Building construction dust fall enclosing wall
By designing splicing and reciprocating push and pull mechanisms in the dust reduction wall in the construction construction, the water mist spraying range is expanded and debris is automatically cleaned, which solves the poor dust reduction effect and water quality problems in the existing technology, and achieves more efficient dust reduction and water resource utilization .
Patent Information
- Application Number
- CN202411548701.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-01
- Publication Date
- 2025-01-07
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing construction dust reduction wall cannot expand the spray range of water mist, resulting in poor dust reduction effect in some areas, and it is impossible to regularly clean the debris on the filter when collecting rainwater, affecting water quality and filtration efficiency.
A construction dust reduction fence including a wall water tank, a connecting frame, a splicing mechanism, atomization dust reduction mechanism and reciprocating push and pulling mechanism was designed. By splicing multiple sets of wall water tanks and starting reciprocating push and pulling mechanisms, the scope of water mist spraying is expanded, and the Automatically scrape and sweep debris during spraying.
It improves the dust reduction effect and water resource utilization efficiency, ensures the normal operation of the dust reduction system, reduces equipment failures caused by debris blockage, and adapts to the needs of construction sites of different sizes.
Smart Images

Figure CN119266625A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of dust reduction walls for building construction, in particular to a dust reduction wall for building construction. Background Art
[0002] In today's society, people have higher and higher requirements for the environment. Construction sites must meet environmental protection standards to carry out normal construction. During construction, the construction area needs to be enclosed with a wall, and sprinkler nozzles are installed on the wall. The sprinkler nozzles spray water mist. When the dust in the construction site spreads to the edge of the wall, the dust absorbs the water mist, and the weight increases, causing the dust to settle, thus ensuring the environment around the construction site.
[0003] For example, the patent with the national authorized patent announcement number CN218901274U discloses a construction dust reduction fence, including a main body, a water collection mechanism and a dust reduction mechanism, wherein the water collection mechanism is located at the upper end of the main body, and the dust reduction mechanism is located at the upper end of the front end of the main body. The main body includes a base plate, a ground nail, a water tank body, a fence body and an uncovered water collection tank, wherein the ground nail is fixedly installed at the lower end of the base plate, the water tank body is fixedly installed at the upper end of the base plate, the fence body is fixedly installed at the upper end of the water tank body, and the uncovered water collection tank is fixedly installed at the upper end of the fence body. The construction dust reduction fence, by installing a water collection mechanism, is convenient for recycling rainwater, saves a certain amount of water resources, reduces a certain amount of water use costs, improves practicality, conforms to the environmental protection concept of today's society, is conducive to sustainable development, is convenient and quick to use, and improves adaptability.
[0004] However, when the water mist is sprayed on the above-mentioned construction dust reduction fence to reduce dust, the sprayed water mist cannot be reciprocated to increase the spraying area of the water mist. In a large area such as a construction site, the limited spraying area cannot fully cover the range where dust reduction is required, which will lead to poor dust reduction effect in some areas, and dust is still easy to fly, affecting the air quality of the construction site and the surrounding area;
[0005] In the process of collecting rainwater, the debris on the filter cannot be cleaned regularly, which will reduce the filtering efficiency of the filter and make the rain entering the water collection tank carry more impurities, affecting the water quality in the water tank and clogging or damaging the filter, which will affect the collection of rainwater. Summary of the invention
[0006] The purpose of the present invention is to provide a construction dust reduction fence to solve the problems raised in the above background technology that when spraying water mist to reduce dust, the sprayed water mist cannot be swung back and forth to increase the spraying area of the water mist, and the debris on the filter net cannot be cleaned regularly during the process of collecting rainwater.
[0007] To achieve the above object, the present invention provides the following technical solutions:
[0008] A construction dust reduction fence, comprising: a fence water tank, connecting frames are fixedly installed on both sides of the fence water tank, and atomizing dust reduction mechanisms are rotatably installed between two groups of connecting frames and in the connecting frames;
[0009] Among them, one end of the two groups of connecting frames is fixedly installed with a splicing mechanism, so that the wall water tank can be buckled on the outer surface of the splicing mechanism of another group of wall water tanks through the splicing mechanism, so as to realize the splicing of multiple groups of wall water tanks;
[0010] Among them, one end of the wall water tank is connected to a back plate, and an installation groove is sealed between the back plates. A reciprocating push-pull mechanism is fixedly installed in the installation groove. The push-pull end of the reciprocating push-pull mechanism is rotatably connected to one end of the atomizing dust reduction mechanism, so that the reciprocating push-pull mechanism can reciprocately push and pull the atomizing dust reduction mechanism to swing up and down and left and right within the two sets of connecting frames.
