High-pile wharf structure for LNG loading and unloading and construction method of high-pile wharf structure
Through pipe piles and prefabricated cast-in-place joint technology, a high pile dock structure is built, which solves the problems of long construction period, high cost and environmental pollution of traditional high pile docks, and achieves rapid and low-cost LNG loading and unloading dock construction, improving structural stability and construction efficiency.
Patent Information
- Application Number
- CN202411228235.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2024-11-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the LNG loading and unloading process, traditional high pile docks have long construction periods, high costs, serious environmental pollution, and safety management and project quality are difficult to control.
Pipe piles are used as the dock foundation, combined with prefabricated pile caps and poured concrete, and frame beams and cast-in-place joint plates are used to form a high pile dock structure. The superstructure is constructed through prefabricated plates and cast-in-place bridge decks, and prefabricated cast-in-place jointing is used to reduce the Construction costs and improve efficiency.
It achieves rapid construction and low cost, improves the overall stability and impact resistance of the dock structure, reduces environmental pollution, and simplifies construction management.
Smart Images

Figure CN118880800A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of port engineering, and more particularly to a high-pile wharf structure for LNG loading and unloading and a construction method thereof. Background Art
[0002] LNG loading and unloading terminals are facilities specifically used for loading and unloading liquefied natural gas (LNG). They play an important role in ensuring energy supply and promoting the use of clean energy, and usually adopt high-pile terminal structures.
[0003] A high-pile wharf is a common port facility, mainly used for loading and unloading cargo and for passengers embarking and disembarking. It consists of a series of decks supported by high piles, which are usually reinforced concrete columns that penetrate into the seabed or riverbed to provide stable support. The design of the high-pile wharf allows ships to dock safely at different water levels and can adapt to large tidal changes. The high-pile wharf is mainly composed of pile foundation and superstructure. Among them, the pile foundation technology has developed rapidly, and the design and construction technology of reinforced concrete piles, prestressed reinforced concrete piles, prestressed large pipe piles, and steel pipe piles have become increasingly mature, adapting to different geological conditions and conditions of use. Different pile types can meet the use requirements; however, the superstructure technology of the high-pile wharf has developed slowly, and there are fewer structural forms to choose from. So far, beam-slab structures are basically used. The high-pile beam-slab wharf is a wharf structure type that is mainly suitable for soft soil foundations. Commonly used foundation pile forms include concrete square piles, concrete pipe piles, steel pipe piles, etc., and the superstructure is a concrete beam-slab structure.
[0004] At present, the traditional high-pile wharf superstructure system generally adopts a large amount of cast-in-place concrete. The casting of cast-in-place pile caps or beams often involves the support and removal of formwork at a lower water level, which results in a short construction window, a long construction period, and low construction efficiency. In addition, a large amount of concrete construction work on water will cause serious environmental pollution such as noise and dust during the on-site construction process, making it very difficult to standardize the operation management, and it is difficult to control the on-site safety and project quality.
[0005] Therefore, how to provide a high-pile wharf structure for LNG loading and unloading that is fast to construct, low in cost, and reduces manpower input is a problem that technical personnel in this field urgently need to solve. Summary of the invention
[0006] In view of this, the present invention provides a high-pile wharf structure for LNG loading and unloading and a construction method thereof, aiming to solve the above technical problems.
[0007] In order to achieve the above object, the present invention adopts the following technical solution:
[0008] A high-pile wharf structure for LNG loading and unloading, comprising:
[0009] A pile foundation group, the pile foundation group comprises a plurality of pipe piles arranged in rows both longitudinally and transversely, the bottom ends of the plurality of pipe piles being inserted into the seabed bearing layer and the top ends being exposed above the water surface;
[0010] Pile caps, wherein a plurality of the pile caps are buckled on the tops of the plurality of pipe piles in a one-to-one correspondence, and the pile caps are provided with through holes correspondingly connected to the inner cavities of the pipe piles so as to pour core concrete into the pipe piles;
[0011] A frame beam, wherein a plurality of frame beams are provided, and the plurality of frame beams form a high-pile wharf frame, and the bottom surface of the beam end of the frame beam abuts against the top surfaces of two adjacent pile caps; and a casting gap is provided between the opposite end surfaces of two adjacent frame beams;
[0012] A cast-in-place joint plate, the cast-in-place joint plate is arranged in the casting gap to engage with the frame beam and connect a plurality of the frame beams into a whole;
[0013] Prefabricated panels, which are multiple and laid on the top surface of the frame beam;
[0014] A cast-in-place bridge deck is cast on the top surface of the high-pile wharf frame to cover a plurality of the precast panels.
