An ecological filter dam based on efficient in-situ interception of pollutants and its application
By designing ecological filter dams with partitioned structures, including front dam interception area, front dam, biological contact oxidation area and rear dam, the problems of high construction difficulty, limited purification capacity and dam blockage in the existing technology are solved, and efficient Water purification and service life are extended.
Patent Information
- Application Number
- CN201911157150.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-11-22
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2039-11-22
AI Technical Summary
The existing ecological filter dams have problems such as high construction difficulty, limited purification capacity, severe blockage of dams and short service life in river management, which limits their application scope.
An ecological filter dam based on efficient in-situ interception of pollutants was designed, including the front interception area, front dam, biological contact oxidation area and rear dam, through water sewage buoys, fishing nets, interlaced matrix and aeration system, etc. Components to realize partition purification and extend the service life of the dam.
It effectively improves the removal capacity of the filter dam, alleviates the problem of dam blockage, extends the service life, and achieves stable purification of water quality, reducing the frequency of matrix replacement.
Smart Images

Figure CN110713324B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of water environment treatment, and in particular relates to an ecological filter dam based on efficient in-situ interception of pollutants and application thereof. Background Art
[0002] In recent decades, with the rapid development of my country's social economy, water pollution has continued to intensify, and the water environment quality is not optimistic. With the large amount of pollutants discharged into the water, most of them eventually converge into the river, causing the water quality of the river to deteriorate. In addition to source control and pollution interception, the existing treatment technologies mainly include ex situ treatment and in situ treatment. However, due to the large fluctuations in the amount of water in the river, the ex situ treatment capacity cannot meet the requirements, and it has limitations such as large land area and high investment. Therefore, the in situ treatment technology of polluted rivers is the current development trend.
[0003] As an important in-situ river management technology, ecological filter dams were first used to reinforce embankments and then applied to water ecological restoration. They mainly use matrix adsorption filtration and biodegradation principles to purify water. Existing ecological filter dams have major problems such as difficult construction, limited purification capacity, serious dam blockage, and short service life, which greatly limit their application in river management. Summary of the invention
[0004] In view of this, the purpose of the present invention is to provide an ecological filter dam based on efficient in-situ interception of pollutants and its application. The ecological filter dam realizes zoned purification, can effectively improve the removal capacity of the filter dam, and fundamentally alleviates the problem of dam body blockage, greatly delaying the service life of the ecological filter dam.
[0005] The present invention provides an ecological filter dam based on efficient in-situ interception of pollutants, which comprises a front interception zone, a front dam, a biological contact oxidation zone and a rear dam in sequence according to the direction of water flow;
[0006] The interception area in front of the dam includes floating pollution-blocking buoys and fishing nets in sequence according to the direction of water flow;
[0007] The front dam is formed by staggered stacking of a number of ecological gabions filled with small and medium-sized matrix and large-sized matrix respectively;
[0008] The biological contact oxidation zone includes an aeration system and a biological filler zone, wherein the aeration system includes an aeration pipe arranged at the bottom of the river channel and a microporous aeration disk attached to the aeration pipe, a filler support body is installed above the aeration system, and biological fillers are hung on the filler support body;
[0009] The rear dam is formed by staggered stacking of a plurality of ecological gabion monomers filled with ultra-fine particle size matrix.
[0010] Preferably, the distance between the above-water trash-blocking buoy and the fishing net is 10 m; the distance between the fishing net and the front dam is 10-20 m.
[0011] Preferably, the above-water trash buoy floats on the water surface and is 20 to 30 cm above the water surface;
[0012] The material of the above-water pollution-blocking buoy is plastic.
[0013] Preferably, the width of the fishing net is 1 to 2 m, the vertical height is not less than 50 cm, the inner mesh size of the fishing net is 1 finger or less, and the top of the fishing net is at least 20 cm above the water surface.
