Construction method of self-walking type electric hanging basket for installing large storage tank

Through the construction method of self-walking electric hanging basket, the problems of high cost, work-related injury risk and low efficiency in the traditional storage tank installation process are solved, and efficient, safe and flexible storage tank installation is achieved, suitable for storage tanks of different types and sizes. Improve construction quality and safety.

CN118992838APending Publication Date: 2024-11-22中邮建技术有限公司
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411088867.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-09
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The traditional large-scale storage tank installation process has problems such as high cost, risk of work-related injury, low efficiency, inadequate storage tanks of different types and sizes, and difficult to monitor construction quality.

Method used

The construction method of self-moving electric hanging basket is adopted, including installing suspension mechanisms, hanging wire ropes, installing hanging basket baskets, safety locks and hoists, and electrical boxes to realize the annular welds of the storage tank body, external insulation layer and maintenance inspection. Improve construction intelligence and accuracy.

Benefits of technology

It improves construction efficiency and safety, reduces manpower investment, realizes real-time monitoring and control, adapts to storage tanks of different types and scales, and reduces resource waste and construction cycles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118992838A_ABST
    Figure CN118992838A_ABST
Patent Text Reader

Abstract

The invention provides a construction method for a self-walking type electric hanging basket used for installation of a large storage tank, and belongs to the technical field of machine.The method comprises the steps that firstly, a hanging mechanism is installed; 2, a steel wire rope is vertically placed; 3, a hanging basket body is installed; 4, a safety lock and an elevator are installed; 5, installing an electrical box; 6, threading a working steel wire rope; 7, threading a safety steel wire rope; 8, a limiting block is installed; and 9, a heavy punch is installed. The self-walking type electric hanging basket can move rapidly and accurately, manpower input is reduced, construction time is shortened, and therefore construction efficiency is greatly improved. An engineering project can be completed faster generally, and the production stagnation time is shortened. According to the automatic control system, highly accurate position control is ensured, so that the engineering quality and accuracy are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of mechanical technology, and in particular to a self-propelled electric hanging basket construction method for installing a large storage tank. Background Art

[0002] The installation of large storage tanks has always been an important part of the engineering construction field and is widely used in many industries such as petroleum, chemical, and food. However, the traditional storage tank installation process has always been subject to a series of problems and challenges. Traditional methods usually require a large amount of manpower input, including highly skilled workers, which not only increases costs but also increases the construction period; traditional storage tank installation methods involve high-risk tasks such as high-altitude operations and the handling of large components, which may lead to work injuries and accidents; traditional methods are inefficient and slow in construction progress, resulting in project delays and further increasing costs; traditional methods are usually a general method that is difficult to adapt to various types and sizes of storage tanks, which leads to inefficient construction and waste of resources; traditional methods are highly dependent on highly skilled workers, which limits the scale and scope of engineering projects; some links in traditional processes are difficult to monitor and control in real time, which may lead to construction quality problems.

[0003] To solve these problems, the present invention proposes a new self-propelled electric hanging basket construction method. The goal of this method is to improve safety, efficiency and flexibility to cope with the problems and challenges of traditional processes. Summary of the invention

[0004] In view of the defects and shortcomings of the above-mentioned prior art, the present invention proposes a self-propelled electric hanging basket construction method for large storage tank installation, which is used for the vertical storage tank installation project of the data center. The self-propelled electric hanging basket construction method can realize the construction of the annular weld of the storage tank body, the outer insulation layer, the outer protective layer, etc., and can also realize the maintenance and inspection of the storage tank body. It makes the construction process more intelligent, reduces the error of human operation, and improves the accuracy of construction.

[0005] A self-propelled electric hanging basket construction method for large storage tank installation comprises the following steps:

[0006] Step 1: Install the suspension mechanism;

[0007] Step 2: Lower the wire rope;

[0008] Step 3: Install the hanging basket body;

[0009] Step 4: Install the safety lock and hoist;

[0010] Step 5: Install the electrical box;

[0011] Step 6: Put on the working wire rope;

[0012] Step 7: Put on the safety wire rope;

[0013] The safety wire rope is located outside the end of the front beam of the suspension mechanism. When threading the rope, insert the wire rope into the lock inlet above the safety lock, push it by hand, and after it passes freely through the safety lock, pull the wire rope out from the rope outlet above the safety lock until the wire rope is tightened.

