Large-section tunnel four-part CRD method mechanical excavation construction technology
By adopting four-part CRD mechanical excavation process in large-section tunnel construction, combined with laser pointing devices and improved support technology, the accuracy, cost and environmental problems in the construction of large-span weak surrounding rock tunnels are solved, and fast and safe are achieved , economical construction effect.
Patent Information
- Application Number
- CN202411249396.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2024-11-12
AI Technical Summary
In the construction of large-span, weak surrounding rock tunnels, the existing CRD construction technology has problems such as difficulty in controlling excavation accuracy, imperfect support system, high cost, long construction period and great environmental impact, especially when crossing existing municipal roads underneath. Especially prominent.
The mechanical excavation construction technology of four-part CRD method of large-section tunnel is adopted. By installing laser pointing devices on the tunnel arch top, the support scheme is improved, and cement slurry is injected with steel pipe openings to improve the stability of surrounding rock , and simplify equipment requirements to reduce costs and construction periods, while controlling dust generation to reduce environmental impacts.
It improves excavation accuracy and surrounding rock stability, reduces costs and construction periods, reduces environmental pollution, realizes rapid, safe and economical construction, and adapts to various construction needs of underpass municipal roads.
Smart Images

Figure CN118933896A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel construction, and in particular to a mechanical excavation construction process for a large-section tunnel using a four-part CRD method. Background Art
[0002] In the field of tunnel engineering, the construction of large-span, soft-rock tunnels has always been an important and challenging topic. Traditional construction methods often have some shortcomings when facing such situations, such as unsatisfactory support effects, difficult to control construction quality, high costs, and greater impact on the environment.
[0003] At present, there are many tunnel construction methods at home and abroad, but in the construction of large-span tunnels with soft surrounding rocks, continuous exploration and improvement are still needed to adapt to complex engineering conditions. The CRD method, as a construction method of partial excavation, steel frame support, and invert first, plays an important role in the construction of large-span tunnels with soft surrounding rocks.
[0004] However, the existing CRD construction technology also has some aspects that need to be improved in practical applications, such as the control of excavation accuracy, the improvement of the support system, the optimization of cost and construction period, and environmental protection during the construction process. In particular, the CRD construction process in the existing technical solution includes two steps: earth excavation and support, and the cross-section (profile, model) of the tunnel remains unchanged throughout the whole process, and the tunnel operation space is relatively small. In order to better solve the above problems and improve the construction quality and efficiency of large-section tunnels passing under existing municipal road tunnels, the present invention comes into being.
[0005] The four-part CRD method mechanical excavation construction process for large-section tunnels involved in the present invention is a number of innovations and improvements made on the basis of existing technologies in combination with actual engineering experience. By installing a laser pointing device at the tunnel arch position, accurate positioning and control of the excavation contour are achieved, effectively improving the over-excavation and under-excavation accuracy and reducing costs. The tunnel support scheme is improved, and the surrounding rock stability and bearing capacity are improved by using technologies such as steel pipe openings and cement slurry injection, while better diffusing and transmitting the load during the excavation process.
[0006] In terms of cost and construction period, the application of milling machines simplifies equipment requirements, reduces purchase and maintenance costs, reduces rework through effective control of over-excavation and under-excavation, achieves cost savings and shortens construction period. In terms of environmental protection, the use of CRD method mechanical construction combined with relevant measures effectively controls dust generation and reduces the impact on the environment.
[0007] The construction process of the present invention has been put into practice and innovatively optimized in the Caijiaguan No. 1 Tunnel Project of the Taijin Line Road Project in Nanming District of the company, showing significant advantages. It is of great significance to improve the construction of large-section tunnels passing under existing municipal road tunnels. Compared with other technologies at home and abroad, the present invention has made improvements and innovations in excavation construction technology and support system technology, and can better adapt to various construction needs of passing under municipal road tunnels, and has broad application prospects. Summary of the invention
[0008] In order to solve the above-mentioned shortcomings and deficiencies, the present invention provides a large-section tunnel four-part CRD method mechanical excavation construction process, which ensures the rapidity, safety and economy of construction and solves the control problem of over-excavation and under-excavation.