[0011] Preferably, water collecting troughs are provided on both sides of the upper surface of the back plate, and filter holes are provided in the water collecting troughs, so that the water collecting troughs are connected with the back plate and the wall water tank through the filter holes, so that the water collecting troughs can receive rainwater and store it in the back plate and the wall water tank.
[0012] Preferably, one end of the back plate is connected to and installed with a tee, and the other end of the tee is connected to and installed with a ball valve, so that the ball valve can be connected to a water pipe to fill water into the wall water tank.
[0013] Preferably, the splicing mechanism includes a first arc clamp, which is fixedly mounted on one end of the connecting frame, and a second arc clamp is rotatably mounted on one end of the first arc clamp, so that the first arc clamp and the second arc clamp can fit the C-shaped column therein, and the C-shaped column is fixedly mounted on one end of the connecting frame on the other side, thereby realizing the splicing of multiple groups of the wall water tanks.
[0014] Preferably, a lock buckle is rotatably installed at one end of the second arc clamp, and the lock buckle can be buckled on the outer surface of the lock tongue. The lock tongue is fixedly installed at one end of the first arc clamp, so that the pulling force of the first arc clamp on the outer surface of the lock tongue through the lock buckle can pull the second arc clamp to one end of the first arc clamp, so that the first arc clamp and the second arc clamp can be firmly mounted on the outer surface of the C-shaped column.
[0015] Preferably, the atomization dust reduction mechanism includes a first connecting pipe and two groups of second connecting pipes, the first connecting pipe and the two groups of second connecting pipes are rotatably installed between the two groups of connecting frames and in the two groups of connecting frames respectively, an L-shaped pipe is rotatably connected between the first connecting pipe and the second connecting pipe, the L-shaped pipe is located in the connecting frame, the lower surface of the second connecting pipe is rotatably installed in a bearing seat, the bearing seat is fixedly installed on the lower surface inside the connecting frame, one end of the bearing seat is connected and installed with a straight pipe, the straight pipe seals and penetrates into the wall water tank, the other end of the straight pipe is connected and installed with a drain outlet of a submersible pump, and the submersible pump is fixedly installed on the lower surface inside the wall water tank.
[0016] Preferably, first bevel gears are fixedly installed on both sides of the first connecting pipe, the first bevel gears rotate in the connecting frame and mesh with the second bevel gears, the second bevel gears are fixedly installed on the upper surface of the second connecting pipe, and one end of the first connecting pipe and the second connecting pipe are both connected and installed with multiple groups of atomizing nozzles.
[0017] Preferably, the reciprocating push-pull mechanism includes a dual-axis motor, which is fixedly mounted in a mounting groove, and an eccentric shaft is fixedly mounted on the outer surface of the output shaft on both sides of the dual-axis motor, a connecting arm is rotatably mounted in the eccentric shaft, and the other end of the connecting arm is rotatably mounted on the outer surface of the docking rod, and the docking rod is fixedly mounted on one end of the outer surface of the first connecting tube.
[0018] Preferably, the connecting arm can be driven by the eccentric shaft of the dual-axis motor to rotate in a reciprocating push-pull shape of the docking rod, so that the docking rod can pull the first connecting tube to swing up and down between the two groups of connecting frames, and the up and down swinging first connecting tube will drive the first bevel gear to mesh and transmit the two groups of second bevel gears, so that the second bevel gear can drive the second connecting tube to swing left and right in the connecting frame.
[0019] Preferably, a C-shaped scraper is fixedly installed at one end of the eccentric shaft, and the C-shaped scraper extends through the installation groove and is rotatably installed in the water collection tank, so that the C-shaped scraper is driven by the dual-axis motor to rotate counterclockwise, so that the C-shaped scraper can scrape and push out the debris in the water collection tank.
[0020] Compared with the prior art, the present invention has the following beneficial effects:
[0021] 1. Through the design of the wall water tank, connecting frame, back plate, water collecting tank, splicing mechanism, atomizing dust reduction mechanism and reciprocating push-pull mechanism, when in use, the staff can splice and discharge multiple sets of wall water tanks through the splicing mechanism according to the site area. This flexibility makes the dust reduction work adaptable to construction sites of different sizes. Whether it is a small construction site or a large construction project site, the dust reduction needs can be met by adjusting the splicing number and arrangement of the wall water tank, which improves the versatility of the equipment. Then, the ball valve can be connected to the external water pipe and water can be injected into the wall water tank for the atomizing dust reduction mechanism to draw the water source in the wall water tank and spray it out in atomization. The water mist can cover the construction site more evenly, effectively absorb dust particles, and reduce the dust content in the air. While spraying the water mist, the reciprocating push-pull mechanism can be started to push and pull the atomizing dust reduction mechanism up and down and left and right to swing, which greatly increases the spraying range of the water mist, further improves the dust reduction effect, and reduces the dust pollution to the construction site and the surrounding environment. In addition, through atomizing dust reduction and spraying in a larger range, the water resources in the wall water tank can be more fully utilized. Compared with spraying in a fixed direction and a limited range, this method can make every drop of water play a greater role in dust reduction, avoid the waste of water resources, and meet the requirements of energy saving and environmental protection.
