Construction method of post-cast strip roof support-free formwork system

Through the support-free formwork system of the rear cast belt top plate, the embedded steel sleeves and hooks are connected, the tie bars are welded, and the stacked plate trusses and bolts are used to solve the construction efficiency and safety hazards of the traditional rear cast belt formwork support system. , realize efficient and convenient construction and material management.

CN118958659APending Publication Date: 2024-11-15BAOYE (CHANGCHUN) CONSTR & DEV CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411133342.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The traditional back-pouring tape formwork support system has a large workload, takes up a lot of space, and is inconvenient for the construction of the lower floor. The supporting materials have a long time to use and the rental fee are high, which increases safety hazards.

Method used

Adopt the support-free formwork system of the rear casting top plate. Through the connection of the embedded steel sleeve and the hook, the tie bar is welded, and the stacked plate truss and bolts are used to achieve the construction process without secondary support, simplify installation and disassembly, and improve the Material turnover rate.

Benefits of technology

It realizes efficient, safe and convenient construction, reduces material accumulation, reduces maintenance costs, improves construction space utilization, and solves the concrete forming quality problems and structural stability in traditional methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958659A_ABST
    Figure CN118958659A_ABST
Patent Text Reader

Abstract

The invention discloses a post-cast strip roof support-free formwork system construction method, and relates to the technical field of house buildings. The method comprises the following steps: 1, pre-burying lower draw hooks into concrete beams on two sides of a post-cast strip; secondly, a bottom formwork, a bolt sleeve, a laminated slab truss, a bolt and a rigid supporting plate enter the site; thirdly, a laminated slab truss is laid in the length direction of the post-cast strip; fourthly, steel bars on the two side plates of the post-cast strip are bound; 5, pouring of the laminated slab trusses on the two sides of the post-cast strip and concrete; sixthly, welding tie bars to be connected with the upper drag hook and the lower drag hook; seventhly, after the concrete slabs on the two sides of the post-cast strip meet the formwork removal requirement, the bottom formwork is removed; eighthly, post-cast strip inner joint steel bars are bound; ninthly, a bolt formwork hanging device is installed, and the positions of bolts are adjusted for fastening; tenthly, post-cast strip concrete is poured; eleventhly, the formwork and the inclined upward support are dismantled; disassembly and assembly are convenient, and the bearing capacity of the supporting structure system is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of house construction, and particularly relates to a construction method of a post-cast zone top slab support-free formwork system. Background Art

[0002] Post-cast strips are concrete strips set aside at the corresponding positions of the foundation slab, wall, and beam in accordance with design or construction specifications to prevent harmful cracks that may occur in reinforced concrete structures due to uneven shrinkage or settlement. The traditional post-cast strip formwork support system uses steel pipe frame formwork, bowl buckle frame formwork, and reinforced concrete column independent support. The main formwork form is supported by the bottom floor. During the construction of the support system, double-row scaffolding is usually set on both sides of the post-cast strip and kept disconnected from the full-floor scaffolding to prevent mutual interference when the scaffolding is removed. This method not only has a large workload and occupies the lower space, but is also inconvenient for the construction of the lower floors.

[0003] In addition, with the traditional post-casting strip support system, the construction process of waiting for the concrete pouring in the post-casting strip to be completed and curing for 28 days greatly occupies the use time of turnover materials such as steel pipe formwork and formwork, resulting in serious accumulation of support materials, excessively high rental fees, and the need for secondary erection and dismantling from time to time, which also greatly increases the safety hazards of the structural system. In summary, how to improve the post-casting strip support system, eliminate the erection of support frames, and increase the turnover rate of frame materials, while improving traffic conditions and improving the utilization of construction space, it is convenient for the full development of the working surface, and provides strong support for the cross-construction of other processes near the post-casting strip. It has become a technical problem that relevant construction technicians urgently need to solve. Summary of the invention

