Prestressed structure construction method
Through the prestressed structure construction methods, including ground leveling, pile sinking, foundation pit excavation and connection structure adjustment, the problem of insufficient bearing capacity of foundation foundation under complex geological conditions is solved, and the Class A bearing capacity and construction safety of foundation foundation are achieved , adapts to the difference in construction height.
Patent Information
- Application Number
- CN202411174540.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-11-22
AI Technical Summary
Under complex geological conditions, the prior art is difficult to ensure the bearing capacity of the foundation, resulting in construction safety and stability issues.
Prestressed structure construction methods are adopted, including site floor leveling, pile sinking construction, foundation pit excavation, determination of connection structure and foundation groove backfill, and PHC series prestressed concrete pipe piles follow the pressure of deep first and shallow first, middle and then outer The pile sequence is to control the pile pressure and pile length, monitor the pile top displacement and bearing capacity characteristic values, adjust the connection structure according to the actual construction height, and ensure the reinforcement and backfilling of the bearing.
Under complex geological conditions, the foundation constructed through this method can have sufficient bearing capacity and meet the Class A foundation standards, ensure construction safety and meet the design service life of 50 years. The connection performance of prestressed concrete pipe piles and the bearing platform is good. Adapt to construction height differences.
Smart Images

Figure CN118997477A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a prestressed structure construction method. Background Art
[0002] In such Figure 1 Construction under the geological conditions shown Figure 2 The complex shown in the figure includes: newly built residential, primary and secondary schools, park green space, protective green space, commercial, business, entertainment and health (complex bus hub) projects, among which there is a basement floor (partially 2 floors) below the ground, and 14 high-rise residential buildings (A1#~A6#, B1#~B8#), 2 high-rise office buildings (B9-2#, B11-2#), 2 6-story commercial buildings (B9-1#, B11-1#), 1 3-story kindergarten (A7#), 1 5-story primary school (A8#), 1 3-story demonstration area ( B10#), A3# building, A4# building, B5#~B8# building elevation 22.800m, A7# building elevation 21.700m, A8# building elevation 22.100m, B1#~B4# building elevation 22.200m, B9-1# building elevation 21.350m, B10# building elevation 21.600m, B11-1# building elevation 21.900m, with a designed service life of 50 years. What kind of foundation to construct under this geological condition to have sufficient bearing capacity has become a technical problem that needs to be solved urgently. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a prestressed structure construction method to overcome the deficiencies in the above-mentioned prior art.
[0004] The technical solution of the present invention to solve the above technical problem is as follows: A prestressed structure construction method comprises the following steps:
[0005] S1. Site surface leveling: Level the site surface to ensure that the surface soil bearing capacity characteristic value meets the requirements for stable operation of the pile driver;
[0006] S2. Pile driving: static pile driving is used. The piles driven are PHC series prestressed concrete pipe piles. The construction progress of pile driving is controlled and the pile driving sequence is followed: deep first, shallow second, middle first, periphery second, main building first, podium second. The depth of the prestressed concrete pipe pile end entering the bearing layer is ≥1.0m;
[0007] S3. Excavation of foundation pit: After all piles are sunk, excavation of foundation pit shall be carried out in layers, and the height difference shall not exceed 1m;
[0008] S4. Determine the connection structure: Determine the connection structure between each prestressed concrete pile and the cap according to the relationship between the actual construction height and the design height of each prestressed concrete pile, and carry out the corresponding operation procedures respectively;
[0009] S5. Backfill the foundation pit: drain the accumulated water, remove the loose soil and construction waste, and fill the soil with clay, gray soil or plain concrete and compact it layer by layer.
[0010] Based on the above technical solution, the present invention can also be improved as follows.
[0011] Furthermore, if the pile driver is a static pressure pile driver, the characteristic value of the surface soil bearing capacity shall not be less than 100 kPa; if the weight of the pile driver is greater than 4000 kN, the characteristic value of the surface soil bearing capacity shall not be less than 120 kPa, otherwise the soil shall be backfilled with crushed stone or construction slag and compacted before construction can begin.
[0012] Furthermore, the pressed piles are PHC series prestressed concrete pipe piles, the pile body concrete strength grade is C80, the pile tip adopts a closed cross pile tip, and the pile end is poured with 1.5m thick C20 shrinkage compensating concrete.
[0013] Furthermore, pile driving is mainly controlled by pile driving force and supplemented by pile length control. Stabilization of pile driving should be carried out before final driving. The stabilization pile driving force should not be less than the final pressure, and the stable pile driving time is 3 minutes. For pile foundations whose pile driving force meets the test pile and design requirements but whose pile length does not reach the designed pile length, the pile driving force should be increased to not less than 1.1 times the designed pile driving force and not exceeding the allowable pile driving force of the pile body. When sinking piles in deep saturated soft soil, if there is no experience in arranging piles densely, the horizontal displacement of the pile top should be monitored during the construction process, and the number of monitored piles should not be less than 6. During the pile driving construction, the changes in the pile top elevation should be monitored, and the number of inspections should not be less than 5% of the total number of piles, and should not be less than 10.