[0014] Preferably, in the front dam, the length×width×height of the ecological gabion unit is 0.5m×0.5m×0.5m or 1m×1m×1m;
[0015] The number of stacked layers does not exceed three, and the total longitudinal length of the dam body decreases by the length of one ecological gabion unit from the bottom to the top of each layer, and each ecological gabion unit in the upper layer has only two ecological gabion units supporting the bottom;
[0016] The staggered stacking method is to separate ecological gabion monomers filled with medium and small particle size matrix by ecological gabion monomers filled with large particle size matrix;
[0017] The front dam has a length of 5 to 20 m, a width of 2 to 20 m, and a height of 1 to 3 m.
[0018] Preferably, the medium and small particle size matrix and the large particle size matrix include steel slag, zeolite or gravel, the medium and small particle size matrix has a particle size of 8 to 20 mm; the large particle size matrix has a particle size of 15 to 30 mm.
[0019] Preferably, the biological contact oxidation zone has a length of 10 to 50 m and a width of 2 to 20 m, the distance between the edge of the filler support and the front dam, rear dam or shore is no more than 0.5 m, and the height of the filler support is lower than the normal water level of the river.
[0020] Preferably, the filler support is a support of a fence structure and four pillars vertically connected at the four corners of the support of the fence structure;
[0021] Biological filler monomers are hung on the support body of the fence structure. The length of the biological filler monomers is 0.5 to 2.5 meters, and the distance between every two biological filler monomers is 10 to 20 cm.
[0022] Preferably, the stacking method of the rear dam is as follows: the total longitudinal length of the dam body decreases by the length of one ecological gabion unit from the bottom to the top of each layer, and each ecological gabion unit of the upper layer has only two ecological gabion units supporting the bottom;
[0023] In the rear dam, the length × width × height of the ecological gabion unit is 0.5m × 0.5m × 0.5m or 1m × 1m × 1m;
[0024] The rear dam has a length of 10 to 20 m, a width of 2 to 20 m, and a height of 1 to 3 m.
[0025] Preferably, the particle size of the ultrafine particle size matrix is 3 to 10 mm.
[0026] The invention provides an application of the ecological filter dam in river water environment management.
[0027] Compared with the prior art, the present invention has the following advantages and effects:
[0028] 1) The overall design of the four treatment units of the ecological filter dam provided by the present invention is reasonable. The interception area in front of the dam is set up with two-level interception - water pollution buoys and fishing nets, which can effectively reduce the flow of floating objects and suspended matter into the dam body to cause blockage. The front dam increases the removal effect of the dam body on ammonia nitrogen and total phosphorus through a matrix with good adsorption performance. The subsequent biological contact oxidation zone can increase the dissolved oxygen content of the water body and further reduce the content of organic matter and ammonia nitrogen. The ultra-fine particle size matrix is used in the rear dam, which is conducive to the denitrification of the dam body and the reduction of the total nitrogen and nitrate nitrogen content in the water body. The above measures are combined to achieve water purification;
[0029] 2) The dam body is composed of ecological gabions. Compared with the existing widely used integrated dams, the construction difficulty is relatively small, and the gabions can be increased, decreased, replaced and removed at any time according to the actual situation. The later maintenance and management are convenient, and the service life is longer, which greatly increases the scope of application of ecological filter dams;
[0030] 3) The hydraulic optimization design of the front dam is carried out. The two particle size matrices are arranged alternately, which is conducive to prolonging the hydraulic retention time and increasing the removal effect of the dam body. The water flow direction is no longer single, which is conducive to alleviating the blockage of the dam body, reducing the frequency of matrix replacement and extending the service life of the dam body. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 A top view of the structure of the ecological filter dam provided by the present invention;
[0032] Figure 2 A longitudinal section view of the front dam provided by the present invention;
[0033] Figure 3 A longitudinal section view of the rear dam provided by the present invention;
[0034] Figure 4 A top view of the biofiller provided by the present invention;
[0035] Figure 5 A physical picture of the filler support provided by the present invention;
[0036] Among them: 1 interception area before the dam; 2 floating pollution-blocking buoy; 3 fishing net; 4 front dam; 5 biological contact oxidation area; 6 biological filler; 7 microporous aeration disk; 8 aeration branch pipe; 9 aeration main pipe; 10 rear dam; 11 river bank; 12 small and medium particle size matrix; 13 large particle size matrix; 14 ecological gabion monomer; 15 river bottom; 16 ultrafine particle size matrix; 17 biological biological filler monomer; 18 filler support. DETAILED DESCRIPTION
[0037] The present invention provides an ecological filter dam based on efficient in-situ interception of pollutants, which comprises a front interception zone, a front dam, a biological contact oxidation zone and a rear dam in sequence according to the direction of water flow;
[0038] The interception area in front of the dam includes floating pollution-blocking buoys and fishing nets in sequence according to the direction of water flow;
[0039] The front dam is formed by staggered stacking of a number of ecological gabions filled with small and medium-sized matrix and large-sized matrix respectively;
[0040] The biological contact oxidation zone includes an aeration system and a biological filler zone, wherein the aeration system includes an aeration pipe arranged at the bottom of the river channel and a microporous aeration disk attached to the aeration pipe, a filler support body is installed above the aeration system, and biological fillers are hung on the filler support body;
[0041] The rear dam is formed by staggered stacking of a plurality of ecological gabion monomers filled with ultra-fine particle size matrix.