[0004] The object of the present invention is to provide a construction method for a support-free formwork system for a top plate of a post-casting belt, which is connected by a steel bar sleeve pre-embedded in a truss plate, and is welded to an upper pre-embedded hook through a tie bar to provide an oblique pulling force for the cantilever plate. In addition, bolt sleeves are pre-embedded on both sides of the post-casting belt truss plate. After the prefabricated plate is hoisted, the position of the bottom formwork is adjusted, and the bolts pass through the rigid support plate and are fastened with the pre-embedded bolt sleeves in the composite truss. The post-casting belt installation process of the method of the present invention can be carried out synchronously with the structural construction, and no secondary formwork is required. After the main structure is demolded, the post-casting belt can be cast by connecting the oblique support and installing the bottom formwork. The method is simple to manufacture and construct, and the support is high in firmness, ensuring that the investment is general, and the installation and disassembly are convenient and reusable, which is conducive to the construction of each team. The method solves the problem that the traditional post-casting belt formwork support system is usually to set double-row scaffolds on both sides of the post-casting belt and keep them disconnected from the full-floor scaffolds to prevent mutual interference when the scaffolds are removed. This method not only has a large workload and occupies the lower space, but is also inconvenient for the construction of the lower floor.

[0005] In order to solve the above technical problems, the present invention is achieved through the following technical solutions: The present invention is a construction method of a post-casting belt top plate support-free formwork system, comprising the following steps: Step 1: Pre-embed the lower hook into the concrete beams on both sides of the post-casting belt; Step 2: Bottom formwork, bolt sleeves, composite plate trusses, bolts, and rigid support plates are brought to the site; Step 3: Lay the composite slab truss in the length direction of the post-cast strip; Step 4: Tie the steel bars on both sides of the post-cast strip; Step 5: pouring the composite slab trusses and concrete on both sides of the post-cast strip; Step 6: Weld the tie bars to connect the upper and lower hooks; Step 7: After the concrete slabs on both sides of the post-casting belt meet the requirements for formwork removal, the bottom formwork is removed; Step 8: Tie the steel bars in the joints of the post-casting belt; Step 9: Install the bolt hanging mold device and adjust the bolt position for tightening; Step 10: pouring the post-casting zone concrete; Step 11: Remove the template and the diagonal upward support.

[0006] Furthermore, in the construction method of the post-casting belt top plate support-free formwork system, in step 1, according to the construction drawing, the embedded position of the lower hook in the concrete beam is accurately measured and marked, and a drilling device is used to drill holes at the marked positions to ensure that the hole diameter and depth meet the design requirements, and the prefabricated lower hook is installed in the drilled hole, and fixed with a special anchoring glue or rebar embedding glue to ensure the verticality and firmness of the lower hook, so as to effectively connect with the tie bar in the subsequent steps; In step two, prepare the required base formwork, bolt sleeves, composite plate trusses, bolts, rigid support plates and other materials in advance. These materials should meet the design specifications and quality standards. Inspect the materials through appearance inspection, dimension measurement and performance testing to ensure construction quality.

[0007] Furthermore, in the construction method of the support-free formwork system for the top slab of the post-cast strip, in step three, a composite slab truss plate is used instead of a wooden formwork, and the plate reinforcement is embedded in the reinforced concrete structure on both sides of the post-cast strip. The assembled composite slab trusses are laid in sequence in the length direction of the post-cast strip. During the laying process, tools such as a spirit level and a laser rangefinder are used to ensure the levelness and alignment of the truss, so that the plate has a certain bearing capacity.

[0008] Furthermore, in the construction method of the post-cast strip top plate unsupported formwork system, step four, during the process of supporting the formwork of the composite slab truss, bolt sleeves, steel sleeves and hooks are embedded inside, and the steel sleeves are selected with a specification of 60*37mm to connect the tensile steel bars with a diameter of 25mm (the steel bar grade is HRB400), and according to the requirements of the "Code for Design of Concrete Structures" B50010-2010 (2015 edition), the embedded steel bars are in the form of a 90° hook at the end, and the anchorage length of the tensile steel bars is calculated according to the anchorage conditions and should not be less than 200mm.