[0014] Step 8: Install the limit block;

[0015] Install the upper limit block on the safety wire rope. When the lower limit is used, the lower limit travel switch is installed on the mounting plate at the bottom of the hoist mounting frame.

[0016] Step 9: Install the weight.

[0017] Further, the specific installation process of step 1 is as follows:

[0018] Step 1.1: Install the center column. The bottom of the center column is welded to the center of the tank top surface to ensure that the verticality deviation is no more than 1 / 1000, and diagonal braces are welded in the four vertical directions to support the center column. The center column is made of DN125 seamless steel pipe, welded and fixed to the center point of the top of the cold storage tank, and reinforced by three triangular plates. The casing is made of DN150 seamless steel pipe, and the casing is fixed with flanges at the top and bottom, and the upper flange is reinforced by three triangular plates.

[0019] Step 1.2: Install the main arm. Install the bearing seat at the inner end of the main arm on the bearing of the middle axis at the upper end of the middle column, and weld the vertical rod and rear tie rod at the specified position of the main arm.

[0020] Step 1.3: Install the roller frame. First install the roller with a diameter of 600mm on the roller frame, then install the outer end of the main arm on the surface of the roller frame with bolts, adjust the turning radius of the roller to 1540mm, and the axes of the two rollers pass through the vertical center line of the center column respectively, and firmly fix the main arm with bolts.

[0021] Step 1.4: Install the boom. Use U-shaped bolts to install the rear ends of the booms on both sides on the rear beam of the roller frame. Place the middle of the boom on the fulcrum. Adjust the front ends of the booms on both sides to keep them vertical to the 2m long hanging basket hanging point. The booms should be extended to keep the inner side of the hanging basket 0.4-0.5m away from the base surface of the tank.

[0022] Step 1.5: Install the working wire rope. Install the rear end of the working wire rope on the tie plate at the top of the vertical pole, tie the front end to the tie plate at the outer end of the boom, fix it with a wire rope clamp, and adjust the screw of the spiral buckle to make the boom tilt up 200mm.

[0023] Further, the specific operation process of step 2 is as follows:

[0024] Step 2.1: Check whether the suspension mechanism components, bolts, and wire rope clamps are installed correctly and firmly. After confirmation, place the suspension mechanism in the working position, fix the working wire rope and safety wire rope on the wire rope suspension frame of the front beam respectively, and keep the working wire rope about 0.6m away from the working surface. Hang the working wire rope sleeve of the machine position above the gutter on the steel pipe bracket and hang it down to the ground hanging basket.

[0025] Step 2.2: The end of the wire rope is buckled on the tail section of the wire rope with a U-shaped bolt, and the clamp seat is buckled on the working section of the wire rope. The number of wire rope clamps is not less than 3, and the interval A is 0.6m, and they are tightened one by one in sequence starting from the ring.

[0026] Step 2.3: Install the rear pull rope on the steel pipe bracket at the machine position above the gutter and tighten it appropriately.

[0027] Further, the specific contents of step 3 are as follows:

[0028] Raise the bottom plate of the suspension platform by 200mm and lay it flat, install the railing, put the lower railing on the side of the working surface, and connect it with bolts; install fixed safety guardrails around the suspension platform, with belly bars, the guardrail height of the working surface is 1.05m, the rear railing height is 1.2m, and the horizontal concentrated load of the guardrail is 1000N. After assembly, tighten all the connecting bolts evenly.

[0029] Further, the specific contents of step 4 are as follows:

[0030] The safety lock and hoist are installed in the safety lock bracket and hoist support on the lifting mounting frame at both ends of the suspension platform respectively. When installing the safety lock, the swing arm roller should face the inner side of the platform. The safety lock is wrapped with plastic cloth to prevent water and pollution.

[0031] The hoist is installed in the suspension platform. During installation, the hoist is moved to the suspension platform, the rectangular concave frame on the back of the hoist is aligned with the hoist support, the pin shaft is inserted and locked with a locking pin, and the hoist is fixed to the crossbar of the hoist mounting frame with two connecting bolts or a handle assembly at the upper end of the hoist box.

[0032] Further, the specific contents of step 6 are as follows:

[0033] Turn the switch on the electrical box panel to the side of the hoist where the wire rope is to be threaded. The working wire rope passes through the limit wheel and retaining ring of the safety lock and is inserted into the upper hole of the hoist. Activate the up button, and the hoist will automatically wind up to complete the threading of the working wire rope. The ratio of the hoist sheave diameter to the wire rope diameter should not be less than 20.

