A warehouse auxiliary device for pouring concrete for antique building pads

By designing a warehouse entry auxiliary device for antique building pads, and using components such as rack pipe tracks and trough side plates, the problems of discontinuous discharge and safety risks during concrete pouring in the prior art are solved, and construction is simplified , reduce waste and improve safety effects.

CN110939273BActive Publication Date: 2024-11-12SINOHYDRO BUREAU 6 CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201911322679.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-12-20
Publication Date
2024-11-12
Estimated Expiration
2039-12-20

AI Technical Summary

Technical Problem

During the pouring of concrete for existing antique building pads, construction personnel need to move and adjust the discharge part many times, resulting in increased risk of concrete congestion, spilling and safety, and the inability to achieve continuous discharge operations.

Method used

A storage access auxiliary device is designed, including rack pipe rails, trough side plates, rubber sheets, scrapers, pulleys and threaded rods. Through the combination of these components, the vertical or horizontal adjustment of the trough base plate and the pre-scraping of concrete are achieved. Flat stacking reduces manual operation and vibration process.

Benefits of technology

The device simplifies the construction process, reduces concrete waste and safety risks, improves labor productivity and construction safety, is suitable for different warehouse widths, and can be reused multiple times.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110939273B_ABST
    Figure CN110939273B_ABST
Patent Text Reader

Abstract

The present invention discloses a silo auxiliary device for pouring concrete for antique building pads, comprising a pipe rack track and a trough side plate, wherein the lower end of the trough side plate is provided with a plurality of trough bottom plates, the plurality of trough bottom plates are rotatably connected in sequence, and the end surface of the trough bottom plate away from the trough side plate is fixedly connected with a rubber sheet and a scraper, and the lower end of the trough side plate is fixedly connected with a pulley. In the present invention, the device has a simple structure, is easy to manufacture, is convenient and quick to install, is labor-saving and economical to operate, can reduce waste caused by spillage of concrete materials, and with the unidirectional movement of the trough body, the scraper can be used to pre-scrape and flatten the super-high piled concrete, thereby eliminating the problem that part of the aggregate still emerges from the silo during the vibration process after unloading. At the same time, during operation, the trough bottom plate is on the inner side of the track, supported by a movable rod and a pad, thereby improving stability and reducing the safety risks caused by repeatedly moving the unloading port baffle or unloading funnel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of concrete pouring, and in particular to a warehouse-entering auxiliary device for pouring concrete of antique building pads. Background Art

[0002] The pads in ancient buildings refer to wooden boards used to fill the gaps between purlins and beams for decoration. In modern antique buildings, since the thickness of the pads basically does not exceed 10 cm and most of them are set up in multiple spans, in order to save wood and reduce costs, concrete structures are now often used as the design form of antique decoration.

[0003] When currently pouring narrow and long concrete components such as pads, most construction workers use a feeding funnel made from simple wooden formwork or even directly use two pieces of waste formwork to obliquely block the two sides of the entry position to assist entry. With this method, at least two construction workers are required to constantly "move, place, and stabilize" the material during pouring in order to continuously change the feeding position to achieve the purpose of entering the warehouse. Not only can the material be discharged continuously, but also there is no time to change the feeding position when it is not coordinated with the concrete pump truck, which can easily cause congestion and spillage of concrete materials. Even when constructing at high working layers, it is very easy to cause safety accidents due to the flustered operation. Summary of the invention

[0004] The purpose of the present invention is to solve the above-mentioned problem that the existing antique building pad concrete pouring is inconvenient, and to propose a warehouse-entering auxiliary device for antique building pad concrete pouring.

[0005] In order to achieve the above object, the present invention adopts the following technical solutions:

[0006] A warehousing auxiliary device for pouring concrete for antique building pads comprises a pipe rack track and a trough side plate, a plurality of trough bottom plates are arranged at the lower end of the trough side plate, the plurality of trough bottom plates are rotatably connected in sequence, and the end surface of the trough bottom plate away from the trough side plate is fixedly connected with a rubber sheet and a scraper, a pulley is fixedly connected with the lower end of the trough side plate, the pulley is located on the pipe rack track, a threaded sleeve and a sliding sleeve are welded to the bottom surface wall of the trough side plate, a threaded rod is threadedly connected to the inner side of the threaded sleeve, a sliding rod is slidably connected to the inner side of the sliding sleeve, and the same movable rod is arranged on the same side of the sliding rod and the threaded rod.