[0022] In daily use, the water collecting trough opened on the upper surface of the back panel can collect and store rainwater in the wall water tank, and can atomize and spray it out when in use. In the process of starting the reciprocating push-pull mechanism, the reciprocating push-pull mechanism will also rotate together in the water collecting trough to scrape out debris, which can prevent debris from accumulating in the water collecting trough and entering the wall water tank or affecting the rainwater collection function of the water collecting trough. Keeping the water collecting trough clean can ensure the normal operation of the entire dust reduction system and reduce equipment failures caused by problems such as blockage by debris.
[0023] 2. Through the design of the first arc clamp, the second arc clamp, the lock buckle, the C-shaped column and the lock tongue, when multiple sets of wall water tanks are spliced together, the top of the C-shaped column at one end of the connecting frame of another set of wall water tanks can be inserted into the first arc clamp, and then the second arc clamp can be turned over and sleeved on the outer surface of the C-shaped column, and the lock buckle at one end of the second arc clamp can be buckled on the outer surface of the lock tongue at one end of the first arc clamp, thereby realizing the locking sleeve of the first arc clamp and the second arc clamp on the outer surface of the C-shaped column, that is, realizing the splicing operation between multiple wall water tanks, and this simple splicing method can make multiple sets of wall water tanks The splicing process is completed quickly. In construction sites, time is often tight. Quick splicing can reduce the time of equipment installation, so that dust reduction work can be put into use faster and the dust reduction function can be brought into play as soon as possible, so that staff can splice and discharge multiple sets of wall water tanks according to the site area. This flexibility allows dust reduction work to adapt to construction sites of different sizes. Whether it is a small construction site or a large construction project site, the dust reduction needs can be met by adjusting the number and arrangement of splicing water tanks, thereby improving the versatility of the equipment.
[0024] 3. Through the design of the first connecting pipe, the second connecting pipe, the first bevel gear, the second bevel gear, the submersible pump and the L-shaped pipe, after splicing multiple sets of wall water tanks, the submersible pump can be started, and the submersible pump can draw water from the wall water tank and discharge it into the second connecting pipe through the straight pipe and the bearing seat, and the second connecting pipe is connected to the first connecting pipe through the L-shaped pipe, so that the submersible pump injects water into the first connecting pipe and the second connecting pipe, and the first connecting pipe and the second connecting pipe spray water mist through the atomizing nozzles connected and installed on the surface, so as to achieve dust reduction operation;
[0025] While spraying water mist, the reciprocating push-pull mechanism can also be started to push and pull the docking rod fixedly installed at one end of the outer surface of the first connecting tube, driving the first connecting tube to rotate in an up and down swing shape between the two sets of connecting frames, and the swinging rotation of the first connecting tube will drive the first bevel gear to mesh with the second bevel gear, so that the second bevel gear drives the second connecting tube to swing left and right horizontally in the connecting frame. This up and down and left and right swinging rotation can greatly increase the coverage of the water mist and achieve all-round dust reduction, which can effectively avoid the dust reduction dead corners caused by spraying in a single direction, so that the dust on the construction site can be more thoroughly suppressed, and through the swinging and rotating operation, the water mist can be more evenly distributed in the construction area, and each drop of water mist can better play a dust reduction role. Compared with spraying in a fixed direction, the waste of water resources caused by local excessive spraying is reduced, and the utilization efficiency of water resources is improved.
