A construction structure and construction method for pile foundation underpinning

By using existing piles and new piles as jacking platforms during pile foundation underpinning, combined with jacking devices and monitoring equipment, the problems of traditional construction methods in tight spaces and busy traffic environments are solved, and the construction period and cost are shortened. Save money and reduce the impact on the surrounding environment.

CN110905014BActive Publication Date: 2024-10-18THE SECOND CONSTR OF CHINA CONSTR EIGHTH ENG DIV
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN201911255746.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-12-10
Publication Date
2024-10-18
Estimated Expiration
2039-12-10

AI Technical Summary

Technical Problem

The traditional pile foundation underpinning construction method is difficult to implement in an environment with small space and heavy traffic, resulting in difficulty in construction, organization and coordination, high construction period and cost, and affecting the surrounding environment.

Method used

The existing piles and new piles are used as the jacking platform. By arranging jacking devices on the new pile caps and pile-holding pile caps, the underpinning beam can be jacked up, shortening the construction period and reducing the cost. Through displacement gauges and strain gauges, Film and inclinometers monitor structural deformation to ensure construction safety.

Benefits of technology

This method greatly saves the construction period and cost, reduces the impact on the surrounding environment, is suitable for the pile foundation underpinning construction of bridge abutments or pile groups, and has good promotion value.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110905014B_ABST
    Figure CN110905014B_ABST
Patent Text Reader

Abstract

The invention discloses a construction structure and a construction method for pile foundation underpinning, which belongs to the technical field of pile foundation underpinning and structural transformation in building construction. The construction structure includes an original cap, an existing pile, a newly built pile and a newly built underpinning beam. The underpinned pile is a pile foundation at the edge of the original cap, and also includes a newly built pile cap and a pile-holding pile cap. The newly built pile cap is located at the top of the newly built pile, and the pile-holding pile cap is located on the existing pile on the adjacent side of the underpinned pile; the jacking devices are arranged on the newly built pile cap and the pile-holding pile cap respectively; the newly built underpinning beam is connected to the original cap, and the newly built underpinning beam is located above the newly built pile. The construction method for pile foundation underpinning uses the existing pile and the newly built pile as a jacking platform to carry out pile foundation underpinning, requisitions the existing pile on the adjacent side of the underpinning pile, constructs the existing pile-holding pile cap on the adjacent side of the existing pile; constructs the new pile, and constructs the new pile cap on the new pile. The invention can save construction period and cost, reduce the impact on the surrounding environment, is suitable for the pile foundation underpinning construction of abutments or pile groups, and is beneficial to promotion.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pile foundation underpinning and structural transformation in building construction, in particular to a construction structure and a construction method for pile foundation underpinning. Background Art

[0002] Pile foundation underpinning is a method of replacing foundations in the form of pile foundations. It is generally used for underground foundation reconstruction of buildings and is a way of foundation treatment and reinforcement. Pile foundation underpinning is mainly used to solve the problem of foundation reinforcement of existing buildings, the need to build underground projects under the foundations of existing buildings or new construction projects that affect the safety of existing buildings, and the conflict between new construction and existing piles.

[0003] When using newly built piles to underpin existing piles, the conventional underpinning scheme is to adopt the "remove one and build two, remove two and build four" scheme, that is, to underpin two existing piles, four new pile foundations need to be built as jacking platforms. For example, if a conflict occurs with the pile foundation of an overpass abutment during construction, the two pile foundations on the easternmost side under the abutment need to be removed by underpinning technology after construction. If the conventional "remove one and build two, remove two and build four" scheme is adopted for the newly built pile foundation, a total of four new pile foundations need to be built as jacking platforms. Two of the newly built piles can be constructed on the east side of the existing abutment, and another newly built pile needs to be constructed under the existing abutment. The space under the abutment is small, and the drilling rig and steel cage are limited by the height of the space, which makes the construction difficult; the other pile is on the approach road of the overpass, and the road needs to be closed during construction to divert traffic. Using this traditional construction method, the construction difficulty, organization difficulty, and coordination difficulty will be greatly increased. Summary of the invention

[0004] The technical task of the present invention is to provide a construction structure and a construction method for pile foundation underpinning in view of the above shortcomings, which can shorten the construction period, reduce the construction cost and reduce the impact on the surrounding environment.