[0009] In order to solve the above problems, the technical solution adopted by the invention is: a large-section tunnel four-part CRD method mechanical excavation construction process, which is characterized by comprising the following steps:
[0010] S100 determines the location of the tunnel face based on tunnel design parameters and geological conditions, and performs pre-construction preparations;
[0011] S200 sets up tunnel body advance pipe shed around the tunnel arch face. The advance pipe shed is set perpendicular to the tunnel face. The construction of tunnel body advance pipe shed includes the following steps:
[0012] S210 uses hot-rolled seamless steel pipes in the construction of the advanced pipe shed in the tunnel body, and the length of the pipe shed is arranged according to the preset rules; the connection of the pipe shed is made by threaded connection with steel pipe connecting sleeves;
[0013] S220 sets a steel cage inside the steel pipe, which includes four main bars and a fixing ring, and the fixing ring is welded to the main bars;
[0014] S230 has grouting holes on the pipe-roof steel pipe, and a grouting stop section without drilling holes is set at the tail of the pipe-roof steel pipe;
[0015] After the construction of S240 pipe shed is completed, before pouring the secondary lining, spray concrete is used to compact the excavation contour surface, and a single layer of steel mesh is used to reinforce the top of the local pipe shed;
[0016] After the construction of S250 pipe shed is completed, grouting will begin. Before grouting, stoppers will be installed on all holes, and the pipe openings and hole openings will be sealed.
[0017] S300 advance small conduit construction, according to the design requirements, accurately place the small conduit on the tunnel face, use drilling equipment to drill holes at the marked positions, the drilling angle is set with an external insertion angle, and the processed advance small conduit is inserted into the drilled hole. The advance small conduit is a hot-rolled seamless steel pipe with grouting holes set on it;
[0018] S400 face advance reinforcement, the whole section is reinforced, PVC pipe is used for reinforcement, and cement slurry or cement water glass double liquid slurry is used for pouring, and finally cement mortar is poured;
[0019] S500 divides the tunnel section of the face into four parts through vertical and horizontal segmentation, namely Part I, Part II, Part III and Part IV;
[0020] S600 face excavation and construction includes the following steps:
[0021] S610 excavates the I part by means of a milling machine, the excavation depth is not greater than the length of the advance small guide tube, and provides initial support and temporary support for the upper section of the hole;
[0022] The specific steps of initial support and temporary support are as follows: determine the position and spacing of anchor rods according to design requirements, use a drilling rig to drill holes in the surrounding rock, insert the anchor rods into the holes, and anchor them with anchoring agents; then install the steel arch frame to ensure that its position is accurate and the connection is firm, connect the steel arch frames with connecting steel bars, lay the steel mesh on the surrounding rock surface according to design requirements, ensure that the steel mesh is firmly connected to the anchor rods and steel arch frames, debug the shotcrete equipment, mix the cement, sand, gravel, admixtures and other materials evenly according to the designed mix ratio, use a sprayer to spray concrete onto the surrounding rock surface, and spray from bottom to top, first the wall and then the arch.
[0023] S620 excavated Section III and provided initial support and temporary support to the section below the tunnel;
[0024] S630 excavated the II section and provided initial support and temporary support for the upper section of the tunnel;
[0025] S640 excavated Section IV and provided initial and temporary support for the section below the tunnel;
[0026] The temporary support and initial support in the above steps are consistent with the initial support and temporary support in S610.
[0027] S650 support monitoring quantity detection;
[0028] S660 removes temporary supports after the support monitoring measurement value is stable, and casts the invert, then lays the waterproof layer and forms the secondary lining as a whole;
[0029] After laying the waterproof layer of S700, back grouting is carried out at the integral mold construction position of the secondary lining, and grouting pipes are reserved during construction.