[0009] Furthermore, in the construction method of the post-casting strip top plate support-free formwork system, in step five and step six, when pouring concrete at the post-casting strip, first connect the steel sleeve embedded in the composite plate truss with the upper tie bar, check the appearance quality of the joint, the exposed part should not exceed 2 buckles, there should be no gap between the steel bar and the connecting sleeve, then double-sided weld the tie bar and the hook embedded in the beam-column node and the composite plate truss, the welding length shall not be less than 10d, the angle between the oblique tie bar and the concrete floor slab is 45°, and the tie bar is welded to the upper and lower embedded hooks ( Double-sided welding for 10 days, the weld is uniform and full, without welding slag and pores, etc.), and connected by the steel sleeve pre-buried under the composite plate truss to form a unique inclined rod design structure (triangular geometric invariant structure), so the force support system is stable and safe. The length of the cantilever plate shall not exceed 4m in general. When the horizontal span of the cantilever plate exceeds 4m, a steel sleeve is added every 2m in the vertical direction of the plate post-casting belt, and an upper pre-buried hook is added every 2m in the direction of the beam-column node, so as to make it more conducive to the force stability of the tie bar and the cantilever section post-casting belt plate; The construction process of steps five and six is: (1) Bolt sleeves are embedded before the production of the composite plate truss. After the prefabricated plates on both sides of the post-casting strip are hoisted, the position of the lower bottom mold is adjusted. The rigid support plate and the bottom mold are made of Q235 steel. The bolt specification is Φ20. A groove is set in the middle of the rigid support plate to embed the bottom mold, and a rectangular horizontal hole is opened to accommodate different bolts to fix it. When the embedded bolt sleeve is offset in the horizontal direction, it can also be positioned and installed in this length direction; (2) Place a rigid support plate under the bottom formwork to embed the complete bottom formwork so that it can better seal the post-casting strip; (3) Through the rectangular hole cavity below the rigid support plate, the bolts are passed through the bolt sleeves embedded in the rigid support plate and the composite plate truss for tightening.

[0010] Furthermore, in the above-mentioned construction method of a post-cast strip top slab support-free formwork system, in step seven, it is determined through experiments or experience whether the concrete slab has reached the strength requirement for demolding. It is usually necessary to conduct a compressive strength test of the test block cured under the same conditions. After ensuring that the concrete slab has reached the demolding requirements, special tools are used to carefully remove the bottom formwork to avoid damage to the concrete. Safety must be paid attention to during the removal process to prevent the formwork from accidentally falling.

[0011] Furthermore, in the construction method of the post-casting belt top plate support-free formwork system, in step eight, in the post-casting belt, the joint area is cleaned to remove impurities such as floating slurry and loose aggregates to ensure that the joint area is clean and tidy, and steel bars are tied in the cleaned joint area. During the tying process, the position of the steel bars must be accurate and the tying must be firm, so as to form an effective force transmission structure during the subsequent pouring of concrete; In step nine, install the pre-prepared bolt formwork device to the designated position, ensure that its connection with the surrounding structure is firm and reliable, adjust the position of the bolts according to actual needs to meet the construction requirements, and tighten the bolts with tools such as wrenches to ensure the stability and safety of the formwork device.

[0012] Furthermore, in the construction method of the post-casting belt top plate free support formwork system, in step 10, a suitable concrete mix ratio is selected, and preparatory work before pouring, pump pipe arrangement, personnel division of labor, etc. are performed, and concrete is poured in the post-casting belt by pumping. During the pouring process, the slump and filling speed of the concrete must be strictly controlled to ensure the uniformity and density of the pouring.

[0013] Furthermore, in the construction method of the post-casting belt top plate support-free formwork system, in step eleven, through structural stability analysis and on-site inspection, it is determined whether the formwork and the oblique upward support can be removed, and the factors such as concrete strength and structural stability are analyzed. After the removal conditions are met, the formwork and the oblique upward support are removed safely and orderly in a predetermined order and method. During the removal process, attention should be paid to the safety protection of the operators to prevent the components from falling and injuring people.