[0005] The technical solution adopted by the present invention to solve its technical problem is:

[0006] A construction structure for pile foundation underpinning includes an original cap, existing piles, newly built piles and newly built underpinning beams. The underpinned piles are the edge pile foundations of the original cap. The structure also includes newly built pile caps and pile-holding pile caps.

[0007] The newly built pile cap is located on the top of the newly built pile, and the pile-holding pile cap is located on the existing pile adjacent to the replaced pile; the jacking devices are arranged on the newly built pile cap and the pile-holding pile cap respectively;

[0008] The newly built underpinning beam is connected to the original pedestal to increase the area of ​​the original pedestal to form an integral underpinning beam. The newly built underpinning beam is located above the newly built piles.

[0009] This structure uses existing piles and newly built piles as jacking platforms to replace the pile foundation. The underpinning beam is supported by arranging jacking devices on the newly built pile cap and the pile-holding pile cap. The underpinning pile is cut off under this support to achieve pile foundation underpinning. Compared with the conventional construction structure of "removing one and building two, removing two and building four", it greatly saves construction time and cost, and can reduce the impact on the surrounding environment.

[0010] Preferably, there are two underpinning piles and two newly built piles; new pile caps are constructed on both newly built piles; two existing piles on the adjacent sides of the two underpinning piles are requisitioned and pile-holding pile caps are constructed on each of them. Lifting devices are arranged on the two newly built pile caps and the two pile-holding pile caps respectively, and the four pile caps are used as jacking platforms to realize the lifting of the underpinning beam.

[0011] Preferably, the jacking device includes a hydraulic jack, a self-locking device and an auxiliary support. Three hydraulic jacks, three auxiliary supports and three self-locking devices are arranged in a herringbone shape on the newly built pile cap and the pile-holding pile cap, respectively. The jacks at the same end use parallel oil circuits to ensure that the oil pressure of each jack at the same end is consistent.

[0012] Preferably, the newly built replacement beam includes an extension portion and a bottom connecting portion, the extension portion is connected to the end of the original pedestal and is located above the newly built pile, and the bottom connecting portion connects the bottom of the extension portion with the bottom of the original pedestal, so that the bottom of the extension portion and the bottom of the original pedestal become one, forming a replacement beam as a whole, thereby realizing the jacking of the newly built pile.

[0013] Preferably, the structure also includes displacement meters, strain gauges and inclinometers, which are installed on the newly built pile caps, pile-holding pile caps and underpinning beams. At least one displacement meter is arranged on each newly built pile cap and pile-holding pile cap to monitor the settlement displacement of the pile foundation; displacement meters are arranged at intervals on the top surfaces of the original pedestal and the newly built underpinning beam to monitor the settlement displacement of the underpinning beam; inclinometers are arranged at the four corners of the top surfaces of the original pedestal and the newly built underpinning beam to monitor the inclination deformation of the beam body; strain gauges are installed on the sides of the original pedestal and the newly built underpinning beam, and the strain gauges are connected to the strain gauges to test the longitudinal stress of the maximum bending moment section of the beam body.

[0014] Preferably, the original cap is a bridge abutment, and the pile to be replaced is a pile foundation at the end of the bridge abutment. The existing piles and the newly built piles are used as a jacking platform for active underpinning, so as to realize the underpinning of the existing piles at the end of the bridge abutment.

[0015] The newly built pile and the replaced pile are piles of equal diameter, and the cross-section of the newly built pile cap is square, with a side length not less than 5 / 3 of the diameter of the existing pile; the cross-section of the pile-holding pile cap is rectangular, with a short side length not less than 5 / 3 of the diameter of the existing pile and a long side length not less than 7 / 3 of the diameter of the existing pile.

[0016] The present invention also claims a construction method for pile foundation underpinning, wherein the underpinning pile is an existing pile foundation at the edge of a cap, and the underpinning pile is underpinned by a newly built underpinning beam and a newly built pile, and the method is characterized in that the existing pile and the newly built pile are used as a jacking platform to underpin the pile foundation.