[0034] Further, the specific contents of step 9 are as follows:

[0035] The weight is fixed at the lower end of the wire rope to tighten and stabilize the wire rope to prevent the suspension platform from pulling up the wire rope together with it when it is lifted, which will affect the normal operation of the suspension platform. The weight is a counterweight with a mass of 25kg. After the wire ropes on both sides are threaded, the suspension platform is raised to 1m above the ground and leveled, and the weight is installed on the working wire rope and the safety wire rope 100mm above the ground. During installation, clamp the second beam half piece at the lower end of the wire rope about 100mm from the ground, and then fasten it to the wire rope with bolts.

[0036] Compared with the prior art, the present invention has the following beneficial effects:

[0037] 1. The self-propelled electric hanging platform can move quickly and accurately, reducing manpower input and construction time, thus greatly improving construction efficiency. Engineering projects can usually be completed faster, reducing production downtime.

[0038] 2. The automatic control system of the present invention ensures highly accurate position control, thereby improving the quality and accuracy of the project. This is especially important for storage tanks that need to strictly meet design requirements.

[0039] 3. The safety monitoring system of the self-propelled electric suspended basket can monitor environmental conditions and the status of the suspended basket in real time, respond to potential dangerous situations in a timely manner, and reduce engineering risks and the possibility of accidents.

[0040] 4. Due to the automation and remote control functions of the hanging basket, engineering personnel can stay away from potential danger areas, thereby improving personnel safety.

[0041] 5. The self-propelled electric hanging basket construction method has high adaptability and can be applied to storage tanks of various types and sizes.

[0042] 6. The site requirements are relatively small, which greatly shortens the construction period and improves the construction quality. It can realize the construction of multiple equipments at the same time and meet the needs of multi-process construction;

[0043] 7. It avoids the impact of scaffolding on the foundation, reduces the circulation and use of scaffolding materials, and saves the cost of scaffolding rental and erection and dismantling;

[0044] 8. Remote control and self-propelled walking can be achieved through electrical control, reducing labor costs;

[0045] 9. Rust removal, painting and insulation spraying operations are carried out at close range on the storage tank body to reduce environmental pollution. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] Figure 1 It is a flow chart of the steps of the present invention.

[0047] Figure 2 This is a schematic diagram of installing the center column.

[0048] Figure 3 The correct arrangement method for wire rope clamps.

[0049] Figure 4 This is the side assembly diagram of the suspension mechanism.

[0050] Figure 5 This is the front assembly drawing of the suspension mechanism.

[0051] Among them: 1-cold storage tank body; 2-basket body; 3-middle column; 4-rear pull rod; 5-vertical pole; 6-main arm; 7-jib; 8-working wire rope; 9-diagonal support rod; 10-roller frame; 11-roller; 12-safety wire rope. DETAILED DESCRIPTION

[0052] The present invention will be further described in detail below in conjunction with the accompanying drawings.

[0053] The hanging basket involved in the present invention has multi-level insurance safety measures, including an electric magnetic brake above the motor, a centrifugal speed limit brake at the connection between the motor and the speed reducer, and independent safety measures on both sides of the hanging basket. The LSF (309 / 30A) anti-tilt safety lock automatically locks the wire rope when the hanging platform of the hanging basket tilts to 3-8 degrees, ensuring that there is no risk of any accidents. It has a reasonable structure, stable performance, convenient lifting, safety and reliability, and is suitable for cold storage tank installation projects.

[0054] Preparation work before installation of hanging basket;

[0055] (1) All parts of the on-site hanging basket must be inspected and checked to see if the bracket, adjustment rod, upper support, front beam, middle beam and rear beam are deformed or cracked. If any, they must be replaced immediately.

[0056] (2) Transport the components of the hanging basket to the assembly location according to the installation flow chart. Use a construction elevator or tower crane to transport the bracket, wire rope and counterweight to the top floor, and move the platform part to the ground at the corresponding position. Note that the counterweight cannot be piled up when it is transported to the floor level.

[0057] (3) Clean the site where the hanging basket is installed to ensure that it is firm, reliable and flat. Pull ropes in the ground construction warning area to prevent passage and send special personnel to guard the area to ensure safety.

