the present invention breaks through the traditional shore model and constructs an ecological buffer zone in the form of imitating natural island chains and matching vegetation as the waterway ecological isolation zone. Figure 1 , thus forming a natural barrier for water wave diversion and absorption. See the schematic diagram of water wave diversion and absorption. Figure 2 , shaping a stable water-land junction area, which can not only effectively eliminate the scouring of ship waves on the revetment, but also effectively block pollutants, improve water transparency, and effectively absorb noise.

[0047] In summary, the waterway ecological isolation zone provided by the present invention, through the ecological island chain model, can, on the one hand, expand the water-land junction protection area, form a protective barrier with the island chain as the main body, and absorb the impact of ship waves and echoes; on the other hand, it can slow down the soil erosion at the water-land interface and the underwater mud surging problems caused by ships in the water body of the waterway; at the same time, the present invention uses green and ecological design means, which not only effectively beautifies the ecological environment and enhances the image of the nearshore landscape, but also effectively reduces ship noise pollution.

[0048] In a preferred embodiment, the island chain design parameters include but are not limited to: the island chain design should be no less than 20 cm below the normal water level, and the width of the island chain above the normal water level should be no less than 2 m.

[0049] In the present invention, the island chain is not less than 20 cm below the normal water level, which is more conducive to the growth and development of emergent plants and fixation of soil through root systems, thereby being more conducive to resisting the direct scouring of the shore by ship waves and wind and waves, while being both ecological and economical; the width of the island chain above the normal water level is not less than 2 m, and sufficient island chain width is more conducive to increasing the amount of terrestrial vegetation, thereby being able to play a more effective buffering role.

[0050] In a preferred embodiment, the terrestrial plants include but are not limited to at least one of reed, Phragmites australis and Reed.

[0051] In a preferred embodiment, the aquatic plants include but are not limited to at least one of emergent plants, floating plants and submerged plants; wherein the emergent plants include but are not limited to reeds, and the submerged plants include but are not limited to at least one of Vallisneria and Hydrilla.

[0052] In the present invention, the island chain can be reinforced with pinewood piles, and perennial grass plants such as reeds and reeds can be planted on the land of the island chain. Aquatic plants can be planted no shallower than 80 cm below the normal water level. The width of the emerging plants planted below the normal water level on the outer edge of the island chain can be 1 m. Figure 3 .

[0053] In a preferred embodiment, aquatic plants can be densely planted on the island chain, and the planting density of the dense planting can be 70 to 90 plants / m 2 , for example, 70 plants / m 2 , 75 plants / m 2 , 80 plants / m 2 , 85 plants / m 2 , 90 plants / m 2 , but not limited to this; at the same time, the lowest point of the aquatic plants is not deeper than 100cm below the normal water level.

[0054] According to a second aspect of the present invention, there is provided a method for constructing a waterway ecological isolation zone as described in any one of the above, comprising the following steps:

[0055] (a) Build cofferdams and regulate the water level in the operation area;

[0056] (b) Clean the work area and ensure that the bottom of the water is clean;

[0057] (c) First, lay out the island chain according to its outline, then reinforce it with pine piles according to the outline, and then pile up soil to stabilize the island chain terrain;

[0058] (d) covering with soil and planting vegetation;

[0059] (e) Maintain the area to form a stable ecological isolation zone and gradually remove the cofferdam.

[0060] The method for constructing a waterway ecological isolation zone provided by the present invention has strong operability, high success rate and is suitable for promotion.

[0061] In a preferred embodiment, the preliminary preparation work is carried out in step (a), including the following steps: selecting a suitable operation area on the bank of the waterway based on underwater geological survey, mapping and hydrological data, carrying out cofferdam work, preparing construction materials, and regulating the water level in the operation area. The water level in the deepest area of ​​the operation area after regulation is no more than 30 cm.

[0062] In a preferred embodiment, step (b) is performed to clean the bottom of the work area, including the following steps: cleaning floating garbage, weeds, dead fish, branches, silt and waste in the work area to ensure that the bottom of the work area is clean.