[0042] The structural top view of the ecological filter dam provided by the present invention is shown in Figure 1 The ecological filter dam includes four units, which are the interception area in front of the dam, the front dam, the biological contact oxidation area and the back dam in order according to the direction of water flow.
[0043] The water from the upstream of the polluted river first passes through the interception area in front of the dam. The interception area in front of the dam includes a floating garbage buoy and a fishing net in sequence according to the direction of water flow. In one embodiment, the distance between the floating garbage buoy and the fishing net is preferably 10m. The floating garbage buoy preferably floats on the water surface and is 20 to 30cm above the water surface; the material of the floating garbage buoy is preferably plastic, such as PVC and PE. The width of the fishing net is preferably 1 to 2m, the vertical height is preferably not less than 50cm, the inner mesh of the fishing net is preferably 1 finger or less, and the top of the fishing net is preferably at least 20cm above the water surface. The interception area in front of the dam serves as the first line of defense for pollutant filtration. The first-level garbage buoy first intercepts large and medium-sized garbage and other floating objects on the water surface, and the second-level fishing net serves as a supplementary interception. After interception and treatment, most of the floating objects can be prevented from entering the front dam matrix and causing blockage.
[0044] A front dam is set at a distance of 10 to 20 meters downstream of the fishing net. In the front dam, a plurality of cubic ecological gabion monomers are combined, and the structure of the ecological gabion monomers is stable and not prone to large deformation. The ecological gabion monomers are stacked and arranged in rows and layers, and each layer contains multiple rows of gabions. The matrix filled between the rows is small and medium-sized matrix and large-sized matrix in sequence. The total length of the next layer is one row less than the previous layer, and the cross-section is an isosceles trapezoid; the number of stacked layers is preferably not more than three layers, and the total longitudinal length of the dam body is reduced by the length of an ecological gabion monomer from the bottom to the top of each layer, and each ecological gabion monomer in the upper layer has only two ecological gabion monomers supporting the bottom. The staggered stacking method is preferably that the ecological gabion monomers filled with small and medium-sized matrix are separated by ecological gabion monomers filled with large-sized matrix (see Figure 2 ). The ecological gabion monomer is a gabion mesh filled with matrix. The gabion mesh is preferably made of galvanized steel wire. The small and medium-sized matrix and the large-sized matrix are preferably matrices with good adsorption effects on ammonia nitrogen and total phosphorus, such as steel slag, zeolite or gravel. The particle size of the small and medium-sized matrix is preferably 8-20 mm; the particle size of the large-sized matrix is preferably 15-30 mm. In one embodiment, the length of the front dam is preferably 10 m, the width is preferably 20 m, and the height is preferably 2 m. The specific size (length × width × height) of the selected ecological gabion monomer is 1 × 1 × 1 m, divided into upper and lower layers, and the longitudinal section is 10 rows in the lower layer and 9 rows in the upper layer, with 10 in each row. In another embodiment, the length of the front dam is preferably 5 m, the width is preferably 8 m, and the height is preferably 1 m. The specific size (length × width × height) of the selected ecological gabion monomer is 0.5 × 0.5 × 0.5 m, divided into upper and lower layers, and the longitudinal section is 10 rows in the lower layer and 9 rows in the upper layer, with 10 in each row.