[0030] The beneficial effects of this program are:
[0031] The advanced pipe shed and the advanced small guide tube are used in combination. A drilling rig is used to drill holes around the tunnel arch, and the steel pipe is inserted into the drill hole and fixed by grouting and other methods. Cement slurry and other materials are injected into the surrounding surrounding rock through the steel pipe to make the steel pipe tightly combined with the surrounding rock. The advanced pipe shed can support and stabilize the surrounding rock in a large range, prevent large-scale collapse and deformation of the surrounding rock, and provide a more macroscopic stable environment for subsequent construction. The advanced small guide tube can supplement and reinforce the weak links of the pipe shed support, penetrate into smaller gaps and weak areas, and enhance local stability. The combination of the two with pre-grouting can make the slurry fully fill the gaps and cracks in the surrounding rock, further improve the integrity and strength of the surrounding rock, and effectively curb the infiltration of groundwater and the influence of adverse geology. Cement slurry and other materials can be injected into the surrounding rock through the steel pipe opening to improve the stability of the surrounding rock structure, and the steel pipe deep inside the rock mass can effectively withstand changes in the rock structure. The stress load generated later greatly improves the stability and safety of the tunnel engineering structure. The application of pipe-roof advance support technology can diffuse and transmit all the loads released outward by the rock mass during excavation. Therefore, in the specific excavation process, the load borne by the steel pipe in the tunnel rock can be diffused in all directions, which can effectively prevent the occurrence rate of vault settlement, greatly improve the strength of the surrounding rock in the tunnel engineering, and effectively avoid the probability of safety accidents such as tunnel collapse. The four-step CRD method is used for excavation. Each step of the excavation is closed into a loop, which has the advantages of the step method and the double-side wall pilot pit method. The settlement and deformation of the surrounding rock are strictly controlled, which is beneficial to the stability of the surrounding rock and ensures the safety of construction. The construction is more convenient, the excavation quality is better, and the process connection is more scientific and reasonable. While shortening the construction period, costs are saved; while avoiding a large amount of waste and abandonment of materials; environmental problems such as noise, air and water resources caused by construction are easier to control.
[0032] Furthermore, in step 210, hot-rolled seamless steel pipes and steel pipes are used, with an outer diameter of 108mm, a wall thickness of 6mm, a pipe shed length of 18m per ring, and a lap length between two rings and with the next type of advanced support measures of not less than 3m. The circumferential spacing of the steel pipes is 30cm, and the external insertion angle is not greater than 2-3°. Steel pipes of this specification can provide sufficient strength and stability to meet the construction needs of large-section tunnels. At the same time, the length of the pipe shed can ensure an effective support range while taking into account construction efficiency. The circumferential spacing can ensure the uniformity and tightness of the support and improve the support effect. The appropriate external insertion angle can ensure the accuracy and stability of the pipe shed installation, better combine with the surrounding rock, and play a good reinforcement role.
[0033] Furthermore, in the step S230, grouting holes are drilled with a hole diameter of Φ6mm and a hole spacing of 150×150mm in a plum blossom shape. A 300mm grouting stop section is left at the tail without drilling a hole, which can ensure the smooth outflow of the slurry and have a certain diffusion effect. Reasonable hole spacing can make the slurry evenly distributed, ensuring the comprehensive reinforcement of the surrounding rock around the pipe roof. The plum blossom shape arrangement further enhances the uniformity and integrity of the reinforcement. The grouting stop section at the tail can effectively prevent the slurry from flowing back, ensure the grouting pressure, improve the grouting efficiency and quality, and reduce slurry waste.
[0034] Furthermore, in the step S250, the order of pipe shed grouting (cement slurry water-cement ratio 1:1) in principle follows the principles of "drill one and grout one" and "from thin to thick". Grouting begins after the pipe shed construction is completed. The "drill one and grout one" order principle can ensure that each pipe shed can be grouted in time, avoiding omissions and delays in the construction process, improving construction efficiency while ensuring the timeliness and integrity of grouting. Following the principle of "from thin to thick", the gaps in the surrounding rock can be better filled in the early stage, allowing the slurry to fully penetrate and diffuse. As the concentration gradually increases, the strength and stability of the slurry can be gradually improved, and the reinforcement effect on the surrounding rock can be better achieved.
[0035] Furthermore, in the step S250, the grouting adopts dual control measures of the final grouting pressure and the grouting amount. The initial pressure is preferably 0.5-1.0MPa, and the final pressure is preferably controlled at 1.0MPa. The grouting is stopped after the pressure is maintained for 3-5mm. It is more appropriate to set the initial pressure at 0.5-1.0MPa, so that the slurry has a certain initial driving force when it starts to be injected, and can smoothly enter the surrounding rock gaps. The final pressure is controlled at 1.0MPa to ensure that the slurry fully fills and reinforces the surrounding rock under a reasonable pressure, so that the reinforcement effect reaches a high level. Stopping the grouting after the pressure is maintained for 3-5mm can ensure that the slurry is fully solidified and stable, and avoid problems such as inaccurate grouting caused by a sudden drop in pressure.
[0036] Furthermore, in the step S400, the soil after the face reinforcement should be tested. The 28-day unconfined compressive strength qu≥0.8Mpa and the permeability coefficient ≤10-7cm / sec can be carried out before the next process can be carried out, which is conducive to ensuring that the reinforced soil has sufficient strength to withstand various forces in the subsequent construction process, prevent soil collapse, deformation and other problems, and ensure the safety of construction personnel and equipment. Limiting the permeability coefficient to ≤10-7cm / sec can effectively control the permeability of the soil, avoid the adverse effects of groundwater, reduce the risks of seepage and water gushing, maintain the stability of the construction environment, and ensure the smooth progress of construction.