[0063] In a preferred embodiment, the work of shaping the island chain is carried out in step (c), including the following steps: firstly laying out the island chain according to the outline, and reinforcing it with pine piles according to the laid-out outline, and then piling up soil to stabilize the island chain terrain, and then artificially leveling the island chain terrain and the underwater island chain to stabilize the slope.

[0064] In a preferred embodiment, step (d) involves planting vegetation on the island, covering the island with soil and planting vegetation, including the following steps: first planting vegetation such as reeds on land, and then planting aquatic plants; water replenishment is required before planting aquatic plants, and the water level is maintained at about 30 cm in the submerged plant planting area. A submerged plant community is first constructed, and after maintenance for 3 to 5 months, water is replenished to the normal water level, and then emergent plants and floating plants are planted.

[0065] According to a third aspect of the present invention, there is provided an application of the waterway ecological isolation zone described in any one of the above items in preventing and controlling ship pollution.

[0066] The application of the waterway ecological isolation zone provided by the present invention can effectively alleviate waterway pollution and improve water transparency.

[0067] The present invention is further described below by way of examples. Unless otherwise specified, the materials in the examples are prepared according to existing methods or directly purchased from the market.

[0068] Example 1

[0069] A waterway ecological isolation zone, including a simulated natural island chain configured in the nearshore area, and vegetation planted in the island chain;

[0070] Among them, the vegetation is terrestrial plants and aquatic plants. The terrestrial plants are reeds, and the aquatic plants are emergent plants, floating plants and submerged plants.

[0071] Aquatic plants are planted at the foot of Shipo Town in the island chain. The aquatic plants include emergent plants, floating plants and submerged plants. The planting density of aquatic plants is 70 to 90 plants / m 2 ; Among them, submerged plants are Vallisneria and Hydrilla; reeds are planted on land on the island chain;

[0072] Island chain design parameters: The highest point of the island chain is not less than 20cm below the normal water level, and the width of the island chain above the normal water level is not less than 2m; the planting width of emergent plants below the normal water level on the outer edge of the island chain is 1m.

[0073] The waterway ecological isolation zone of this embodiment constructs an ecological buffer zone in the form of imitating a natural island chain with vegetation, forming a natural barrier for absorbing and diverting water, and shaping a stable water-land junction area. It can effectively eliminate the scouring of the revetment by ship waves, effectively block pollutants, significantly improve water transparency, and significantly absorb noise.

[0074] Example 2

[0075] This embodiment is a method for constructing a waterway ecological isolation zone of Embodiment 1, comprising the following steps:

[0076] Step 1: Preliminary preparation (cofferdam, water level control):

[0077] Select a suitable operation area on the shore of the waterway based on underwater geological survey, mapping and hydrological data, carry out cofferdam work, prepare construction materials, and carry out water level control in the operation area. After control, the water level in the deepest area is no higher than 30cm;

[0078] Step 2: Base cleaning (garbage cleaning, terrain shaping):

[0079] Clean up floating garbage, weeds, dead fish, branches, silt and waste in the operation area to ensure that the bottom of the water in the operation area is clean;

[0080] Step 3: Island chain shaping (laying out lines, stabilizing with pine stakes, and covering with planting soil):

[0081] Lay out the island chain according to its outline, use pinewood piles with a length of 3m and a diameter of not less than 8cm to reinforce the island chain terrain (fill height not less than 50cm), artificially level the island chain terrain and the underwater island chain slope (fill height not less than 30cm);

[0082] Step 4: Planting vegetation (planting terrestrial plants and aquatic plants):

[0083] Emergent, floating and submerged plants are planted at the foot of the island chain, while reeds are planted on land above the island chain;

[0084] Priority should be given to planting reeds on land. Watering is required before planting aquatic plants. The water level should be kept at about 30 cm in the submerged plant planting area to build a submerged plant community. After 3 to 5 months of maintenance, water should be added to the normal water level, and then emergent plants and floating plants should be planted. The construction should be mainly carried out by manual transplanting, supplemented by manual seeding. Plants with well-developed rhizomes, strong plants and no diseases and insect pests should be selected for operation. At the same time, disease and insecticides should be used to pre-treat the seedlings, control the planting density, and ensure the survival rate;

[0085] Step 5: Use and maintenance (regularly clean up the garbage on the outer edge):

[0086] After the overall completion, it will require 6 months of maintenance to form a stable ecological isolation zone. The cofferdam will then be dismantled, and the dead seedlings on the outer edge will be monitored in real time, and the floating garbage on the outer edge will be cleaned up regularly.