[0026] 4. Through the design of the double-shaft motor, eccentric shaft, connecting arm and U-shaped scraper, when the first connecting pipe and the second connecting pipe spray water mist, the double-shaft motor can be started to drive the connecting arm at one end of the eccentric shaft to rotate, and the other end of the connecting arm is rotatably installed on the outer surface of the docking rod, so that the connecting arm pushes and pulls the docking rod up and down to drive the first connecting pipe to rotate between the two sets of connecting frames, and then the first connecting pipe can be driven by the first bevel gear to mesh with the second bevel gear on the upper surface of the second connecting pipe, so as to drive the first connecting pipe and the second connecting pipe to swing and rotate in the up and down and left and right directions to increase the coverage of the water mist and achieve all-round dust reduction;
[0027] In addition, the dual-axis motor drives the eccentric shaft to rotate while also driving the C-shaped scraper to rotate and scrape inside the water collection tank. This automatic scraping function reduces the workload of manual cleaning of the water collection tank, making equipment maintenance more convenient. There is no need to arrange special personnel to perform frequent cleaning work, which can ensure the normal operation of the water collection tank and the entire dust reduction equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 This is a schematic diagram of the overall structure of the construction dust reduction wall of the present invention;
[0029] Figure 2 It is a schematic structural diagram of the back plate and the water collecting tank of the present invention;
[0030] Figure 3 It is a structural schematic diagram of the atomization dust reduction mechanism of the present invention;
[0031] Figure 4 It is a schematic diagram of the structure in which the first bevel gear and the second bevel gear of the present invention are meshed;
[0032] Figure 5 It is a structural schematic diagram of the submersible pump of the present invention;
[0033] Figure 6 It is a structural schematic diagram of the reciprocating push-pull mechanism of the present invention;
[0034] Figure 7 It is a schematic structural diagram of the U-shaped scraper blade of the present invention.
[0035] In the figure: 1. wall water tank; 101. connecting frame; 102. back plate; 103. ball valve; 104. three-way pipe; 105. water collecting trough; 106. bearing seat; 107. mounting groove; 2. splicing mechanism; 201. first arc clamp; 202. second arc clamp; 203. lock buckle; 204. U-shaped column; 205. lock tongue; 3. atomization dust suppression mechanism; 301. first connecting pipe; 302. first bevel gear; 303. L-shaped pipe; 304. second bevel gear; 305. second connecting pipe; 306. submersible pump; 307. straight pipe; 308. docking rod; 4. reciprocating push-pull mechanism; 401. double-axis motor; 402. eccentric shaft; 403. connecting arm; 404. U-shaped scraper. DETAILED DESCRIPTION
[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0037] See also Figure 1-Figure 7 , this embodiment provides the following technical solutions:
[0038] like Figure 1-Figure 2 As shown, a construction dust reduction fence comprises: a fence water tank 1, connecting frames 101 are fixedly installed on both sides of the fence water tank 1, and atomizing dust reduction mechanisms 3 are rotatably installed between two sets of connecting frames 101 and in the connecting frames 101;
[0039] Among them, the two sets of connecting frames 101 are fixedly installed with a splicing mechanism 2 at one end, so that the wall water tank 1 can be buckled on the outer surface of the splicing mechanism 2 of another set of wall water tanks 1 through the splicing mechanism 2, so as to realize the splicing of multiple sets of wall water tanks 1;
[0040] Among them, one end of the wall water tank 1 is connected to a back plate 102, and an installation groove 107 is sealed between the back plates 102. A reciprocating push-pull mechanism 4 is fixedly installed in the installation groove 107. The push-pull end of the reciprocating push-pull mechanism 4 is rotatably connected to one end of the atomizing dust reduction mechanism 3, so that the reciprocating push-pull mechanism 4 can reciprocately push and pull the atomizing dust reduction mechanism 3 to swing up and down and left and right within the two sets of connecting frames 101 and the connecting frames 101.
[0041] Water collecting grooves 105 are provided on both sides of the upper surface of the back plate 102. Filter holes are provided in the water collecting grooves 105, so that the water collecting grooves 105 are connected with the back plate 102 and the wall water tank 1 through the filter holes, so that the water collecting grooves 105 can receive rainwater and store it in the back plate 102 and the wall water tank 1.
[0042] One end of the back plate 102 is connected to a tee pipe 104 , and the other end of the tee pipe 104 is connected to a ball valve 103 , so that the ball valve 103 can be connected to a water pipe to fill water into the wall water tank 1 .
[0043] Through the design of the wall water tank 1, the connecting frame 101, the back plate 102, the water collecting trough 105, the splicing mechanism 2, the atomizing dust reduction mechanism 3 and the reciprocating push-pull mechanism 4, when in use, the staff can splice and discharge multiple sets of wall water tanks 1 through the splicing mechanism 2 according to the area of the site. This flexibility allows the dust reduction work to adapt to construction sites of different sizes. Whether it is a small construction site or a large construction project site, the dust reduction needs can be met by adjusting the splicing number and arrangement of the wall water tank 1, thereby improving the versatility of the equipment. Subsequently, the ball valve 103 can be connected to the external water pipe and water can be injected into the wall water tank 1, so that the atomizing dust reduction mechanism 3 can draw the water source in the wall water tank 1 into the wall water tank 1 and inject the water into the wall water tank 1. The atomized water mist can cover the construction site more evenly, effectively absorb dust particles, and reduce the dust content in the air. While spraying the water mist, the reciprocating push-pull mechanism 4 can be started to reciprocate and push-pull the atomizing dust reduction mechanism 3 to perform up and down and left and right swing operations, which greatly increases the spraying range of the water mist, further improves the dust reduction effect, and reduces the dust pollution to the construction site and the surrounding environment. In addition, through atomizing dust reduction and spraying in a larger range, the water resources in the wall water tank 1 can be more fully utilized. Compared with spraying in a fixed direction and a limited range, this method can make every drop of water play a greater role in dust reduction, avoid waste of water resources, and meet the requirements of energy saving and environmental protection.