[0058] like Figure 1 As shown, the specific construction method steps of the present invention are as follows:

[0059] Step 1: Install the suspension mechanism

[0060] The suspension mechanism includes the center column, vertical pole, rear pull rod, main arm, suspension arm, support rod, roller frame, and roller, which are installed on the top surface of the cold storage tank. When assembling and welding the suspension basket frame, it must be done after the internal annular seams of the cold storage tank cylinder section are all completed. The parts, components, and wire ropes of the suspension mechanism are hoisted to the top surface for installation.

[0061] (1) Install the center column: The bottom of the center column is welded to the center of the tank top surface to ensure that the verticality deviation is no more than 1 / 1000, and diagonal braces are welded in the four vertical directions to support the center column. The center column is made of DN125 seamless steel pipe, welded and fixed to the center point of the top of the cold storage tank, and reinforced by three triangular plates. The casing is made of DN150 seamless steel pipe, and the upper and lower casings are fixed with flanges. The upper flange is reinforced by three triangular plates. Figure 2 .

[0062] (2) Install the main arm: Install the bearing seat at the inner end of the main arm on the bearing of the central axis at the upper end of the center column, and weld the vertical pole and rear pull rod at the specified position of the main arm.

[0063] (3) Install the roller frame: first install the roller with a diameter of 600mm on the roller frame, then install the outer end of the main arm on the surface of the roller frame with bolts, adjust the roller's turning radius to 1540mm, and the axes of the two rollers pass through the vertical center line of the center column, and firmly fix the main arm with bolts. (4) Install the boom: Use U-shaped bolts to install the rear ends of the two booms on the rear crossbeam of the roller frame, and place the middle of the boom on the fulcrum. Adjust the front ends of the two booms to keep them vertical with the 2m long hanging basket hanging point, and the extension of the boom should make the inner side of the hanging basket 0.4-0.5m away from the surface of the tank base. (5) Install the lifting wire rope: Install the rear end of the lifting wire rope on the tie plate at the top of the vertical pole, tie the front end to the tie plate at the outer end of the boom, fix it with a wire rope clamp, and adjust the screw of the spiral buckle to make the boom tilt up 200mm.

[0064] Step 2: Lower the wire rope

[0065] (1) Check whether the above components, bolts and wire rope clamps are installed correctly and firmly. After confirmation, place the suspension mechanism in the working position, fix the working wire rope and safety wire rope on the wire rope suspension bracket of the front beam respectively, and keep the working wire rope about 0.6m away from the working surface. Hang the working wire rope sleeve of the machine position above the gutter on the steel pipe bracket and hang it down to the ground hanging basket.

[0066] (2) The method of fixing the end of the wire rope is as per the instruction manual of the ZLP series high-altitude work platform. The U-shaped bolt is buckled on the tail section of the wire rope, and the clamp seat is buckled on the working section of the wire rope. They cannot be reversed. The wire rope clamps shall not be arranged alternately on the wire rope. The number shall be no less than 3, with an interval of about 0.6m. They shall be tightened one by one starting from the ring in sequence. See Figure 3 .

[0067] (3) When lowering the wire rope, place the free coil of the wire rope on the floor, carefully pull out the rope, and then slowly slide it down along the wall.

[0068] (4) After the wire rope is released, the tangled rope should be carefully separated and pressed down, and the excess wire rope on the ground should be carefully coiled and tied tightly.

[0069] (5) Install the rear pull rope on the steel pipe support of the machine position above the gutter, and install the rear pull rope according to the position of the anchor point in the machine position setting plan, and tighten it appropriately.

[0070] Step 3: Basket Installation

[0071] (1) Raise the bottom plate of the suspension platform by 200 mm and lay it flat, install the railings, place the lower railing on one side of the working surface, and connect it with bolts;

[0072] (2) The suspended platform should be equipped with fixed safety guardrails around it. The guardrails should be equipped with web bars. The guardrail height on the working surface is 1.05m, and the rear railing height is 1.2m. The guardrail should be able to withstand a horizontal concentrated load of 1000N.

[0073] (3) After assembly, tighten all connecting bolts evenly.

[0074] (4) Installation, adjustment and precautions

[0075] 1) Choose a floor that is as flat as possible as the installation surface.

[0076] 2) The joints of each basic section should be aligned, and after pre-tightening, the entire platform frame should be straight without obvious distortion.

[0077] 3) When installing the hoists at both ends, the safety lock should face the outside of the platform.

[0078] 4) After assembly, tighten all connecting bolts evenly without any looseness or false tightening.