[0087] Example 3

[0088] The difference between this embodiment and embodiment 1 is that the aquatic plants planted in the island chain in this embodiment are only emergent plants and floating plants, that is, no submerged plants are planted;

[0089] The rest is the same as in Example 1, forming a waterway ecological isolation zone.

[0090] Compared with Example 1, the defect of the waterway ecological isolation zone of this embodiment is that the sediment cannot be fixed, resulting in increased turbidity of the water body and excessive growth of algae.

[0091] Example 4

[0092] The difference between this embodiment and embodiment 1 is that the aquatic plants planted in the island chain in this embodiment are only emergent plants, that is, floating plants and submerged plants are not planted;

[0093] The rest is the same as in Example 1, forming a waterway ecological isolation zone.

[0094] Compared with Example 1, the drawback of the waterway ecological isolation zone of this example is that, in addition to the inability to fix sediments, increased water turbidity and excessive growth of algae, the ability to intercept floating pollutants on the water surface is also reduced.

[0095] Example 5

[0096] The difference between this embodiment and embodiment 1 is that the aquatic plants planted in the island chain in this embodiment are only submerged plants, that is, no emergent plants and floating plants are planted;

[0097] The rest is the same as in Example 1, forming a waterway ecological isolation zone.

[0098] Compared with Example 1, the defect of the waterway ecological isolation zone of this embodiment is that it causes instability of the island chain and cannot form an effective buffer against wind waves and ship waves.

[0099] Example 6

[0100] The difference between this embodiment and embodiment 1 is that the planting density of aquatic plants in this embodiment is 50 to 70 plants / m 2 ;

[0101] The rest is the same as in Example 1, forming a waterway ecological isolation zone.

[0102] Example 7

[0103] The difference between this embodiment and embodiment 1 is that the planting density of aquatic plants in this embodiment is 30 to 50 plants / m 2 ;

[0104] The rest is the same as in Example 1, forming a waterway ecological isolation zone.

[0105] Comparative Example 1

[0106] The difference between this comparative example and Example 1 is that in this comparative example, a non-streamlined artificial island chain is used to replace the simulated natural island chain;

[0107] The rest is the same as in Example 1, forming a waterway ecological isolation zone.

[0108] Compared with Example 1, the defect of the waterway ecological isolation zone of this comparative example is that the island chain morphology cannot be stabilized and the buffering effect on waves is reduced.

[0109] Comparative Example 2

[0110] The difference between this comparative example and Example 1 is that in this comparative example, no aquatic plants (i.e., no emergent plants, floating plants, and submerged plants) are planted in the island chain;

[0111] The rest is the same as in Example 1, forming a waterway ecological isolation zone.

[0112] Compared with Example 1, the defect of the waterway ecological isolation zone of this comparative example is that it can only slow down part of the trough scouring and cannot form an ecological system.

[0113] Comparative Example 3

[0114] This comparative example provides a traditional channel bank model, which adopts a model of hardened revetments combined with near-shore underwater vegetation to form an isolation zone;

[0115] Compared with Example 1, the isolation zone formed in this comparative example cannot effectively prevent the scouring of the revetment by ship waves, nor can it improve the transparency of the water body. At the same time, ship waves and echoes will accelerate the death of underwater vegetation.

[0116] Test example

[0117] In order to verify the effects of the waterway ecological isolation zone of the present invention, namely, the technical effects of blocking the scouring of ship waves on the revetment, improving water transparency and absorbing noise, this test example tested the isolation zones formed by Example 1, Examples 3-7 and Comparative Examples 1-3, and the test results are shown in Table 1.

