A foundation pit horizontal bottom sealing water-proof test device and method

By designing the foundation pit horizontal bottom seal water isolation test device and controlling the bottom seal material parameters, the problem of the lack of horizontal bottom seal water isolation model tests in the existing technology has been solved, and a detailed analysis of the foundation pit dewatering effect and the optimal selection of bottom seal material parameters have been achieved.

CN108344839BInactive Publication Date: 2024-10-01CCCC STRAIT CONSTR INVESTMENT DEV CO LTD +2
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN201810342040.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2018-04-17
Publication Date
2024-10-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing foundation pit precipitation model tests lack simulation of horizontal bottom seal water isolation, and cannot effectively study the influence of bottom seal material parameters on precipitation effects.

Method used

A horizontal bottom seal water isolation test device for foundation pits is designed, including a model box, water supply hole, observation hole, soil layer, bottom seal material, pressure measuring tube and booster pump. By controlling the thickness and position of the bottom seal material, different working conditions can be simulated. To analyze its impact on the water-stopping effect.

Benefits of technology

It realizes the free adjustment of pressurized water pressure, studies the influence of the thickness and position of the back sealing material on the water isolation effect, provides a basis for selecting reasonable back sealing materials, and the device can be reused and configured with different stratigraphic structures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN108344839B_ABST
    Figure CN108344839B_ABST
Patent Text Reader

Abstract

The present invention discloses a foundation pit horizontal bottom waterproofing test device and method. Different working conditions are set according to the bottom sealing material and its position in the soil layer. A booster pump with adjustable water supply pressure is used to supply water to the soil layer. The water supply pressure of the booster pump is dynamically controlled until the bottom sealing material of each working condition is destroyed. In order to study the changes in water level and water pressure in the soil, multiple observation holes are arranged along the depth on the inner side of the model box. The observation hole joints are inserted into the soil layer to form a communicating vessel. The reading of the pressure gauge connected to the pressure measuring tube on the left side reflects the change in water pressure in the corresponding soil layer in the model box. By recording the changes in soil layer water pressure under each working condition and the water supply pressure when the bottom sealing material is destroyed, the influence of various parameters of the foundation pit horizontal bottom sealing is explored.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of foundation pit dewatering engineering, in particular to a foundation pit horizontal bottom sealing water-proofing test device and method. Background Art

[0002] As the development and utilization of urban underground space has become a trend in today's modernization construction, some areas require large-scale precipitation during foundation pit excavation due to the rich hydraulic power of groundwater. Therefore, optimizing precipitation projects to improve precipitation efficiency, reduce precipitation costs, and reduce the impact of precipitation on the environment has become a hot issue in engineering construction at this stage.

[0003] At present, the research on indoor foundation pit dewatering model tests is increasing. For example, Tang Yiqun et al. designed an on-site scaled dewatering model test, conducted a three-dimensional scaled simulation of the end well foundation pit of Shanghai Metro Yishan Road Station, generalized the on-site soil layer, used a water tank to connect the edge injection holes of the model box for boundary water supply, and buried pore water pressure gauges, soil pressure gauges, and water measuring pipes to monitor water and soil pressure and water level; Yang Bin et al. designed a two-dimensional seepage model box, which controlled the water level of the model edge by adjusting the water level height of the water inlet tank and the drainage tank connected to the model. The boundary water level and the water level height in the pit are connected to the pressure measuring tube from the pressure measuring hole on the side of the model and installed on the outer pressure measuring plate to monitor the water pressure at each point in the seepage field; Wang Jianxiu et al. designed a transparent soil test method and device to simulate the groundwater seepage in the pressurized aquifer during foundation pit dewatering. Water was supplied by setting an outer water supply interlayer with an adjustable water level. Transparent soil was used to simulate the soil layer in the model box. The pore water pressure distribution at different positions of the model was measured with a pore pressure measuring device. The curtain seepage path was directly observed by releasing tracers and photographing their flow states.