[0015] The beneficial effect of the above technical solution is that pipe piles are used as the foundation of the wharf, the construction is efficient, fast and low-cost, the unique design of the pile cap can be consolidated with the core concrete, so that the pile cap and the pipe pile form a whole, the precast panel is used as a frame panel and forms the upper panel structure of the wharf with the cast-in-place bridge panel, and the high-pile wharf is formed by combining pipe piles and precast cast-in-place, which effectively improves the construction efficiency and reduces the construction cost.
[0016] Preferably, the pile cap is a prefabricated component, including a cover plate and a sleeve fixed on the bottom surface of the cover plate, the top surface of the cover plate is provided with a pouring hole connected to the inner cavity of the sleeve, the diameter of the pouring hole is smaller than the inner diameter of the sleeve so that a step surface is formed between the inner wall of the cover plate and the inner wall of the sleeve, the pile cap is sleeved on the outer wall of the top end of the pipe pile and the top end surface of the pipe pile abuts against the step surface. The pile cap adopts the method of on-site assembly of prefabricated components, which is more efficient to install. The pipe pile is clamped at the step surface of the pile cap, and the core concrete can be cast into the pipe pile through the pouring hole, ensuring the effective connection between the pipe pile and the pile cap.
[0017] Preferably, it also includes a steel cage, the bottom end of which is fixed with a support plate and inserted into the inner cavity of the pipe pile, and the top end of which is exposed from the pile cap and anchored in the concrete of the cast-in-place joint plate and the cast-in-place bridge deck. The steel cage is arranged in the inner cavity of the pipe pile, and the support plate is used as a plugging plate of the inner cavity of the pipe pile. The core concrete is poured only in the stress-bearing part of the pile head, which reduces the construction cost. At the same time, the steel cage is anchored in the cast-in-place joint plate and the cast-in-place bridge deck, so that the pipe pile, the cast-in-place joint plate and the cast-in-place bridge deck are consolidated into a whole, which effectively improves the overall stability and impact resistance of the wharf structure.
[0018] Preferably, the frame beams include precast longitudinal beams and precast transverse beams; the frame beams include precast longitudinal beams and precast transverse beams; the precast longitudinal beams are arranged on both sides of the high-pile wharf frame in the longitudinal direction, and the precast transverse beams are arranged in the transverse direction of the high-pile wharf frame; the beam ends of the precast longitudinal beams and the precast transverse beams are overlapped with the top surfaces of two adjacent pile caps corresponding thereto, and the opposite end surfaces of two adjacent precast longitudinal beams and two adjacent precast transverse beams form a casting gap corresponding to the inner cavity of the pipe piles, and the cast-in-place joint plate is cast in the casting gap. The precast longitudinal beams and precast transverse beams serve as the four sides of the wharf frame, and precast plates are laid on the top surfaces of the precast longitudinal beams and precast transverse beams, while cast-in-place bridge panels are cast to form the upper beam-slab structure of the wharf. The precast and cast-in-place jointing method is adopted to improve the construction efficiency and effectively ensure the integrity of the wharf structure.
[0019] Preferably, the frame beam further comprises a prefabricated connecting beam, the length direction of the prefabricated connecting beam is arranged in parallel with the length direction of the prefabricated longitudinal beam, and the prefabricated connecting beam is arranged in the middle of the pile foundation group to longitudinally divide the high-pile wharf frame into a first frame unit and a second frame unit; a plurality of prefabricated connecting beams are provided, and the bottom surfaces at both ends of the plurality of prefabricated connecting beams are respectively abutted against the top surfaces of the two adjacent pile caps corresponding thereto, and the cast-in-place joint plates are cast on the opposite end surfaces of the two adjacent prefabricated connecting beams and at the top ends corresponding to the pile caps;
[0020] Wherein, both end surfaces of the prefabricated longitudinal beam, the prefabricated transverse beam and the prefabricated connecting beam are provided with slots, the cast-in-place joining plate is formed with plug blocks adapted to the slots, and the cast-in-place joining plate is engaged with the prefabricated longitudinal beam or the prefabricated transverse beam or the prefabricated connecting beam through the plug blocks and the slots.
