A production method and Simmons technology, applied in mattresses, spring mattresses, padded mattresses, etc., can solve the problems of poor side support and low efficiency of Simmons mattresses, and achieve improved support performance, good recovery performance, and installation efficiency. improved effect
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2020-02-04
- Estimated Expiration
- Not applicable · inactive patent
Abstract
Description
technical field
[0001] The invention relates to the technical field of production methods of Simmons mattresses, in particular to a production method of Simmons mattresses. Background technique
[0002] Simmons mattresses have the characteristics of classic style design, noble and gorgeous appearance, fine manufacturing technology, health and environmental protection. Both in design and function, they lead the development trend of mattresses in the world.
[0003] The production method of the traditional Simmons mattress is that when the spring is connected with the horizontal wire drawing and the longitudinal wire drawing, the spring needs to be inserted into the curling channel of the horizontal wire drawing and the longitudinal wire drawing, so the efficiency is low, and the side support of the Simmons mattress made by the traditional production method Poor, therefore, urgently need a kind of improved technology to solve this problem that exists in the prior art. Conten...
Examples
Embodiment 1
[0035] A kind of production method of Simmons mattress, comprises the following steps:
[0036] Step 1: According to the required size, the upper frame and the lower frame with rectangular rounded corners are prepared, and the upper end panel and the lower end panel are prepared according to the upper frame and the lower frame, and several holes are evenly opened on the upper end panel and the lower end panel. hole;
[0037] Step 2: spot-weld the upper coaming plate on the lower surface of the upper frame, and spot-weld the lower coaming plate on the surface of the lower frame;
[0038] Step 3: Set vertically intersecting horizontal wire drawing and longitudinal wire drawing inside the upper frame and the lower frame respectively;
[0039] Step 4: Prepare the support frame so that the distance from the support frame to the upper frame and the lower frame is 5cm;
[0040] Step 5: Fix the support frame to the inside of the upper frame and the lower frame respectively through h...
Embodiment 2
[0046] A kind of production method of Simmons mattress, comprises the following steps:
[0047] Step 1: According to the required size, the upper frame and the lower frame with rectangular rounded corners are prepared, and the upper end panel and the lower end panel are prepared according to the upper frame and the lower frame, and several holes are evenly opened on the upper end panel and the lower end panel. hole;
[0048] Step 2: spot-weld the upper coaming plate on the lower surface of the upper frame, and spot-weld the lower coaming plate on the surface of the lower frame;
[0049] Step 3: Set vertically intersecting horizontal wire drawing and longitudinal wire drawing inside the upper frame and the lower frame respectively;
[0050] Step 4: Prepare the support frame so that the distance from the support frame to the upper frame and the lower frame is 7cm;
[0051] Step 5: Fix the support frame to the inside of the upper frame and the lower frame respectively through h...
Embodiment 3
[0057] A kind of production method of Simmons mattress, comprises the following steps:
[0058] Step 1: According to the required size, the upper frame and the lower frame with rectangular rounded corners are prepared, and the upper end panel and the lower end panel are prepared according to the upper frame and the lower frame, and several holes are evenly opened on the upper end panel and the lower end panel. hole;
[0059] Step 2: spot-weld the upper coaming plate on the lower surface of the upper frame, and spot-weld the lower coaming plate on the surface of the lower frame;
[0060] Step 3: Set vertically intersecting horizontal wire drawing and longitudinal wire drawing inside the upper frame and the lower frame respectively;
[0061] Step 4: Prepare the support frame so that the distance from the support frame to the upper frame and the lower frame is 10cm;