[0037] Furthermore, in the step S400, the water-cement ratio of the cement slurry is 1:1, and the grouting pressure is 0.5-1.0 MPa. For cement-water glass double slurry, the water-cement ratio of the cement slurry is 1:1, the volume ratio of cement slurry to water glass is 1:0.5, the water glass modulus is preferably 2.4-3.4, the concentration is 30-45 degrees Baume, and the grouting pressure is 0.5-1.0 MPa.
[0038] Furthermore, in S600, the excavation depth is not greater than the length of the small pipe in advance. When the excavation depth is not greater than its length, the small pipe can fully play its supporting and reinforcing role to ensure the stability of the soil in front. During the excavation process, it can effectively prevent the occurrence of accidents such as soil collapse and falling blocks, and provide a relatively safe working environment for construction personnel.
[0039] Furthermore, the grouting holes in the S300 are arranged in a plum blossom shape, the front end of the small conduit should be processed into a cone head, and the tail of the small conduit ahead of the small conduit is welded to the I-beam. The grouting holes arranged in a plum blossom shape can make the slurry spread more evenly around the small conduit. Under the action of the grouting pressure, the slurry can penetrate into the soil from all directions, improve the uniformity of the reinforcement effect, and avoid the situation of insufficient or excessive local reinforcement. The tail of the small conduit is welded to the I-beam, so that the small conduit and the I-beam can form an integral support structure. The I-beam has high strength and rigidity, and can withstand large soil pressure and external loads, thereby enhancing the stability of the entire support system. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] Figure 1 Schematic diagram of the long pipe shed + small advance guide tube structure in the tunnel section;
[0041] Figure 2 Schematic diagram of the longitudinal arrangement of the long pipe shed + advanced small guide tube in the tunnel section;
[0042] Figure 3 Schematic diagram of the tunnel face;
[0043] Figure 4 Schematic diagram of four CRD excavation;
[0044] Figure 5 This is a schematic diagram of the pipe shed;
[0045] Figure 6 This is a diagram showing the arrangement of observation points of the present invention. DETAILED DESCRIPTION
[0046] The following is further described in detail through specific implementation methods:
[0047] The figure marks in the drawings of the specification include: seamless steel pipe 1, advance small conduit 2, I-beam 3, primary sprayed concrete layer 4, secondary sprayed concrete layer 5, secondary lining integral mold 6, grouting hole 7, PVC pipe 8, heading face 9, part I 10, part II 11, part III 12, part IV 13, steel cage 14, advance pipe shed 15, observation point 16.
[0048] Attached Figure 1 To Attachment Figure 6 As shown in the figure, the four-part CRD mechanical excavation construction process for large-section tunnels includes the following steps:
[0049] S100 determines the location of the tunnel face 9 according to the tunnel design parameters and geological conditions, and performs pre-construction preparations;
[0050] S200, an advance pipe shed 15 for the tunnel body is arranged around the tunnel face 9 of the arch portion, the advance pipe shed 15 is composed of a plurality of seamless steel pipes 1, and the advance pipe shed 15 is arranged perpendicular to the tunnel face 9. The construction of the advance pipe shed 15 for the tunnel body includes the following steps:
[0051] S210, accurately placing the position of the advance pipe shed 15 on the tunnel face 9 of the tunnel arch according to the design drawings, determining the drilling angle of the advance pipe shed 15 with a measuring instrument, and ensuring that the advance pipe shed 15 is perpendicular to the tunnel face 9;
[0052] S220 installs the drilling equipment, adjusts the drilling angle and position, starts drilling, controls the drilling speed and pressure, ensures the verticality and accuracy of the drilling, pays attention to the geological conditions during the drilling process, stops drilling in time if any abnormal situation occurs, and takes corresponding measures, and cleans the hole after the drilling reaches the designed depth to remove the rock cuttings and debris in the hole.