[0021] Prefabricated connecting beams can reinforce the wharf frame and improve its structural strength and stability; the frame beams and cast-in-place joint plates are engaged with each other by means of plug-ins and slots, thus ensuring the overall stability between the upper wharf frame and the lower pile foundation group.
[0022] Preferably, the precast panels include a first precast panel and a second precast panel; the first precast panel is laid on the first frame unit, and the second precast panel is laid on the second frame unit. The thickness of the first precast panel is less than that of the second precast panel, and a dome is formed on the bottom surface of the second precast panel. The first precast panel and the second precast panel of different thicknesses are laid on the top surface of the wharf frame. When casting the cast-in-place bridge deck, the bottom surface of the cast-in-place bridge deck forms a step relative to the first precast panel and the second precast panel, thereby ensuring the bite performance between the cast-in-place bridge deck and the precast panels and improving the integrity of the superstructure of the high-pile wharf; the bottom surface of the higher second precast panel forms a dome, which saves the use of materials and reduces construction costs.
[0023] Preferably, the diameter of the pipe pile is not less than 1.4 m, and the center distance between two adjacent pipe piles is not more than 6 m, so as to ensure that the pipe pile has sufficient rigidity to ensure the stability of the wharf frame.
[0024] Preferably, the thickness of the cast-in-place joint plate is the same as the height of the frame beam, so as to ensure the flatness between the frame beam and the cast-in-place joint plate, so that the cast-in-place bridge deck can completely cover the precast plate.
[0025] The present invention also provides a method for constructing a high-pile wharf for LNG loading and unloading, which is constructed using the high-pile wharf structure in the above technical solution, and comprises the following steps:
[0026] S1, pile foundation construction, inserting the pipe drill into the seabed bearing layer through the pile driver;
[0027] S2, putting the pile cap on the top of the pipe pile and pouring the core concrete;
[0028] After the pile cap is installed, a steel cage is installed in the pile. The top surface of the steel cage is higher than the top elevation of the precast slab. The bottom of the steel cage is the maximum stress point on the top of the pile. The top elevation of the core concrete is flush with the top surface of the pile cap.
[0029] S3, installing frame beams, each frame beam is overlapped with the top surfaces of two adjacent pile caps;
[0030] Prefabricated longitudinal beams are installed on both sides of the high-pile wharf frame structure, prefabricated connecting beams are installed in the middle, and prefabricated longitudinal beams are installed in the transverse direction. Note that the lap length between the beam and the pile cap should not be less than 35cm; and the gap between two adjacent beams should be connected to the corresponding grouting holes on the pile cap so that the steel cage can extend out of the pile cap;
[0031] S4, pouring cast-in-place joint plate;
[0032] The top surface of the cast-in-place joint plate is roughened to seal the gap between two adjacent beams. The concrete of the cast-in-place joint plate is consolidated with the core concrete into one, and the cast-in-place joint plate and the frame beam are engaged by means of inserts and slots, ultimately ensuring that the cast-in-place joint plate, frame beam and pipe pile form an integral structure.
[0033] S5. Lay precast slabs and cast in-situ bridge deck.
[0034] The length direction of the precast slabs is parallel to the length direction of the precast longitudinal beams. There is a height difference between the precast slabs in the first frame and the second frame. After the precast slabs are laid, the cast-in-place bridge deck is poured. The concrete of the cast-in-place bridge deck completely covers the precast slabs, so that the cast-in-place bridge deck, precast slabs and frame beams form an overall stable structure.