[0014] Furthermore, excavation of foundation pits for silt and saturated clay should be carried out 10 days after all pile sinking is completed. Saturated clay contains silt and silty soil. The earthwork within 1.0m above the pile top should be carried out by small machinery in combination with manual labor. If the pile tops are uneven during foundation pit excavation, the pile heads should be excavated out manually in batches, and then excavation should be carried out after the piles are cut. Excavation of foundation pits in soft soil areas should be carried out in a balanced and layered manner using small machinery in combination with manual labor.
[0015] Furthermore, single pile joints should be carried out after the pile tip passes through the hard soil layer to avoid the pile tip being close to the hard bearing layer or the pile tip being in the hard bearing layer. The number of joints for any single pile shall not exceed 2.
[0016] Furthermore, when pipe piles are used in high-rise buildings, if there is soft soil with a bearing capacity characteristic value of 70kPa or less under the pedestal, cement-soil mixing piles should be used to fully interlock the soil under the pedestal. Concrete or sand and gravel replacement can also be used. The reinforcement or replacement treatment depth should not be less than 2m below the bottom of the pedestal, or to the top surface of the better soil layer below the bottom of the pedestal. The reinforcement range around the pedestal should not be less than 1m. After the soil reinforcement, continuous penetration dynamic probing and core drilling detection should be carried out.
[0017] Furthermore, S4 has the following situations:
[0018] ① If the actual construction height of the prestressed concrete pipe pile is less than the design height, the soil above the top of the pipe pile is excavated to form a hole surrounding the pipe pile. The bottom of the excavated hole is lower than the top of the pipe pile. The outer steel cage and the inner steel cage are respectively made according to the inner diameter of the excavated hole and the inner diameter of the pipe pile. The outer steel cage is arranged in the excavated hole. The lower end of the inner steel cage is welded with a support plate and then placed in the prestressed concrete pipe pile. The support bars in the middle area of the inner steel cage are placed on the top of the pipe pile to allow the inner steel cage to be suspended. The micro-expansive concrete core filling with a strength grade not less than C30 and not less than the cap strength grade is poured in the pipe pile, and the connection pile concrete with a grade higher than the cap concrete and not less than C30 is poured in the excavated hole. After the concrete solidifies, a plain concrete cushion layer is poured outside the connection pile that is lower than the top of the connection pile. Finally, the cap is poured. The additional vertical bars at the top of the outer steel cage and the anchor bars at the top of the inner steel cage are in the poured cap.
[0019] ② If the actual construction height of the prestressed concrete pile is equal to the design height, an inner steel cage is made according to the inner diameter of the pile, and a support plate is welded at the lower end of the inner steel cage and then placed in the prestressed concrete pile. The support bars in the middle area of the inner steel cage are placed on the top of the pile to allow the inner steel cage to be suspended. A micro-expansive concrete core is poured in the pile with a strength grade not lower than C30 and not lower than the cap. After the concrete solidifies, a plain concrete cushion layer is poured around the pile that is lower than the top of the pile. Finally, the cap is poured, and the anchor steel bars at the top of the inner steel cage are in the poured cap.
[0020] ③. If the actual construction height of the prestressed concrete pipe pile is equal to the design height, a ring-shaped end plate is fixed on the top of the pipe pile, and multiple anchor plates are welded in a ring shape on the ring-shaped end plate. Anchor bars extending outward are welded on each anchor plate. An inner steel cage is made according to the inner diameter of the pipe pile, and a support plate is welded at the lower end of the inner steel cage and then placed in the prestressed concrete pipe pile. A micro-expansive concrete core filling with a strength grade not lower than C30 and not lower than the cap strength grade is poured in the pipe pile. After the concrete solidifies, a plain concrete cushion layer is poured around the outer periphery of the pipe pile that is lower than the top of the pipe pile. Finally, the cap is poured, and the anchor bars on the anchor plate and the anchor steel bars at the top of the inner steel cage are in the poured cap.
[0021] ④. If the actual construction height of the prestressed concrete pipe pile is equal to the design height, the soil above the top of the pipe pile is excavated to form a hole surrounding the pipe pile. The bottom of the excavated hole is lower than the top of the pipe pile. Then a casing is cast to protect the hole. The top of the casing has a surrounding plain concrete cushion layer. The plain concrete cushion layer is lower than the top of the pipe pile. According to the inner diameter of the casing and the inner diameter of the pipe pile, an outer steel cage and an inner steel cage are respectively made. The outer steel cage is arranged in the casing. After the lower end of the inner steel cage is welded with a support plate, it is lowered into the prestressed concrete pipe pile. A micro-expansive concrete core filling of not less than C30 and not less than the strength grade of the cap is cast in the pipe pile, and concrete of the same strength grade as the cap is cast in the casing. After the concrete solidifies, the cap is finally cast. The additional vertical reinforcement at the top of the outer steel cage, the anchor reinforcement at the top of the inner steel cage and the prestressed reinforcement of the pipe pile body are in the cast cap.