[0079] Step 4: Installation of safety lock and hoist

[0080] The safety lock and hoist are installed in the safety lock bracket and hoist support on the lifting mounting frame at both ends of the suspension platform respectively:

[0081] (1) When installing the safety lock, the swing arm roller should face the inner side of the platform. During construction, the safety lock should be wrapped with plastic sheeting to prevent water and contamination.

[0082] (2) The hoist is installed in the suspension platform. During installation, the hoist is moved to the suspension platform, the rectangular concave frame on the back of the hoist is aligned with the hoist support, the pin is inserted and locked with a lock pin, and the hoist is fixed to the crossbar of the hoist mounting frame with two connecting bolts or a handle assembly at the upper end of the hoist box. Alternatively, after power is turned on, the working wire rope is passed into the hoist at the suspension platform, and the rising button is pressed to lift the hoist into the suspension platform for installation. When the latter method is used for installation, the rope outlet of the hoist must be properly padded, and the rope must be carefully led out by hand when the wire rope is exposed from the rope outlet to prevent the head of the wire rope from hitting the ground and being damaged.

[0083] Step 5: Electrical Box Installation

[0084] The electrical box is installed on the rear (high) railing in the middle of the suspension platform, with the door of the electrical box facing the inside of the suspension platform. The electrical box is fixed to the railing with two hanging plates.

[0085] After the electrical box is installed and fixed, insert the connector plugs of the power cable, motor cable, and operating switch cable into the corresponding sockets at the bottom of the electrical box. When inserting the connector plug, carefully align the pin position and push it in evenly to avoid damaging the connector.

[0086] Step 6: Thread the working wire rope

[0087] (1) Turn the switch on the electrical box panel to the side of the hoist where the wire rope is to be threaded. The working wire rope passes through the limit wheel and retaining ring of the safety lock and is inserted into the upper hole of the hoist. Activate the up button and the hoist will automatically wind up the working wire rope to complete the threading and advancement.

[0088] (2) Pay close attention to any abnormalities during the rope threading process. If any abnormalities are found, stop threading the rope immediately.

[0089] (3) The working wire rope and the safety wire rope must be straightened before they can be inserted into the hoist and the safety lock respectively to avoid twisting of the wire rope.

[0090] (4) The ratio of the hoist sheave diameter to the wire rope diameter should not be less than 20.

[0091] Step 7: Thread the safety wire rope

[0092] The safety wire rope is located outside the end of the front beam of the suspension mechanism. When threading the rope, insert the wire rope end into the lock inlet above the safety lock, push it by hand, and after it passes through the safety lock freely, pull the wire rope out from the rope outlet above the safety lock until the wire rope is tightened.

[0093] Step 8: Install the limit block

[0094] Install the upper limit block at the appropriate position of the safety wire rope. When the lower limit is used, the lower limit travel switch is installed on the mounting plate at the bottom of the hoist mounting frame.

[0095] Step 9: Heavy Hammer Installation

[0096] (1) The weight is fixed at the lower end of the wire rope to tighten and stabilize the wire rope to prevent the suspension platform from pulling up the wire rope when it is lifted, thus affecting the normal operation of the suspension platform. The weight is a counterweight with a mass of 25kg.

[0097] (2) After the wire ropes on both sides are threaded, raise the suspension platform to 1m above the ground and level it. Install a heavy hammer 100mm above the ground on the working wire rope and safety rope.

[0098] (3) During installation, clamp the second half of the beam at the lower end of the wire rope about 100 mm above the ground, and then fasten it to the wire rope with bolts.

[0099] After the installation of the hanging basket is completed, it shall be inspected by the statutory agency. Only after the inspection is qualified can the acceptance be organized. After the installation of the hanging basket is completed, inspection and acceptance shall be carried out. The hanging basket must be accepted before it can be used. The acceptance shall be led by the general contractor, and the user unit, the leasing unit, the installation unit, and the supervision unit shall be organized to conduct a joint acceptance, and an installation acceptance record shall be formed. After the installation of the hanging basket is completed, the supervision unit, the user unit, and the installation unit shall be notified to conduct a joint acceptance, and at the same time, the inspection unit shall be reported to the inspection unit for inspection and it can be used only after the inspection is qualified.