[0035] It can be seen from the above technical scheme that compared with the prior art, the present invention discloses a high-pile wharf structure for LNG loading and unloading and a construction method thereof, in which the lower foundation adopts pipe piles as support, the upper frame adopts a prefabricated cast-in-place joint method, and the upper beams and slabs also adopt a prefabricated and cast-in-place joint method, which can reduce construction costs while improving construction efficiency. The bite method between the beams and slabs improves the overall stability of the wharf structure. At the same time, the injection of core concrete improves the stress performance of the pile foundation group, which can ensure the compressive performance of the pile foundation group while improving its resistance to water flow impact loads, thereby ensuring the integrity and effectiveness of the wharf structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0037] Figure 1 A schematic diagram of the high-pile wharf structure provided by the present invention;
[0038] Figure 2 A top view of the high-pile wharf provided by the present invention;
[0039] Figure 3 for Figure 2 AA longitudinal section diagram in;
[0040] Figure 4 for Figure 2 Schematic diagram of BB longitudinal section;
[0041] Figure 5 for Figure 2 Schematic diagram of CC longitudinal section;
[0042] Figure 6 for Figure 2 DD cross-section diagram in FIG.
[0043] Figure 7 for Figure 2 EE cross-section diagram in FIG.
[0044] Figure 8 A cross-sectional view of a pile cap provided by the present invention;
[0045] Fig. 9 A top view of the pile cap provided by the present invention.
[0046] in,
[0047] 1-pile foundation group; 11-rebar cage; 12-core concrete; 2-pile cap; 21-cover plate; 22-casing; 23-step surface; 24-casting hole; 3-precast longitudinal beam; 4-precast cross beam; 5-cast-in-place joint plate; 6-precast plate; 61-first precast plate; 62-second precast plate; 7-cast-in-place bridge deck; 8-precast connecting beam. DETAILED DESCRIPTION
[0048] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0049] In the description of the present invention, it should be understood that the terms "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0050] In the description of the present invention, “plurality” means two or more than two, unless otherwise clearly and specifically defined.
[0051] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or a welding connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0052] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0053] Embodiment 1:
[0054] See attached Figures 1 to 9 The embodiment of the present invention discloses a high-pile wharf structure for LNG loading and unloading, comprising:
[0055] Pile foundation group 1, the pile foundation group 1 comprises a plurality of pipe piles arranged in rows both longitudinally and transversely, the bottom ends of the plurality of pipe piles being inserted into the seabed bearing layer, and the top ends being exposed above the water surface;
[0056] Pile caps 2, where a plurality of pile caps 2 are buckled on the tops of a plurality of pipe piles one by one, and a through hole corresponding to the inner cavity of the pipe pile is opened on the pile caps 2 to pour core concrete 12 into the pipe piles;
[0057] Frame beams, there are multiple frame beams, and the multiple frame beams form a high-pile wharf frame, and the bottom surface of the beam end of the frame beam abuts against the top surfaces of two adjacent pile caps 2; there is a casting gap between the two opposite end surfaces of the two adjacent frame beams;
[0058] A cast-in-place joint plate 5, which is arranged in the casting gap to engage with the frame beam and connect the plurality of frame beams into a whole;
[0059] Prefabricated panels 6, which are multiple and laid on the top surface of the frame beam;
[0060] The cast-in-place bridge deck 7 is cast on the top surface of the high-pile wharf frame to cover a plurality of precast panels 6 .
[0061] In this embodiment, there are 5 longitudinal pipe piles and 5 transverse pipe piles, and the wharf frame foundation is arranged in a five-column and five-row form. Figure 1 and 4 As shown; the high-pile wharf uses pipe piles as the supporting foundation, the top surface of the pipe piles is covered with pile caps, and the core concrete is poured into the pipe piles through the pouring holes of the pile caps; the top surfaces of two adjacent pile caps are overlapped with frame beams, and the beams are connected by cast-in-place joint plates, and the cast-in-place joint plates are consolidated with the core concrete; precast panels are laid on the top surface of the frame beams, every six pipe piles form a frame unit, and multiple precast panels are laid in one frame unit, and there is a gap between the side end surfaces of the precast panels corresponding to two adjacent frame units, and cast-in-place bridge deck concrete is poured on the top surface of the frame beam, the gap between two adjacent frame units and the top surface of the precast panels. After the pouring is completed, the precast panels, frame beams, cast-in-place joint plates, pipe piles and cast-in-place bridge decks form an integrated stable high-pile wharf structure.