[0017] Expropriate the existing piles adjacent to the replacement piles, and construct pile caps on the existing piles; construct new piles, and construct new pile caps on the new piles; construct new replacement beams above the new piles to form a replacement beam as a whole with the original cap;

[0018] A jacking device is installed on the pile-holding pile cap and the newly built pile cap, and displacement monitoring points are arranged on the pile-holding pile cap, the newly built pile cap and the underpinning beam respectively.

[0019] Preferably, the jacking includes a stage of jacking existing piles and a stage of jacking new piles and existing piles simultaneously, wherein in the stage of jacking existing piles only the ends of existing piles are pressurized; in the stage of jacking new piles and existing piles simultaneously, the existing piles and new piles located at both ends of the replacement beam are pressurized simultaneously.

[0020] After the equipment and monitoring are debugged normally, the existing pile lifting stage begins. In this stage, the optimal truncation lifting force of the existing pile is determined and the existing pile is truncated. After the existing pile is truncated and the structure is stable without obvious changes, the new pile and the existing pile are simultaneously lifted. In this stage, the optimal pile breaking lifting force of the replaced pile is determined and the replaced pile is cut off.

[0021] The main objectives of the existing pile jacking phase are:

[0022] The actual optimum breaking pile lifting force is analyzed and determined by loading and stabilizing the existing pile ends step by step. The structural safety of the underpinning system, especially the pile-holding pile cap, is tested by theoretical overpressure.

[0023] The main purpose of the synchronous lifting stage of new piles and existing piles is to:

[0024] At this time, the existing piles have been cut off, and the early settlement of the pile foundation is eliminated by synchronous step-by-step loading and stabilizing the pressure at both ends; the displacement of the underpinning beam is monitored during the step-by-step pressurization process to determine the optimal lifting force for the broken pile of the underpinned pile; and the partial pull-out resistance of the underpinned pile is used to overpressure to test the structural safety.

[0025] Furthermore, the specific construction steps of the construction method are as follows:

[0026] 1) Construction of new piles;

[0027] 2) Excavate the foundation pit while supporting it to the designed elevation;

[0028] 3) Construction of new pile caps, existing pile caps and replacement beams;

[0029] 4) Calculate the jacking force values ​​of the new pile end and the existing pile end respectively, and install the jacking device after the replacement beam and pile cap concrete are strong. The jacking device includes a self-locking device, auxiliary support and jack;

[0030] 5) Arrange displacement monitoring points, stress-strain monitoring points and tilt monitoring points on the pile cap and underpinning beam respectively, and collect original test data;

[0031] 6) Lifting, synchronously detecting and cutting off the existing pile;

[0032] 7) Jacking and simultaneous testing of newly built piles;

[0033] 8) New piles are lifted synchronously with existing piles;

[0034] 9) Being cut off by the underpinning pile;

[0035] 10) The jack returns to the oil and the load is transferred to the self-locking device and auxiliary support;

[0036] 11) Pour concrete at the underpinning nodes and use existing piles and newly built piles as the pile foundation of the jacking platform to complete the underpinning.

[0037] Preferably, the newly built pile ends and the existing pile ends are pressurized step by step according to the calculated values ​​of 30%, 20%, 15%, 10%, 10%, 10%, 5%, 5%, 3%, and 2%, and a theoretical overpressure test is carried out. After each level of loading, the pressure is maintained for 5 minutes, and each data is monitored and comprehensively analyzed.

[0038] Compared with the prior art, the construction structure and construction method of the pile foundation underpinning of the present invention have the following advantages:

[0039] Beneficial effects:

[0040] This construction structure and method utilizes both existing piles and newly built piles as a jacking platform, which greatly saves construction time and cost compared to the conventional pile foundation underpinning scheme of "eliminating one and building two, eliminating two and building four", and reduces the impact on the surrounding environment. It is suitable for pile foundation underpinning construction of abutments or pile groups, and has great value for use and promotion. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] Figure 1 is a cross-sectional schematic diagram of using existing piles and newly built piles to underpin the pile foundation of the jacking platform in the embodiment;

[0042] Figure 2 It is a BIM rendering of using existing piles and newly built piles to replace the pile foundation of the jacking platform.