[0007] As a further description of the above technical solution:

[0008] The inner surface walls of the trough side plate and the trough bottom plate are both provided with pads, and the top end surface of the trough side plate is connected with the top end bolts of the pads.

[0009] As a further description of the above technical solution:

[0010] The pad is formed by splicing a plurality of wooden boards with a thickness of 0.5-0.8 mm, and the splicing parts of the wooden boards are lined with rubber strips.

[0011] As a further description of the above technical solution:

[0012] The scraper is made of rubber, and both horizontal ends of the scraper are bent upwards.

[0013] As a further description of the above technical solution:

[0014] The outer side wall of the trough side plate is bolted with a booster handle, which is formed by bending a thin steel pipe with a length of 20 cm and a diameter of 20 mm and is sleeved with a non-slip rubber sleeve.

[0015] As a further description of the above technical solution:

[0016] There are two sliding rods, and the two sliding rods are respectively located at the horizontal ends of the movable rod, and the movable rod is fixedly connected to the two sliding rods.

[0017] As a further description of the above technical solution:

[0018] The movable rod is rotatably connected to the threaded rod.

[0019] As a further description of the above technical solution:

[0020] A cushion block is fixedly connected to one side of the movable rod close to the bottom plate of the trough, and the bottom plate of the trough and the cushion block are fitted to each other.

[0021] As a further description of the above technical solution:

[0022] A connecting piece is provided on the bottom end surface of the trough side plate, and the connecting piece is composed of two layers of inner and outer steel lining plates with a width of 3 cm and a thickness of 3 mm. The trough side plate, pulley and connecting piece are all connected by bolts.

[0023] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:

[0024] 1. In the present invention, the device has a simple structure, is easy to manufacture, convenient and quick to install, saves labor and effort in operation, is economical and applicable, can reduce waste caused by spillage of concrete materials, and with the unidirectional movement of the trough body, the scraper can be used to pre-scrape and level the super-high concrete, thereby eliminating the problem that part of the aggregate still comes out of the bin during the vibration process after unloading. At the same time, during operation, the bottom plate of the trough is on the inner side of the track and is supported by the movable rod and the pad, which improves stability and reduces the safety risks caused by repeatedly moving the unloading port baffle or the unloading funnel.

[0025] 2. In the present invention, the rubber sheet and the scraper can be adjusted according to the width of the warehouse number, so as to adapt to different warehouse numbers. The device can be reused many times without generating excess waste. It has high firmness and is easy to adjust. It can greatly improve labor productivity, greatly reduce auxiliary workload, and improve construction safety.

[0026] 3. In the present invention, the threaded rod can push the movable rod to move by rotating, thereby making different trough bottom plates vertical or horizontal, so that the discharge port area can be adjusted, thereby improving the practicality of the device. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the overall structure of the auxiliary device in the present invention;

[0028] Figure 2 This is a schematic diagram of the bottom end surface structure of the trough bottom plate of the present invention;

[0029] Figure 3 This is a schematic diagram of the top view of the bottom plate of the trough in the present invention;

[0030] Figure 4 It is a schematic diagram of the side structure of the scraper in the present invention.

[0031] Legend:

[0032] 1. Pipe rack rail; 2. Material trough side plate; 3. Material trough bottom plate; 4. Rubber sheet; 5. Scraper; 6. Pulley; 7. Connector; 8. Pad; 9. Boost handle; 10. Threaded sleeve; 11. Sliding sleeve; 12. Movable rod; 13. Sliding rod; 14. Threaded rod; 15. Pad. DETAILED DESCRIPTION

[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0034] Embodiment 1:

[0035] See also Figure 1 , Figure 2 and Figure 4, a warehousing auxiliary device for pouring concrete for antique building pads, including a pipe rack track 1 and a trough side plate 2, a plurality of trough bottom plates 3 are provided at the lower end of the trough side plate 2, and the plurality of trough bottom plates 3 are rotatably connected in sequence, and the end surface of the trough bottom plate 3 away from the trough side plate 2 is fixedly connected with a rubber sheet 4 and a scraper 5, and the lower end of the trough side plate 2 is fixedly connected with a pulley 6, and the pulley 6 is located on the pipe rack track 1, and a threaded sleeve 10 and a sliding sleeve 11 are welded to the bottom surface wall of the trough side plate 2, a threaded rod 14 is threadedly connected to the inner side of the threaded sleeve 10, and a sliding rod 13 is slidably connected to the inner side of the sliding sleeve 11, and the same movable rod 12 is provided on the same side of the sliding rod 13 and the threaded rod 14, the scraper 5 is made of rubber material, and the horizontal ends of the scraper 5 are bent upward, and the outer side surface wall of the trough side plate 2 is bolted with a booster handle 9, and the booster handle 9 is made of a thin steel pipe with a length of 20 cm and a diameter of 20 mm and is bent, and is sleeved with an anti-slip rubber sleeve , there are two sliding rods 13, and the two sliding rods 13 are respectively located at the horizontal ends of the movable rod 12, the movable rod 12 is fixedly connected to the two sliding rods 13, the movable rod 12 is rotatably connected to the threaded rod 14, the bottom end surface of the trough side plate 2 is provided with a connecting piece 7, and the connecting piece 7 is composed of an inner and outer layer of 3cm wide and 3mm thick steel lining plates, the trough side plate 2, the pulley 6 and the connecting piece 7 are all connected by bolts, and the movable rod 12 is fixedly connected with a pad 15 on one side close to the trough bottom plate 3, the trough bottom plate 3 and the pad 15 fit each other, the threaded rod 14 can move along its own radial direction by rotation, thereby playing a role of supporting the trough bottom plate 3, and by contacting with different trough bottom plates 3, the unloading area of ​​the unloading port is adjusted, so that the device can cast concrete for warehouses of various widths, and the scraper 5 can scrape the concrete after unloading, which plays a role of pre-scraping, and the two ends of the scraper 5 are tilted to prevent it from being inserted into the concrete.

[0036] Embodiment 2:

[0037] See also Figure 1-4, a warehousing auxiliary device for pouring concrete for antique building pads, comprising a pipe rack track 1 and a trough side plate 2, a plurality of trough bottom plates 3 are provided at the lower end of the trough side plate 2, the plurality of trough bottom plates 3 are rotatably connected in sequence, and the end surface of the trough bottom plate 3 away from the trough side plate 2 is fixedly connected with a rubber sheet 4 and a scraper 5, a pulley 6 is fixedly connected at the lower end of the trough side plate 2, and the pulley 6 is located on the pipe rack track 1, a threaded sleeve 10 and a sliding sleeve 11 are welded to the bottom surface wall of the trough side plate 2, a threaded rod 14 is threadedly connected to the inner side of the threaded sleeve 10, a sliding rod 13 is slidably connected to the inner side of the sliding sleeve 11, and the same movable rod 12 is provided on the same side of the sliding rod 13 and the threaded rod 14, the scraper 5 is made of rubber material, and the horizontal ends of the scraper 5 are bent upward, and the outer side surface wall of the trough side plate 2 is bolted with a booster handle 9, which is made of a thin steel pipe with a length of 20 cm and a diameter of 20 mm and is bent and sleeved. There is an anti-slip rubber sleeve, two slide bars 13 are provided, and the two slide bars 13 are respectively located at the horizontal ends of the movable rod 12, the movable rod 12 is fixedly connected to the two slide bars 13, the movable rod 12 is rotatably connected to the threaded rod 14, the bottom end surface of the trough side plate 2 is provided with a connecting piece 7, and the connecting piece 7 is composed of an inner and outer layer of 3cm wide and 3mm thick steel lining plates, the trough side plate 2, the pulley 6 and the connecting piece 7 are all connected by bolts, and the movable rod 12 is fixedly connected with a pad 15 on one side close to the trough bottom plate 3, the trough bottom plate 3 and the pad 15 fit each other, the inner surface walls of the trough side plate 2 and the trough bottom plate 3 are provided with pads 8, the top surface of the trough side plate 2 is connected to the top bolt of the pad 8, the pad 8 is made of multiple wooden boards with a thickness of 0.5-0.8mm, and the splicing part of the wooden boards is lined with rubber strips, and the pad 8 plays a role in concrete seepage prevention, making it difficult for concrete to leak, thereby reducing the waste of concrete.