[0062] In this embodiment, the pile cap 2 is a prefabricated component, including a cover plate 21 and a sleeve 22 fixed to the bottom surface of the cover plate 21. A perfusion hole 24 connected to the inner cavity of the sleeve 22 is opened on the top surface of the cover plate 21. The hole diameter of the perfusion hole 24 is smaller than the inner diameter of the sleeve 22 so that a step surface 23 is formed between the inner wall of the cover plate 21 and the inner wall of the sleeve 22. The pile cap 2 is sleeved on the outer wall of the top end of the pipe pile and the top end surface of the pipe pile abuts against the step surface 23.
[0063] like Figure 8 and 9 As shown, the pile cap is a prefabricated pile cap, which can be prefabricated in the factory in advance. When the pipe pile is inserted and driven, the pile cap can be directly installed, which saves the production time of the pile cap. The pile cap can be directly located on the top of the pipe pile, and is sleeved on the outer periphery of the pipe pile through a casing. The cover plate is covered on the top surface of the pipe pile. A step surface is cleverly formed between the casing and the cover plate, which can adapt to the cross-sectional form of the pipe pile and firmly clamp it in the pile cap. The core concrete can be poured into the inner cavity of the pipe pile through the pouring hole of the cover plate. Compared with the traditional construction method, the construction efficiency is greatly improved and the investment in resources and equipment is reduced.
[0064] In order to further optimize the above technical solution and improve the rigidity and load-bearing capacity of the upper part of the pipe pile, a steel cage 11 is also included. A support plate is fixed at the bottom end of the steel cage 11 and inserted into the inner cavity of the pipe pile. The top end of the steel cage 11 exposes the pile cap 2 and is anchored in the concrete of the cast-in-place joint plate 5 and the cast-in-place bridge deck 7. The support plate is a circular plate and is adapted to the inner diameter of the pipe pile; during installation, the steel cage is vertically lowered into the inner cavity of the pipe pile to a predetermined position. The circular support plate is stuck on the inner wall of the pipe pile to prevent the core concrete from leaking into the lower part of the pipe pile; the top end of the steel cage exposes the pile cap and is anchored in the panels of the cast-in-place joint plate and the cast-in-place bridge deck, respectively, so that the cast-in-place part is consolidated with the pipe pile into a whole, and the cast-in-place part is consolidated with the prefabricated part, ensuring that the formed wharf is a complete and stable steel-concrete composite structure.
[0065] In order to further optimize the above technical solution, according to the characteristics of the superstructure, the distribution of the pipe piles and the friction resistance of the seabed bearing layer, the height of the core concrete at the top of the pipe piles is between 4.7m and 9.3m.
[0066] In this embodiment, the frame beam includes precast longitudinal beams 3 and precast transverse beams 4; the precast longitudinal beams 3 are arranged on both sides of the high-pile wharf frame in the longitudinal direction, and the precast transverse beams 4 are arranged in the transverse direction of the high-pile wharf frame; the beam ends of the precast longitudinal beams 3 and the precast transverse beams 4 are respectively overlapped with the top surfaces of the two adjacent pile caps 2 corresponding to them, and the two opposite end surfaces of the two adjacent precast longitudinal beams 3 and the two adjacent precast transverse beams 4 form a casting gap corresponding to the inner cavity of the pipe pile, and a cast-in-place joint plate 5 is cast in the casting gap.
[0067] The frame beam also includes a precast connecting beam 8, the length direction of which is parallel to the length direction of the precast longitudinal beam 3, and the precast connecting beam 8 is arranged in the middle of the pile foundation group 1 to longitudinally divide the high-pile wharf frame into a first frame unit and a second frame unit; there are multiple precast connecting beams 8, and the bottom surfaces at both ends of the multiple precast connecting beams 8 are respectively abutted against the top surfaces of the two adjacent pile caps 2 corresponding thereto, and cast-in-place joint plates 5 are cast on the opposite end surfaces of the two adjacent precast connecting beams 8 and the top ends of the corresponding pile caps 2.