[0043] 1. Existing foundation, 2. New underpinning beam, 3. New pile, 4. Existing pile, 5. Underpinning pile, 6. New pile cap, 7. Pile-holding pile cap, 8. Lifting device, 9. Displacement meter, 10. Strain gauge, 11. Inclinometer, 12. Underpinning node. DETAILED DESCRIPTION

[0044] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0045] A construction structure for pile foundation underpinning includes an original cap 1, an existing pile 4, a newly built pile 3 and a newly built underpinning beam 2. The underpinned pile 5 is a side pile foundation of the original cap 1. The structure also includes a newly built pile cap 6 and a pile-holding pile cap 7. The newly built pile cap 6 is located on the top of the newly built pile 3, and the pile-holding pile cap 7 is located on the existing pile 4 adjacent to the underpinned pile 5.

[0046] The jacking device 8 is arranged on the newly built pile cap 6 and the pile-holding pile cap 7 respectively. The newly built replacement beam 2 is connected to the original pedestal 1 to increase the area of ​​the original pedestal to form an integral replacement beam. The newly built replacement beam 2 is located above the newly built pile 3.

[0047] The original cap 1 is the abutment, and the underpinned pile 5 is the pile foundation at the end of the abutment. The existing pile 4 and the newly built pile 3 are used as a jacking platform to actively underpin, thereby realizing the underpinning of the existing pile at the end of the abutment.

[0048] There are two underpinning piles 5 and two newly built piles 3. New pile caps 6 are constructed on both newly built piles 3. Two existing piles 4 on the adjacent sides of the two underpinning piles 5 are requisitioned, and pile-holding pile caps 7 are constructed respectively. Jacking devices 8 are arranged on the two newly built pile caps 6 and the two pile-holding pile caps 7 respectively, and the four pile caps are used as jacking platforms to realize the jacking of the underpinning beam. The newly built underpinning beam 2 includes an extension part and a bottom connecting part. The extension part is connected to the end of the original pedestal 1 and is located above the newly built pile 4. The bottom connecting part connects the bottom of the extension part with the bottom of the original pedestal 1, so that the bottom of the extension part and the bottom of the original pedestal 1 become one, forming the underpinning beam as a whole, and realizing the jacking of the newly built pile 3.

[0049] The jacking device 8 includes a hydraulic jack, a self-locking device and an auxiliary support. Three hydraulic jacks, three auxiliary supports and three self-locking devices are arranged in a herringbone shape on the newly built pile cap 6 and the pile-holding pile cap 7 respectively. The jacks at the same end use parallel oil circuits to ensure that the oil pressure of each jack at the same end is consistent.

[0050] The structure also includes displacement meters 9, strain gauges 10 and inclinometers 11, which are installed on the newly built pile caps 6, pile-holding pile caps 7 and underpinning beams. At least one displacement meter 9 is arranged on each newly built pile cap 6 and pile-holding pile cap 7 to monitor the settlement displacement of the pile foundation; displacement meters 9 are arranged at intervals on the top surfaces of the original cap 1 and the newly built underpinning beam 2 to monitor the settlement displacement of the underpinning beam; inclinometers 11 are arranged at the four corners of the top surfaces of the original cap 1 and the newly built underpinning beam 2 to monitor the inclination deformation of the beam body; strain gauges 10 are installed on the sides of the original cap 1 and the newly built underpinning beam 2, and the strain gauges 10 are connected to the strain gauges to test the longitudinal stress of the maximum bending moment section of the beam body.

[0051] A construction method for pile foundation underpinning, wherein the underpinning pile is an edge pile foundation of an original cap 1, and a new underpinning beam 2 and a new pile 3 are built to underpin the underpinning pile. The method uses the existing pile 4 and the new pile 3 as a jacking platform to underpin the pile foundation.