[0053] During the initial support process of S230, hot-rolled seamless steel pipe 1 is used in the construction of the advanced pipe shed 15 of the tunnel body, and the outer diameter of the seamless steel pipe 1 is 108mm, the wall thickness is 6mm, the length of the advanced pipe shed 15 is set according to 18m, and the lap length of the advanced pipe shed 15 is not less than 3m. On the cross section of the tunnel, the distance between the centers of two adjacent steel pipes is 30cm, and the angle between the advanced pipe shed 15 and the longitudinal axis of the tunnel is not more than 2-3°;
[0054] S240 sets a steel cage 14 in the seamless steel pipe 1. The steel cage 14 consists of four main bars and a fixing ring. The diameter of the main bar is HRB400Φ20mm. The fixing ring is a stirrup of HPB300Φ10mm, which is welded to the main bar and arranged at a spacing of 0.5m. Grouting holes 7 are drilled on the seamless steel pipe 1 on the leading pipe shed 15. The hole diameter is Φ6mm and the hole spacing is 150×150mm. They are arranged in a plum blossom shape. A grouting stop section of 300mm is left at the tail without drilling holes. The leading pipe shed 1 5 is connected by a Φ121*9mm seamless steel pipe 1 connection sleeve for threaded connection. Both ends of each section of the advanced pipe shed 15 are pre-processed into external threads, but the number of joints in the same section shall not exceed 50% of the total number of steel pipes. A steel cage 14 is used in the advanced pipe shed 15 to increase the rigidity of the advanced pipe shed 15. The main reinforcement diameter of the steel cage 14 is HRB400Φ20mm, and the fixing ring is a stirrup of HPB300Φ10mm, which is welded to the main reinforcement and arranged at a spacing of 0.5m;
[0055] After the construction of S250 advanced pipe shed 15 is completed, before pouring the secondary lining, C30 shotcrete is used to spray and compact the excavation contour surface, and I22b+HPB300Φ8mm single-layer steel mesh is used to strengthen the local advanced pipe shed 15 top-in. The advanced pipe shed 15 must be drilled strictly according to the designed position, and the direction and angle of the advanced pipe shed 15 must be strictly controlled, and the geological records of each drilling hole must be kept; the external insertion angle of the advanced pipe shed 15 should be minimized as much as possible, so that the advanced pipe shed 15 passes through the middle of the steel arch frame, and the tail of the seamless steel pipe 1 is welded to the arch frame;
[0056] S260 drills grouting holes on the seamless steel pipe 1 of the advanced pipe shed 15, and a stop grouting section without drilling holes is set at the tail of the seamless steel pipe 1. The grouting sequence of the advanced pipe shed 15 (cement slurry water-cement ratio 1:1) follows the principle of "drill one and inject one" and "from thin to thick". Grouting begins after the construction of the advanced pipe shed 15 is completed. Before grouting, stop grouting plugs are installed on all holes, and the pipe mouth and the hole side are sealed. The grouting is injected from the hole once. In order to make the slurry in the pipe full and dense, the exhaust hole has an inlet when grouting. When the same slurry flows out, final pressure grouting is carried out. Dual control measures of final pressure and grouting volume are adopted for grouting. The initial pressure is 0.5-1.0MPa, and the final pressure is controlled at 1.0MPa. Grouting is stopped after the pressure is maintained for 3-5mm. If the grouting volume exceeds the limit and the pressure requirement is not met, the slurry concentration should be adjusted to continue grouting until it meets the grouting quality standards. It is ensured that the rock mass around the borehole and the pores around the steel pipe are filled with slurry before grouting is stopped. After the grouting is completed, fill it with M20 cement mortar to enhance the rigidity and strength of the pipe roof.