[0068] like Figure 2 As shown, the pile group has five rows in the longitudinal direction and five rows in the transverse direction. The prefabricated cross beams are arranged in five rows. The prefabricated cross beams in each row are disconnected at the pile cap to form a gap that is connected to the grouting hole. There are two rows of prefabricated longitudinal beams, which are arranged on both sides of the pile group in the longitudinal direction (see Appendix). Figure 2 In the upper and lower directions of the middle, a row of precast coupling beams are arranged in the middle of the longitudinal direction of the pile foundation group; cast-in-place joint plates are cast between two adjacent precast longitudinal beams, between two adjacent precast transverse beams, between two adjacent precast coupling beams, between the connection nodes of the precast transverse beams and the precast longitudinal beams, and between the connection nodes of the precast transverse beams and the precast coupling beams.
[0069] In order to further optimize the above technical solution and improve the bonding performance between the cast-in-place joint plate and the frame beam, slots are provided on both end faces of the precast longitudinal beam 3, the precast cross beam 4 and the precast connecting beam 8, and the cast-in-place joint plate 5 is formed with plugs adapted to the slots, and the cast-in-place joint plate 5 is engaged with the precast longitudinal beam 3 or the precast cross beam 4 or the precast connecting beam 8 through the plugs and the slots. The engagement performance between the cast-in-place joint plate and the frame beam can be improved by means of the plugs and the slots, ensuring that the frame beam, the cast-in-place joint plate and the pipe pile form an integral stable structure.
[0070] In order to further optimize the above technical solution, the prefabricated panel 6 includes a first prefabricated panel 61 and a second prefabricated panel 62; the first prefabricated panel 61 is laid on the first frame unit, and the second prefabricated panel 62 is laid on the second frame unit.
[0071] As shown in the figure, every six pipe piles form a group as a unit. Each unit frame includes four precast cross beams, one precast longitudinal beam and one precast connecting beam. The length direction of the precast slab is parallel to the length direction of the precast longitudinal beam. Four precast slabs are laid in each unit frame. There is a gap between the precast slabs of two adjacent unit frames for pouring cast-in-place bridge decks.
[0072] In order to further optimize the above technical solution, the thickness of the first prefabricated panel 61 is smaller than the thickness of the second prefabricated panel 62 , and a dome is formed on the bottom surface of the second prefabricated panel 62 .
[0073] like Figure 1 , 6 As described in 7, the precast slab is divided into two parts, with the precast connecting beam as the axis. The first frame unit is laid with the first precast slab, which is a flat plate with a thickness of 375 mm; the first frame unit is laid with the second precast slab with a thickness of 700 mm. In order to reduce the material consumption of the second precast slab, a dome is formed on the bottom surface of the second precast slab, and the cast-in-place bridge deck covers the first precast slab and the second precast slab. At this time, the lower cast-in-place bridge deck forms a step shape on the bottom surface due to the height difference between the first precast slab and the second precast slab, which improves the covering effect of the first precast slab and the second precast slab, and effectively ensures the overall performance between the cast-in-place bridge deck and the precast slab.
[0074] In order to further optimize the above technical solution and ensure that the wharf foundation has sufficient strength, the diameter of the pipe piles shall not be less than 1.4m, and the center distance between two adjacent pipe piles shall not be greater than 6m.
[0075] In order to further optimize the above technical solution and ensure effective bonding and fixation between the frame beam and the cast-in-place joint plate, the thickness of the cast-in-place joint plate 5 is the same as the height of the frame beam.