[0004] Most of the existing foundation pit dewatering model tests simulate the dewatering by combining vertical water-stop curtains and dewatering wells, but lack model tests on the horizontal bottom sealing and waterproofing of foundation pits. However, the dewatering by combining horizontal bottom sealing and dewatering wells has been widely used at construction sites at home and abroad.

[0005] References:

[0006] [1] Tang Yiqun, Luan Changqing. Analysis of large-scale model test on indoor precipitation at Yishan Road Station of Shanghai Metro. Chinese Journal of Underground Space and Engineering. 2008; 4(3): 483-488.

[0007] [2] Xue Liying, Yang Bin, Liu Fengmin, et al., Research on groundwater seepage model test system for foundation pit engineering. Chinese Journal of Geotechnical Engineering. 2017, 39(s1): 126-130

[0008] [3] Liu Chun, Shi Bin, Wu Jinghong, et al., Model box test on deformation response of sandy clay layer under drainage and irrigation conditions. Chinese Journal of Engineering, 2017, 39(s9): 1746-1752.

[0009] [4] Wang Jianxiu, Liu Shaoli, Liu Xiaotian, et al., Transparent soil test method for simulating groundwater seepage in confined aquifers during foundation pit dewatering, National Invention Patent: ZL 201610130987.8

[0010] [5] Wang Jianxiu, Gao Feng, Liu Shaoli, et al., Transparent soil test device for simulating groundwater seepage in confined aquifers during foundation pit dewatering, National Invention Patent: ZL 201610129898.1 Summary of the invention

[0011] The technical problem to be solved by the present invention is to provide a foundation pit horizontal bottom waterproofing test device and method to address the deficiencies in the prior art, to conduct experimental research on the control variables of various parameters of the bottom sealing material, and thus to analyze the influence of various design parameters on the precipitation effect.

[0012] In order to solve the above technical problems, the technical solution adopted by the present invention is: a foundation pit horizontal bottom sealing water-proof test device, which comprises:

[0013] Model box;

[0014] Multiple water supply holes are provided on both sides of the bottom of the model box;

[0015] A plurality of observation holes are provided on at least one side of the model box;

[0016] Multiple soil layers filled in the model box;

[0017] A bottom sealing material for separating adjacent soil layers;

[0018] A plurality of pressure measuring tubes respectively connected to the observation holes;

[0019] a pressure gauge connected to the plurality of pressure measuring tubes;

[0020] as well as,

[0021] A plurality of booster pumps are respectively connected to the water supply holes.

[0022] The corners of the model box are reinforced by angle steels.

[0023] The water supply hole is communicated with the booster pump through a bellows.

[0024] The water supply hole and the bellows, as well as the observation hole and the pressure measuring tube are sealed and connected via sealing rings.

[0025] Accordingly, the present invention also provides a foundation pit horizontal bottom waterproofing test method, which comprises the following steps:

[0026] 1) Cover the water supply orifice and observation orifice with wire mesh, and then wrap them with two layers of geotextile;

[0027] 2) Fill the model box with soil in layers and tamp it. After all the soil layers are filled, continue tamping to speed up the consolidation of the soil layers and make the permeability coefficient of the soil layers uniform;

[0028] 3) Turn on the booster pump and adjust the speed, observe the reading of the pressure gauge, when the value of the pressure gauge remains unchanged, the water supply is stable;

[0029] 4) According to the test requirements, adjust the reading of the booster pump until the bottom sealing material is destroyed;

[0030] 5) According to the test requirements, change the thickness and position of the backing material, and repeat the above steps to test the next working condition.

[0031] The specific implementation process of step 2) includes: spreading the soil evenly in the model box at a layer of 5 cm, compacting the soil layer, and then gently flattening it with an iron trowel, scraping the soil layer with a long wooden board, ensuring that the soil layers are on the same horizontal line, and completing the pouring of the bottom sealing material when filling to the pouring position of the bottom sealing material, and continuing to fill the soil to the specified elevation after it is consolidated and stabilized.