[0022] ⑤. If the actual construction height of the prestressed concrete pipe pile is less than the design height, the soil above the top of the pipe pile is excavated to form a hole surrounding the pipe pile. The bottom of the excavated hole is lower than the top of the pipe pile. An annular end plate is fixed on the top of the pipe pile, and multiple anchor plates are welded in a ring shape on the end plate. Anchor bars are welded on each anchor plate. An outer steel cage and an inner steel cage are made according to the inner diameter of the excavated hole and the inner diameter of the pipe pile. The outer steel cage is arranged in the excavated hole. After the support plate is welded at the lower end of the inner steel cage, it is lowered into the prestressed concrete pipe pile. The support bars in the middle area of the inner steel cage are placed on the top of the pipe pile to allow the inner steel cage to be suspended. A micro-expansive concrete core filling of not less than C30 and not less than the strength grade of the cap is poured in the pipe pile, and a connection pile concrete of one grade higher than the cap concrete and not less than C30 is poured in the excavated hole. After the concrete solidifies, a plain concrete cushion layer lower than the top of the pipe pile is poured around the connection pile. Finally, the cap is poured. The additional vertical bars and anchor bars at the top of the outer steel cage are in the poured cap.
[0023] Furthermore, in case ①, the inner diameter of the hole is 300mm larger than the outer diameter of the pipe pile, and the bottom of the hole is at least 500mm lower than the top of the pipe pile; in case ④, the inner diameter of the casing is 400mm larger than the outer diameter of the pipe pile, and the inner bottom of the casing is at least 350mm lower than the top of the pipe pile; in case ⑤, the inner diameter of the hole is 400mm larger than the outer diameter of the pipe pile, and the bottom of the hole is at least 500mm lower than the top of the pipe pile.
[0024] Furthermore, the micro-expansive concrete core filled in the pipe pile with a strength grade not lower than C30 and not lower than the foundation strength grade is C35 micro-expansive concrete.
[0025] The beneficial effects of the present invention are as follows: under the geological conditions, the prestressed structure constructed by this method as a foundation can have sufficient bearing capacity, and the grade of the constructed foundation can be Class A, thereby ensuring that the complex can be smoothly constructed and meet the designed service life. In addition, the connection performance between the prestressed concrete pipe piles and the pedestals is good, and compression piles and pull-out piles can be formed. When there is a gap between the actual construction height of the pipe piles and the designed height, construction can also be carried out flexibly. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a diagram of the geological conditions of the construction area in the present invention;
[0027] Figure 2 It is a layout diagram of the complex to be constructed in the present invention;
[0028] Figure 3 This is a first connection structure diagram in the present invention;
[0029] Figure 4 This is a second connection structure diagram in the present invention;
[0030] Figure 5 This is a third connection structure diagram in the present invention;
[0031] Figure 6 This is a fourth connection structure diagram of the present invention;
[0032] Figure 7 This is the fifth connection structure diagram in the present invention.
[0033] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0034] 1. Prestressed concrete pipe piles, 2. External steel cage, 210, additional vertical bars, 3. Internal steel cage, 310, anchor bars, 4. Support plate, 5. Micro-expansive concrete, 6. Connecting pile concrete, 7. Connecting piles, 8. Plain concrete cushion, 9. Cap, 10. Annular end plate, 11. Anchor plate, 12. Anchor bars, 13. Casing, 14. Concrete. DETAILED DESCRIPTION
[0035] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0036] Example 1
[0037] like Figure 2 to Figure 7 As shown, a prestressed structure construction method comprises the following steps:
[0038] S1. Site surface leveling: Level the site surface to ensure that the surface soil bearing capacity characteristic value meets the requirements for stable operation of the pile driver;
[0039] S2. Pile driving: Static pile driving is carried out by pile driver. The pile driven is PHC series prestressed concrete pipe pile 1. The production of prestressed concrete pipe pile 1 shall meet the requirements of Appendix A of DB42 / 489-2008, and the construction progress of pile driving shall be controlled. The pile driving sequence principle of deep first and shallow second, middle first and outer second, main building first and podium building second shall be followed. The adjacent buildings and construction site shall be observed and monitored. Necessary measures shall be taken according to the specific situation to protect the surrounding buildings and facilities. During the construction period, the soil upwelling between piles shall be detected. When pile driving is difficult, pile driving with a guide hole or pile driver with a hydraulic vibrator can be used to assist pile driving. When a large area of foundation soil is found to be uplifted during the detection, a guide hole can be used to take soil at the pile position. The depth of the prestressed concrete pipe pile end entering the bearing layer shall be ≥1.0m. The distance between the pile centers of two adjacent prestressed concrete pipe piles 1 shall be greater than 4 times the pile diameter.
[0040] S3. Excavation of foundation pit: After all piles are sunk, excavation of foundation pit shall be carried out in layers, and the height difference shall not exceed 1m;
[0041] S4, determine the connection structure: according to the relationship between the actual construction height and the design height of each prestressed concrete pipe pile 1, determine the connection structure between each prestressed concrete pipe pile 1 and the cap 9, and carry out corresponding operation procedures respectively;
[0042] S5. Backfill the foundation pit: drain the accumulated water, remove the loose soil and construction waste, and fill the soil with clay, gray soil or plain concrete and compact it layer by layer.
[0043] Example 2
[0044] This embodiment is a further improvement on the basis of embodiment 1, and the details are as follows:
[0045] If the pile driver is a static pressure pile driver, the characteristic value of the surface soil bearing capacity shall not be less than 100kPa. If the weight of the pile driver is greater than 4000kN, the characteristic value of the surface soil bearing capacity shall not be less than 120kPa. Otherwise, backfill with crushed stone or construction slag and compact it before construction.