[0045] A biological contact oxidation zone is set at 0.5 m downstream of the front dam (see Figure 4 ). The length of the biological contact oxidation zone is preferably 20 to 30 m, and the width is preferably 8 to 20 m. The biological contact oxidation zone includes an aeration system and a biological filler area. The aeration system includes an aeration pipe arranged at the bottom of the river channel and a microporous aeration disk attached to the aeration pipe. A filler support is installed above the aeration system, and biological fillers are hung on the filler support. The filler support and the biological fillers constitute a biological filler area. The distance between the edge of the filler support and the back dam or the shore is preferably 0.5 m; the height of the filler support is lower than the normal water level of the river channel. The filler support is a support body of a fence structure and four pillars connected at the four corners of the support body of the fence structure (see Figure 5), the filler support is fixed to the bottom of the river channel by 4 pillars; the support of the fence structure is divided into two layers distributed in parallel, the spacing between the two layers is preferably 0.5-2.5m, and the support of the lower fence structure is 0.2-0.3m away from the bottom of the river channel. Biological filler monomers are hung on the support of the upper fence structure, and the lower ends of the biological filler monomers are vertically fixed on the support of the lower fence structure to prevent them from floating with the water flow. The length of the biological filler monomer is 0.5-2.5m, and the spacing between every two biological filler monomers is 10-20cm. In one embodiment, the length of the filler support is 19m, the width is 19m, and the height is 1.8m; on the filler support, preferably a stainless steel pipe is provided every 1m, with a total of 20 pipes, and biological filler monomers are hung on the stainless steel pipes. The length of the biological filler monomer is preferably 1m, and the spacing between every two biological filler monomers is preferably 10-20cm. In another embodiment, the biological contact oxidation zone is 30m long and 8m wide. A biological filler monomer filled with biological fillers is hung on the filler support. The biological filler monomer is 0.7m long. An aeration device is set at the bottom of the river. An aeration main pipe is arranged on both sides of the bank. The length of the aeration main pipe is 29m. An aeration branch pipe is arranged every 1m on the aeration main pipe, with a total of 30 pipes. Microporous aeration disks are arranged on the aeration branch pipes, and the distance between every two microporous aeration disks is 1m. The present invention has no special restrictions on the type of the biological filler. The biological filler well known in the art can be used. The biological filler is preferably a three-dimensional elastic filler. The setting of the biological contact oxidation zone can increase the dissolved oxygen content of the water body, while further reducing the organic matter and ammonia nitrogen content.
[0046] A rear dam is set at a distance of 0.5m downstream of the biological contact oxidation zone. The stacking method of the rear dam is preferably the same as that of the front dam, specifically as follows: the total longitudinal length of the dam body decreases by the length of one ecological gabion unit from the bottom to the top, and each ecological gabion unit at the upper layer has only two ecological gabion units at the bottom (see Figure 3 ). In the rear dam, the length × width × height of the ecological gabion unit is 0.5m × 0.5m × 0.5m or 1m × 1m × 1m. The length of the rear dam is 10 to 20m, the width is 2 to 20m, and the height is 1 to 3m. The particle size of the ultrafine particle size matrix is preferably 3 to 10mm. The types of the ultrafine particle size matrix preferably include gravel, steel slag, etc. The rear dam is filled with a matrix with a smaller particle size, which is conducive to further improving the interception effect of pollutants.
[0047] The construction method of the ecological filter dam based on efficient in-situ interception of pollutants provided by the present invention can be arranged according to the above description. The construction method of the ecological filter dam can significantly reduce the difficulty of construction, and the zoning purification can effectively improve the removal capacity of the filter dam, and fundamentally alleviate the problem of dam body blockage, greatly delaying the service life of the ecological filter dam.