[0118] The test method is as follows:

[0119] 1. Wave characteristic data adopts the wave observation method proposed to adopt the buoy observation method. The SDB380W wave observation buoy with a diameter of 38cm and a weight of 10kg (including batteries and counterweights) is used. The measured data is measured by the maximum wave height average.

[0120] 2. Water transparency was obtained by comparing data inside and outside the ecological isolation zone using the Secchi disk method (Methods for Monitoring and Analysis of Water and Wastewater (4th edition), State Environmental Protection Administration (2002), Part 3, Chapter 1, V (II)).

[0121] 3. A multifunctional sound level meter (AWA588) and a sound calibrator (AWA6021A) are used to eliminate noise, and the noise measurement plan is based on the requirements of the "Noise Environment Quality Standard" (GB 3096-2008).

[0122] Table 1

[0123]

[0124] As can be seen from Table 1, the present invention configures simulated natural island chains and planted plants in the nearshore area to form an ecological isolation zone, breaking the single structural mode of traditional revetments combined with aquatic plants planted in the waters near the revetments. It not only more effectively blocks the erosion of the revetments by ship waves, but also helps to improve the transparency of the water body, effectively prolong the life of the banks, and form a more stable waterway water-land interlaced zone.

[0125] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A waterway ecological isolation zone, characterized in that: including island chains arranged in nearshore areas, and vegetation planted in said island chains; Said vegetation includes terrestrial plants and aquatic plants; The island chain includes an imitation natural island chain; The simulated natural island chain includes at least one of a willow-leaf island chain, an oval island chain and a spindle-shaped island chain.

2. The waterway ecological isolation zone according to claim 1 is characterized in that: The highest point of the island chain is not less than 20 cm below the normal water level.

3. The waterway ecological isolation zone according to claim 2 is characterized in that: The width of the island chain above normal water level is not less than 2m.

4. The waterway ecological isolation zone according to any one of claims 1 to 3, characterized in that: The terrestrial plants include at least one of reed, Phragmites australis and Reed.

5. The waterway ecological isolation zone according to any one of claims 1 to 3, characterized in that: The aquatic plants include at least one of emergent plants, floating plants and submerged plants; The emergent plants include reeds; The submerged plants include at least one of Vallisneria and Hydrilla.

6. The waterway ecological isolation zone according to claim 5 is characterized in that: The aquatic plants are densely planted on the island chain; The planting density of the dense planting is 70 to 90 plants / m 2 ; The lowest point of the aquatic plant planting is no deeper than 100 cm below the normal water level.

7. A method for constructing a waterway ecological isolation zone according to any one of claims 1 to 6, characterized in that: The following steps are involved: (a) Build cofferdams and regulate the water level in the operation area; (b) Clean the work area and ensure that the bottom of the water is clean; (c) First, lay out the island chain according to its outline, then reinforce it with pine piles according to the outline, and then pile up soil to stabilize the island chain terrain; (d) covering with soil and planting vegetation; (e) Maintain the area to form a stable ecological isolation zone and gradually remove the cofferdam.

8. The construction method according to claim 7, characterized in that: The deepest area of ​​the working area after water level adjustment is no more than 30cm.

9. The construction method according to claim 7, characterized in that: The planting of vegetation comprises the following steps: Plant terrestrial plants first, then aquatic plants; Before planting aquatic plants, water should be replenished. First, a submerged plant community should be built. After maintenance for 3 to 5 months, water should be replenished to the normal water level, and then emergent plants and floating plants can be planted.

10. Use of the waterway ecological isolation zone according to any one of claims 1 to 6 in preventing and controlling pollution from ships.

Citation Information

Patent Citations

  • Movable type plant floating island chain applicable to estuary of lake

    CN102139960A

  • Ecological water area function isolation submerged island and river

    CN112624343A

  • Construction method of water and soil conservation ecosystem during construction of landscape terrain in estuary region

    CN114215003A

  • Water ecological treatment system for protecting biodiversity and application of water ecological treatment system in channel protection

    CN118186981A

  • Artificial floating island and accommodated facilities

    JP1996133178A

Cited By

  • Method for ecological restoration of river channel based on construction of ecological island

    CN121611099A