A concrete column node area steel sleeve and concrete column-beam node connection structure
By designing steel sleeves and construction methods in the concrete column joint areas, the existing problems of difficult construction and poor integrity of prefabricated concrete frame joints have been solved, high stiffness and efficient beam-column connections have been achieved, and the construction quality and quality of prefabricated buildings have been improved. Seismic performance.
Patent Information
- Application Number
- CN201911240633.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-12-06
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2039-12-06
AI Technical Summary
Existing prefabricated concrete frame nodes have difficulties in on-site construction, poor integrity, and low degree of industrialization and modularization, resulting in the lateral stiffness of the prefabricated structure being inferior to the cast-in-place structure.
A steel sleeve in the joint area of concrete columns is designed, including angle steel, longitudinal bars, positioning stirrups, tie plates, positioning steel plates and upper flange connection angle steel in the joint area. It is welded to form a high-stiffness beam-column joint joint, which is used in The connection structure is prefabricated in the factory, and only the beams and connections need to be installed on site, simplifying the construction process.
It improves the convenience and integrity of on-site construction, enhances the stiffness and seismic performance of beam-column connections, meets the requirements of "strong joints and weak structures", and improves the construction efficiency and quality of prefabricated buildings.
Smart Images

Figure CN110924538B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a concrete column node area steel sleeve and a concrete column-beam node connection structure, belonging to the technical fields of building technology and structural engineering technology. Background Art
[0002] my country is promoting new types of building industrialization. Prefabricated buildings stand out with their advantages such as convenient mechanized construction, green and energy-saving environment, and standardized design and management. They also combine the three technologies of "low energy consumption, integration, prefabrication and cast-in-place" to make the best use of their strengths and avoid their weaknesses, thus opening a new milestone in the construction industry. However, my country's prefabricated buildings started late, and due to the limitations of architectural design and construction technology, my country's prefabricated buildings lag slightly behind those of the United States, Japan and other countries. The node connection problem of prefabricated components is an important factor restricting the development of prefabricated buildings. As an important hub for force transmission, the node is related to the bearing capacity, seismic resistance, structural stiffness, etc. of the entire structure, and must meet the requirements of "strong nodes and weak components". In addition, the node design should also facilitate on-site construction.
[0003] The existing prefabricated concrete frame nodes still have the following major problems:
[0004] First, on-site construction is difficult. During on-site installation, connection problems caused by tolerances in the manufacture of prefabricated components, the proficiency of installers, environmental factors at the time, etc. make on-site construction difficult.
[0005] Second, the degree of industrialization and modularization is low, and the various connectors are not standardized;
[0006] Third, the integrity is poor. Prefabricated components often have dimensional errors. At the same time, prefabricated concrete structures still need to cast concrete on site at the joints of the components. The adhesion between the new and old concrete on the contact surface is poor, making the connection between prefabricated components not as stable as the cast-in-place structure, resulting in the integrity and lateral stiffness of the prefabricated structure being inferior to the cast-in-place structure.
[0007] Based on the above shortcomings, it is extremely important to design a beam-column node with simple on-site construction, strong integrity and high rigidity. Summary of the invention
[0008] The present invention provides a concrete column node area steel sleeve, which has the advantage of reducing the difficulty of on-site operation.
[0009] A steel sleeve for a concrete column node area comprises angle steels distributed at the four corners of the concrete column, a number of reinforced concrete column longitudinal bars inside the angle steels, positioning stirrups at the bottom of the angle steels, stirrups at the bottom of the positioning stirrups, a certain number of tie plates between every two angle steels, a first positioning steel plate at the bottom between every two angle steels in the direction of a first U-shaped steel concrete beam, an upper flange connecting angle steel of the first node area at the top of two angle steels in the direction of the first U-shaped steel concrete beam, a second positioning steel plate at the bottom between every two angle steels in the direction of a second U-shaped steel concrete beam, and an upper flange connecting angle steel of the second node area at the top of two angle steels in the direction of the second U-shaped steel concrete beam.
[0010] The first positioning steel plate is an "L"-shaped steel plate, the bottom edge of the short leg of the first positioning steel plate is horizontally aligned with the bottom edge of the angle steel in the direction of the first U-shaped steel concrete beam, and the two sides of the short leg of the first positioning steel plate are vertically welded to the two sides of the angle steel.
[0011] The second positioning steel plate is an "L"-shaped steel plate, the bottom edge of the short leg of the second positioning steel plate is horizontally aligned with the bottom edge of the angle steel in the direction of the second U-shaped steel concrete beam, and the two sides of the short leg of the second positioning steel plate are vertically welded to the two sides of the angle steel.
[0012] The upper flange connection angle steel of the first node area is an "L"-shaped steel plate. The top edge of the short leg of the upper flange connection angle steel of the first node area is horizontally aligned with the top edge of the angle steel in the direction of the first U-shaped steel concrete beam, and the two sides of the short leg of the upper flange connection angle steel of the first node area are vertically welded to the two sides of the angle steel.
[0013] The upper flange connection angle steel of the second node area is an "L"-shaped steel plate, the top edge of the short leg of the upper flange connection angle steel of the second node area is horizontally aligned with the top edge of the angle steel in the direction of the second U-shaped steel concrete beam, and the two sides of the short leg of the upper flange connection angle steel of the second node area are vertically welded to the two sides of the angle steel.
[0014] The diameter of the positioning stirrups at the lower side of the angle steel of the column node unit is greater than or equal to the thickness of the angle steels at the four corners of the concrete column.
[0015] Another object of the present invention is to provide a construction method for a steel sleeve in a concrete column node area.
[0016] A construction method for a steel sleeve in a concrete column node area comprises the following steps:
[0017] S1. Locate the positions of the four angle steels according to the size of the column section.
[0018] S2, vertically weld the first positioning steel plate to the lower side between the two angle steels in the direction of the first U-shaped steel concrete beam,
[0019] S3, weld the three sides of the lower flange steel plate of the first node area to the first positioning steel plate in the direction of the first U-shaped steel concrete beam.