[0014] The present invention has the following beneficial effects: 1. The present invention is easy to disassemble and assemble, the supporting structure system has a high bearing capacity, the supporting structure materials can be circulated and reused, and the utilization rate of resources can be improved by recycling, thereby reducing the serious accumulation of materials such as steel pipe scaffolding and formwork, reducing the cost of daily maintenance, and meeting the requirements of civilized construction, green construction and efficient construction.

[0015] 2. The present invention adopts welded tie bars to connect upper and lower embedded hooks as oblique supports, and uses the composite plate truss as a support-free formwork system for the bottom formwork. The angle between the oblique tie bars and the concrete floor is 45°, forming an oblique tie rod design structure (a triangular geometrically invariant structure), which solves the problem of concrete forming quality on both sides of the post-cast zone and can reduce the deformation, cracks and sinking of concrete caused by the collision of the construction work with the supporting structure.

[0016] 3. In the present invention, the bolt-hanging formwork post-casting strip provides convenience for the bottom formwork support, avoids the workload caused by installing the formwork and support on the lower floor, and can effectively improve the problem of the frame occupying the construction channel during the traditional post-casting strip construction process, facilitates the full development of the working surface, and saves the use of steel pipe materials. The installation process is formed in one step without false support, the structural form is relatively stable, easy to disassemble and install, has a high turnover rate, and the support structure system is more universally applicable.

[0017] 4. In the present invention, a groove is provided in the middle of the rigid support plate to embed the bottom template, and a rectangular horizontal hole cavity is provided to accommodate different bolts to fix it. When the embedded bolt sleeve is displaced in the horizontal direction, it can also be positioned and installed in the length direction. The template device is easier to install on site, and the controllability of construction quality is greatly improved.

[0018] Of course, any product implementing the present invention does not necessarily need to achieve all of the advantages described above at the same time. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for describing the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.

[0020] Figure 1 This is a construction process flow chart of a post-casting top plate support-free formwork system of the present invention; Figure 2 It is a schematic diagram of the rigid support plate of the present invention; Figure 3 It is a schematic diagram of the support-free formwork system for the top slab of the post-cast zone of the present invention.

[0021] In the accompanying drawings, the components represented by the reference numerals are listed as follows: 1. Tie steel bars; 2. Upper pre-embedded hooks; 3. Lower pre-embedded hooks; 4. Steel bar sleeves; 5. Bolt sleeves; 6. Composite plate trusses; 7. Bottom formwork; 8. Bolts; 9. Rigid support plates. DETAILED DESCRIPTION

[0022] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0023] See also Figure 1-3 As shown, the present invention is a construction method of a post-casting belt top plate support-free formwork system, comprising the following steps: Step 1: Pre-embed the lower hook into the concrete beams on both sides of the post-casting belt; Step 2: Bottom formwork, bolt sleeves, composite plate trusses, bolts, and rigid support plates are brought to the site; Step 3: Lay the composite slab truss in the length direction of the post-cast strip; Step 4: Tie the steel bars on both sides of the post-cast strip; Step 5: pouring the composite slab trusses and concrete on both sides of the post-cast strip; Step 6: Weld the tie bars to connect the upper and lower hooks; Step 7: After the concrete slabs on both sides of the post-casting belt meet the requirements for formwork removal, the bottom formwork is removed; Step 8: Tie the steel bars in the joints of the post-casting belt; Step 9: Install the bolt hanging mold device and adjust the bolt position for tightening; Step 10: pouring the post-casting zone concrete; Step 11: Remove the template and the diagonal upward support.

[0024] A construction method for a post-casting belt top plate support-free formwork system, in step 1, according to the construction drawing, accurately measure and mark the embedded position of the lower hook in the concrete beam, use drilling equipment to drill holes at the marked positions, ensure that the hole diameter and depth meet the design requirements, install the prefabricated lower hook in the drilled hole, and fix it with special anchor glue or rebar glue to ensure the verticality and firmness of the lower hook, so as to effectively connect it with the tie bar in the subsequent steps; In step two, prepare the required base formwork, bolt sleeves, composite plate trusses, bolts, rigid support plates and other materials in advance. These materials should meet the design specifications and quality standards. Inspect the materials through appearance inspection, dimension measurement and performance testing to ensure construction quality.