[0044] In the process of daily use, the water collecting trough 105 opened on the upper surface of the back plate 102 can collect and store rainwater in the wall water tank 1, and can spray it out in atomization when in use. In the process of starting the reciprocating push-pull mechanism 4, the reciprocating push-pull mechanism 4 will also rotate in the water collecting trough 105 to scrape out debris, which can prevent debris from accumulating in the water collecting trough 105, avoid debris from entering the wall water tank 1 or affecting the rainwater collection function of the water collecting trough 105, keep the water collecting trough 105 clean, and ensure the normal operation of the entire dust reduction system, and reduce equipment failures caused by problems such as blockage by debris.
[0045] like Figure 3 As shown, the splicing mechanism 2 includes a first arc clamp 201, which is fixedly mounted on one end of the connecting frame 101, and a second arc clamp 202 is rotatably mounted on one end of the first arc clamp 201, so that the first arc clamp 201 and the second arc clamp 202 can fit a C-shaped column 204 therein, and the C-shaped column 204 is fixedly mounted on one end of the connecting frame 101 on the other side, thereby realizing the splicing of multiple sets of wall water tanks 1.
[0046] A lock buckle 203 is rotatably installed at one end of the second arc clamp 202, and the lock buckle 203 can be buckled on the outer surface of the lock tongue 205. The lock tongue 205 is fixedly installed at one end of the first arc clamp 201, so that the pulling force of the first arc clamp 201 on the outer surface of the lock tongue 205 through the lock buckle 203 can pull the second arc clamp 202 to one end of the first arc clamp 201, so that the first arc clamp 201 and the second arc clamp 202 can be firmly mounted on the outer surface of the U-shaped column 204.
[0047] Through the design of the first arc clip 201, the second arc clip 202, the lock buckle 203, the C-shaped column 204 and the lock tongue 205, when multiple sets of wall water tanks 1 are spliced together, the C-shaped column 204 at one end of the connecting frame 101 of another set of wall water tanks 1 can be inserted into the first arc clip 201, and then the second arc clip 202 can be turned over and sleeved on the outer surface of the C-shaped column 204, and the lock buckle 203 at one end of the second arc clip 202 can be buckled on the outer surface of the lock tongue 205 at one end of the first arc clip 201, thereby realizing the locking sleeve of the first arc clip 201 and the second arc clip 202 on the outer surface of the C-shaped column 204, that is, the splicing of multiple wall water tanks 1 is realized. The simple splicing method can quickly complete the splicing process between multiple sets of wall water tanks 1. At construction sites, time is often tight, and fast splicing can reduce the time for equipment installation, so that the dust reduction work can be put into use faster and the dust reduction function can be brought into play as soon as possible, so that the staff can splice and discharge multiple sets of wall water tanks 1 according to the site area. This flexibility allows the dust reduction work to adapt to construction sites of different sizes. Whether it is a small construction site or a large construction project site, the dust reduction needs can be met by adjusting the splicing quantity and arrangement of the water tanks, thereby improving the versatility of the equipment.
[0048] like Figure 4-Figure 5 As shown, the atomization dust reduction mechanism 3 includes a first connecting pipe 301 and two groups of second connecting pipes 305. The first connecting pipe 301 and the two groups of second connecting pipes 305 are rotatably installed between the two groups of connecting frames 101 and in the two groups of connecting frames 101 respectively. An L-shaped pipe 303 is rotatably connected between the first connecting pipe 301 and the second connecting pipe 305. The L-shaped pipe 303 is located in the connecting frame 101. The lower surface of the second connecting pipe 305 is rotatably installed in the bearing seat 106. The bearing seat 106 is fixedly installed on the lower surface of the connecting frame 101. One end of the bearing seat 106 is connected and installed with a straight pipe 307. The straight pipe 307 is sealed and penetrates into the wall water tank 1. The other end of the straight pipe 307 is connected and installed with the drain outlet of the submersible pump 306. The submersible pump 306 is fixedly installed on the lower surface of the wall water tank 1.