[0048] The present invention provides the application of the ecological filter dam in river water environment management. The river is preferably a small or medium-sized river. The ecological filter dam is used to manage the water environment of the river, so that the water quality treatment effect tends to be stable, the dam body operates well, and the water flow at the front and rear ends of the dam is uniform without blockage. At the same time, the river water quality monitoring results show that the removal rate of TN is 29.4% to 40.7%, the removal rate of TP is 30.6% to 32.4%, and the removal rate of NH4 + -N removal rate is 35.1%~36.7%, COD Cr The removal rate is 28.8% to 35.6%, indicating that this application can efficiently purify water.
[0049] The following is a detailed description of an ecological filter dam based on efficient in-situ interception of pollutants provided by the present invention in conjunction with the embodiments, but they should not be understood as limiting the scope of protection of the present invention.
[0050] Example 1
[0051] In the in-situ restoration of a polluted river, a fishing net was first set up upstream of the river management area. The net was 22 meters long, 1.5 meters wide, and had a mesh size of 1 finger. Both ends of the net were tied to fixed piles on the shore with nylon ropes. The top of the fishing net was about 0.5 meters above the water surface, and the rest was submerged below the water surface.
[0052] The front dam is 20m downstream of the fishing net. The total length of the dam is 10m, the total width is 20m, and the total height is 2m. The gabion mesh is made of galvanized steel wire. The size of the gabion unit (length×width×height) is 1×1×1m, which is divided into upper and lower layers. The longitudinal section shows 10 rows in the lower layer and 9 rows in the upper layer, with 10 in each row. The matrix is gravel, and the large particle size is 15-30mm, and the small and medium particle size is 8-20mm. The two particle size matrix gabion units are staggered, and each row uses the same particle size, that is, along the direction of water flow, the lower layer 1, 3, 5, 7, 9 rows and the upper layer 1, 3, 5, 7, 9 rows use large particle size fillers, and the lower layer 2, 4, 6, 8, 10 rows and the upper layer 2, 4, 6, 8 rows use small and medium particle size fillers.
[0053] Behind the front dam is the biological contact oxidation zone, which is 20m long and 20m wide. The edge of the filler support is 0.5m away from the front dam, the rear dam and the shore. The total length, width and height of the support are 19m, 19m and 1.8m respectively. There is a stainless steel pipe every 1m on the support, for a total of 20 pipes. Elastic fillers are hung on the stainless steel pipes. The elastic fillers are 1m long and 10cm apart.
[0054] The biological contact oxidation zone is connected to the rear dam. The total length of the dam is 10m, the total width is 20m, and the total height is 2m. The size of the gabion unit (length × width × height) is 1×1×1m. It is divided into upper and lower layers. The longitudinal section shows 10 rows in the lower layer and 9 rows in the upper layer, with 10 in each row. An ultra-fine particle size matrix is used, and the gravel particle size is 3 to 10mm.
[0055] After one month of trial operation of this embodiment, the water quality treatment effect tended to be stable, the dam body operated well, and the water flow at the ends of the front dam and the rear dam was uniform without blockage. The river water quality monitoring results are shown in Table 1.
[0056] Table 1 Water quality monitoring results upstream and downstream of the ecological filter dam (mean)
[0057]
[0058] Example 2
[0059] The upstream water of a certain city river is mainly tail water of a sewage treatment plant, and the water quality entering the river is the Class A standard of "Pollutant Discharge Standard for Urban Sewage Treatment Plants" (GB 18918-2002). An ecological filter dam system is established 100m downstream of the outlet, which is different from Example 1 in that: the small-mesh fishing net is 10m long and 0.5m wide; a single-layer front dam is set 10m downstream of the fishing net, and the total length of the dam body is 5m, the width is 8m, and the height is 1m; the front dam is connected to a biological contact oxidation zone, which is 30m long and 8m wide, and an elastic biological filler monomer is hung on the filler support body, the monomer is 0.7m long, and the bottom is microporous aeration. An aeration main pipe is arranged on both sides of the coast, and the pipe length is 29m. An aeration branch pipe is arranged every 1m on the main pipe, and a total of 30 pipes are arranged. The aeration disk is arranged on the aeration branch pipe with a spacing of 1m; a single-layer back dam is behind the biological contact oxidation zone, and the total length of the dam body is 12m, the width is 8m, and the height is 1m.