[0052] The method uses the existing pile 4 adjacent to the underpinning pile 5, constructs the existing pile-holding pile cap 7 on the adjacent existing pile 4; constructs a new pile 3, and constructs a new pile cap 6 on the new pile 3; constructs a new underpinning beam 2 above the corresponding new pile 3, and forms an underpinning beam integrally with the original cap 1. A jacking device 8 is installed on the pile-holding pile cap 7 and the new pile cap 6, and displacement monitoring points are arranged on the pile-holding pile cap 7, the new pile cap 6 and the underpinning beam.

[0053] The jacking includes the jacking stage of existing piles and the synchronous jacking stage of newly built piles and existing piles. In the jacking stage of existing piles, only the ends of existing piles are pressurized. In the synchronous jacking stage of newly built piles and existing piles, the existing piles 4 and newly built piles 3 located at both ends of the replacement beam are pressurized synchronously.

[0054] After the equipment and monitoring are debugged normally, the existing pile lifting stage is entered. In this stage, the optimal truncation lifting force of the existing pile 4 is determined and the existing pile 4 is truncated. After the existing pile 4 is truncated and the structure is stable without obvious changes, the new pile and the existing pile are simultaneously lifted. In this stage, the optimal pile breaking lifting force of the replaced pile 5 is determined and the replaced pile 5 is cut off.

[0055] The main objectives of the existing pile jacking phase are:

[0056] By loading and stabilizing the existing pile ends step by step, the actual optimal pile-breaking lifting force is analyzed and determined; the structural safety of the underpinning system is tested by theoretical overpressure, especially the pile-holding pile cap 7.

[0057] The main purpose of the synchronous lifting stage of new piles and existing piles is to:

[0058] At this time, the existing pile 4 has been cut off, and the early settlement of the pile foundation is eliminated by synchronous step-by-step loading and stabilizing the pressure at both ends; the displacement of the underpinning beam is monitored during the step-by-step pressurization process to determine the optimal jacking force of the broken pile of the underpinning pile; and the partial pull-out resistance of the underpinning pile 5 is used to overpressure to test the structural safety.

[0059] The specific construction steps of this construction method are as follows:

[0060] 1) Construction of new piles;

[0061] 2) Excavate the foundation pit while supporting it to the designed elevation;

[0062] 3) Construction of new pile caps, existing pile caps and replacement beams;

[0063] 4) Calculate the jacking force values ​​of the new pile end and the existing pile end respectively, and install the jacking device after the replacement beam and pile cap concrete are strong. The jacking device includes a self-locking device, auxiliary support and jack;

[0064] 5) Arrange displacement monitoring points, stress-strain monitoring points and tilt monitoring points on the pile cap and underpinning beam respectively, and collect original test data;

[0065] 6) Lifting, synchronously detecting and cutting off the existing pile;

[0066] 7) Jacking and simultaneous testing of newly built piles;

[0067] 8) New piles are lifted synchronously with existing piles;

[0068] 9) Being cut off by the underpinning pile;

[0069] 10) The jack returns to the oil and the load is transferred to the self-locking device and auxiliary support;

[0070] 11) Pour concrete at the underpinning nodes and use existing piles and newly built piles as the pile foundation of the jacking platform to complete the underpinning.

[0071] Taking the Zhengzhou Rail Transit Line 3 Phase I project as an example, the shield method was used to construct the section between Shamen Road Station and Xinglongpu Road Station of the Zhengzhou Rail Transit Line 3 Phase I project. The right-line tunnel collides with the pile foundation (friction pile) NYT1-1 and NYT1-5 of the NY-1 abutment of the Nanyang Road North Third Ring Interchange at mileage DK7+930.0, and the soil cover depth at the conflict point is about 11.78m. There are 8 bored piles with a diameter of 1500mm and a length of 23.5m under the NY1 abutment. Among them, the two easternmost pile foundations NYT1-1 and NYT1-5 conflict with the right-line tunnel and need to be removed after the construction by using the underpinning technology.