[0057] During the construction of S300 advanced small conduit 2, according to the design requirements, the position of the advanced small conduit 3 is accurately placed on the tunnel face 9, and a drilling device is used to drill holes at the marked positions. The drilling angle is provided with an external insertion angle, and the processed advanced small conduit 2 is inserted into the drilled hole. The advanced small conduit 2 is provided with a grouting hole 7, which is arranged in a plum blossom shape. The front end of the advanced small conduit 2 should be processed into a cone head, and the tail of the advanced small conduit is welded to the I-beam 3. The advanced small conduit 2 adopts φ42×4mm hot-dip grouting hole 7. Rolled seamless steel pipe, length 3.5m; the diameter of the grouting hole of the leading small conduit 2 should be 6mm, the spacing is 15cm, and it is arranged in a plum blossom shape. The front end of the small conduit should be processed into a cone head, and the tail length is not less than 100cm as the grouting section. The circumferential spacing is 30cm, the longitudinal spacing is 2m, the external insertion angle is 14°~16°, the longitudinal overlap length is greater than 1.5m, the grouting material is cement slurry with a water-cement ratio of 1:1, the grouting pressure is 0.5-1MPa, and the tail of the leading small conduit is welded with an I-beam 3;
[0058] S400 face 9 advance reinforcement is used to reinforce the entire section. According to the design requirements, the drilling position and angle are determined on the face 9, and drilling equipment is used to drill holes to control the depth and accuracy of the holes. Φ50mm high-pressure PVC pipe 8 is used for reinforcement. The single-cycle reinforcement length is 10m, and it is arranged in a plum blossom shape with a spacing of 1.5m*1.5m. The overlap length between two cycles is 3m. Cement slurry is used for PVC pipe grouting. When the surrounding rock is broken and the rock grouting effect is not good When cement-water glass double slurry is used, (1) the water-cement ratio of cement slurry is 1:1 (weight ratio), and the grouting pressure is 0.5-1.0MPa. For cement-water glass double slurry, the water-cement ratio of cement slurry is 1:1, the volume ratio of cement slurry to water glass is 1:0.5, the modulus of water glass should be 2.4-3.4, the concentration is 30-45 degrees Baume, and the grouting pressure remains unchanged. After the PVC pipe is set and grouting is completed, M20 cement mortar is poured into the pipe and ensured to be dense to enhance the strength of the PVC pipe.
[0059] The grouting diffusion radius should not be less than 0.5m. The soil of face 9 should be tested after reinforcement. The next construction process can be carried out only after passing the test. The test requirements are: 28-day unconfined compressive strength qu≥0.8Mpa, permeability coefficient ≤10-7cm / sec.
[0060] Detailed steps in excavation:
[0061] After the excavation, initial support and temporary initial support of Section 10 of Part I are completed within 8 meters, the excavation, initial support of side wall and invert arch of Section 12 of Part III are carried out. After the excavation and initial support of the lower section are completed for 21-24 meters, the right side construction is carried out; after the excavation and initial support of Section 11 of Part II are completed within 8 meters, the excavation, initial support of side wall and invert arch of half section 13 of Part IV are carried out; the secondary lining follows the excavation surface for no more than 6 meters; the specific steps of initial support in the above excavation process are to determine the position and spacing of anchor rods according to design requirements, drill holes in the surrounding rock with a drilling rig, insert the anchor rods into the holes, and anchor them with anchoring agent; then install the steel arch frame to ensure its accurate position and firm connection, connect the steel arch frames with connecting steel bars, lay the steel mesh on the surrounding rock surface according to design requirements, and ensure Ensure that the steel mesh is firmly connected to the anchor rod and steel arch frame, debug the shotcrete equipment, mix cement, sand, gravel, admixtures and other materials evenly according to the designed mix ratio, use a sprayer to spray concrete onto the surface of the surrounding rock, and spray from bottom to top, first the wall and then the arch. The second lining of the right tunnel is constructed by spraying. After the strength reaches 80% of the designed strength, the left tunnel is constructed with the same process. The support involved in the above plan includes anchor rod L=3000, Φ8 steel mesh 250x250 (single layer), C25 shotcrete with an average thickness of 200, 118 I-beams 3, and the longitudinal distance is the same as the corresponding lining I-beam spacing; after the excavation is completed, the support monitoring measurement value is monitored and stabilized, and the temporary support is removed, and the invert is cast, and then the waterproof layer is laid and the secondary lining is integrally molded 6.
[0062] During the tunnel excavation process, the excavation is carried out in the order of first excavating the upper left, then the lower left, then the upper right, and finally the lower right. Tunnel excavation will cause the surrounding rock stress to be redistributed. Excavating the upper left part first can gradually release the surrounding rock stress, avoiding the one-time large-scale excavation that causes stress concentration and causes surrounding rock instability. As the excavation progresses, the surrounding rock stress can be adjusted more evenly, reducing the damage to the tunnel structure caused by stress mutations. After excavating the upper left and lower left parts first, the surrounding rock of the upper right and lower right parts will be subject to certain constraints, thereby reducing its deformation into the tunnel. When excavating the upper right and lower right parts, the upper left and lower left parts that have completed support can provide certain support for them, which is conducive to maintaining the stability of the tunnel.
[0063] The support process of Part I, Part II, Part III and Part IV in the above steps is consistent with the initial support and temporary support in S610. During construction, for each cycle of initial support construction, the circumferential spacing is 500mm, the longitudinal spacing is 1000mm, and a 1000mmΦ30 grouting pipe is reserved. After one cycle is completed, the initial support back grouting is carried out to ensure that there is no delamination between the tunnel and the rock and soil surface after the initial support is completed, so as to ensure that the tunnel construction has less impact on the settlement of the existing tunnel.