[0060] Since the trial operation of this embodiment for 3 months, the system has been running well, the water removal rate is relatively stable, and no blockage has been found. The monitoring results of the system inlet and outlet water are shown in Table 2.
[0061] Table 2 Water quality monitoring results upstream and downstream of the ecological filter dam (mean)
[0062]
[0063] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. An ecological filter dam based on efficient in-situ interception of pollutants, characterized in that: According to the water flow direction, they are the interception area before the dam, the front dam, the biological contact oxidation area and the back dam; The interception area in front of the dam is composed of floating pollution-blocking buoys and fishing nets in the direction of water flow; The front dam is formed by staggered stacking of a number of ecological gabions filled with small and medium-sized matrix and large-sized matrix respectively; The staggered stacking method is to separate ecological gabion monomers filled with medium and small particle size matrix by ecological gabion monomers filled with large particle size matrix; The types of the medium and small particle size matrix and the large particle size matrix include steel slag, zeolite or gravel; The particle size of the medium and small particle size matrix is 8 to 20 mm; the particle size of the large particle size matrix is 15 to 30 mm; The biological contact oxidation zone is an aeration system and a biological filler zone. The aeration system includes an aeration pipe arranged at the bottom of the river channel and a microporous aeration plate attached to the aeration pipe. A filler support is installed above the aeration system, and biological fillers are hung on the filler support. The rear dam is formed by staggered stacking of a plurality of ecological gabion monomers filled with ultra-fine particle size matrix.
2. The ecological filter dam according to claim 1, characterized in that: The distance between the above-water pollution-blocking buoy and the fishing net is 10m; the distance between the fishing net and the front dam is 10-20m.
3. The ecological filter dam according to claim 1 or 2, characterized in that: The above-water pollution-blocking buoy floats on the water surface and is 20 to 30 cm above the water surface; The material of the above-water pollution-blocking buoy is plastic.
4. The ecological filter dam according to claim 1 or 2, characterized in that: The width of the fishing net is 1 to 2 meters, the vertical height is not less than 50 cm, the inner mesh size of the fishing net is 1 finger or less, and the top of the fishing net is at least 20 cm above the water surface.
5. The ecological filter dam according to claim 1, characterized in that: In the front dam, the length × width × height of the ecological gabion unit is 0.5m × 0.5m × 0.5m or 1m × 1m × 1m; The number of stacked layers does not exceed three, and the total longitudinal length of the dam body decreases by the length of one ecological gabion unit from the bottom to the top of each layer, and each ecological gabion unit in the upper layer has only two ecological gabion units supporting the bottom; The front dam has a length of 5 to 20 m, a width of 2 to 20 m, and a height of 1 to 3 m.
6. The ecological filter dam according to claim 1, characterized in that: The biological contact oxidation zone has a length of 10 to 50 m and a width of 2 to 20 m. The distance between the edge of the filler support and the front dam, the rear dam or the bank is no more than 0.5 m. The height of the filler support is lower than the normal water level of the river.
7. The ecological filter dam according to claim 1, characterized in that: The filler support body is a support body of a fence structure and four pillars vertically connected at the four corners of the support body of the fence structure; Biological filler monomers are hung on the support body of the fence structure. The length of the biological filler monomers is 0.5 to 2.5 meters, and the distance between every two biological filler monomers is 10 to 20 cm.
8. The ecological filter dam according to claim 1 or 5, characterized in that: The stacking method of the rear dam is as follows: the total longitudinal length of the dam body is reduced by the length of one ecological gabion unit from the bottom to the top of each layer, and each ecological gabion unit at the upper layer has only two ecological gabion units supporting the bottom; In the rear dam, the length × width × height of the ecological gabion unit is 0.5m × 0.5m × 0.5m or 1m × 1m × 1m; The length of the rear dam is 10 to 20 m, the width is 2 to 20 m, and the height is 1 to 3 m; The particle size of the ultrafine particle size matrix is 3 to 10 mm.
9. Use of the ecological filter dam described in any one of claims 1 to 8 in river water environment management.