[0046] Example 3
[0047] This embodiment is a further improvement on the basis of Embodiment 1 or 2, and the details are as follows:
[0048] The pressed piles are PHC series prestressed concrete pipe piles 1, with a pile body concrete strength grade of C80. The pile tip adopts a closed cross pile tip, and the pile end is poured with 1.5m thick C20 shrinkage compensation concrete. The engineering pile is 31m long and is made up of multiple sections of pipe piles. For the prestressed concrete pipe piles 1 entering the construction site, the appearance dimensions of the pipe piles, the configuration of steel bars, the tensile strength and elongation of the main bars, the thickness of the steel bar protective layer, the thickness of the end plate and other items should be tested. At the same time, the concrete strength of the pile body should be tested by core drilling. For different types of pipe piles entering the construction site, one section of the pipe pile is randomly selected and 6 core samples are drilled at different locations for concrete compression tests. Piles with a pile body concrete strength test less than 85% of the design strength should be judged as waste piles. Piles with cracks or defects are prohibited. At the same time, random witnessed sampling tests on pipe piles entering the construction site should comply with the requirements of Article 9.0.2 of DB42 / 489-2008.
[0049] The characteristic value of the vertical compressive bearing capacity of prestressed concrete pipe pile 1 is 1800KN, the natural ground design pile pressure is 4800KN, the characteristic value of the pull-out bearing capacity of the single pile is 480KN, the compressive static load detection limit load is 4400KN, and the pull-out static load detection limit load is 4800KN.
[0050] Example 4
[0051] This embodiment is a further improvement on any one of Embodiments 1 to 3, and the details are as follows:
[0052] The pile driving is mainly controlled by the pile driving force, supplemented by the pile length control. The pile driving force should be stabilized before the final pressure. The pile driving force should not be less than the final pressure. The stable pile driving time is 3 minutes. During the pressure application process, the verticality of the pile body should be monitored by instruments in two perpendicular directions. When sinking the pile, the pile body should be vertical, and the verticality deviation should not exceed 1%. The verticality deviation of the first section of the pile when inserted into the ground should not exceed 0.5%. For the foundation piles whose pile driving force meets the test pile and design requirements but whose pile length does not reach the designed pile length, the pile driving force should be increased to not less than 1.1 times the designed pile driving force and not more than the allowable pile driving force of the pile body. When sinking piles in deep saturated soft soil, when there is no experience in arranging piles densely, the horizontal displacement of the pile top should be monitored during the construction process, and the number of monitored piles should not be less than 6. During the pile driving construction, the changes in the pile top elevation should be monitored, and the number of inspections should not be less than 5% of the total number of piles, and should not be less than 10. The construction should also comply with the relevant provisions of "DB42 / 489-2008" and 10G409.
[0053] Before the upper pile section is sunk into the soil layer, recyclable foam plastics or bagged mineral wool balls should be stuffed into the inner hole of the upper end of the pipe pile to ensure that dirt and debris cannot enter the inner hole of the pipe pile.
[0054] Example 5
[0055] This embodiment is a further improvement on any one of Embodiments 1 to 4, and the details are as follows:
[0056] The excavation of foundation pit for silt and saturated clay should be carried out 10 days after the pile sinking is completed. The foundation pit shall not be excavated while the piles are sinking. Saturated clay contains silt and silty soil. The earthwork within 1.0m above the pile top shall be carried out by small machinery in combination with manual labor. If the pile tops are uneven during the excavation of the foundation pit, the pile heads shall be excavated manually in batches, and the excavation shall be carried out after the piles are cut. The pile heads shall be cut with a pile saw, and it is strictly forbidden to use a sledgehammer to knock the piles horizontally or to forcibly pull the piles. The excavation of foundation pits in soft soil areas shall be carried out in a balanced and layered manner with small machinery in combination with manual labor.
[0057] The connection of single piles 7 should be carried out after the pile tip passes through the hard soil layer to avoid the pile tip approaching the hard bearing layer or the pile tip being in the hard bearing layer. The number of joints of any single pile shall not exceed 2. When connecting piles, the steel bars shall be mechanically connected and the end plates shall be welded.
[0058] When pipe piles are used in high-rise buildings, if there is soft soil with a bearing capacity characteristic value of 70kPa or less under the pedestal 9, cement-soil mixing piles should be used to fully interlock the soil under the pedestal 9. Concrete or sand and gravel replacement can also be used. The reinforcement or replacement treatment depth should not be less than 2m below the bottom surface of the pedestal 9, or to the top surface of the better soil layer below the bottom surface of the pedestal 9. The reinforcement range around the pedestal 9 should not be less than 1m. After the soil reinforcement, continuous penetration dynamic probing and core drilling detection should be carried out.
