Deck house hoisting structure and hoisting method
By installing a combined structure of steel pipes and connecting ear plates on the side walls of the deck chamber, the problems of waste and labor intensity of deck chamber hoisting materials in the prior art are solved, and material saving and production efficiency are improved.
Patent Information
- Application Number
- CN201911201904.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-11-29
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2039-11-29
AI Technical Summary
The existing deck room lifting technology has problems such as waste of materials, high labor intensity, long construction cycle and high cost. Especially during the lifting of aluminum alloy deck room, deformation control and construction convenience are difficult to achieve.
Two pairs of windows are set up on the side wall of the deck room, and steel pipes are installed. The combination structure of lifting code and steel pipes is replaced by a combination of the channel steel angle steel base to control the lifting deformation, and can be detached and reused after lifting to reduce the Materials and labor intensity.
It has achieved material cost savings and improved production efficiency, simplified the lifting process, and reduced construction risks and costs.
Smart Images

Figure CN110790123B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of hoisting construction, in particular to a deckhouse hoisting structure and a hoisting method. Background Art
[0002] At present, most deckhouses are made of aluminum alloy, with semi-three-dimensional sections, large openings, and weak strength. They are light in weight, easy to deform, and difficult to repair. During the lifting process, the requirements for deformation control are higher than those for steel sections. The added reverse reinforcement due to deformation is more complicated during lifting, and the wear of the lifting wire on the sections must also be prevented. Therefore, the lifting process needs to focus on controlling deformation and construction convenience.
[0003] The commonly used lifting scheme for building a deckhouse is to add a steel channel steel base, connect and fix the lower mouth of the entire aluminum deckhouse to the base with angle steel, aluminum plate and other materials, lift up the entire open surface, and concentrate the force points on the base for turning over and lifting. At the same time, since the deckhouse is almost entirely made in an inverted mode, that is, the top is at the bottom, the aluminum lifting code will be welded to the hull's strong structure for lifting. This lifting method is suitable for all sections, but it requires more reinforcements, and needs to be dismantled and recycled after lifting. This will undoubtedly consume labor and materials, prolong the construction period and cost, and the materials of the tooling also increase the lifting weight, increasing the risk. Summary of the invention
[0004] In view of the problems existing in the prior art, the present invention provides a deckhouse hoisting structure and a hoisting method, which can save material costs and improve production efficiency.
[0005] To achieve the above-mentioned object of the invention, the technical solution of the present invention is as follows:
[0006] The deckhouse hoisting structure includes deckhouse windows arranged on the side wall of the deckhouse, each of which is provided with connecting ear plates vertically near the outer wall of the top of the deckhouse. Steel pipes are passed through the deckhouse windows, and connecting steel plates matching and fixedly connected to the connecting ear plates are vertically provided on the outer wall of the steel pipes. Hanging weights are respectively provided at both ends of the steel pipes. Such a hoisting structure can control the reverse deformation of the deckhouse during the hoisting process, and the steel pipes, hanging weights, etc. can be removed and retained after hoisting and applied to subsequent products; at the same time, such a structure reduces the labor intensity of workers, saves material costs, and improves production efficiency.
[0007] Preferably, the steel pipe is 6-8 meters long, 280-300 mm in diameter, 10-12 mm thick, and made of CCSB-grade shipboard material. Such a setting can ensure that the steel pipe has sufficient strength during hoisting.
[0008] Preferably, the connecting lugs are made of aluminum plates. Such an arrangement can ensure strength while the connecting lugs do not increase the weight of the deckhouse too much.
[0009] Preferably, the aluminum plate is an aluminum plate with a thickness of 16-20 mm. Such a setting can ensure the strength of the connecting ear plate.
[0010] Preferably, the connecting ear plate is connected to the connecting steel plate by bolts, so that it can be removed and reused after hoisting.
[0011] Preferably, the connecting steel plate is a steel plate with a thickness of 10-14 mm. Such a setting ensures the strength of the connecting steel plate without increasing the weight of the hoisting structure too much.
[0012] The method for hoisting the deck house hoisting structure comprises the following steps:
[0013] Step 1: Make steel pipes, including welding hangers and connecting steel plates; the inner side of the deckhouse window position is partially strengthened, which can be connected by slats or diagonal braces. By strengthening, the force of the hanger is transmitted to the side wall, while reducing the deformation during lifting.