[0020] S4. Vertically weld the second positioning steel plate to the lower side between the two angle steels in the direction of the second U-shaped steel concrete beam.
[0021] S5. In the direction of the second U-shaped steel concrete beam, weld the three sides of the lower flange steel plate of the second node area to the second positioning steel plate.
[0022] S6. Weld several tie plates vertically between the angle steels.
[0023] S7. Vertically weld the first node area connecting angle steel to the upper side between the two angle steels in the direction of the first U-shaped steel concrete beam.
[0024] S8. In the direction of the first U-shaped steel concrete beam, weld the upper flange steel plate of the first node area horizontally on three sides to the upper flange connecting angle steel of the first node area.
[0025] S9. Vertically weld the second node area connecting angle steel to the upper side between the two angle steels in the direction of the second U-shaped steel concrete beam.
[0026] S10. In the direction of the second U-shaped steel concrete beam, weld the upper flange steel plate of the second node area horizontally on three sides to the upper flange connecting angle steel of the second node area.
[0027] S11. Vertically weld the web connecting plate of the first node area to the angle steel in the direction of the first U-shaped steel concrete beam.
[0028] S12. Horizontally connect the upper side of the web connection plate in the first node area with the connecting angle steel of the upper flange in the first node area.
[0029] S13, horizontally connect the lower side of the web connection plate in the first node area to the first positioning steel plate,
[0030] S14, vertically weld the web connecting plate of the second node area to the angle steel in the direction of the second U-shaped steel concrete beam,
[0031] S15. Horizontally connect the upper side of the web connection plate in the second node area with the connecting angle steel of the upper flange in the second node area.
[0032] S16. Horizontally connect the lower side of the web connection plate in the second node area to the positioning steel plate to form a beam-column connection joint.
[0033] Another object of the present invention is to provide a concrete column-beam node joint.
[0034] A concrete column-beam node joint, comprising an upper flange steel plate in a node area, a lower flange steel plate in a first node area, a lower flange of a first U-shaped steel concrete beam horizontally connected to the lower flange steel plate in the first node area, a lower flange steel plate in a second node area, a lower flange of a second U-shaped steel concrete beam horizontally connected to the lower flange steel plate in the second node area, an upper flange connecting angle steel in the first node area vertically connected to the upper flange steel plate in the node area in the direction of the first U-shaped steel concrete beam, an upper flange connecting angle steel in the second node area vertically connected to the upper flange steel plate in the node area in the direction of the second U-shaped steel concrete beam, and a lower flange connecting angle steel in the first U-shaped steel concrete beam vertically connected to the upper flange steel plate in the node area in the direction of the second U-shaped steel concrete beam. The upper flange of the first U-shaped steel-concrete beam horizontally connected to the upper flange steel plate of the node area in the direction, the upper flange of the second U-shaped steel-concrete beam horizontally connected to the upper flange steel plate of the node area in the direction of the second U-shaped steel-concrete beam, the first node area web connecting plate between the upper flange connection angle steel of the first node area and the first positioning steel plate, the web of the first U-shaped steel-concrete beam horizontally connected to the web connecting plate of the first node area, the second node area web connecting plate between the upper flange connection angle steel of the second node area and the second positioning steel plate, and the web of the second U-shaped steel-concrete beam horizontally connected to the web connecting plate of the second node area.
[0035] The upper flange steel plate of the node area is placed on the upper flange connection angle steel of the first node area in the direction of the first U-shaped steel concrete beam and is welded to the upper flange connection angle steel of the first node area on three sides; the upper flange steel plate of the node area is placed on the upper flange connection angle steel of the second node area in the direction of the second U-shaped steel concrete beam and is welded to the upper flange connection angle steel of the second node area on three sides; the upper flange of the first U-shaped steel concrete beam is connected to the upper flange steel plate of the node area in the direction of the first U-shaped steel concrete beam; the upper flange of the second U-shaped steel concrete beam is connected to the upper flange steel plate of the node area in the direction of the second U-shaped steel concrete beam; the web connecting plate of the first node area is connected to the upper flange connection angle steel of the first node area and the first positioning steel plate in the horizontal direction in the direction of the first U-shaped steel concrete beam and the lower side; the web connecting plate of the second node area is connected to the upper flange connection angle steel of the first node area and the first positioning steel plate in the direction of the second U-shaped steel concrete beam. The upper and lower sides are respectively connected to the upper flange connection angle steel and the second positioning steel plate in the horizontal direction of the second node area; the web connection plate of the first node area is connected to the angle steel in the vertical direction on the side close to the angle steel; the web connection plate of the second node area is connected to the angle steel in the vertical direction on the side close to the angle steel; the lower flange steel plate of the first node area is placed on the first positioning steel plate and is welded to the first positioning steel plate on three sides; the lower flange steel plate of the second node area is placed on the second positioning steel plate and is welded to the second positioning steel plate on three sides; the lower flange of the first U-shaped steel concrete beam is connected to the lower flange steel plate of the first node area; the lower flange of the second U-shaped steel concrete beam is connected to the lower flange steel plate of the second node area; the web of the first U-shaped steel concrete beam is connected to the web connection plate of the first node area; the web of the second U-shaped steel concrete beam is connected to the web connection plate of the second node area.
[0036] A construction method for a reinforced concrete column-beam node joint comprises the following steps:
[0037] S1. The first U-shaped steel concrete beam is placed on the first positioning steel plate, and the lower flange of the first U-shaped steel concrete beam is welded to the lower flange steel plate of the first node area through the first hand hole of the web connecting plate of the first node area;
[0038] S2, spot welding the first rear supplementary plate 22 at the first hand hole position of the web connecting plate in the node area to seal it;
[0039] S3, welding the upper flange of the first U-shaped steel concrete beam to the upper flange steel plate of the first node area;
[0040] S4, welding the web connecting plate of the first node area to the web of the first U-shaped steel concrete beam;
[0041] S5, placing the second U-shaped steel concrete beam on the second positioning steel plate, and welding the lower flange of the second U-shaped steel concrete beam to the lower flange steel plate of the second node area through the second hand hole of the web connecting plate of the second node area;
[0042] S6. Spot weld the second rear supplementary plate at the second hand hole position to seal it, and weld the upper flange of the second U-shaped steel concrete beam to the upper flange steel plate of the second node area;
[0043] S7, welding the web connecting plate of the second node area to the web of the second U-shaped steel concrete beam;
[0044] S8. Use concrete pouring at one time to connect the new reinforced concrete column node unit and the U-shaped steel concrete beam into a whole.