[0059] Example 6
[0060] This embodiment is a further improvement on any one of Embodiments 1 to 5, and the details are as follows:
[0061] S4 has the following situations:
[0062] ①, such as Figure 3As shown, if the actual construction height of the prestressed concrete pipe pile 1 is less than the designed height, the soil above the top of the pipe pile is excavated to form a hole surrounding the pipe pile, and the bottom of the excavated hole is lower than the top of the pipe pile. As a preferred embodiment, the height difference between the bottom of the excavated hole and the top of the pipe pile is ≥ D (pile diameter), and ≥ 500mm. Since the outer diameter of the prestressed concrete pipe pile 1 used is 500mm, D is 500mm at this time. The outer steel cage 2 and the inner steel cage 3 are respectively made according to the inner diameter of the excavated hole and the inner diameter of the pipe pile. Steel cage 3, where the vertical reinforcement of the outer steel cage 2 is 6ф18mm, i.e., grade 3 steel, and the stirrup is Φ8@200mm. The vertical reinforcement of the inner steel cage 3 (which will also correspond to the anchor reinforcement later) is 6ф18mm, i.e., grade 3 steel, and the stirrup is Φ8@200mm. The outer steel cage 2 is arranged in the excavated hole, the inner diameter of the excavated hole is 300mm larger than the outer diameter of the pile, and the lower end of the inner steel cage 3 is welded with a support plate 4 and then placed in the prestressed concrete pile 1, with a lowering depth of ≥2000m. m, the supporting bars in the middle area of the inner steel cage 3 are placed on the top of the pipe pile to allow the inner steel cage 3 to be suspended, and the micro-expansion concrete 5 with a strength grade not lower than C30 and not lower than the cap 9 is poured into the pipe pile to fill the core, and the connection pile concrete 6 with a grade higher than the cap 9 concrete and not lower than C30 is poured into the excavated hole. After the concrete solidifies, a plain concrete cushion layer 8 is poured around the connection pile 7, which is lower than the top of the connection pile 7. The upper surface of the plain concrete cushion layer 8 is 50mm lower than the top of the connection pile 7. Finally, the cap 9 is poured. , the additional vertical reinforcement 210 at the top of the outer reinforcement cage 2 and the anchor reinforcement (vertical reinforcement of the inner reinforcement cage 3) 310 at the top of the inner reinforcement cage 3 are in the cast cap 9, the length of the additional vertical reinforcement 210 in the cap 9 is LaE, and ≥40d (d is the diameter of the additional vertical reinforcement 210), the length of the anchor reinforcement 310 in the cap 9 is LaE, and ≥40d (d is the diameter of the anchor reinforcement 310), and the distance between the top of the connecting pile 7 and the top of the prestressed concrete pipe pile 1 is ≤1000mm;
[0063] ②, such as Figure 4As shown, if the actual construction height of the prestressed concrete pipe pile 1 is equal to the design height, the inner steel cage 3 is made according to the inner diameter of the pipe pile, the vertical reinforcement specification of the inner steel cage 3 is 6ф18mm, that is, the third-grade steel bar, the stirrup specification is Φ8@200mm, and the support plate 4 is welded at the lower end of the inner steel cage 3 and then placed in the prestressed concrete pipe pile 1, the lowering depth is ≥1500mm, and the support reinforcement in the middle area of the inner steel cage 3 is placed on the top of the pipe pile to allow the inner steel cage 3 to be suspended in the air, and the concrete is poured in the pipe pile. The core is filled with micro-expansive concrete 5 of strength grade C30 and not lower than that of the cap 9. After the concrete solidifies, a plain concrete cushion layer 8 is poured around the pipe pile and is lower than the top of the pipe pile. The upper surface of the plain concrete cushion layer 8 is 50mm lower than the top of the prestressed concrete pipe pile 1. Finally, the cap 9 is poured. The anchor steel bar 310 at the top of the inner steel cage 3 is in the poured cap 9. The length of the anchor steel bar 310 in the cap 9 is LaE, and is ≥40d (d is the diameter of the anchor steel bar 310);
[0064] ③. If Figure 5 As shown, if the actual construction height of the prestressed concrete pipe pile 1 is equal to the design height, an annular end plate 10 is fixed on the top of the pipe pile, and a plurality of anchor plates 11 are welded in a ring shape on the annular end plate 10, such as 12 anchor plates 11, the height of the anchor plates 11 is 30mm, and an outwardly extending anchor bar 12 is welded on each anchor plate 11, the inclination angle of the anchor bar 12 is 30°, and the specification of the anchor bar 12 is 6ф18mm. The inner steel cage 3 is made according to the inner diameter of the pipe pile, and the vertical bar specification of the inner steel cage 3 is 6ф18mm, that is, the third-grade steel bar, and the stirrup specification is Φ8@200mm. After the support plate 4 is welded at the lower end of the inner steel cage 3, it is placed in the prestressed concrete pipe pile 1. For PHC-500B-125 piles, the distance between the lower end of the inner steel cage 3 and the upper surface of the annular end plate 10 is ≥4000mm. For PHC-500AB-125 piles, the distance between the lower end of the inner steel cage 3 and the upper surface of the annular end plate 10 is ≥3000mm. A micro-expansive concrete 5 with a strength grade not lower than C30 and not lower than the cap 9 is poured into the pile to fill the core. After the concrete solidifies, a plain concrete cushion 8 is poured around the pile that is lower than the top of the pile. The distance between the upper surface of the annular end plate 10 and the upper surface of the plain concrete cushion 8 is 50mm. Finally, the cap 9 is poured. The anchor bars 12 on the anchor plate 11 and the anchor bars 310 at the top of the inner steel cage 3 are in the poured cap 9. The length of the anchor bars 310 in the cap 9 is LaE, and is ≥40d (d is the diameter of the anchor bars 310). The inclined section of the anchor bars 12 is in the cap 9, and its length is LaE, and is ≥40d (d is the diameter of the anchor bars 12).