[0014] Step 2: Weld the connecting lug plate on the upper outer wall of the left and right symmetrical deckhouse windows, pass the steel pipe through the symmetrical deckhouse windows, and adjust the symmetry center of the circular pipe to coincide with the center line of the deckhouse, then fix the connecting steel plate on the steel pipe to the connecting lug plate, and repeat the above operation with another steel pipe on the other left and right symmetrical deckhouse window;
[0015] Step 3: Lifting and turning over the deckhouse: connect the main hook of the lifting trolley to the two lifting hooks on the same side of the deckhouse through slings, and then connect the auxiliary hook of the lifting trolley to the two lifting hooks on the other side of the deckhouse through slings. After the main hook and the auxiliary hook simultaneously lift the deckhouse to a distance of 1.5 meters from the ground, the main hook continues to rise, and the auxiliary hook remains unchanged. After the main hook stands up the deckhouse as a whole, loosen the shackle of the lifting hook at the auxiliary hook end, and then pull the deckhouse with a rope, turn the front and rear ends, and after the direction is adjusted to the right position, reconnect the lifting hook with the auxiliary hook and pull up the sections. At the same time, one side of the main hook is lowered. When the heights of the two sides of the deckhouse are roughly parallel, it is lowered to the flatbed truck for loading and transportation;
[0016] Step 4: The deckhouse is hoisted onto the ship and closed: The deckhouse is hoisted onto the ship at the corresponding position using two cranes at the front and rear ends. Wooden pads are placed at the bottom of the deckhouse to reduce deformation and fix it. The connecting ear plates are cut off and the entire deckhouse is pulled out of the deckhouse window together with the steel pipes and recycled for the next hoisting. The hoisting is completed.
[0017] Beneficial effects of the present invention:
[0018] 1. The present invention fully considers the characteristics of the aluminum deckhouse and the reverse deformation of the lifting process. The criss-crossed channel steel and angle steel base are replaced by two round steels and several lifting brackets. The tooling can be removed synchronously during the segmented positioning process without affecting the installation progress. The removed tooling can be retained and applied to subsequent products.
[0019] 2. The present invention can reduce the labor intensity of workers, save material costs and improve production efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 A schematic structural diagram of a deckhouse hoisting structure provided by an embodiment of the present invention;
[0021] Figure 2 A schematic diagram of steel pipes in a deckhouse hoisting structure provided by an embodiment of the present invention;
[0022] Figure 3 A cross-sectional view of a deckhouse hoisting structure provided by an embodiment of the present invention;
[0023] Figure 4 Deckhouse hoisting structure provided by the embodiment of the present invention Figure 3 Middle PP section view;
[0024] Figure 5 A schematic diagram of the deckhouse hoisting structure and hoisting method provided by an embodiment of the present invention during the process of hoisting and turning over the deckhouse;
[0025] Figure 6 A schematic diagram of the deckhouse hoisting structure and hoisting method provided by an embodiment of the present invention after the deckhouse is hoisted and turned over;
[0026] In the figure, 1-lifting crane, 2-lifting bridge, 3-connecting steel plate, 4-deck house window, 5-connecting ear plate, 6-deck house, 7-lifting rope, 8-steel pipe. DETAILED DESCRIPTION
[0027] In order to explain the technical content, achieved objectives and effects of the present invention in detail, the following is a description of the embodiments in conjunction with the accompanying drawings.
[0028] Example
[0029] like Figure 1-6 As shown, the present invention provides a deckhouse hoisting structure, including deckhouse windows 4 arranged on the side walls of the deckhouse 6 in pairs, the deckhouse windows 4 are vertically provided with connecting ear plates 5 close to the outer wall of the top of the deckhouse 6, and steel pipes 8 are penetrated by the deckhouse windows 4 in pairs. Connecting steel plates 3 that match and are fixedly connected to the connecting ear plates 5 are vertically provided on the outer walls of the steel pipes 8, and hanging codes 2 are respectively provided at both ends of the steel pipes 8.