[0049] First bevel gears 302 are fixedly installed on both sides of the first connecting pipe 301. The first bevel gears 302 rotate in the connecting frame 101 and mesh with the second bevel gears 304. The second bevel gears 304 are fixedly installed on the upper surface of the second connecting pipe 305. One end of the first connecting pipe 301 and the second connecting pipe 305 are connected and multiple groups of atomizing nozzles are installed.
[0050] Through the design of the first connecting pipe 301, the second connecting pipe 305, the first bevel gear 302, the second bevel gear 304, the submersible pump 306 and the L-shaped pipe 303, after a plurality of sets of wall water tanks 1 are spliced together, the submersible pump 306 can be started, and the submersible pump 306 can draw water from the wall water tank 1 and discharge it into the second connecting pipe 305 through the straight pipe 307 and the bearing seat 106, and the second connecting pipe 305 is connected to the first connecting pipe 301 through the L-shaped pipe 303, so that the submersible pump 306 injects water into the first connecting pipe 301 and the second connecting pipe 305, so that the first connecting pipe 301 and the second connecting pipe 305 spray water mist through the atomizing nozzles connected and installed on the surface, thereby realizing the dust reduction operation;
[0051] When spraying water mist, the reciprocating push-pull mechanism 4 can be started to push and pull the docking rod 308 fixedly installed at one end of the outer surface of the first connecting tube 301, driving the first connecting tube 301 to rotate in an up and down swinging shape between the two sets of connecting frames 101, and the swinging rotation of the first connecting tube 301 will drive the first bevel gear 302 to mesh with the second bevel gear 304, so that the second bevel gear 304 drives the second connecting tube 305 to rotate horizontally in the connecting frame 101. This up and down and left and right swinging rotation can greatly increase the coverage of the water mist and achieve all-round dust reduction. It can effectively avoid the dust reduction dead corners caused by spraying in a single direction, so that the dust on the construction site can be more thoroughly suppressed. Moreover, through the swinging and rotating operation, the water mist can be more evenly distributed in the construction area, and each drop of water mist can better play a dust reduction role. Compared with spraying in a fixed direction, the waste of water resources caused by local excessive spraying is reduced, and the utilization efficiency of water resources is improved.
[0052] like Figure 6-Figure 7 As shown, the reciprocating push-pull mechanism 4 includes a dual-axis motor 401, which is fixedly installed in the installation groove 107. The outer surfaces of the output shafts on both sides of the dual-axis motor 401 are fixedly installed with eccentric shafts 402. A connecting arm 403 is rotatably installed in the eccentric shaft 402. The other end of the connecting arm 403 is rotatably installed on the outer surface of the docking rod 308. The docking rod 308 is fixedly installed on one end of the outer surface of the first connecting tube 301.
[0053] The connecting arm 403 can be driven by the eccentric shaft 402 of the dual-axis motor 401 to rotate in a reciprocating push-pull state of the docking rod 308, so that the docking rod 308 can pull the first connecting tube 301 to swing up and down between the two groups of connecting frames 101, and the up and down swinging first connecting tube 301 will drive the first bevel gear 302 to mesh and transmit the two groups of second bevel gears 304, so that the second bevel gear 304 can drive the second connecting tube 305 to swing left and right in the connecting frame 101.
[0054] A C-shaped scraper 404 is fixedly installed at one end of the eccentric shaft 402. The C-shaped scraper 404 passes through the installation groove 107 and is rotatably installed in the water collection tank 105, so that the C-shaped scraper 404 is driven by the dual-axis motor 401 to rotate counterclockwise, so that the C-shaped scraper 404 can scrape and push out the debris in the water collection tank 105.
[0055] Through the design of the double-axis motor 401, the eccentric shaft 402, the connecting arm 403 and the U-shaped scraper 404, when the first connecting tube 301 and the second connecting tube 305 spray water mist, the double-axis motor 401 can be started to drive the connecting arm 403 at one end of the eccentric shaft 402 to rotate, and the other end of the connecting arm 403 is rotatably installed on the outer surface of the docking rod 308, so that the connecting arm 403 pushes and pulls the docking rod 308 up and down to drive the first connecting tube 301 to rotate between the two groups of connecting frames 101, and then the first connecting tube 301 can be driven by the first bevel gear 302 to mesh with the second bevel gear 304 on the upper surface of the second connecting tube 305, so as to drive the first connecting tube 301 and the second connecting tube 305 to swing and rotate in the up-down and left-right directions to increase the coverage of the water mist and realize all-round dust reduction;
[0056] When the dual-axis motor 401 drives the eccentric shaft 402 to rotate, it will also drive the U-shaped scraper 404 to rotate and scrape inside the water collection tank 105. This automatic scraping function reduces the workload of manual cleaning of the water collection tank 105, making the maintenance of the equipment more convenient. There is no need to arrange special personnel to perform frequent cleaning work, which can ensure the normal operation of the water collection tank 105 and the entire dust reduction equipment.