[0065] ④, such as Figure 6As shown, if the actual construction height of the prestressed concrete pipe pile 1 is equal to the design height, the soil above the top of the pipe pile is excavated to form a hole surrounding the pipe pile, the bottom of the excavated hole is lower than the top of the pipe pile, and then a casing 13 is poured to protect the hole. The top of the casing 13 has a surrounding plain concrete cushion 8, which is lower than the top of the pipe pile, and is 50mm lower in this embodiment. The plain concrete cushion 8 is at least 1.5Ler higher than the bottom of the excavated hole, and ≥300mm. The outer steel cage 2 is made according to the inner diameter of the casing 13 and the inner diameter of the pipe pile. As well as the inner steel cage 3, the vertical reinforcement specification of the outer steel cage 2 is Φ12@200mm, that is, the third-grade steel bar, the stirrup specification is Φ8@50mm, the vertical reinforcement specification of the inner steel cage 3 is 6ф18mm, that is, the third-grade steel bar, the stirrup specification is Φ8@200mm, the outer steel cage 2 is arranged in the casing 13, and the lower end of the inner steel cage 3 is welded with a support plate 4 and then placed in the prestressed concrete pipe pile 1. For PHC-500B-125 piles, the distance between the lower end of the inner steel cage 3 and the top of the prestressed concrete pipe pile 1 is ≥4000mm, for For PHC-500AB-125 piles, the distance between the lower end of the inner steel cage 3 and the top of the prestressed concrete pipe pile 1 is ≥3000mm. A micro-expansion concrete 5 with a strength grade not lower than C30 and not lower than the cap 9 is poured into the pipe pile to fill the core, and concrete 14 with the same strength grade as the cap 9 is poured into the casing 13. After the concrete solidifies, the cap 9 is finally poured. The additional vertical reinforcement 210 at the top of the outer steel cage 2, the anchor reinforcement 310 at the top of the inner steel cage 3, and the prestressed reinforcement 110 of the pipe pile body are in the poured In the cap 9, the ends of some prestressed tendons 110 are bent horizontally, and the bending length is 15d (d is the diameter of the prestressed tendons 110), the length of the additional vertical tendons 210 in the cap 9 is 500mm, and the specification of the additional vertical tendons 210 is ф12@200mm, that is, the third-level steel bar, the length of the anchoring steel bar 310 in the cap 9 is LaE, and ≥40d (d is the diameter of the anchoring steel bar 310), and the length of the prestressed tendons 110 in the cap 9 is ≥50d (d is the diameter of the prestressed tendons 110), and ≥500mm;
[0066] ⑤. If Figure 7As shown, if the actual construction height of the prestressed concrete pipe pile 1 is less than the designed height, the soil above the top of the pipe pile is excavated to form a hole surrounding the pipe pile, the bottom of the excavated hole is lower than the top of the pipe pile, and the bottom of the excavated hole is at least 500mm lower than the top of the pipe pile. An annular end plate 10 is fixed on the top of the pipe pile, and a plurality of anchor plates 11 are welded in a ring shape on the end plate, for example, 12 anchor plates 11, the height of the anchor plates 11 is 30mm, and anchor bars 12 are welded on each anchor plate 11. The anchor bars 12 are distributed vertically. The anchor bars 12 The specification is 6ф20mm. According to the inner diameter of the excavated hole and the inner diameter of the pile, the outer steel cage 2 and the inner steel cage 3 are respectively made. The vertical reinforcement specification of the outer steel cage 2 is Φ12@200mm, that is, the third-grade steel bar, and the stirrup specification is Φ8@50mm. The vertical reinforcement specification of the inner steel cage 3 is 6ф18mm, that is, the third-grade steel bar, and the stirrup specification is Φ8@200mm. The outer steel cage 2 is arranged in the excavated hole, and the lower end of the inner steel cage 3 is welded with a support plate 4 and then placed in the prestressed concrete pile 1. For PHC- For 500B-125 piles, the distance between the lower end of the inner steel cage 3 and the upper surface of the annular end plate 10 is ≥4000mm. For PHC-500AB-125 piles, the distance between the lower end of the inner steel cage 3 and the upper surface of the annular end plate 10 is ≥3000mm. The support bars in the middle area of the inner steel cage 3 are placed on the top of the pile to allow the inner steel cage 3 to be suspended. A micro-expansive concrete 5 with a strength grade not lower than C30 and not lower than the foundation 9 is poured into the pile to fill the core, and concrete with a strength grade higher than the foundation 9 is poured into the excavated hole. The pile connection concrete 6 is one grade higher and not lower than C30. After the concrete solidifies, a plain concrete cushion layer 8 lower than the top of the pipe pile is poured around the pile connection 7, and finally the cap 9 is poured. The additional vertical reinforcement 210 and the anchor reinforcement 12 at the top of the outer steel cage 2 are in the poured cap 9. The length of the additional vertical reinforcement 210 in the cap 9 is LaE, and ≥40d (d is the diameter of the additional vertical reinforcement 210). The anchor reinforcement 12 is in the cap 9, and the length is LaE, and ≥40d (d is the diameter of the anchor reinforcement 12).
