A construction method of high-speed railway catenary pillar foundation structure
A technology of basic structure and construction method, applied in basic structure engineering, construction and other directions, can solve the problems of no proposed construction method, large environmental pollution and large impact of excavation, and achieve easy popularization and use, convenient and efficient construction, and foundation pit excavation. less digging effect
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2021-05-25
Smart Images

Figure 1
Abstract
Description
technical field
[0001] The invention relates to railway engineering, in particular to a construction method for a high-speed railway catenary pillar foundation structure. Background technique
[0002] The catenary pillar foundation set on the railway embankment is usually excavated by rotary drilling rig or manual digging after the foundation filling of the roadbed is completed, and then reinforced concrete is poured into the foundation pit. There are following problems in this construction method:
[0003] (1) It is difficult and inefficient to excavate a small-diameter foundation pit with a depth of 2-3m after subgrade filling;
[0004] (2) The excavation of the foundation pit affects the compactness of the filled subgrade, and has a greater impact on the high-speed railway;
[0005] (3) When the filling roadbed is provided with a waterproof and drainage geotechnical material layer, the excavation will easily damage the waterproof and drainage geotechnical material, whic...
Examples
Embodiment Construction
[0029] Below in conjunction with accompanying drawing and embodiment the present invention will be further described:
[0030] refer to figure 1 , the construction method of a kind of high-speed railway catenary pillar foundation structure provided by the present invention, comprises the following steps:
[0031] ①Fill the subgrade filling body 10 in layers to reach the bottom elevation position of the catenary pillar foundation;
[0032] ②Continue to fill the subgrade subgrade filling body 10 and subgrade surface structure 30 above the bottom elevation of the catenary pillar foundation in layers, and fill with water seepage filler at the corresponding position of the catenary pillar foundation to form a water seepage filler filling body 20 until the subgrade surface structure 30 20-30cm below the top surface;
[0033] ③ Lay a layer of composite geomembrane 40 on the top of the water seepage filling body 20, the size of the composite geomembrane 40 is larger than the base si...