[0045] Through the optimized design of the present invention, the connection structure between the new reinforced concrete column node unit and the U-shaped steel concrete beam of the present invention has the following advantages:
[0046] 1. The connection joint between the new reinforced concrete column node unit and the U-shaped steel concrete beam designed by the present invention can be completed in the factory. Only installation and beam connection are required on site. It has a high degree of industrialization and modularization, reduces on-site construction work, speeds up the construction process, and ensures construction quality.
[0047] 1. The connection joint between the new reinforced concrete column node unit and the U-shaped steel concrete beam designed by the present invention is that when the beam is installed and connected, the beam is first placed on the positioning steel plate, and then the flange and the web are welded. During on-site welding, only the upper and lower flanges and the web need to be welded. In addition, a tie steel plate is provided in the node area of the column unit, which eliminates the need for stirrup binding in the node area, reduces the workload of on-site construction, facilitates welding construction, and also improves the quality of the weld. The entire installation process is stable and convenient.
[0048] 2. The connection joint between the new reinforced concrete column node unit and the U-shaped steel concrete beam designed by the invention mainly adopts welding connection. Compared with the connection structure that requires the connection nails to be aligned with the holes, the welding connection has lower requirements on the accuracy of the components. It only requires the U-shaped steel concrete beam to be accurately placed when connected. The web of the U-shaped steel concrete beam extends into the connection joint for a certain length, which greatly improves the efficiency of beam-column connection installation;
[0049] 3. In the new reinforced concrete column-steel concrete beam node unit involved in the present invention, the connector extends a certain length from the column side, and the thickness of the connector is increased, and the node area is strengthened, so that the plastic hinge moves outward under the action of an earthquake, meeting the requirements of "strong node and weak structure" for seismic design;
[0050] 4. The new reinforced concrete column-steel concrete beam node unit designed in the present invention adopts steel sleeves at the nodes, and the beam is provided with a U-shaped steel concrete beam to eliminate the formwork. The steel is installed and then cast in an integrated manner, which strengthens the rigidity of the node; the U-shaped steel concrete beam and the node unit are welded and connected at the upper and lower flanges and the web and cast in an integrated manner, which strengthens the rigidity of the beam end; the above shows that the new reinforced concrete column-steel concrete beam-column node unit designed in the present invention can effectively strengthen the rigidity of each connection, so that each connection has better force-bearing performance and deformation capacity. BRIEF DESCRIPTION OF THE DRAWINGS
[0051] Figure 1 It is a front elevation view of the node joint between the reinforced concrete column and the U-shaped steel concrete beam of the present invention;
[0052] Figure 2 It is a side elevation view of the node joint between the reinforced concrete column and the U-shaped steel concrete beam of the present invention;
[0053] Figure 3 It is an overall schematic diagram of the node joint between the reinforced concrete column and the U-shaped steel concrete beam of the present invention;
[0054] Figure 4 It is a schematic diagram of the steel sleeve of the node between the reinforced concrete column and the U-shaped steel concrete beam of the present invention;
[0055] Figure 5 It is a schematic diagram of the upper flange steel plate of the node between the reinforced concrete column and the U-shaped steel concrete beam of the present invention.
[0056] In the figure, 1, the upper flange steel plate of the node area; 2, the connecting angle steel of the upper flange of the first node area; 3, the web connecting plate of the first node area; 4, the tie steel plate; 5, the angle steel; 6, the first positioning steel plate; 7, the lower flange steel plate of the first node area; 8, the longitudinal reinforcement of the reinforced concrete column; 9, the positioning stirrups; 10, the upper flange connecting angle steel of the second node area; 11, the web connecting plate of the second node area; 12, the second positioning steel plate; 13, the lower flange steel plate of the second node area; 14, the first Upper flange of U-shaped steel concrete beam; 15. Web of first U-shaped steel concrete beam; 16. Lower flange of first U-shaped steel concrete beam; 17. Upper flange of second U-shaped steel concrete beam; 18. Web of second U-shaped steel concrete beam; 19. Lower flange of second U-shaped steel concrete beam; 20. First hand hole; 21. Second hand hole; 22. First rear supplementary plate; 23. Second rear supplementary plate; 24. Stirrups; 25. First steel plate; 26. Second steel plate; 27. Third steel plate. DETAILED DESCRIPTION
[0057] The ordinary concrete involved in this embodiment is C40 concrete, with a 3 The concrete contains 185 kg of water, 420 kg of cement, 572 kg of sand and 1273 kg of gravel.
[0058] The detection method involved in this embodiment is as follows:
[0059] Node ultimate bearing capacity detection method:
[0060] The ultimate bearing capacity test of the new reinforced concrete column-U-shaped steel concrete beam node was conducted using a quasi-static loading test. Planar hinge supports were used at the column head and column foot to simulate the boundary conditions of the inflection point, and horizontal sliding hinge supports were used at the beam end, so that the specimen was only subjected to vertical forces during the test and not horizontal forces. The test system included a 1000-ton vertical actuator (maximum thrust: 10000kN, maximum tension: 3000kN, stroke: ±300mm) and a 150-ton horizontal actuator (maximum thrust: 1500kN, maximum tension: 1500kN, stroke: ±400mm). Rollers were set between the top and bottom plates so that the horizontal position of the actuator could be adjusted during the test.