[0076] Embodiment 2:
[0077] The embodiment of the present invention discloses a method for constructing a high-pile wharf for LNG loading and unloading, which is constructed by using a high-pile wharf structure for LNG loading and unloading in Example 1, and includes the following steps:
[0078] S1, pile foundation construction, inserting the pipe drill into the seabed bearing layer through the pile driver;
[0079] The pipe piles are driven vertically into the seabed bearing layer at the installation design point, and the steel pipe joints of each pipe pile are fully welded to ensure the verticality of the pipe piles;
[0080] S2, putting the pile cap on the top of the pipe pile and pouring the core concrete;
[0081] After the pile foundation group is constructed, measure the pile top elevation, and if it is qualified, snap the pile cap onto the top of the pipe pile;
[0082] Install the steel cage inside the pile, the support plate is in contact with the inner wall of the pile, the steel cage is fixed to the inner wall of the top of the pile by welding with supporting bars, the steel cage is fastened by hanging, the top elevation of the steel cage is monitored by surveyors, after the steel cage is fixed, pour the core concrete into the pile through the pouring hole; the top surface of the core concrete is flush with the top surface of the pile cap;
[0083] S3, installing frame beams, each frame beam is overlapped with the top surfaces of two adjacent pile caps;
[0084] Install the precast longitudinal beams, precast cross beams and precast connecting beams in sequence. It should be noted that the lap length between the beam and the pile cap should not be less than 35cm;
[0085] S4, pouring cast-in-place joint plate;
[0086] Check the installation quality of the frame beam to ensure that the bottom surface of the frame beam is in contact with the top surface of the pile cap. Roughen the top surface of the core concrete to improve the bonding performance between the core concrete and the cast-in-place joint plate. Install the formwork and cast the cast-in-place joint plate.
[0087] S5. Lay precast slabs and cast in-situ bridge deck.
[0088] Precast slabs are laid at the designed installation position on the top surface of the frame beam. It should be noted that the difference between the top surface elevation of the steel cage in the pipe pile and the top surface elevation of the cast-in-place bridge deck is only the thickness of the steel protection layer of the cast-in-place bridge deck; the formwork is installed and the cast-in-place bridge deck is cast, and the cast-in-place bridge deck completely covers the precast slabs and the steel cage.
[0089] The high-pile wharf provided by the present invention uses pipe piles as the lower supporting foundation of the wharf, and the upper structure of the wharf adopts a prefabrication + cast-in-place joint method, so the construction is efficient and fast and the production cost is low.
[0090] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.
[0091] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A high-pile wharf structure for LNG loading and unloading, characterized in that: include: A pile foundation group (1), the pile foundation group (1) comprising a plurality of pipe piles arranged in rows both longitudinally and transversely, the bottom ends of the plurality of pipe piles being inserted into a seabed bearing layer and the top ends being exposed above the water surface; Pile caps (2), wherein a plurality of the pile caps (2) are buckled on the top ends of a plurality of the pipe piles in a one-to-one correspondence, and the pile caps (2) are provided with through holes correspondingly connected to the inner cavities of the pipe piles so as to pour core concrete (12) into the pipe piles; A frame beam, wherein a plurality of frame beams are provided, and the plurality of frame beams form a high-pile wharf frame, wherein the bottom surface of the beam end of the frame beam abuts against the top surfaces of two adjacent pile caps (2); and a casting gap is provided between the opposite end surfaces of two adjacent frame beams; A cast-in-place joint plate (5), the cast-in-place joint plate (5) being arranged in the casting gap to engage with the frame beam and connect a plurality of the frame beams into a whole; Prefabricated panels (6), the prefabricated panels (6) being multiple pieces and laid on the top surface of the frame beam; A cast-in-place bridge deck (7) is cast on the top surface of the high-pile wharf frame to cover the plurality of prefabricated panels (6).
2. A high-pile wharf structure for LNG loading and unloading according to claim 1, characterized in that: The pile cap (2) is a prefabricated component, comprising a cover plate (21) and a sleeve (22) fixed to the bottom surface of the cover plate (21); a perfusion hole (24) communicating with the inner cavity of the sleeve (22) is provided on the top surface of the cover plate (21); the diameter of the perfusion hole (24) is smaller than the inner diameter of the sleeve (22) so that a step surface (23) is formed between the inner wall of the cover plate (21) and the inner wall of the sleeve (22); the pile cap (2) is sleeved on the outer wall of the top end of the pipe pile and the top end surface of the pipe pile abuts against the step surface (23).
3. A high-pile wharf structure for LNG loading and unloading according to claim 2, characterized in that: It also comprises a steel cage (11), the bottom end of which is fixed with a support plate and inserted into the inner cavity of the pipe pile, and the top end of which is exposed from the pile cap (2) and anchored in the concrete of the cast-in-place joint plate (5) and the cast-in-place bridge deck (7).