[0030] Before hoisting, connecting ear plates 5 are vertically welded on the upper outer walls of the deck house windows 4 that are symmetrical on the left and right of the deck house 6, and a steel pipe 8 is used to pass through the symmetrical deck house windows. A connecting steel plate 3 is welded on the steel pipe 8, and the connecting steel plate 3 is also vertically arranged, which can be fixedly connected to the connecting ear plates 5 on both sides of the deck house windows 4, and the two ends of the steel pipe 8 are provided with hanging weights 2, which are connected to the lifting trolley 1 through the sling 7. Similarly, a steel pipe 8 is inserted and installed in another symmetrical deck house window 4, and the hanging weights 2 thereon are connected to the lifting trolley 1 through the sling 7, so that hoisting can begin. Through such a hoisting structure, the hoisting force acts on the side wall, so that the reverse deformation of the deck house during hoisting can be controlled, and the steel pipe 8 can be removed and retained after hoisting and applied to subsequent products; at the same time, such a structure reduces the labor intensity of workers, saves material costs, and improves production efficiency.
[0031] Furthermore, the steel pipe 8 is 6-8 meters long, 280-300 mm in diameter, 10-12 mm thick, and made of CCSB-grade shipboard material. Such a configuration can ensure that the steel pipe 8 has sufficient strength during hoisting.
[0032] Further, the connecting lug plate 5 is made of an aluminum plate. Such an arrangement can ensure strength while the connecting lug plate 5 does not increase the weight of the deckhouse too much.
[0033] Furthermore, the aluminum plate is an aluminum plate with a thickness of 16-20 mm. Such a configuration can ensure the strength of the connecting ear plate 5.
[0034] Furthermore, if Figure 4 As shown, the connecting ear plate 5 is fitted with the connecting steel plate 3, and both have corresponding bolt holes and are connected by bolts. In this way, the steel pipe 8 can be removed after hoisting and reused in another hoisting.
[0035] Furthermore, the connecting steel plate 3 is a steel plate with a thickness of 10-14 mm. Such a configuration ensures the strength of the connecting steel plate 3 without increasing the weight of the hoisting structure too much.
[0036] The method for hoisting the deck house hoisting structure comprises the following steps:
[0037] Step 1: Make steel pipe 8, including welding 10T load-bearing hanger 2 and connecting steel plate 3 on the steel pipe 8; the inner side of the deck house window 4 is partially strengthened, which can be connected by slats or diagonal braces, and the force of the hanger is transmitted to the side wall through strengthening, while reducing the deformation during lifting.
[0038] Step 2, weld the connecting ear plate 5 on the upper outer wall of the left-right symmetrical deckhouse window 4, pass the steel pipe 8 through the symmetrical deckhouse window 4, and adjust the symmetry center of the steel pipe 8 to coincide with the center line of the deckhouse 6, and then fix the connecting steel plate 3 on the steel pipe 8 to the connecting ear plate 5, for example, drilling connecting holes at corresponding positions of the connecting steel plate 3 and the connecting ear plate 5, and tightly connecting the connecting steel plate 3 and the connecting ear plate 5 through the connecting holes with bolts, and repeat the above operation with another steel pipe 8 in another left-right symmetrical deckhouse window 4;
[0039] Step 3: Lift and turn over the deck house 6: Figure 5 As shown, the main hook of the lifting trolley 1 is connected to the two lifting weights 2 on the same side of the deck house 6 through the sling 7, and then the auxiliary hook of the lifting trolley 1 is connected to the two lifting weights 2 on the other side of the deck house 6 through the sling 7. After the main hook and the auxiliary hook synchronously lift the deck house 6 to a distance of 1.5M from the ground, the main hook continues to rise, and the auxiliary hook remains unchanged. After the main hook stands up the deck house 6 as a whole, the lifting weight at the auxiliary hook end is released from the shackle, and then the deck house 6 is pulled with a rope and the front and rear ends are turned. After the direction is adjusted to the right position, the lifting weight is reconnected with the auxiliary hook and the segment is pulled up, and at the same time, one side of the main hook is lowered. When the heights of the two sides of the deck house 6 are roughly parallel, it is lowered to the flatbed truck for loading and transportation;
[0040] Step 4: The deckhouse 6 is hoisted onto the ship and closed: The deckhouse 6 is hoisted onto the ship at the corresponding position by two cranes according to the front and rear ends. The lower mouth of the deckhouse 6 is padded with wooden pads to reduce deformation and fix. The connecting ear plate 5 is cut off and the whole deckhouse window 4 is pulled out together with the steel pipe 8 and recovered for the next hoisting. The hoisting is completed.