[0032] In step 3), after turning on the water pump, adjust the water pump to a suitable speed. When the water supply starts, the water pressure in the soil is still unstable. When the pressure gauge reading remains unchanged, it can be considered that the water pressure has stabilized. At this time, the reading of the booster pump is the water supply pressure, and the reading of the pressure gauge at 20 cm is the pressurized water pressure.

[0033] In step 4), the water supply pressure of the booster pump is continuously increased. When the pressure gauge data on the upper part of the bottom sealing material begins to increase to a value close to that on the bottom of the bottom sealing material, it indicates that the bottom sealing material has been damaged. All the pressure gauge data at this time are recorded.

[0034] When testing the influence of the thickness of the backing material on the waterproof effect in step (5), the position of the backing material is controlled not to change, and only its thickness is changed. Then, the test steps are repeated while keeping other parameters the same to simulate its influence.

[0035] When testing the influence of the position of the bottom sealing material on the waterproofing effect in step (5), the position of pouring the bottom sealing material is changed during the soil laying process in step (2), and then the test steps are repeated while keeping other parameters the same to simulate its influence.

[0036] Compared with the prior art, the present invention has the following beneficial effects:

[0037] 1. The water pressure of the pressurized water can be freely adjusted, which can better study the bearing capacity of the horizontal bottom sealing technology of the foundation pit.

[0038] 2. Experimental research on the control variables of various parameters of the bottom sealing material can be carried out. Finally, based on the experimental data of multiple working conditions, the influence of the thickness of the bottom sealing material and the position of the bottom sealing material from the bottom of the foundation pit on the water-stopping effect can be obtained, thereby providing a reference basis for selecting a safe and reasonable thickness of the bottom sealing material and its casting position under different conditions.

[0039] 3. Use the photography method to directly record data, reduce the fluctuation of values ​​during the data reading process caused by the long reading time of the pressure gauge, and further reduce errors;

[0040] 4. The device can be reused, and different model soil layers can be configured to simulate the effect of horizontal bottom sealing under different stratum structures. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] Figure 1 This is the main view of the test system;

[0042] Figure 2 It is the top view of the model box;

[0043] Figure 3 is a schematic diagram of an aperture joint;

[0044] Among them, 1-model box, 2-boosting pump, 3-water supply hole, 4-observation hole, 5-pressure gauge, 6-bottom sealing material, 7-soil layer, 8-pressure measuring tube, 9-corrugated pipe, 10-steel foot, 11-angle steel, 12-sealing ring, 13-wire mesh and geotextile. DETAILED DESCRIPTION

[0045] like Figure 1-Figure 3 As shown, the test device of the present invention includes a model box 1, a booster pump 2, a water supply hole 3, an observation hole 4, a pressure gauge 5, a bottom sealing material 6, a soil layer 7, a pressure measuring tube 8, a bellows 9, a rigid foot 10 and other components. The model box 1 is a hollow, uncovered rectangular parallelepiped, and the joints (corners) are reinforced by angle steels 11. Each aperture joint is sealed with a sealing ring 12 and filtered by a wire mesh and a geotextile 13, so that it has good sealing and pressure bearing capacity.

[0046] The model box is made of 10mm thick plexiglass, and angle steel is used for reinforcement welding at the corners of the model. The model box is a topless rectangular steel box with a 20cm high stainless steel foot at the bottom.

[0047] The test steps are as follows:

[0048] Step 1: Filling and equipment installation. Fill the soil in layers according to the specified generalized stratum structure. During the filling process 7, pour the bottom sealing material 6 at the specified location according to the step instructions, wrap the aperture with wire mesh and geotextile 13, connect the pressure gauge 5 with the observation hole 4 through the pressure measuring tube 8, and connect the booster pump 2 with the water supply hole 3.

[0049] Step 2: Turn on the booster pump and adjust it to a lower power. After a period of time, when the soil layer under the bottom sealing material is saturated, start changing the power of the booster pump.