[0061] Before applying the low-cycle reciprocating load, the specimen is first pre-loaded twice using a vertical jack installed at the top of the column, with a preload value of 0.4P=714.3kN, and then the vertical axial pressure is applied in two stages to the predetermined load, which are 0.5P=892.8kN and 1.0P=1785.6kN, respectively, where P is the axial pressure value (axial pressure ratio is 0.4). After each level of load is applied, the load is maintained for 1 minute and data is collected. After the vertical predetermined axial force is applied, the beam end support is installed to ensure that no additional internal force is introduced at the beam end during the application of the axial force. Finally, a low-cycle reciprocating load is applied to the column end until the specimen fails, and the axial force at the top of the column remains constant during the entire loading process.
[0062] The test adopts the load-displacement dual control loading method, with push as the positive loading direction and pull as the negative loading direction. Load control is used before the specimen yields, where the yield load Py is 130kN, and one reciprocating cycle is performed at loads of 0.6Py, 0.8Py, and 1.0Py, respectively, corresponding to loads of 78kN, 104kN, and 130kN; after the specimen yields, displacement control is used, and loading is performed at multiples of the interlayer displacement angle, and the displacement angle values are 1 / 450, 1 / 400, 1 / 350, 1 / 300, 1 / 300, 1 / 250, 1 / 200, 1 / 150, 1 / 10 The displacement angles of the two layers are as follows: 0, 1 / 75, 1 / 50, 1 / 25, and 1 / 20, and the corresponding displacement values are 8mm, 9mm, 10mm, 12mm, 15mm, 18mm, 24mm, 36mm, 49mm, 73mm, 146mm, and 182mm respectively. One cycle is carried out when the inter-layer displacement angles are 1 / 450, 1 / 400, 1 / 350, 1 / 300, and 1 / 250, and 3 cycles are carried out at other inter-layer displacement angles. The test is terminated when the specimen load drops to 85% of the peak load or the hysteresis loop becomes unstable.
[0063] A displacement meter was arranged at the top of the column and the bottom of the upper column of the specimen to measure the deformation of the upper column during loading. A cross displacement meter was arranged at the column node area to measure the shear deformation of the node area. An oblique displacement meter was arranged at the root of the beam to measure the deformation of the plastic hinge area. A horizontal displacement meter was arranged at the root of the beam to measure the deformation of the beam. Five strain gauges were arranged diagonally along the diagonal of each stirrup in the node area, two strain rosettes were arranged along the longitudinal and transverse directions on one side of the U-shaped steel concrete beam, and three strain rosettes were arranged longitudinally. A strain gauge was arranged at the position corresponding to the side strain rosette on the upper and lower flanges.
[0064] Example 1
[0065] A steel sleeve for a node area of a concrete column, comprising angle steels 5 distributed at four corners of the concrete column, a plurality of reinforced concrete column longitudinal bars 8 inside the angle steels, positioning stirrups 9 at the lower side of the angle steels, stirrups 24 at the lower side of the positioning stirrups 9, a certain number of tie plates 4 between every two angle steels 5, a first positioning steel plate 6 at the bottom between every two angle steels 5 in the direction of a first U-shaped steel concrete beam, a first node area upper flange connecting angle steel 2 at the tops of the two angle steels in the direction of the first U-shaped steel concrete beam, a second positioning steel plate 12 at the bottom between every two angle steels 5 in the direction of a second U-shaped steel concrete beam, and a second The upper flange connection angle steel 10 of the second node area at the top of the two angle steels in the direction of the U-shaped steel concrete beam; wherein, the lower sides of both sides of the angle steel 5 are welded to the first positioning steel plate 6 and the second positioning steel plate 12; the upper sides of both sides of the angle steel 5 are welded to the upper flange connection angle steel 2 of the first node area and the upper flange connection angle steel 10 of the second node area; both sides of the angle steel 5 are welded to the short sides of the tie plate 4; the positioning stirrups 9 are welded to several reinforced concrete column longitudinal bars 8 on the same horizontal plane; the stirrups 24 are tied to several reinforced concrete column longitudinal bars 8.
[0066] The first positioning steel plate 6 is an "L"-shaped steel plate, the bottom edge of the short leg of the first positioning steel plate 6 is horizontally aligned with the bottom edge of the angle steel 5 in the direction of the first U-shaped steel concrete beam, and the two sides of the short leg of the first positioning steel plate 6 are vertically welded to the two sides of the angle steel 5;
[0067] The second positioning steel plate 12 is an "L"-shaped steel plate, the bottom edge of the short leg of the second positioning steel plate 12 is horizontally aligned with the bottom edge of the angle steel 5 in the direction of the second U-shaped steel concrete beam, and the two sides of the short leg of the second positioning steel plate 12 are vertically welded to the two sides of the angle steel 5;
[0068] The first node area upper flange connection angle steel 2 is an "L"-shaped steel plate, the top edge of the short leg of the first node area upper flange connection angle steel 2 is horizontally aligned with the top edge of the angle steel 5 in the direction of the first U-shaped steel concrete beam, and the two sides of the short leg of the first node area upper flange connection angle steel 2 are vertically welded to the two sides of the angle steel 5;
[0069] The second node area upper flange connection angle steel 10 is an "L"-shaped steel plate, the top edge of the short leg of the second node area upper flange connection angle steel 10 is horizontally aligned with the top edge of the angle steel 5 in the direction of the second U-shaped steel concrete beam, and the two sides of the short leg of the second node area upper flange connection angle steel 10 are vertically welded to the two sides of the angle steel 5;
[0070] In one embodiment of the present invention, the diameter of the positioning stirrup 9 on the lower side of the column node unit angle steel is greater than or equal to the thickness of the angle steel 5 at the four corners of the concrete column to ensure that the steel sleeve in the column node area is placed on the positioning stirrup 9 and will not fall off;
[0071] In one embodiment of the present invention, the tie plate 4 is provided with studs 11 on the inner side of the new reinforced concrete column, and the spacing between the studs is 100-200 mm;
[0072] In one embodiment of the present invention, a certain number of tie plates 4 are provided between every two angle steels 5, and the spacing between the tie plates 4 is greater than 50 mm to facilitate the circulation of concrete.