4. The high-pile wharf structure for LNG loading and unloading according to claim 1, characterized in that: The frame beam comprises a prefabricated longitudinal beam (3) and a prefabricated transverse beam (4); the prefabricated longitudinal beam (3) is arranged on both sides of the high-pile wharf frame in the longitudinal direction, and the prefabricated transverse beam (4) is arranged in the transverse direction of the high-pile wharf frame; the beam ends of the prefabricated longitudinal beam (3) and the prefabricated transverse beam (4) are respectively overlapped with the top surfaces of two adjacent pile caps (2) corresponding thereto, and the opposite end surfaces of the two adjacent prefabricated longitudinal beams (3) and the two adjacent prefabricated transverse beams (4) form a casting gap corresponding to the inner cavity of the pipe pile, and the cast-in-place joint plate (5) is cast in the casting gap.
5. A high-pile wharf structure for LNG loading and unloading according to claim 4, characterized in that: The frame beam further comprises a prefabricated connecting beam (8), the length direction of the prefabricated connecting beam (8) being arranged parallel to the length direction of the prefabricated longitudinal beam (3), and the prefabricated connecting beam (8) being arranged in the middle of the pile foundation group (1) to longitudinally separate the high-pile wharf frame into a first frame unit and a second frame unit; a plurality of prefabricated connecting beams (8) are provided, and the bottom surfaces at both ends of the plurality of prefabricated connecting beams (8) are respectively abutted against the top surfaces of the two adjacent pile caps (2) corresponding thereto, and the cast-in-place joint plates (5) are cast on the opposite end surfaces of the two adjacent prefabricated connecting beams (8) and corresponding to the top ends of the pile caps (2); Wherein, both end surfaces of the prefabricated longitudinal beam (3), the prefabricated transverse beam (4) and the prefabricated connecting beam (8) are provided with slots, the cast-in-place joint plate (5) is formed with plugs adapted to the slots, and the cast-in-place joint plate (5) is engaged with the prefabricated longitudinal beam (3) or the prefabricated transverse beam (4) or the prefabricated connecting beam (8) through the plugs and the slots.
6. A high-pile wharf structure for LNG loading and unloading according to claim 5, characterized in that: The prefabricated panel (6) comprises a first prefabricated panel (61) and a second prefabricated panel (62); the first prefabricated panel (61) is laid on the first frame unit, and the second prefabricated panel (62) is laid on the second frame unit.
7. A high-pile wharf structure for LNG loading and unloading according to claim 6, characterized in that: The thickness of the first prefabricated plate (61) is smaller than the thickness of the second prefabricated plate (62), and a dome is formed on the bottom surface of the second prefabricated plate (62).
8. The high-pile wharf structure for LNG loading and unloading according to claim 1, characterized in that: The diameter of the pipe pile is not less than 1.4m, and the center distance between two adjacent pipe piles is not more than 6m.
9. The high-pile wharf structure for LNG loading and unloading according to claim 1, characterized in that: The thickness of the cast-in-place joint plate (5) is the same as the height of the frame beam.
10. A method for constructing a high-pile wharf for LNG loading and unloading, using a high-pile wharf structure for LNG loading and unloading according to any one of claims 1 to 9 for construction, comprising the following steps: S1, pile foundation construction, inserting the pipe drill into the seabed bearing layer through the pile driver; S2, putting the pile cap on the top of the pipe pile and pouring the core concrete; S3, installing frame beams, each frame beam is overlapped with the top surfaces of two adjacent pile caps; S4, pouring cast-in-place joint plate; S5. Lay precast slabs and cast in-situ bridge deck.
Citation Information
Patent Citations
Fabricated pile foundation wharf structure and construction method thereof
CN107975059A
Standardized fabricated pile foundation wharf structure and building method thereof
CN108797513A
Plate-girder prefabricated high-pile wharf structure
CN111778921A
Structural form for consolidation of bridge pier beam of steel plate composite beam
CN117552316A
Novel assembly type high pile beam plate type wharf structure
CN211849244U
Cited By
Fabricated full straight pile wharf structure and construction method thereof
CN120649410A
Prefabricated wharf and construction method therefor
NL2040883A