[0038] Working principle: When in use, during the preparation of the warehouse number, the workers set up the pipe rack track 1. The pipe rack track 1 is a long horizontal bar added by welding a 28mm diameter steel bar plug and socket connection method at the top of the vertical pole used to reinforce the formwork. Then, according to the width of the warehouse number, the workers manually rotate the threaded rod 14 and adjust the position of the movable rod 12 to make the spacing between the trough bottom plates 3 on both sides of the bottom of the trough side plates 2 adapt to the width of the warehouse number. The device can be placed on the warehouse number. When unloading, a construction worker extends the pump pipe into the trough side plate 2, cooperates with the speed of the pump truck to push the device to the other end of the warehouse number at a uniform speed using the booster handle 9. The part where the material is paved is followed by another construction worker holding a small vibrator to vibrate and compact the paved concrete and smooth it. By continuing to operate forward, the pouring work of this warehouse number can be completed conveniently and quickly.

[0039] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A silo auxiliary device for pouring concrete for antique building pads, comprising a pipe rack track (1) and a trough side plate (2), characterized in that: A plurality of trough bottom plates (3) are provided at the lower end of the trough side plate (2), the plurality of trough bottom plates (3) are rotatably connected in sequence, and the end surface of the trough bottom plate (3) away from the trough side plate (2) is fixedly connected with a rubber sheet (4) and a scraper (5), the lower end of the trough side plate (2) is fixedly connected with a pulley (6), the pulley (6) is located on the pipe rack track (1), a threaded sleeve (10) and a sliding sleeve (11) are welded to the bottom surface wall of the trough side plate (2), the inner side of the threaded sleeve (10) is threadedly connected with a threaded rod (14), the inner side of the sliding sleeve (11) is slidably connected with a sliding rod (13), and the same side of the sliding rod (13) and the threaded rod (14) is provided with the same movable rod (12); The inner surface walls of the trough side plate (2) and the trough bottom plate (3) are both provided with a backing plate (8), and the top end surface of the trough side plate (2) is bolted to the top end of the backing plate (8); The scraper (5) is made of rubber, and both horizontal ends of the scraper (5) are bent upwards.

2. The silo-entering auxiliary device for pouring concrete for antique building pads according to claim 1 is characterized in that: The pad (8) is formed by splicing together a plurality of wooden boards with a thickness of 0.5-0.8 mm, and the spliced ​​parts of the wooden boards are lined with rubber strips.

3. The silo-entering auxiliary device for pouring concrete for antique building pads according to claim 1 is characterized in that: The outer side wall of the trough side plate (2) is bolted with a booster handle (9), the booster handle (9) is formed by bending a thin steel pipe with a length of 20 cm and a diameter of 20 mm, and is sleeved with an anti-slip rubber sleeve.

4. The storage auxiliary device for pouring concrete for antique building pads according to claim 1 is characterized in that: Two sliding rods (13) are provided, and the two sliding rods (13) are respectively located at two horizontal ends of the movable rod (12), and the movable rod (12) is fixedly connected to the two sliding rods (13).

5. The storage auxiliary device for pouring concrete for antique building pads according to claim 1 is characterized in that: The movable rod (12) is rotatably connected to the threaded rod (14).

6. The storage auxiliary device for pouring concrete for antique building pads according to claim 1 is characterized in that: A cushion block (15) is fixedly connected to one side of the movable rod (12) close to the trough bottom plate (3), and the trough bottom plate (3) and the cushion block (15) are in contact with each other.

7. The storage auxiliary device for pouring concrete for antique building pads according to claim 1 is characterized in that: The bottom end surface of the trough side plate (2) is provided with a connecting piece (7), and the connecting piece (7) is composed of two layers of inner and outer steel lining plates with a width of 3 cm and a thickness of 3 mm. The trough side plate (2), the pulley (6) and the connecting piece (7) are all connected by bolts.