[0050] Step 3: Continue to increase the water supply pressure of the booster pump 2 until the reading of the pressure gauge connected to the observation hole on the upper part of the bottom sealing material increases significantly, indicating that the bottom sealing material has been damaged. Each time the power of the booster pump is changed, wait until the reading of the pressure gauge 5 is basically stable, and then use a camera to take pictures of the readings of each pressure gauge.

[0051] Step 4: After completing one working condition, first unscrew the bellows 9 connected to the four water supply holes to drain the water in the soil layer, then refill the soil and pour the bottom sealing material, and complete the simulation test of multiple working conditions according to the above steps.

Claims

1. A foundation pit horizontal bottom waterproofing test device, characterized in that: include: Model box (1); A plurality of water supply holes (3) are provided on both sides of the bottom of the model box (1); A plurality of observation holes (4) are provided on at least one side of the model box (1); A plurality of soil layers (7) filled in the model box (1); A bottom sealing material (6) for separating adjacent soil layers (7); A plurality of pressure measuring tubes (8) respectively connected to the observation holes (4); A pressure gauge (5) connected to the plurality of pressure measuring tubes (8); as well as, A plurality of booster pumps (2) respectively connected to the water supply holes (3); The corners of the model box (1) are reinforced by angle steels (11); The water supply hole (3) is connected to the booster pump (2) via a bellows (9).

2. The foundation pit horizontal bottom waterproofing test device according to claim 1, characterized in that: The water supply hole (3) and the bellows (9), as well as the observation hole (4) and the pressure measuring tube (8) are sealed and connected via sealing rings.

3. The foundation pit horizontal bottom waterproofing test device according to claim 1, characterized in that: The model box (1) is made of organic glass.

4. The foundation pit horizontal bottom waterproofing test device according to claim 1, characterized in that: The thickness of the soil layer (7) is 5 cm.

5. The foundation pit horizontal bottom waterproofing test device according to claim 1, characterized in that: Wire meshes are provided at the water supply hole (3) and the observation hole (4), and geotextiles (13) are wound around the wire meshes.

6. A method for testing the waterproofing of the horizontal bottom of a foundation pit, using the test device according to any one of claims 1 to 5, characterized in that: The following steps are involved: Wrap the water supply orifice and observation orifice with wire mesh, and then wrap them with two layers of geotextile; Fill the model box with soil in layers and tamp it. After all the soil layers are filled, continue tamping to speed up the consolidation of the soil layers and make the permeability coefficient of the soil layers uniform. Turn on the booster pump and adjust the speed, observe the pressure gauge reading, when the pressure gauge value remains unchanged, the water supply is stable; According to the test requirements, adjust the reading of the booster pump until the bottom sealing material is destroyed; According to the test requirements, change the thickness and position of the backing material, and repeat the above steps to test the next working condition.

7. The method according to claim 6, characterized in that The specific implementation process of step 2) includes: spreading the soil evenly in the model box at a thickness of 5 cm, compacting the soil layer, flattening the soil layer, scraping the soil layer, ensuring that the soil layers are on the same horizontal line, and completing the pouring of the bottom sealing material when filling to the pouring position of the bottom sealing material, and continuing to fill the soil to the specified elevation after the bottom sealing material is consolidated and stabilized.

8. The method according to claim 6, characterized in that In step 4), when the pressure gauge data on the upper part of the back cover material begins to increase to the same level as the bottom of the back cover material, it indicates that the back cover material has been damaged.

Citation Information

Patent Citations

  • Transparent soil test device used for simulating seepage of foundation pit dewatering confined aquifer underground water

    CN105784562A

  • Testing device and method of ground deformation caused by simulating metro shield tunnel construction

    CN103105310A

  • Simulation test device and simulation test method for in-situ chemical and biological remediation of underground water

    CN103630659A

  • Transparent soil test method for simulating groundwater seepage of drawdown and confined aquifer of foundation pit

    CN105756103A

  • Experimental device and method for simulating water burst fracturing of waterproof rock

    CN105758730A