[0057] According to the above technical scheme, the working steps of this scheme are summarized and sorted out: when in use, the staff can splice and arrange multiple sets of wall water tanks 1 according to the area of the site, and when splicing, the top of the U-shaped column 204 at one end of the connecting frame 101 of another set of wall water tanks 1 can be inserted into the first arc clamp 201, and then the second arc clamp 202 can be turned over and sleeved on the outer surface of the U-shaped column 204, and the lock buckle 203 at one end of the second arc clamp 202 can be buckled on the outer surface of the lock tongue 205 at one end of the first arc clamp 201. The first arc clamp 201 and the second arc clamp 202 are locked on the outer surface of the U-shaped column 204, that is, the splicing operation between multiple wall water tanks 1 is realized. After the multiple sets of wall water tanks 1 are spliced, the submersible pump 306 can be started, and the submersible pump 306 can draw water from the wall water tank 1 and discharge it into the second connecting pipe 305 through the straight pipe 307 and the bearing seat 106, and the second connecting pipe 305 is connected to the first connecting pipe 301 through the L-shaped pipe 303. , so that the submersible pump 306 injects water into the first connecting pipe 301 and the second connecting pipe 305, so that the first connecting pipe 301 and the second connecting pipe 305 spray water mist through the atomizing nozzle installed on the surface, so as to realize dust reduction operation, and while spraying water mist, the dual-axis motor 401 can also be started to drive the connecting arm 403 at one end of the eccentric shaft 402 to rotate, and the other end of the connecting arm 403 is rotatably installed on the outer surface of the docking rod 308, so that the connecting arm 403 pushes and pulls the docking rod 308 up and down to drive the first connecting pipe 301 to perform an up and down swinging rotation operation between the two sets of connecting frames 101, and the swinging rotation of the first connecting pipe 301 will drive the first bevel gear 302 to mesh with the second bevel gear 304, so that the second bevel gear 304 drives the second connecting pipe 305 to swing left and right horizontally in the connecting frame 101, and this swinging rotation in the up and down and left and right directions can greatly increase the coverage of the water mist and realize all-round dust reduction.
[0058] In summary: through the up and down and left and right swinging water mist spraying operation, the dust reduction dead corners caused by single-direction spraying can be effectively avoided, and the dust on the construction site can be more thoroughly suppressed. Through the swinging and rotating operation, the water mist can be more evenly distributed in the construction area, and each drop of water mist can better play a dust reduction role. Compared with spraying in a fixed direction, it reduces the waste of water resources caused by local excessive spraying and improves the utilization efficiency of water resources.
[0059] Parts not involved in the present invention are the same as the prior art or can be implemented by the prior art. Although the embodiments of the present invention have been shown and described, it is understood by those skilled in the art that various changes, modifications, substitutions and deformations can be made to these embodiments without departing from the principles and spirit of the present invention, and the scope of the present invention is defined by the attached claims and their equivalents.
Claims
1. A construction dust reduction fence, characterized in that: include: A wall water tank (1), wherein connecting frames (101) are fixedly installed on both sides of the wall water tank (1), and an atomizing dust reduction mechanism (3) is rotatably installed between the two groups of connecting frames (101) and in the connecting frames (101), wherein: A splicing mechanism (2) is fixedly mounted on one end of the two groups of connecting frames (101), so that the wall water tank (1) can be buckled onto the outer surface of the splicing mechanism (2) of another group of wall water tanks (1) through the splicing mechanism (2), thereby realizing the splicing of multiple groups of wall water tanks (1); One end of the wall water tank (1) is connected to a back plate (102) installed thereon, a mounting groove (107) is sealed between the back plates (102), a reciprocating push-pull mechanism (4) is fixedly installed in the mounting groove (107), and the push-pull end of the reciprocating push-pull mechanism (4) is rotatably connected to one end of the atomizing dust reduction mechanism (3), so that the reciprocating push-pull mechanism (4) can reciprocately push and pull the atomizing dust reduction mechanism (3) to swing up and down and left and right within the two sets of connecting frames (101) and the connecting frame (101).
2. A construction dust reduction fence according to claim 1, characterized in that: Water collecting grooves (105) are provided on both sides of the upper surface of the back plate (102), and filter holes are provided in the water collecting grooves (105), so that the water collecting grooves (105) are connected with the back plate (102) and the wall water tank (1) through the filter holes, so that the water collecting grooves (105) can receive rainwater and store it in the back plate (102) and the wall water tank (1).