[0064] During tunnel construction, it is necessary to monitor the tunnel. The monitoring and measurement contents include: arch crown sinking, peripheral convergence, and surface sinking. The specific measurement methods and frequencies are shown in the following table:
[0065] On-site measurement must be measured
[0066]
[0067]
[0068] Immediately after excavation, the engineering geological and hydrogeological conditions should be observed and recorded, and a geological description should be made; after excavation, the peripheral displacement of the surrounding rock and initial support and the vault settlement should be measured in a timely manner; after the initial support is completed, the surface of the sprayed layer should be observed and recorded, and a crack description should be made; the monitoring and measurement parts and measurement points should be installed as soon as possible within 2 meters of the excavation surface, and the installation spacing should meet the design requirements.
[0069] The data of this section of tunnel should be measured and plotted in time. When an inflection point appears on the displacement-time curve, it indicates that the surrounding rock and support are unstable. At this time, the surrounding rock should be closely observed and measured dynamically, and the support should be strengthened.
[0070] The following is a list of early warning mechanisms established through monitoring and measurement in the tunnel:
[0071] Surrounding rock displacement alarm value list
[0072] Displacement(mm) Construction status <![CDATA[U<U d / 3]]> Normal construction <![CDATA[U d / 3<U<2U d / 3]]> Strengthen monitoring, measurement and support <![CDATA[U>2U d / 3]]> Take special measures and corresponding engineering countermeasures
[0073] Note: U-monitored value of surrounding rock displacement; Ud-designed value of surrounding rock displacement
[0074] Surrounding rock displacement rate alarm value list
[0075] Displacement rate (mm / d) Surrounding rock state <0.2 Basic stability 0.2~1.0 Not yet stable, strengthen observation >1.0 Rapid deformation, take measures
[0076] like Figure 6 As shown in the figure, the project department sent personnel to check the status of the left and right sections of the existing tunnels before the tunnel impact range, and collected evidence on the current quality defects of the No. 1 Nursery Tunnel, such as structural cracks, water seepage, and road damage, and reported them to the property rights unit for confirmation. During the construction process, inspections were conducted three times a day to monitor and record whether the existing cracks had any development trends and other new problems. The monitoring and measurement points were arranged on the left and right arches of the No. 1 Nursery Tunnel and the sidewalks of the road, with one monitoring section every 10m, and 5 settlement observation points were arranged on each side for observation.
[0077] After the back arch is filled, the temporary support is removed before the construction of the secondary lining. The removal must be carried out after the initial support monitoring measurement value is relatively stable, and oxygen and acetylene cutting are used. During the removal process, the secondary lining is constructed closely to ensure that the tunnel is closed into a ring as a whole. After the construction of the right side secondary lining is completed, the same process will be carried out on the left side.
[0078] The above is only an embodiment of the invention, and the common knowledge such as the known specific structure and characteristics in the scheme is not described in detail here. It should be pointed out that for those skilled in the art, several deformations and improvements can be made without departing from the structure of the invention, which should also be regarded as the scope of protection of the invention, and these will not affect the effect of the implementation of the invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.