[0072] However, if the new pile foundation adopts the conventional "remove one and build two, remove two and build four" replacement scheme, a total of four new pile foundations will be needed as the jacking platform. Two of the new piles can be constructed on the east side of the existing abutment, and another new pile needs to be constructed under the existing abutment. The space under the abutment is small, and the drilling rig and steel cage are limited by the height of the space, which makes construction difficult; the other pile is on the overpass approach, and the road needs to be closed during construction to divert traffic. If this method is used to replace NYT1-1 and NYT1-5, the construction difficulty, organizational difficulty, and coordination difficulty will be greatly increased.

[0073] After comprehensively considering the site environment, construction period, cost, safety and other factors, it was finally decided to build two new replacement piles with a length of 35m and a diameter of 1500mm on the east side of the original pier as pile caps. In addition, the existing pile foundations NYT1-2 and NYT1-6 of the abutment were requisitioned to construct pile-holding pile caps as a jacking platform, and the upper original abutment was enlarged as a replacement beam to form the abutment pile foundation replacement system.

[0074] Construction method

[0075] The tunnel between Shamen Road Station and Xinglongpu Road Station of Zhengzhou Metro Line 3 Phase I Project crosses Nanyang Road and the North Third Ring Interchange. The right-line tunnel is crossing the NYT1-1 and NYT1-5 piles of the NY1 bridge abutment, and the pile foundation needs to be replaced. The design uses the existing piles and the newly built piles as the jacking platform for active replacement. First, the new underpinning piles XZ-1 and XZ-2 are constructed, and then the foundation pit is excavated to 2.2m below the old pedestal. 2500×2500×1500mm and 2500×3500×1500mm pile caps are respectively applied on the underpinning piles and the existing piles as the jacking platform. After the pile caps are completed, as shown in the attached Figure 1 , the original cap is enlarged in size to serve as the underpinning beam, forming this underpinning system, as shown in the attached Figure 2 .

[0076] According to the load of 18795.36KN transmitted to the bottom of the replacement beam by the abutment and superstructure provided by the design institute, the load was redistributed. Taking into account the negative friction and safety reserve of the original pile foundation, the load coefficient was taken as 1.2 for mechanical verification. The theoretical values ​​of the jacking force at the existing pile end and the newly built pile end were calculated to be 14903.388KN and 7695.044KN respectively. The two ends of the jacking platform were pressurized step by step according to the theoretical design values ​​of 30%, 20%, 15%, 10%, 10%, 10%, 5%, 5%, 3%, and 2%.

[0077] After the concrete of the to-be-added structure reaches the same strength, remove the formwork and start installing the jacking device and arranging monitoring points. On each pile cap, install 3 sets of 320T hydraulic jacks, 3 auxiliary supports, and 3 self-locking devices in a "pin" shape. The jacks at the same end adopt a parallel oil circuit to ensure that the oil pressure of each jack at the same end is the same. The main parts for arranging monitoring points are the pile cap and the underpinning beam. One displacement monitoring point is arranged on the upper part of each pile cap to monitor the settlement displacement of the pile foundation; after grinding and leveling the fixed point on the north side of the underpinning beam with a angle grinder, paste strain gauges and connect the strain gauges to test the longitudinal stress of the maximum bending moment section of the beam body. A total of 15 strain gauges are arranged; 4 displacement gauges are arranged at intervals on the top surface of the underpinning beam concrete to monitor the settlement displacement of the underpinning beam, and inclinometers are arranged at the four corners to monitor the inclination deformation of the beam body. After all the jacking equipment and monitoring points are installed, debug the equipment and collect and record the original monitoring data.

[0078] After the equipment and monitoring are debugged normally, enter the stage of jacking the existing piles. Main purposes: 1. Analyze and determine the actual optimal pile-cutting jacking force by gradually loading and stabilizing the pressure only at the ends of the existing piles; 2. Conduct a theoretical overpressure test on the underpinning system to check the structural safety (especially the outer pile cap).