[0073] Secondly, the present invention provides a node beam end connection structure between the above-mentioned new reinforced concrete column and the U-shaped steel concrete beam, and the node beam end connection structure between the concrete column and the first U-shaped steel concrete beam and the second U-shaped steel concrete beam includes an upper flange steel plate 1 in the node area, a lower flange steel plate 7 in the first node area, a lower flange 16 of the first U-shaped steel concrete beam horizontally connected to the lower flange steel plate 7 in the first node area, a lower flange steel plate 13 in the second node area, a lower flange 19 of the first U-shaped steel concrete beam horizontally connected to the lower flange steel plate 13 in the second node area, an upper flange connection angle steel 2 in the first node area vertically connected to the upper flange steel plate 1 in the node area in the direction of the first U-shaped steel concrete beam, and a lower flange connection angle steel 2 in the first node area vertically connected to the upper flange steel plate 1 in the node area in the direction of the second U-shaped steel concrete beam. The second node area upper flange connecting angle steel 10, the first U-shaped steel concrete beam upper flange 14 horizontally connected to the node area upper flange steel plate 1 in the direction of the first U-shaped steel concrete beam, the second U-shaped steel concrete beam upper flange 17 horizontally connected to the node area upper flange steel plate 1 in the second U-shaped steel concrete beam direction, the first node area web connecting plate 3 between the first node area upper flange connecting angle steel 2 and the first positioning steel plate 6, the first U-shaped steel concrete beam web 15 horizontally connected to the first node area web connecting plate 3, the second node area web connecting plate 11 between the second node area upper flange connecting angle steel 10 and the second positioning steel plate 12, and the second U-shaped steel concrete beam web 18 horizontally connected to the second node area web connecting plate 11.
[0074] Wherein, the upper flange steel plate 1 of the node area is placed on the upper flange connection angle steel 2 of the first node area in the direction of the first U-shaped steel concrete beam and is welded to the upper flange connection angle steel 2 of the first node area on three sides; the upper flange steel plate 1 of the node area is placed on the upper flange connection angle steel 10 of the second node area in the direction of the second U-shaped steel concrete beam and is welded to the upper flange connection angle steel 10 of the second node area on three sides; the upper flange 14 of the first U-shaped steel concrete beam is connected to the upper flange steel plate 1 of the node area in the direction of the first U-shaped steel concrete beam; the upper flange 17 of the second U-shaped steel concrete beam is connected to the upper flange steel plate 1 of the node area in the direction of the second U-shaped steel concrete beam; the web connecting plate 3 of the first node area is connected to the upper flange connection angle steel 2 of the first node area and the first positioning steel plate 6 in the horizontal direction on the upper and lower sides in the direction of the first U-shaped steel concrete beam; the web connecting plate 11 of the second node area is connected to the upper flange connection angle steel 2 of the first node area and the first positioning steel plate 6 in the horizontal direction on the lower side in the direction of the second U-shaped steel concrete beam The first node area web connecting plate 3 is connected to the angle steel 5 in the vertical direction on the side close to the angle steel 5; the second node area web connecting plate 11 is connected to the angle steel 5 in the vertical direction on the side close to the angle steel 5; the first node area lower flange steel plate 7 is placed on the first positioning steel plate 6 and is welded to the first positioning steel plate 6 on three sides; the second node area lower flange steel plate 13 is placed on the second positioning steel plate 12 and is welded to the second positioning steel plate 12 on three sides; the first U-shaped steel concrete beam lower flange 16 is connected to the first node area lower flange steel plate 7; the second U-shaped steel concrete beam lower flange 19 is connected to the second node area lower flange steel plate 13; the first U-shaped steel concrete beam web 15 is connected to the first node area web connecting plate 3; the second U-shaped steel concrete beam web 18 is connected to the second node area web connecting plate 11.
[0075] In one embodiment of the present invention, the upper flange steel plate 1 of the node area is welded into a "well" steel plate by two first steel plates in the direction of the first U-shaped steel concrete beam, two second steel plates at both ends of the second U-shaped steel concrete beam, and two third steel plates in the middle of the second U-shaped steel concrete beam.
[0076] In one embodiment of the present invention, the width of the upper flange connection angle steel 2 of the first node area in the direction of the first U-shaped steel concrete beam is smaller than the width of the web connection plate 3 of the first node area in the direction of the first U-shaped steel concrete beam, so as to ensure that the upper flange 14 of the first U-shaped steel concrete beam is safely placed on the connection angle steel 2 of the first node area;
[0077] In one embodiment of the present invention, the width of the second node area upper flange connection angle steel 10 in the direction of the second U-shaped steel concrete beam is smaller than the width of the second node area web connection plate 11 in the direction of the second U-shaped steel concrete beam, ensuring that the second U-shaped steel concrete beam upper flange 17 is safely placed on the second node area connection angle steel 10;
[0078] In one embodiment of the present invention, the width of the web 15 of the first U-shaped steel concrete beam along the direction of the first U-shaped steel concrete beam is smaller than the width of the upper flange of the first U-shaped steel concrete beam;
[0079] In one embodiment of the present invention, the width of the web 18 of the second U-shaped steel concrete beam along the direction of the second U-shaped steel concrete beam is smaller than the width of the upper flange of the second U-shaped steel concrete beam;
[0080] In one embodiment of the present invention, the inner width of the web connecting plate 3 in the first node area in the direction of the first U-shaped steel concrete beam is slightly larger than the outer width of the web 15 of the first U-shaped steel concrete beam;
[0081] In one embodiment of the present invention, a hand hole is left at the lower side of the web connecting plate 3 of the first node area near the end of the lower flange steel plate 7 of the first node area, so as to facilitate welding of the lower flange steel plate 7 of the first node area with the lower flange 16 of the first U-shaped steel concrete beam;