[0025] A construction method for a post-cast strip top slab unsupported formwork system, wherein in step three, a composite slab truss plate is used instead of a wooden formwork, and the plate reinforcement is embedded in the reinforced concrete structure on both sides of the post-cast strip, and the assembled composite slab trusses are laid in sequence in the length direction of the post-cast strip. During the laying process, tools such as a level and a laser rangefinder are used to ensure the levelness and alignment of the trusses, so that the plate has a certain bearing capacity.

[0026] A construction method for a post-casting strip top plate support-free formwork system, step four, in the process of composite plate truss formwork, the bolt sleeve, steel sleeve and hook are embedded inside, the steel sleeve is selected with a specification of 60*37mm, which is used to connect the tension steel bar with a diameter of 25mm (the steel bar grade is HRB400), and according to the requirements of "Concrete Structure Design Code" B50010-2010 (2015 edition), the embedded steel bar adopts the form of a 90° hook at the end, and the anchorage length of the tension steel bar is calculated according to the anchorage conditions and should not be less than 200mm.

[0027] A construction method for a post-casting belt top plate support-free formwork system, in step five and step six, when pouring concrete at the post-casting belt, first connect the steel sleeve embedded in the composite plate truss with the upper tie bar, check the appearance quality of the joint, the exposed should not exceed 2 buckles, there is no gap between the steel bar and the connecting sleeve, then double-sided weld the tie bar and the hook embedded in the beam-column node and the composite plate truss, the welding length shall not be less than 10d, the angle between the inclined tie bar and the concrete floor slab is 45°, and the tie bar is welded to the upper and lower embedded hooks (double-sided welding 1 0d, the weld is uniform and full, without welding slag and pores, etc.), and is connected by the steel sleeve pre-buried under the composite plate truss to form a unique inclined rod design structure (triangular geometric invariant structure), so the force support system is stable and safe. The length of the cantilever plate shall generally not exceed 4m. When the horizontal span of the cantilever plate exceeds 4m, a steel sleeve is added every 2m in the vertical direction of the plate post-casting belt, and an upper pre-buried hook is added every 2m in the direction of the beam-column node, so as to make it more conducive to the force stability of the tie bar and the cantilever section post-casting belt plate; The construction process of steps five and six is: (1) Bolt sleeves are embedded before the production of the composite plate truss. After the prefabricated plates on both sides of the post-casting strip are hoisted, the position of the lower bottom mold is adjusted. The rigid support plate and the bottom mold are made of Q235 steel. The bolt specification is Φ20. A groove is set in the middle of the rigid support plate to embed the bottom mold, and a rectangular horizontal hole is opened to accommodate different bolts to fix it. When the embedded bolt sleeve is offset in the horizontal direction, it can also be positioned and installed in this length direction; (2) Place a rigid support plate under the bottom formwork to embed the complete bottom formwork so that it can better seal the post-casting strip; (3) Through the rectangular hole cavity below the rigid support plate, the bolts are passed through the bolt sleeves embedded in the rigid support plate and the composite plate truss for tightening.

[0028] A construction method for a post-cast strip top plate support-free formwork system. In step seven, whether the concrete slab has reached the strength requirement for demolding is determined through experiments or experience. Usually, a compressive strength test of a test block cured under the same conditions is required. After ensuring that the concrete slab has reached the demolding requirement, the bottom formwork is carefully removed using special tools to avoid damage to the concrete. Safety must be paid attention to during the removal process to prevent the formwork from accidentally falling.