[0067] Example 7
[0068] This embodiment is a further improvement on the basis of the embodiment 6, and the details are as follows:
[0069] The core filling of the micro-expansive concrete 5 poured in the pipe pile with a strength grade not lower than C30 and not lower than the pedestal 9 is C35 micro-expansive concrete.
[0070] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.
Claims
1. A prestressed structure construction method, characterized in that: The steps include: S1. Site surface leveling: Level the site surface to ensure that the surface soil bearing capacity characteristic value meets the requirements for stable operation of the pile driver; S2. Pile driving: static pile driving is used. The piles driven are PHC series prestressed concrete pipe piles. The construction progress of pile driving is controlled and the pile driving sequence is followed: deep first, shallow second, middle first, periphery second, main building first, podium second. The depth of the prestressed concrete pipe pile end entering the bearing layer is ≥1.0m; S3. Excavation of foundation pit: After all piles are sunk, excavation of foundation pit shall be carried out in layers, and the height difference shall not exceed 1m; S4. Determine the connection structure: Determine the connection structure between each prestressed concrete pile and the cap according to the relationship between the actual construction height and the design height of each prestressed concrete pile, and carry out the corresponding operation procedures respectively; S5. Backfill the foundation pit: drain the accumulated water, remove the loose soil and construction waste, and fill the soil with clay, gray soil or plain concrete and compact it layer by layer.
2. A prestressed structure construction method according to claim 1, characterized in that: If the pile driver is a static pressure pile driver, the characteristic value of the surface soil bearing capacity shall not be less than 100kPa; if the weight of the pile driver is greater than 4000kN, the characteristic value of the surface soil bearing capacity shall not be less than 120kPa, otherwise, backfill with crushed stone or construction slag and compact it before construction.
3. A prestressed structure construction method according to claim 1 or 2, characterized in that: The pressed piles are PHC series prestressed concrete pipe piles. The concrete strength grade of the pile body is C80. The pile tip adopts a closed cross pile tip, and the pile end is poured with 1.5m thick C20 shrinkage compensating concrete.
4. A prestressed structure construction method according to claim 1, 2 or 3, characterized in that: Pile driving is mainly controlled by pile driving force and supplemented by pile length control. Stabilization of pile driving should be carried out before final driving. The stabilization pile driving force should not be less than the final pressure and the stable pile driving time is 3 minutes. For pile foundations whose pile driving force meets the test pile and design requirements but whose pile length does not reach the designed pile length, the pile driving force should be increased to not less than 1.1 times of the designed pile driving force and not exceeding the allowable pile driving force of the pile body. When sinking piles in deep saturated soft soil, if there is no experience in arranging piles densely, the horizontal displacement of the pile top should be monitored during the construction process, and the number of monitored piles should not be less than 6. During the pile driving construction, the changes in the pile top elevation should be monitored, and the number of inspections should not be less than 5% of the total number of piles, and should not be less than 10.
5. A prestressed structure construction method according to claim 1, characterized in that: The excavation of foundation pits for silt and saturated clay should be carried out 10 days after all pile sinking is completed. Saturated clay contains silt and silty soil. The earthwork within 1.0m above the pile top should be carried out by small machinery in combination with manual labor. If the pile tops are uneven during foundation pit excavation, the pile heads should be excavated out manually in batches, and then excavation should be carried out after the piles are cut. The excavation of foundation pits in soft soil areas should be carried out in a balanced and layered manner by small machinery in combination with manual labor.
6. A prestressed structure construction method according to claim 1, characterized in that: Single pile connection should be carried out after the pile tip passes through the hard soil layer to avoid the pile tip approaching the hard bearing layer or the pile tip being in the hard bearing layer. The number of joints for any single pile shall not exceed 2.
7. A prestressed structure construction method according to claim 1, characterized in that: When pipe piles are used in high-rise buildings, if there is soft soil with a bearing capacity characteristic value of 70kPa or less under the pedestal, cement-soil mixing piles should be used to fully interlock the soil under the pedestal. Concrete or sand and gravel replacement can also be used. The reinforcement or replacement treatment depth should not be less than 2m below the bottom of the pedestal, or to the top surface of the better soil layer below the bottom of the pedestal. The reinforcement range around the pedestal should not be less than 1m. After the soil reinforcement, continuous penetration dynamic probing and core drilling detection should be carried out.