[0082] In one embodiment of the present invention, the inner width of the web connecting plate 11 in the second node area of the second U-shaped steel concrete beam is slightly larger than the outer width of the web 18 of the first U-shaped steel concrete beam;
[0083] In one embodiment of the present invention, a hand hole is left at the lower side of the web connecting plate 3 of the second node area near the end of the lower flange steel plate 13 of the second node area, so as to facilitate welding of the lower flange steel plate 13 of the second node area with the lower flange 19 of the second U-shaped steel concrete beam;
[0084] Third, the present invention provides a construction method for the node connection joint of the above-mentioned new reinforced concrete column and the U-shaped steel concrete beam, the method is to first locate the positions of the four angle steels 5 according to the size of the column cross section, vertically weld the first positioning steel plate 6 to the lower side between the two angle steels 5 in the direction of the first U-shaped steel concrete beam, weld the lower flange steel plate 7 of the first node area to the first positioning steel plate 6 on three sides in the direction of the first U-shaped steel concrete beam, vertically weld the second positioning steel plate 12 to the lower side between the two angle steels 5 in the direction of the second U-shaped steel concrete beam, weld the lower flange steel plate 13 of the second node area to the second positioning steel plate 12 on three sides in the direction of the second U-shaped steel concrete beam, vertically weld a plurality of tie plates 4 between the angle steels 5 in pairs, vertically weld the first node area connecting angle steel 2 to the upper side between the two angle steels 5 in the direction of the first U-shaped steel concrete beam, horizontally weld the upper flange steel plate 1 of the first node area to three sides in the direction of the first U-shaped steel concrete beam Welded to the upper flange connection angle steel 2 of the first node area, vertically weld the second node area connection angle steel 10 on the upper side between the two angle steels 5 in the direction of the second U-shaped steel concrete beam, horizontally weld the upper flange steel plate 1 of the second node area to the upper flange connection angle steel 10 of the second node area on three sides in the direction of the second U-shaped steel concrete beam, vertically weld the web connection plate 3 of the first node area with the angle steel 5 in the direction of the first U-shaped steel concrete beam, horizontally connect the upper side of the web connection plate 3 of the first node area with the upper flange connection angle steel 2 of the first node area, horizontally connect the lower side of the web connection plate of the first node area with the first positioning steel plate 6, vertically weld the web connection plate 11 of the second node area with the angle steel 5 in the direction of the second U-shaped steel concrete beam, horizontally connect the upper side of the web connection plate 11 of the second node area with the upper flange connection angle steel 10 of the second node area, and horizontally connect the lower side of the web connection plate 11 of the second node area with the positioning steel plate 12, thereby forming a beam-to-column connection joint.
[0085] Fourth, the present invention provides a construction method for the above-mentioned new reinforced concrete column node unit, which is to first erect a number of longitudinal bars 8 according to design requirements, tie the stirrups 24 to the longitudinal bars 8, and then weld the positioning stirrups 5 to the longitudinal bars according to the position of the U-shaped steel concrete beam in the concrete column, support the formwork and pour concrete to the bottom of the positioning stirrups 5, and after the concrete reaches a certain strength, place the beam-column connection joint on the positioning stirrups 5.
[0086] Fifth, the present invention also provides a construction method for connecting a novel reinforced concrete column node unit with a U-shaped steel concrete beam, wherein the method first places the first U-shaped steel concrete beam on the first positioning steel plate 6, welds the lower flange 16 of the first U-shaped steel concrete beam to the lower flange steel plate 7 of the first node area through the first hand hole 20 of the web connecting plate 3 of the first node area, spot welds the first rear supplementary plate 22 at the first hand hole 20 position of the web connecting plate 3 of the node area to seal, welds the upper flange 14 of the first U-shaped steel concrete beam to the upper flange steel plate 1 of the first node area, and welds the web connecting plate 3 of the first node area to the web 15 of the first U-shaped steel concrete beam. Welding is performed, the second U-shaped steel concrete beam is placed on the second positioning steel plate 12, the lower flange 19 of the second U-shaped steel concrete beam is welded to the lower flange steel plate 13 of the second node area through the second hand hole 21 of the web connecting plate 11 of the second node area, the second rear supplementary plate 23 is spot welded at the position of the second hand hole 21 to seal, the upper flange 17 of the second U-shaped steel concrete beam is welded to the upper flange steel plate 1 of the second node area, the web connecting plate 11 of the second node area is welded to the web 18 of the second U-shaped steel concrete beam, and finally, concrete is poured once to connect the new reinforced concrete column node unit and the U-shaped steel concrete beam as a whole.
[0087] Embodiment 3:
[0088] The present invention also provides a method for detecting a concrete column-beam node, and the specific detection steps are as follows:
[0089] 24 steel bars with a diameter of 12mm are selected for the longitudinal reinforcement in the concrete column. The longitudinal reinforcement adopts HRB500 steel bars. The diameter of the column stirrups is 6mm, the stirrup spacing is 150mm, the stirrups adopt HPB235 grade smooth round steel bars, the diameter of the node area positioning stirrups is 10mm, and the positioning stirrups adopt HPB235 grade smooth round steel bars; the steel material is Q345 steel, the four corner angle steels are L100×8, the upper flange steel plate of the node area is 40×8×600, and the upper flange connection angle steel of the node area is L 100×50×8, tie steel plate is 50×8×300, positioning steel plate L150×50×8, node area lower flange steel plate is 75×8×600, node area web connection plate is 150×6×525, U-shaped steel concrete beam upper flange is 50×6×2010, U-shaped steel concrete beam web is 514×3×2010, U-shaped steel concrete beam lower flange is 300×5×2010, and the end plate section size is 800mm×800mm×10mm. According to Example 1, a new type of reinforced concrete beam-column node unit is prepared with a height of 3580mm, a column section size of 500mm×500mm, and a U-shaped steel concrete beam section size of 525mm×300mm. Concrete is poured to the position of the positioning stirrups. After reaching the predetermined strength, according to Example 2, the reinforced concrete column is connected to the U-shaped steel concrete beam. Finally, pour the concrete inside the beam and the nodes.