[0029] A method for constructing a post-casting belt top plate support-free formwork system, in step eight, in the post-casting belt, the joint area is cleaned to remove impurities such as floating slurry and loose aggregates to ensure that the joint area is clean and tidy, and steel bars are tied in the cleaned joint area. During the tying process, the steel bars must be accurately positioned and firmly tied so as to form an effective force transmission structure during the subsequent pouring of concrete; In step nine, install the pre-prepared bolt formwork device to the designated position, ensure that its connection with the surrounding structure is firm and reliable, adjust the position of the bolts according to actual needs to meet the construction requirements, and tighten the bolts with tools such as wrenches to ensure the stability and safety of the formwork device.

[0030] A construction method for a post-casting belt top plate free support formwork system, in step 10, a suitable concrete mix ratio is selected, and preparatory work before pouring, pump pipe arrangement, personnel division of labor, etc., is performed, and concrete is poured in the post-casting belt by pumping. During the pouring process, the slump and filling speed of the concrete must be strictly controlled to ensure the uniformity and density of the pouring.

[0031] A post-casting top plate support-free formwork system construction method, in step eleven, through structural stability analysis and on-site inspection, determine whether the formwork and the oblique upward support can be removed, analyze factors such as concrete strength and structural stability, and after the removal conditions are met, remove the formwork and the oblique upward support in a safe and orderly manner in a predetermined order and method. During the removal process, attention should be paid to the safety protection of operators to prevent components from falling and injuring people.

[0032] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0033] The preferred embodiments of the present invention disclosed above are only used to help illustrate the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.

Claims

1. A construction method for a post-casting belt top plate support-free formwork system, characterized in that: The steps include: Step 1: Pre-embed the lower hook into the concrete beams on both sides of the post-casting belt; Step 2: Bottom formwork, bolt sleeves, composite plate trusses, bolts, and rigid support plates are brought to the site; Step 3: Lay the composite slab truss in the length direction of the post-cast strip; Step 4: Tie the steel bars on both sides of the post-cast strip; Step 5: pouring the composite slab trusses and concrete on both sides of the post-cast strip; Step 6: Weld the tie bars to connect the upper and lower hooks; Step 7: After the concrete slabs on both sides of the post-casting belt meet the requirements for formwork removal, the bottom formwork is removed; Step 8: Tie the steel bars in the joints of the post-casting belt; Step 9: Install the bolt hanging mold device and adjust the bolt position for tightening; Step 10: pouring the post-casting zone concrete; Step 11: Remove the template and the diagonal upward support.

2. The construction method of a post-casting top plate free support formwork system according to claim 1, characterized in that: In step 1, according to the construction drawings, accurately measure and mark the embedded position of the lower hook in the concrete beam, use drilling equipment to drill holes at the marked positions, ensure that the hole diameter and depth meet the design requirements, install the prefabricated lower hook in the drilled hole, and fix it with special anchor glue or rebar glue to ensure the verticality and firmness of the lower hook, so as to effectively connect it with the tie bar in the subsequent steps; In step two, prepare the required base formwork, bolt sleeves, composite plate trusses, bolts, rigid support plates and other materials in advance. These materials should meet the design specifications and quality standards. Inspect the materials through appearance inspection, dimension measurement and performance testing to ensure construction quality.

3. The construction method of a post-casting top plate support-free formwork system according to claim 1, characterized in that: In step three, composite slab truss plates are used instead of wooden formworks, and the plate reinforcement is embedded in the reinforced concrete structure on both sides of the post-cast strip. The assembled composite slab trusses are laid sequentially in the length direction of the post-cast strip. During the laying process, tools such as spirit levels and laser rangefinders are used to ensure the levelness and alignment of the trusses, so that the plates have a certain bearing capacity.

4. The construction method of a post-casting top plate support-free formwork system according to claim 1, characterized in that: Step 4. During the formwork support process of the composite slab truss, bolt sleeves, steel sleeves and hooks are embedded inside. The steel sleeves are selected with a specification of 60*37mm to connect the tensile steel bars with a diameter of 25mm (the steel bar grade is HRB400). According to the requirements of the "Code for Design of Concrete Structures" B50010-2010 (2015 edition), the embedded steel bars are in the form of 90° hooks at the ends. The anchorage length of the tensile steel bars is calculated according to the anchorage conditions and should not be less than 200mm.