[0100] The hanging basket must be inspected and adjusted before each operation:

[0101] (1) Check whether there is abnormal wear, corrosion, surface cracks, loose connection, desoldering, etc. at the connection between the hanging basket, hoist, and hoist and the hanging platform;

[0102] (2) Check whether each connection part is firm and reliable, whether there is any desoldering phenomenon, whether the nut is tightened, whether the wire rope is intact, and whether the wire rope clamp is arranged correctly;

[0103] (3) Check whether the counterweight is placed correctly and is not missing;

[0104] (4) Check whether the wire rope is fixed correctly and whether there is any abnormal phenomenon such as excessive wear, breakage, etc.;

[0105] (5) Whether the heavy hammer hanging at the lower end of the wire rope is installed correctly;

[0106] (6) Check whether the electrical box, cables, control buttons and plugs are in good condition;

[0107] (7) Check whether the upper (lower) limit switch, hand-held switch, etc. are flexible and reliable and have no leakage.

[0108] (8) Check the operating condition of the hanging basket. The hoist should have no abnormal sound or vibration. The electromagnetic brake should be flexible and reliable, and the safety lock rope should function normally.

[0109] Inspection and maintenance during the use of the hanging basket:

[0110] (1) During the use of the hanging basket, the wire rope, suspension mechanism, suspension platform, electrical control system, etc. should be inspected regularly and an operation test should be carried out.

[0111] (2) The hanging basket should be inspected and maintained regularly during use.

[0112] Shifting operation of hanging basket:

[0113] Only one hanging basket is installed on the flat facade of each cold storage tank. When the operation on one facade is completed and another vertical operation area is used, the rotating electric mechanism can be started to rotate the shifting hanging basket in a clockwise direction to the next flow section to install the external insulation material.

[0114] Disassembly process of hanging basket:

[0115] The removal and installation methods of the hanging basket are the same, but the procedures are opposite. Before dismantling, the hanging basket platform must be lowered to the ground or the lowest point of the construction, and it must be confirmed that the wire rope is completely free of stress and in a relaxed state. Before dismantling, the hanging basket should be fully inspected and the damage should be recorded.

[0116] Operating environment of hanging basket construction:

[0117] (1) Normal ambient temperature: (-20~+40)℃. Operation is strictly prohibited on rainy days or at night.

[0118] (2) It is strictly forbidden to put sand, stone, screws, nuts, steel wire and other debris into the hoist wire rope entrance to avoid the hoist biting and cutting the wire rope and causing danger. (3) It is not suitable to work in corrosive environments such as acid and alkali. When the gust wind speed at the work place is greater than 7.2.3m / s (equivalent to level 5 wind force), the operator is not allowed to operate the basket.

[0119] (4) The normal operating voltage should be kept within the range of 380±38V. When the voltage on site is lower than 342V, no operation shall be carried out.

[0120] (5) When the on-site power supply voltage is within the range of 361V to 342V or the ambient temperature exceeds 40°C, the maximum load mass of the electric hanging basket shall not exceed 80% of the rated load.

[0121] (6) A conspicuous warning sign or a safety supervisor must be set up below the construction area.

[0122] (7) There should be a sufficient safety distance between the hanging basket and high-voltage wires and high-voltage devices during use. During on-site use, there should be no high-voltage wires within 10m of the entire machine.

[0123] The hanging basket machine involved in the present invention includes: a suspension mechanism, a hanging basket body, a hoist, a safety lock, a working wire rope, a safety wire rope, an electrical box, such as Figure 4 , 5 shown.

[0124] The suspension mechanism is installed on the top surface of the cold storage tank, including the middle column, vertical pole, rear tie rod, main arm, boom, support rod, roller frame, and roller. The middle column is welded in the center of the tank top, and four diagonal support rods are welded symmetrically. The rear end of the main arm is installed on the top of the middle column through a rolling bearing, and the front end of the main arm is welded to the roller frame, and the vertical pole and rear tie rod are welded at the specified position of the main arm; one end of the rear tie rod is connected to the middle column, and the other end is connected to the top of the vertical pole; two rollers are installed under the roller frame, and the roller, roller frame, and boom are driven by an electric device to rotate around the middle column, with a rolling radius of 1.54m. The rear part of the boom is installed on the roller frame through U-bolts, and the upper part of the front end of the boom is tied to the vertical pole with a wire rope. The lower end of the boom is hung with a basket body, and the boom rotation radius is 3.5m. The basket body is hung under the two booms, driving the suspension mechanism to rotate around the facade of the cold storage tank, and gradually changing the construction area of ​​the facade.

[0125] The safety lock and the hoist are respectively installed in the safety lock bracket and the hoist support on the lifting mounting frames at both ends of the hanging basket body.