[0090] The test results were as follows: the ultimate load at the column top level was 132.9 kN and the ultimate displacement was 78.6 mm.
[0091] Comparative Example 1:
[0092] The specific steps are as follows:
[0093] Prefabricated and precast beams are processed in factories. Pre-set steel bars and stirrups are first arranged in the factory. The length of the steel bars generally exceeds the length of the column by a certain distance, which is used for the sleeve connection between the columns. Then the formwork is arranged and the prefabricated reinforced concrete column is cast. The prefabricated reinforced concrete column is transported to the site, and then the protruding steel bars of the upper and lower column sections are connected by sleeves to connect the two columns. If it needs to be connected to the beam, the longitudinal bars of the beam are hooked on the protruding steel bars of the column, or connected to the longitudinal bars of the opposite beam through sleeves, and then cast on site into a whole at the nodes, that is, the connection points of each longitudinal bar.
[0094] The cross-section size of the beam is 525mm×300mm, and the cross-section size of the column is 500mm×500mm. The longitudinal reinforcement is HRB500 grade steel bars, and the reinforcement is symmetrical. The upper and lower reinforcements in the beam are 2 steel bars with a diameter of 20mm, and the cross-section of the column is 4 steel bars with a diameter of 22mm. The stirrups in the column are HPB235 grade round steel bars with a diameter of 6mm, the stirrup spacing is 150mm, and the column end densification area is 100mm; the stirrups in the beam are HPB235 grade round steel bars with a diameter of 6mm, the stirrup spacing is 150mm, and the beam end densification area is 100mm. The stirrups are bent at a certain length at the upper longitudinal reinforcement according to the diameter of the longitudinal reinforcement. The end plate is made of Q345 steel plate with a cross-section size of 800mm×800mm×10mm. The specimen height is 3580mm, and the concrete is C40 ordinary concrete.
[0095] The test results were as follows: the peak load of the node hysteresis curve was 121.3 kN and the peak displacement was 83.5 mm.
[0096] From the comparative example, it can be seen that the greater the load peak value of the node hysteresis curve and the smaller the displacement peak value, the higher the integrity of the beam-column connection. Therefore, the parameters in Example 3 are preferred values.
[0097] Although the present invention has been disclosed as above in the form of a preferred embodiment, it is not intended to limit the present invention. Anyone familiar with this technology can make various changes and modifications without departing from the spirit and scope of the present invention. Therefore, the scope of protection of the present invention should be based on the definition of the claims.
Claims
1. A steel sleeve for a concrete column node area, characterized in that: It comprises angle steels (5) distributed at the four corners of the concrete column, a plurality of reinforced concrete column longitudinal bars (8) inside the angle steels, positioning stirrups (9) at the bottom of the angle steels, stirrups (24) at the bottom of the positioning stirrups (9), a certain number of tie plates (4) between every two angle steels (5), a first positioning steel plate (6) at the bottom between every two angle steels (5) in the direction of the first U-shaped steel concrete beam, a first node area upper flange connection angle steel (2) at the top of the two angle steels in the direction of the first U-shaped steel concrete beam, a second positioning steel plate (12) at the bottom between every two angle steels (5) in the direction of the second U-shaped steel concrete beam, and a second node area upper flange connection angle steel (10) at the top of the two angle steels in the direction of the second U-shaped steel concrete beam; The first positioning steel plate (6) is an "L"-shaped steel plate, the bottom edge of the short leg of the first positioning steel plate (6) is horizontally aligned with the bottom edge of the angle steel (5) in the direction of the first U-shaped steel concrete beam, and the two sides of the short leg of the first positioning steel plate (6) are vertically welded to the two sides of the angle steel (5); The second positioning steel plate (12) is an "L"-shaped steel plate, the bottom edge of the short leg of the second positioning steel plate (12) is horizontally aligned with the bottom edge of the angle steel (5) in the direction of the second U-shaped steel concrete beam, and the two sides of the short leg of the second positioning steel plate (12) are vertically welded to the two sides of the angle steel (5); The first node area upper flange connection angle steel (2) is an "L"-shaped steel plate, the top edge of the short leg of the first node area upper flange connection angle steel (2) is horizontally aligned with the top edge of the angle steel (5) in the direction of the first U-shaped steel concrete beam, and the two sides of the short leg of the first node area upper flange connection angle steel (2) are vertically welded to the two sides of the angle steel (5); The second node area upper flange connection angle steel (10) is an "L"-shaped steel plate, the top edge of the short leg of the second node area upper flange connection angle steel (10) is horizontally aligned with the top edge of the angle steel (5) in the direction of the second U-shaped steel concrete beam, and the two sides of the short leg of the second node area upper flange connection angle steel (10) are vertically welded to the two sides of the angle steel (5); The diameter of the positioning stirrup (9) at the lower side of the angle steel of the column node unit is greater than or equal to the thickness of the angle steel (5) at the four corners of the concrete column; The construction method of the steel sleeve in the node area of the concrete column comprises the following steps: S1. Locate the four angle steels (5) according to the size of the column section. S2. Vertically weld the first positioning steel plate (6) to the lower side between the two angle steels (5) in the direction of the first U-shaped steel concrete beam. S3, welding the lower flange steel plate (7) of the first node area to the first positioning steel plate (6) on three sides in the direction of the first U-shaped steel concrete beam, S4. Vertically weld the second positioning steel plate (12) to the lower side between the two angle steels (5) in the direction of the second U-shaped steel concrete beam. S5. In the direction of the second U-shaped steel concrete beam, the lower flange steel plate (13) of the second node area is welded on three sides to the second positioning steel plate (12). S6. Weld several tie plates (4) vertically between two angle steels (5). S7. Vertically weld the first node area connecting angle steel (2) to the upper side between the two angle steels (5) in the direction of the first U-shaped steel concrete beam. S8. In the direction of the first U-shaped steel concrete beam, the upper flange steel plate (1) of the first node area is horizontally welded on three sides to the upper flange connecting angle steel (2) of the first node area. S9. Vertically weld the second node area connecting angle steel (10) to the upper side between the two angle steels (5) in the direction of the second U-shaped steel concrete beam. S10, horizontally welding the upper flange steel plate (1) of the second node area to the upper flange connecting angle steel (10) of the second node area on three sides in the direction of the second U-shaped steel concrete beam, S11, vertically welding the web connecting plate (3) of the first node area to the angle steel (5) in the direction of the first U-shaped steel concrete beam, S12, horizontally connecting the upper side of the web connecting plate (3) of the first node area to the upper flange connecting angle steel (2) of the first node area, S13, horizontally connecting the lower side of the web connecting plate in the first node area to the first positioning steel plate (6), S14, vertically welding the web connecting plate (11) of the second node area to the angle steel (5) in the direction of the second U-shaped steel concrete beam, S15, horizontally connecting the upper side of the web connecting plate (11) of the second node area to the upper flange connecting angle steel (10) of the second node area, S16. Horizontally connect the lower side of the web connecting plate (11) of the second node area to the positioning steel plate (12), thereby forming a beam-column connecting joint.