5. The construction method of a post-casting top plate support-free formwork system according to claim 1, characterized in that: In step 5 and step 6, when pouring concrete at the post-casting zone, first connect the steel sleeve embedded in the composite slab truss with the upper tie bar, check the appearance quality of the joint, the exposed should not exceed 2 buckles, there should be no gap between the steel bar and the connecting sleeve, then double-sided weld the tie bar and the hook embedded in the beam-column node and the composite slab truss, the welding length shall not be less than 10d, the angle between the inclined tie bar and the concrete floor is 45°, the tie bar is welded to the upper and lower embedded hooks (double-sided welding 10d, the weld is even and full , no welding slag pores and other problems), and connected by the steel sleeve pre-buried under the composite slab truss to form a unique inclined rod design structure (triangular geometric invariant structure), so the force support system is stable and safe. The length of the cantilever slab shall generally not exceed 4m. When the horizontal span of the cantilever slab exceeds 4m, a steel sleeve is added every 2m in the vertical direction of the slab post-casting belt, and an upper pre-buried hook is added every 2m in the direction of the beam-column node, so that it is more conducive to the force stability of the tie bar and the cantilever section post-casting belt slab; The construction process of steps five and six is: (1) Bolt sleeves are embedded before the production of the composite plate truss. After the prefabricated plates on both sides of the post-casting strip are hoisted, the position of the lower bottom mold is adjusted. The rigid support plate and the bottom mold are made of Q235 steel. The bolt specification is Φ20. A groove is set in the middle of the rigid support plate to embed the bottom mold, and a rectangular horizontal hole is opened to accommodate different bolts to fix it. When the embedded bolt sleeve is offset in the horizontal direction, it can also be positioned and installed in this length direction; (2) Place a rigid support plate under the bottom formwork to embed the complete bottom formwork so that it can better seal the post-casting strip; (3) Through the rectangular hole cavity below the rigid support plate, the bolts are passed through the bolt sleeves embedded in the rigid support plate and the composite plate truss for tightening.

6. The construction method of a post-casting top plate free support formwork system according to claim 1, characterized in that: In step seven, determine whether the concrete slab has reached the strength requirements for demolding through experiments or experience. It is usually necessary to conduct a compressive strength test of the test blocks cured under the same conditions. After ensuring that the concrete slab has reached the demolding requirements, use special tools to carefully remove the bottom formwork to avoid damage to the concrete. Pay attention to safety during the removal process to prevent the formwork from accidentally falling.

7. The construction method of a post-cast zone top plate free support formwork system according to claim 1, characterized in that: In step eight, the joint area is cleaned in the post-casting zone to remove impurities such as floating slurry and loose aggregates to ensure that the joint area is clean and tidy. The steel bars are tied in the cleaned joint area. During the tying process, the steel bars must be accurately positioned and firmly tied to form an effective force transmission structure during the subsequent pouring of concrete. In step nine, install the pre-prepared bolt formwork device to the designated position, ensure that its connection with the surrounding structure is firm and reliable, adjust the position of the bolts according to actual needs to meet the construction requirements, and tighten the bolts with tools such as wrenches to ensure the stability and safety of the formwork device.

8. The construction method of the post-casting strip top plate free support formwork system according to claim 1, characterized in that: In step 10, select the appropriate concrete mix ratio, and carry out pre-pouring preparations, such as pump pipe layout, personnel division of labor, etc., and use pumping to pour concrete into the post-casting zone. During the pouring process, the slump and filling speed of the concrete must be strictly controlled to ensure the uniformity and density of the pouring.

9. The construction method of the post-casting zone top plate free support formwork system according to claim 1, characterized in that: In step 11, through structural stability analysis and on-site inspection, determine whether the formwork and the diagonal support can be removed, analyze factors such as concrete strength and structural stability, and after the removal conditions are met, remove the formwork and the diagonal support safely and orderly in accordance with the predetermined sequence and method. During the removal process, pay attention to the safety protection of operators to prevent components from falling and injuring people.