[0041] In a certain lifting product, the original lifting plan required 54 meters of angle steel, 84 meters of channel steel, and 3 days of labor by 4 assemblers and 2 welders of the construction team. After adopting the lifting plan of the present invention, only about 12 meters of steel pipes and four 10T hanging brackets are needed, and 2 assemblers can position and install them in 1 day; thus, the lifting tooling construction process saves 54 meters of 75*75*6 angle steel and 84 meters of 20# channel steel, and the installation and dismantling tooling construction team saves 6 assemblers and 2 welders for 2 days of labor, which greatly reduces the construction cost, reduces the labor intensity of workers, saves materials, and improves production efficiency.
[0042] Although the present invention has been described in detail above with specific embodiments, it is obvious to those skilled in the art that some modifications or improvements can be made to the present invention. Therefore, these modifications or improvements made without departing from the spirit of the present invention all belong to the scope of protection claimed by the present invention.
Claims
1. The deck house hoisting structure is characterized by: The invention comprises deckhouse windows (4) arranged on the side wall of the deckhouse (6) in pairs, the deckhouse windows (4) being provided with connecting ear plates (5) vertically arranged near the outer wall of the top of the deckhouse (6), the deckhouse windows (4) being provided with steel pipes (8) passing through the deckhouse windows (4) in pairs, the outer wall of the steel pipe (8) being provided with connecting steel plates (3) matched and fixedly connected with the connecting ear plates (5), and the two ends of the steel pipe (8) being provided with hanging brackets (2) respectively; The steel pipe (8) is 6-8 meters long, 280-300 mm in diameter, 10-12 mm thick, and made of CCSB grade ship plate material; The connecting ear plate (5) is made of an aluminum plate; The aluminum plate is 16-20 mm thick; The connecting ear plate (5) is connected to the connecting steel plate (3) by bolts; The connecting steel plate (3) is a steel plate with a thickness of 10-14 mm.
2. A method for hoisting the deckhouse hoisting structure according to claim 1, characterized in that: The steps include: Step 1, making steel pipes (8), including welding hangers (2) and connecting steel plates (3); locally strengthening the inner side of the deckhouse window (4) by connecting with slats or diagonal braces, so as to transmit the force of the hanger to the side wall and reduce the deformation during lifting; Step 2: Weld the connecting ear plate (5) on the upper outer wall of the left-right symmetrical deckhouse window (4), pass the steel pipe (8) through the symmetrical deckhouse window (4), and adjust the symmetry center of the steel pipe (8) to coincide with the center line of the deckhouse (6), then fix the connecting steel plate (3) on the steel pipe (8) and the connecting ear plate (5), and repeat the above operation with another steel pipe (8) on the other left-right symmetrical deckhouse window (4); Step 3: Lifting and turning over the deckhouse (6): connect the main hook of the lifting trolley (1) to the two lifting weights (2) on the same side of the deckhouse (6) through the sling (7), and then connect the auxiliary hook of the lifting trolley (1) to the two lifting weights (2) on the other side of the deckhouse (6) through the sling (7). After the main hook and the auxiliary hook synchronously lift the deckhouse (6) to a distance of 1.5 meters from the ground, the main hook continues to rise, and the auxiliary hook remains unchanged. After the main hook has erected the deckhouse (6) as a whole, release the shackle of the lifting weight at the auxiliary hook end, and then pull the deckhouse (6) with a rope to turn the front and rear ends. After the direction is adjusted to the right position, reconnect the lifting weight with the auxiliary hook and pull up the sections. At the same time, one side of the main hook is lowered. When the heights of the two sides of the deckhouse (6) are roughly parallel, it is lowered to the flatbed truck for loading and transportation; Step 4: The deckhouse (6) is hoisted onto the ship and closed: The deckhouse (6) is hoisted onto the ship at the corresponding position by two cranes at the front and rear ends. The lower mouth of the deckhouse (6) is padded with wood to reduce deformation and fix it. The connecting ear plate (5) is cut off and the whole deckhouse is pulled out from the deckhouse window (4) together with the steel pipe (8) and recycled for the next hoisting. The hoisting is completed.