2. A reinforced concrete column and U-shaped steel concrete beam node connection structure, characterized in that: The invention comprises a node area upper flange steel plate (1), a first node area lower flange steel plate (7), a first U-shaped steel concrete beam lower flange (16) horizontally connected to the first node area lower flange steel plate (7), a second node area lower flange steel plate (13), a second U-shaped steel concrete beam lower flange (19) horizontally connected to the second node area lower flange steel plate (13), a first node area upper flange connecting angle steel (2) vertically connected to the node area upper flange steel plate (1) in the direction of the first U-shaped steel concrete beam, a second node area upper flange connecting angle steel (10) vertically connected to the node area upper flange steel plate (1) in the direction of the second U-shaped steel concrete beam, and a node area upper flange connecting angle steel (2) vertically connected to the node area upper flange steel plate (1) in the direction of the first U-shaped steel concrete beam. (1) a first U-shaped steel concrete beam upper flange (14) connected horizontally, a second U-shaped steel concrete beam upper flange (17) connected horizontally to the node area upper flange steel plate (1) in the direction of the second U-shaped steel concrete beam, a first node area web connecting plate (3) between the first node area upper flange connecting angle steel (2) and the first positioning steel plate (6), a first U-shaped steel concrete beam web (15) connected horizontally to the first node area web connecting plate (3), a second node area web connecting plate (11) between the second node area upper flange connecting angle steel (10) and the second positioning steel plate (12), and a second U-shaped steel concrete beam web (18) connected horizontally to the second node area web connecting plate (11); The node area upper flange steel plate (1) is placed on the first node area upper flange connection angle steel (2) in the direction of the first U-shaped steel concrete beam and is welded to the first node area upper flange connection angle steel (2) on three sides; the node area upper flange steel plate (1) is placed on the second node area upper flange connection angle steel (10) in the direction of the second U-shaped steel concrete beam and is welded to the second node area upper flange connection angle steel (10) on three sides; the first U-shaped steel concrete beam upper flange (14) is connected to the node area upper flange steel plate (1) in the direction of the first U-shaped steel concrete beam; the second U-shaped steel concrete beam upper flange (17) is connected to the node area upper flange steel plate (1) in the direction of the second U-shaped steel concrete beam; the first node area web connecting plate (3) is connected to the first node area upper flange connection angle steel (2) and the first positioning steel plate (6) in the horizontal direction in the direction of the first U-shaped steel concrete beam and the lower side; the second node area web connecting plate (11) is connected to the second node area upper flange in the direction of the second U-shaped steel concrete beam and the lower side The flange connecting angle steel (10) and the second positioning steel plate (12) are connected in the horizontal direction; the web connecting plate (3) of the first node area is connected to the angle steel (5) on one side thereof; the web connecting plate (11) of the second node area is connected to the angle steel (5) on one side thereof; the lower flange steel plate (7) of the first node area is placed on the first positioning steel plate (6) and is welded to the first positioning steel plate (6) on three sides; the lower flange steel plate (13) of the second node area is placed on The first U-shaped steel concrete beam is connected to the second positioning steel plate (12) and is welded to the second positioning steel plate (12) on three sides; the first U-shaped steel concrete beam lower flange (16) is connected to the first node area lower flange steel plate (7); the second U-shaped steel concrete beam lower flange (19) is connected to the second node area lower flange steel plate (13); the first U-shaped steel concrete beam web (15) is connected to the first node area web connecting plate (3); the second U-shaped steel concrete beam web (18) is connected to the second node area web connecting plate (11); The construction method of the reinforced concrete column and U-shaped steel concrete beam node connection structure comprises the following steps: S1, placing a first U-shaped steel concrete beam on a first positioning steel plate (6), and welding a lower flange (16) of the first U-shaped steel concrete beam to a lower flange steel plate (7) of the first node area through a first hand hole (20) of a web connecting plate (3) in the first node area; S2, spot welding the first rear supplementary plate (22) at the position of the first hand hole (20) of the web connecting plate (3) in the node area to seal it; S3, welding the upper flange (14) of the first U-shaped steel concrete beam to the upper flange steel plate (1) of the first node area; S4, welding the first node area web connecting plate (3) to the web (15) of the first U-shaped steel concrete beam; S5, placing the second U-shaped steel concrete beam on the second positioning steel plate (12), and welding the lower flange (19) of the second U-shaped steel concrete beam to the lower flange steel plate (13) of the second node area through the second hand hole (21) of the web connecting plate (11) of the second node area; S6, spot welding the second rear supplementary plate (23) at the position of the second hand hole (21) to seal it, and welding the upper flange (17) of the second U-shaped steel concrete beam to the upper flange steel plate (1) of the second node area; S7, welding the second node area web connecting plate (11) to the web (18) of the second U-shaped steel concrete beam; S8. Use concrete pouring at one time to connect the new reinforced concrete column node unit and the U-shaped steel concrete beam into a whole.