[0079] In the jacking operation at this stage, only gradually load the ends of the existing piles, and do not load the stable self-locking devices at the ends of the newly built piles. According to ten-level loading, pressurize in stages, stabilize the pressure for 5 minutes after each level of loading, monitor each data, and conduct comprehensive analysis. When it is monitored that the underpinning beam has an upward trend after pressurizing to a certain level, it can be determined that the optimal cut-off jacking force of the existing pile 4 is near the previous level of jacking force. At this time, analyze the settlement displacement data of the underpinning beam and the pile-holding pile cap 7. If there is no slip of the existing pile 4 relative to the pile-holding pile cap 7, check the structural appearance and analyze the monitoring data to be normal, and still further loading can be carried out to check the structural bearing capacity. When loading to a higher level, it is monitored that the displacement of the underpinning beam rises within 1 mm, and the edge displacement of the pile-holding pile cap 7 sinks. Then check the structural appearance and analyze the monitoring data. If both are normal, it means that the structural bearing capacity has met the requirements and there is no need to continue loading. Release the oil to the optimal jacking force, stabilize the pressure, and cut off the existing pile 4 with a wire saw.

[0080] After the structure is stable and there is no obvious change, enter the stage of synchronous jacking of the four piles at both ends of the underpinning beam, that is, the stage of synchronous jacking of the newly built piles and the existing piles. Main purposes: 1. At this time, the existing pile 4 has been cut off. Eliminate the initial settlement of the pile foundation by gradually loading and stabilizing the pressure at both ends synchronously; 2. Monitor the displacement of the underpinning beam during the process of gradually pressurizing to determine the optimal cut-off jacking force of the pile 5 to be underpinned; 3. Use part of the uplift force of the pile 5 to be underpinned for overpressure test of the structural safety.

[0081] At this time, the existing pile 4 has been stabilized to the best lifting force before the pile is broken. First, the new pile end is graded and pressurized to the best lifting force before the existing pile 4 is broken, so as to achieve synchronous lifting with the existing pile 4 end. Then, the two ends are pressurized synchronously step by step. When the pressure is increased to a certain level, it is monitored that the underpinning beam has an upward lifting trend. At this time, in order to prevent the upper structure from "rebounding" after the pile is broken, the upper level of lifting force can be determined as the best pile breaking lifting force. The appearance of the structure is checked and the monitoring data is analyzed if they are normal. In order to further verify the safety of the structure, the pressure is increased synchronously to a higher level. After stabilization, the lifting of the underpinning beam and the sinking of the pile cap are monitored. The lifting of the underpinning beam is controlled within 1mm, and the sinking of the pile cap is controlled within 5mm, mainly based on the changes of the underpinning beam. If the lifting of the underpinning beam is close to 1mm and the sinking of the pile cap is too large, it means that the friction of the soil around the pile is small, and it is necessary to properly grout around the pile to increase the friction around the pile. When the sinking of the pile cap is small, it means that the friction around the pile meets the requirements. When the structural appearance is checked and the monitoring data are analyzed and found to be normal, the last jacking force can be determined as the final jacking force. Then the oil in the jack is returned to the optimal pile-breaking jacking force, and the pile to be replaced is cut off after the pressure is stabilized.

[0082] As the jacking is cut off, the synchronous self-locking device is grouting and locking, and the auxiliary support is welded and reinforced. After the monitoring is stable, the jacks return oil step by step to complete the load transfer. After all the jacks are withdrawn, grouting is applied to the broken pile of the existing pile and the existing pile reinforcement is restored. The reinforcement of the replacement node is tied to complete the concrete pouring. The construction process of using the existing piles and the newly built piles as the pile foundation of the jacking platform is completed.

[0083] Through the above specific implementations, those skilled in the art can easily implement the present invention. However, it should be understood that the present invention is not limited to the above specific implementations. On the basis of the disclosed implementations, those skilled in the art can arbitrarily combine different technical features to achieve different technical solutions.

[0084] Except for the technical features described in the specification, all other technical features are known technologies to those skilled in the art.