Claims
1. The four-part CRD mechanical excavation construction process for large-section tunnels is characterized by: The following steps are involved: S100 determines the location of the tunnel face based on tunnel design parameters and geological conditions, and performs pre-construction preparations; S200, an advance pipe shed for the tunnel body is set around the tunnel arch face, and the advance pipe shed is set perpendicular to the tunnel face. The construction of the advance pipe shed for the tunnel body includes the following steps: S210 uses hot-rolled seamless steel pipes in the construction of the advanced pipe shed in the tunnel body, and the length of the pipe shed is arranged according to the preset rules; the connection of the pipe shed is made by threaded connection with steel pipe connecting sleeves; S220 sets a steel cage inside the steel pipe, which includes four main bars and a fixing ring, which is welded to the main bars; S230 has grouting holes on the pipe-roof steel pipe, and a grouting stop section without drilling holes is set at the tail of the pipe-roof steel pipe; After the construction of S240 pipe shed is completed, before pouring the secondary lining, spray concrete is used to compact the excavation contour surface, and a single layer of steel mesh is used to reinforce the top of the local pipe shed; After the construction of S250 pipe shed is completed, grouting will begin. Before grouting, stoppers will be installed on all holes, and the pipe openings and hole openings will be sealed. For the construction of S300 advanced small conduit, according to the design requirements, the position of the small conduit is accurately placed on the tunnel face, and drilling equipment is used to drill holes at the marked positions. The drilling angle is provided with an external insertion angle, and the processed advanced small conduit is inserted into the drilled hole. The advanced small conduit is a hot-rolled seamless steel pipe, and a grouting hole is provided on the advanced small conduit; the grouting hole is arranged in a plum blossom shape, the front end of the small conduit should be processed into a cone head, and the tail of the advanced small conduit is welded to the I-beam; The S400 face advance reinforcement is used to reinforce the entire section. During the reinforcement, PVC pipes are used for reinforcement, and cement slurry or cement-water-glass double liquid slurry is used for pouring, and finally cement mortar is poured. S500 divides the tunnel section of the face into four parts through vertical and horizontal segmentation, namely Part I, Part II, Part III and Part IV; S600 face excavation and construction includes the following steps: S610 excavates the I part through the milling machine, and provides temporary support and initial support for the upper section of the hole; S620, excavate Section III and provide temporary and initial support for the section below the tunnel; S630 excavated the II section and provided temporary support and initial support to the section above the tunnel; S640 excavated the IV section and provided temporary support and initial support to the section under the tunnel; The temporary support and initial support in the above steps are consistent with the initial support and temporary support in S610. S650 support monitoring quantity detection; S660 removes temporary supports after the support monitoring measurement value is stable, and casts the invert, then lays the waterproof layer and forms the secondary lining as a whole; S700, after laying the waterproof layer, back grouting is carried out at the integral mold construction position of the secondary lining, and grouting pipes are reserved during construction.
2. The four-part CRD mechanical excavation construction process for large-section tunnels according to claim 1 is characterized in that: In step 210, hot-rolled seamless steel pipes and steel pipes are used, with an outer diameter of 108 mm and a wall thickness of 6 mm. The length of the pipe rack is 18 m per ring, and the overlap length between two rings and with the next type of advanced support measures is not less than 3 m. The annular spacing of the steel pipes is 30 cm, and the external insertion angle is not greater than 2-3°.
3. The four-part CRD mechanical excavation construction process for large-section tunnels according to claim 1 is characterized in that: In the step S230, grouting holes are drilled with a hole diameter of Φ6 mm and a hole spacing of 150×150 mm in a plum blossom shape, with a 300 mm grouting stop section at the tail that is not drilled.
4. The four-part CRD mechanical excavation construction process for large-section tunnels according to claim 1 is characterized in that: In the step S250, the order of pipe-roof grouting (cement slurry water-cement ratio 1:1) in principle follows the principles of "drill one and grout one" and "from thin to thick". Grouting begins after the pipe-roof construction is completed.
5. The four-part CRD mechanical excavation construction process for large-section tunnels according to claim 1 is characterized in that: In the step S250, the grouting adopts dual control measures of the final grouting pressure and the grouting amount. The initial pressure is preferably 0.5-1.0 MPa, and the final pressure is preferably controlled at 1.0 MPa. The grouting is stopped after the pressure is maintained for 3-5 mm.
6. The four-part CRD mechanical excavation construction process for large-section tunnels according to claim 1 is characterized in that: In the step S400, the soil after the face reinforcement should be tested, and the 28-day unconfined compressive strength qu≥0.8Mpa and the permeability coefficient≤10-7cm / sec can be carried out before the next construction process can be carried out.
7. The large-section tunnel four-part CRD mechanical excavation construction process according to claim 1 is characterized in that: In the step S400, the water-cement ratio of the cement slurry is 1:1, and the grouting pressure is 0.5-1.0 MPa. For the cement-water glass double slurry, the water-cement ratio of the cement slurry is 1:1, the volume ratio of the cement slurry to the water glass is 1:0.5, the water glass modulus is 2.4-3.4, the concentration is 30-45 degrees Baume, and the grouting pressure is 0.5-1.0 MPa.
8. The four-part CRD mechanical excavation construction process for large-section tunnels according to claim 1 is characterized in that: In the above S600, the excavation depth is not greater than the length of the leading small conduit.
9. The large-section tunnel four-part CRD mechanical excavation construction process according to claim 1 is characterized in that: The grouting holes in the S300 are arranged in a plum blossom shape, the front end of the small conduit should be processed into a cone head, and the tail of the leading small conduit is welded to the I-beam.