[0126] The safety wire rope is located on the outside of the front beam end of the suspension mechanism. The upper end is tied to the top fence of the cold storage tank, and the other end is tied to the construction worker's safety belt. The contact between the safety wire rope and the steel structure is wrapped with rubber to take anti-wear measures.

[0127] The rear end of the working wire rope is installed on the top of the vertical pole, and the front end is tied to the outer end of the boom and fixed with a wire rope clamp.

[0128] The electrical box is installed on the rear (high) railing in the middle part of the hanging basket body, with the electrical box door facing the inside of the hanging basket body, and the electrical box is fixed to the railing with two hanging plates.

[0129] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A self-propelled electric hanging basket construction method for large storage tank installation, It is characterized in that The steps include: Step 1: Install the suspension mechanism; Step 2: Lower the wire rope; Step 3: Install the hanging basket body; Step 4: Install the safety lock and hoist; Step 5: Install the electrical box; Step 6: Put on the working wire rope; Step 7: Put on the safety wire rope; The safety wire rope is located outside the end of the front beam of the suspension mechanism. When threading the rope, insert the wire rope end into the lock inlet above the safety lock, push it by hand, and after it passes through the safety lock freely, pull the wire rope out from the rope outlet above the safety lock until the wire rope is tightened. Step 8: Install the limit block; Install the upper limit block on the safety wire rope. When the lower limit is used, the lower limit travel switch is installed on the mounting plate at the bottom of the hoist mounting frame; Step 9: Install the weight.

2. A self-propelled electric hanging basket construction method for large storage tank installation according to claim 1, It is characterized in that The specific installation process of step 1 is as follows: Step 1.1: Install the center column. The bottom of the center column is welded to the center of the tank top surface to ensure that the verticality deviation is no more than 1 / 1000. Diagonal braces are welded in the four vertical directions to support the center column. The center column is made of DN125 seamless steel pipe, welded and fixed to the center point of the top of the cold storage tank, and reinforced by three triangular plates. The casing is made of DN150 seamless steel pipe, and the casing is fixed with flanges at the top and bottom. The upper flange is reinforced by three triangular plates. Step 1.2: Install the main arm, install the bearing seat at the inner end of the main arm on the bearing of the middle axis at the upper end of the middle column, and weld the vertical rod and rear tie rod at the specified position of the main arm; Step 1.3: Install the roller frame. First, install the roller with a diameter of 600mm on the roller frame, and then install the outer end of the main arm on the surface of the roller frame with bolts. Adjust the turning radius of the roller to 1540mm, and the axes of the two rollers pass through the vertical center line of the center column respectively. Fix the main arm firmly with bolts; Step 1.4: Install the boom. Use U-shaped bolts to install the rear ends of the booms on both sides on the rear beam of the roller frame. Place the middle of the boom on the fulcrum. Adjust the front ends of the booms on both sides to keep them vertical with the 2m long hanging basket hanging point. The booms are extended so that the inner side of the hanging basket is 0.4-0.5m away from the base surface of the tank. Step 1.5: Install the working wire rope. Install the rear end of the working wire rope on the tie plate at the top of the vertical pole, tie the front end to the tie plate at the outer end of the boom, fix it with a wire rope clamp, and adjust the screw of the spiral buckle to make the boom tilt up 200mm.

3. A self-propelled electric hanging basket construction method for large storage tank installation according to claim 1, It is characterized in that The specific operation process of step 2 is as follows: Step 2.1: Check whether the suspension mechanism components, bolts and wire rope clamps are installed correctly and firmly. After confirming that they are correct, place the suspension mechanism in the working position, fix the working wire rope and safety wire rope on the wire rope suspension frame of the front beam respectively, and keep the working wire rope about 0.6m away from the working surface. Hang the working wire rope sleeve of the machine position above the gutter on the steel pipe bracket and hang it down to the ground hanging basket body; Step 2.2: Use a U-shaped bolt to buckle the end of the wire rope to the tail section of the wire rope, and buckle the clamp seat to the working section of the wire rope. The number of wire rope clamps should be no less than 3, with an interval A of 0.6m, and tighten them one by one starting from the ring; Step 2.3: Install the rear pull rope on the steel pipe bracket at the machine position above the gutter and tighten it appropriately.