3. A construction dust reduction fence according to claim 1, characterized in that: One end of the back plate (102) is connected to a tee pipe (104), and the other end of the tee pipe (104) is connected to a ball valve (103), so that the ball valve (103) can be connected to a water pipe to fill water into the wall water tank (1).
4. A construction dust reduction fence according to claim 1, characterized in that: The splicing mechanism (2) comprises a first arc clamp (201), the first arc clamp (201) is fixedly mounted on one end of a connecting frame (101), and a second arc clamp (202) is rotatably mounted on one end of the first arc clamp (201), so that the first arc clamp (201) and the second arc clamp (202) can fit a U-shaped column (204) therein, and the U-shaped column (204) is fixedly mounted on one end of the connecting frame (101) on the other side, thereby realizing the splicing of multiple sets of the wall water tanks (1).
5. A construction dust reduction fence according to claim 4, characterized in that: A lock buckle (203) is rotatably mounted on one end of the second arc clamp (202), and the lock buckle (203) can be buckled on the outer surface of a lock tongue (205). The lock tongue (205) is fixedly mounted on one end of the first arc clamp (201), so that the first arc clamp (201) is sleeved on the outer surface of the lock tongue (205) through the pulling force of the lock buckle (203) to pull the second arc clamp (202) to one end of the first arc clamp (201), so that the first arc clamp (201) and the second arc clamp (202) can be stably sleeved on the outer surface of the U-shaped column (204).
6. The construction dust reduction fence according to claim 1, characterized in that: The atomization dust reduction mechanism (3) comprises a first connecting pipe (301) and two groups of second connecting pipes (305); the first connecting pipe (301) and the two groups of second connecting pipes (305) are rotatably mounted between the two groups of connecting frames (101) and in the two groups of connecting frames (101), respectively; an L-shaped pipe (303) is rotatably connected between the first connecting pipe (301) and the second connecting pipe (305); the L-shaped pipe (303) is located in the connecting frame (101); and the second connecting pipe (303) is rotatably connected to the first connecting pipe (301) and the second connecting pipe (305). The lower surface of the through pipe (305) is rotatably mounted in a bearing seat (106), and the bearing seat (106) is fixedly mounted on the inner lower surface of the connecting frame (101). A straight pipe (307) is connected and mounted on one end of the bearing seat (106), and the straight pipe (307) is sealed and penetrates into the wall water tank (1). The other end of the straight pipe (307) is connected and mounted to the drainage outlet of a submersible pump (306), and the submersible pump (306) is fixedly mounted on the inner lower surface of the wall water tank (1).
7. A construction dust reduction fence according to claim 6, characterized in that: First bevel gears (302) are fixedly installed on both sides of the first connecting pipe (301); the first bevel gears (302) rotate in the connecting frame (101) and mesh with the second bevel gears (304); the second bevel gears (304) are fixedly installed on the upper surface of the second connecting pipe (305); and one end of the first connecting pipe (301) and the second connecting pipe (305) are both connected and installed with multiple groups of atomizing nozzles.
8. The construction dust reduction fence according to claim 1, characterized in that: The reciprocating push-pull mechanism (4) comprises a double-axis motor (401), the double-axis motor (401) is fixedly mounted in the mounting groove (107), the outer surfaces of the output shafts on both sides of the double-axis motor (401) are fixedly mounted with eccentric shafts (402), a connecting arm (403) is rotatably mounted in the eccentric shaft (402), the other end of the connecting arm (403) is rotatably mounted on the outer surface of a docking rod (308), and the docking rod (308) is fixedly mounted on one end of the outer surface of the first connecting tube (301).
9. A construction dust reduction fence according to claim 8, characterized in that: The connecting arm (403) can be driven by the eccentric shaft (402) of the dual-axis motor (401) to rotate in a push-pull manner of the docking rod (308), thereby enabling the docking rod (308) to pull the first connecting tube (301) between the two groups of connecting frames (101) to swing up and down, and the first connecting tube (301) swinging up and down drives the first bevel gear (302) to mesh and transmit the two groups of second bevel gears (304), thereby enabling the second bevel gear (304) to drive the second connecting tube (305) to swing left and right in the connecting frame (101).
10. The construction dust reduction fence according to claim 8, characterized in that: A C-shaped scraper (404) is fixedly mounted on one end of the eccentric shaft (402). The C-shaped scraper (404) passes through the mounting groove (107) and is rotatably mounted in the water collecting tank (105). The C-shaped scraper (404) is driven by the double-shaft motor (401) to rotate counterclockwise, so that the C-shaped scraper (404) can scrape and push out the debris in the water collecting tank (105).
Citation Information
Patent Citations
Building construction dust fall enclosing wall
CN218901274U
Cited By
Building construction dust falling device
CN120550537A
Building construction dust reducing device
CN120550537B