8. A prestressed structure construction method according to claim 1, characterized in that: S4 has the following situations: ① If the actual construction height of the prestressed concrete pipe pile is less than the design height, the soil above the top of the pipe pile is excavated to form a hole surrounding the pipe pile. The bottom of the excavated hole is lower than the top of the pipe pile. The outer steel cage and the inner steel cage are respectively made according to the inner diameter of the excavated hole and the inner diameter of the pipe pile. The outer steel cage is arranged in the excavated hole. The lower end of the inner steel cage is welded with a support plate and then placed in the prestressed concrete pipe pile. The support bars in the middle area of the inner steel cage are placed on the top of the pipe pile to allow the inner steel cage to be suspended. The micro-expansive concrete core filling with a strength grade not less than C30 and not less than the cap strength grade is poured in the pipe pile, and the connection pile concrete with a grade higher than the cap concrete and not less than C30 is poured in the excavated hole. After the concrete solidifies, a plain concrete cushion layer is poured outside the connection pile that is lower than the top of the connection pile. Finally, the cap is poured. The additional vertical bars at the top of the outer steel cage and the anchor bars at the top of the inner steel cage are in the poured cap. ② If the actual construction height of the prestressed concrete pile is equal to the design height, an inner steel cage is made according to the inner diameter of the pile, and a support plate is welded at the lower end of the inner steel cage and then placed in the prestressed concrete pile. The support bars in the middle area of the inner steel cage are placed on the top of the pile to allow the inner steel cage to be suspended. A micro-expansive concrete core is poured in the pile with a strength grade not lower than C30 and not lower than the cap. After the concrete solidifies, a plain concrete cushion layer is poured around the pile that is lower than the top of the pile. Finally, the cap is poured, and the anchor steel bars at the top of the inner steel cage are in the poured cap. ③. If the actual construction height of the prestressed concrete pipe pile is equal to the design height, a ring-shaped end plate is fixed on the top of the pipe pile, and multiple anchor plates are welded in a ring shape on the ring-shaped end plate. Anchor bars extending outward are welded on each anchor plate. An inner steel cage is made according to the inner diameter of the pipe pile, and a support plate is welded at the lower end of the inner steel cage and then placed in the prestressed concrete pipe pile. A micro-expansive concrete core filling with a strength grade not lower than C30 and not lower than the cap strength grade is poured in the pipe pile. After the concrete solidifies, a plain concrete cushion layer is poured around the outer periphery of the pipe pile that is lower than the top of the pipe pile. Finally, the cap is poured, and the anchor bars on the anchor plate and the anchor steel bars at the top of the inner steel cage are in the poured cap. ④. If the actual construction height of the prestressed concrete pipe pile is equal to the design height, the soil above the top of the pipe pile is excavated to form a hole surrounding the pipe pile. The bottom of the excavated hole is lower than the top of the pipe pile. Then a casing is cast to protect the hole. The top of the casing has a surrounding plain concrete cushion layer. The plain concrete cushion layer is lower than the top of the pipe pile. According to the inner diameter of the casing and the inner diameter of the pipe pile, an outer steel cage and an inner steel cage are respectively made. The outer steel cage is arranged in the casing. After the lower end of the inner steel cage is welded with a support plate, it is lowered into the prestressed concrete pipe pile. A micro-expansive concrete core filling of not less than C30 and not less than the strength grade of the cap is cast in the pipe pile, and concrete of the same strength grade as the cap is cast in the casing. After the concrete solidifies, the cap is finally cast. The additional vertical reinforcement at the top of the outer steel cage, the anchor reinforcement at the top of the inner steel cage and the prestressed reinforcement of the pipe pile body are in the cast cap. ⑤. If the actual construction height of the prestressed concrete pipe pile is less than the design height, the soil above the top of the pipe pile is excavated to form a hole surrounding the pipe pile. The bottom of the excavated hole is lower than the top of the pipe pile. An annular end plate is fixed on the top of the pipe pile, and multiple anchor plates are welded in a ring shape on the end plate. Anchor bars are welded on each anchor plate. An outer steel cage and an inner steel cage are made according to the inner diameter of the excavated hole and the inner diameter of the pipe pile. The outer steel cage is arranged in the excavated hole. After the support plate is welded at the lower end of the inner steel cage, it is lowered into the prestressed concrete pipe pile. The support bars in the middle area of the inner steel cage are placed on the top of the pipe pile to allow the inner steel cage to be suspended. A micro-expansive concrete core filling of not less than C30 and not less than the strength grade of the cap is poured in the pipe pile, and a connection pile concrete of one grade higher than the cap concrete and not less than C30 is poured in the excavated hole. After the concrete solidifies, a plain concrete cushion layer lower than the top of the pipe pile is poured around the connection pile. Finally, the cap is poured. The additional vertical bars and anchor bars at the top of the outer steel cage are in the poured cap.
9. A prestressed structure construction method according to claim 8, characterized in that: In case ①, the inner diameter of the hole is 300mm larger than the outer diameter of the pipe pile, and the bottom of the hole is at least 500mm lower than the top of the pipe pile; in case ④, the inner diameter of the casing is 400mm larger than the outer diameter of the pipe pile, and the inner bottom of the casing is at least 350mm lower than the top of the pipe pile; in case ⑤, the inner diameter of the hole is 400mm larger than the outer diameter of the pipe pile, and the bottom of the hole is at least 500mm lower than the top of the pipe pile.
10. A prestressed structure construction method according to claim 8, characterized in that: The micro-expansive concrete core poured in the pipe pile is C35 micro-expansive concrete with a strength grade not lower than C30 and not lower than the foundation.
Citation Information
Cited By
PHC pile with conical integrated concrete pile tip and construction method of PHC pile
CN120061330A
PHC Pile with a Concrete Conical Integrated Pile Tip and Its Construction Method
CN120061330B