4. A self-propelled electric hanging basket construction method for large storage tank installation according to claim 1, It is characterized in that The specific contents of step 3 are as follows: Raise the bottom plate of the suspension platform by 200mm and lay it flat, install the railing, place the lower railing on one side of the working surface and connect it with bolts; install fixed safety guardrails around the suspension platform, the guardrails are equipped with belly bars, the guardrail height of the working surface is 1.05m, the rear railing height is 1.2m, the horizontal concentrated load of the guardrail is 1000N, and all connecting bolts are tightened evenly after assembly.

5. A self-propelled electric hanging basket construction method for large storage tank installation according to claim 1, It is characterized in that The specific contents of step 4 are as follows: The safety lock and hoist are installed in the safety lock bracket and hoist support on the lifting mounting frame at both ends of the suspension platform respectively. When installing the safety lock, the swing arm roller should face the inside of the platform. The safety lock should be wrapped with plastic cloth to prevent water and pollution; The hoist is installed in the suspension platform. During installation, the hoist is moved to the suspension platform, the rectangular concave frame on the back of the hoist is aligned with the hoist support, the pin shaft is inserted and locked with a locking pin, and the hoist is fixed to the crossbar of the hoist mounting frame with two connecting bolts or a handle assembly at the upper end of the hoist box.

6. A self-propelled electric hanging basket construction method for large storage tank installation according to claim 1, It is characterized in that The specific contents of step 6 are as follows: Turn the conversion switch on the electrical box panel to the side of the hoist where the wire rope is to be threaded. The working wire rope passes through the limit wheel and retaining ring of the safety lock and is inserted into the upper hole of the hoist. Activate the up button and the hoist will automatically wind up the working wire rope to complete the threading and advancement. The ratio of the hoist sheave diameter to the wire rope diameter shall not be less than 20.

7. A self-propelled electric hanging basket construction method for large storage tank installation according to claim 1, It is characterized in that The specific contents of step 9 are as follows: The weight is fixed at the lower end of the wire rope to tighten and stabilize the wire rope to prevent the suspension platform from pulling up the wire rope when it is lifted and affecting the normal operation of the suspension platform. The weight is a counterweight with a mass of 25kg. After the wire ropes on both sides are threaded, the suspension platform is raised to 1m from the ground and leveled. The weight is installed on the working wire rope and safety wire rope 100mm from the ground. During installation, clamp the two beam halves at the lower end of the wire rope about 100mm from the ground, and then fasten it to the wire rope with bolts.

8. A self-propelled electric hanging basket construction method for large storage tank installation according to any one of claims 1 to 7, It is characterized in that The whole machine of the hanging basket includes: a suspension mechanism, a hanging basket body, a hoist, a safety lock, a working wire rope, a safety wire rope, and an electrical box; The suspension mechanism is installed on the top surface of the cold storage tank, including the middle column, vertical pole, rear tie rod, main arm, boom, support rod, roller frame, and roller. The middle column is welded in the center of the tank top, and four diagonal support rods are welded symmetrically. The rear end of the main arm is installed on the top of the middle column through a rolling bearing, and the front end of the main arm is welded to the roller frame, and the vertical pole and rear tie rod are welded at the specified position of the main arm; one end of the rear tie rod is connected to the middle column, and the other end is connected to the top of the vertical pole; two rollers are installed under the roller frame, and the rollers, roller frame, and boom are driven by an electric device to rotate around the middle column, with a rolling radius of 1.54m. The rear part of the boom is installed on the roller frame through U-bolts, and the upper part of the front end of the boom is tied to the vertical pole with a wire rope. The lower end of the boom is hung with a hanging basket, and the boom rotation radius is 3.5m. The hanging basket is hung under the two booms, driving the suspension mechanism to rotate around the facade of the cold storage tank, and gradually changing the construction area of ​​the facade. The safety lock and the hoist are respectively installed in the safety lock bracket and the hoist support on the lifting mounting frames at both ends of the hanging basket body; The safety wire rope is located outside the front beam end of the suspension mechanism. The upper end is tied to the top fence of the cold storage tank, and the other end is tied to the safety belt of the construction personnel. The contact between the safety wire rope and the steel structure is wrapped with rubber to prevent wear. The rear end of the working wire rope is installed on the top of the vertical pole, and the front end is tied to the outer end of the boom and fixed with a wire rope clamp; The electrical box is installed on the rear (high) railing in the middle part of the hanging basket body, with the electrical box door facing the inside of the hanging basket body, and the electrical box is fixed to the railing with two hanging plates.