Claims

1. A construction structure for pile foundation underpinning, comprising an existing cap, existing piles, newly built piles and newly built underpinning beams, wherein the underpinned piles are the edge pile foundations of the existing cap. Features The structure also includes new pile caps and pile caps. The newly built pile cap is located on the top of the newly built pile, and the pile-holding pile cap is located on the existing pile adjacent to the replaced pile; the jacking devices are arranged on the newly built pile cap and the pile-holding pile cap respectively; The newly built underpinning beam is connected to the original cap, and the newly built underpinning beam is located above the newly built piles; There are two replaced piles and two newly built piles; new pile caps are constructed on both newly built piles; two existing piles adjacent to the two replaced piles are requisitioned and pile-holding pile caps are constructed on each of them; The original pedestal is a bridge abutment, and the replaced pile is a pile foundation at the end of the bridge abutment; the newly built replacement beam includes an extension portion and a bottom connecting portion, the extension portion is connected to the end of the original pedestal and is located above the newly built pile, and the bottom connecting portion connects the bottom of the extension portion with the bottom of the original pedestal, so that the bottom of the extension portion and the bottom of the original pedestal become one.

2. A construction structure for pile foundation underpinning according to claim 1, Features The jacking device includes a hydraulic jack, a self-locking device and an auxiliary support. Three hydraulic jacks, three auxiliary supports and three self-locking devices are arranged in a herringbone shape on the newly built pile cap and the pile-holding pile cap.

3. A construction structure for pile foundation underpinning according to claim 1, Features At least one displacement meter is arranged on each newly built pile cap and pile-holding pile cap, displacement meters are arranged at intervals on the top surfaces of the original pedestal and the newly built replacement beam, inclinometers are arranged at the four corners of the top surfaces of the original pedestal and the newly built replacement beam, strain gauges are installed on the sides of the original pedestal and the newly built replacement beam, and the strain gauges are connected to the strain gauges.

4. A construction method for underpinning a pile foundation, wherein the underpinning pile is an existing pile foundation at the edge of a cap, and a new underpinning beam and a new pile are constructed to underpin the underpinning pile. Features This method uses existing piles and newly built piles as jacking platforms to replace pile foundations. Expropriate the existing piles adjacent to the replacement piles, and construct pile caps on the existing piles; construct new piles, and construct new pile caps on the new piles; construct new replacement beams above the new piles to form a replacement beam as a whole with the original cap; Install jacking devices on the pile caps and newly built pile caps, and arrange displacement monitoring points on the pile caps, newly built pile caps and underpinning beams; The jacking includes the jacking stage of existing piles and the jacking stage of newly built piles and existing piles simultaneously. In the jacking stage of existing piles, only the ends of existing piles are pressurized. In the jacking stage of newly built piles and existing piles simultaneously, the existing piles and newly built piles located at both ends of the replacement beam are pressurized simultaneously.

5. A construction method for pile foundation underpinning according to claim 4, Features The specific construction steps are as follows: 1) Construction of new piles; 2) Excavate the foundation pit while supporting it to the designed elevation; 3) Construction of new pile caps, existing pile caps and underpinning beams; 4) Calculate the lifting force of the new pile end and the existing pile end respectively, and install the lifting device after the replacement beam and pile cap concrete are strong. The lifting device includes a self-locking device, auxiliary support and jack; 5) Arrange displacement monitoring points, stress-strain monitoring points and tilt monitoring points on the pile cap and underpinning beam respectively, and collect original test data; 6) Lifting, synchronously detecting and cutting off the existing pile; 7) Lifting and simultaneous testing of newly built piles; 8) New piles are lifted synchronously with existing piles; 9) Being cut off by the underpinning pile; 10) The jack returns to the oil and the load is transferred to the self-locking device and auxiliary support; 11) Pour concrete at the underpinning nodes and use existing piles and newly built piles as the pile foundation for the jacking platform to complete the underpinning.

6. A construction method for pile foundation underpinning according to claim 4, Features The newly built pile ends and existing pile ends are pressurized step by step according to the calculated values ​​of 30%, 20%, 15%, 10%, 10%, 10%, 5%, 5%, 3% and 2%.

Citation Information

Patent Citations

  • Pile foundation building slant rectification pile-cutting replacement limiting structure and construction method thereof

    CN109356210A

  • Underpinning limiting structure for tilt-rectifying cut-off pile of pile foundation building

    CN209243794U

  • Pile foundation underpinning construction structure

    CN212052920U